HomeMy WebLinkAboutAGENDA REPORT 1998 0520 CC REG ITEM 10GITEM 10 • ere
CITY OF MOORPAIM CALIFORNIA
CITY COUNCIL AGENDA REPORT City Council Meeting
CITY OF MOORPARK of 5 • 2 o - 11 S
ACTION: A p p r o v ecl S+ a �-P
r'��oMrv�endatto.�
TO: The Honorable City Council
FROM: Mary K. Lindley, Director of Community Services }�
DATE: May 13, 1998 (CC Meeting of May 20, 1998)
SUBJECT: Consider Arroyo Vista Community Park Tennis Court Conceptual Plan
Summaa
On April 13, 1998, the City secured the services of a landscape architect, Community Works
Design Group, to design eight lighted tennis courts at Arroyo Vista Community Park (AVCP).
Since that time, City and MUSD representatives have met with the architect to discuss the
placement of the courts, potential additional parking, and other desirable amenities. The architect
has provided the City with a conceptual layout plan and developed preliminary cost estimates.
Staff is requesting Council approval of the conceptual layout and seeking direction on
construction phasing.
Background
On October 1, 1997, the City Council appropriated $176,000 towards the construction of the
tennis courts with the understanding that MUSD would contribute an additional $176,000 (total
amount of funds committed to the project is $352,000). The Agreement for design services was
approved at a cost of $10,000, which leaves approximately $342,000 for construction and project
management costs. Additionally on October 1, the Council approved a location for the courts at
the southwest end of AVCP, adjacent to Moorpark High School.
The conceptual layout plan places the courts in sets of four, divided by the existing mature black
walnut tree (Attachment A). The initial cost estimates for the Plan, including all improvements
and amenities such as hardscape (concrete walk ways), landscaping, fencing, court lighting,
shelters, bleachers, benches, two drinking fountains, and security lights is approximately
$471,000.
Since the initial costs of fully constructing the tennis court complex, with its various amenities,
exceeds the amount of funds currently allocated to the project, the architect developed a proposal
for phasing construction. Phase I ($328,066) includes only work that is necessary to initiate play
on the courts including: construction of the courts, installation of lights and fences, court striping,
and grading and drainage work. Additionally, Phase I would include some minimal preparation
C ADOCSIADM1MCOURTDSG.AGD
00bU(;;4
work for items that are to be constructed in Phase II when doing so will save future costs such as
plumbing for electrical and water. Phase II ($142,851) includes additional hardscape, landscape
and other amenities desirable at a tennis court complex including: drinking fountains, bleachers,
concrete walkways, court wind screens, and security lighting.
Staff proposes that the City proceed with the completion and finalization of the design of the
lighted tennis complex, but only initiate the construction of Phase I. As additional funding
becomes available, the City can proceed with Phase II of the project (See phasing plan on
Attachment B). Staff proposes that the construction Request for Proposal (RFP) include Phase
II's various improvements as a bid alternate. If the bid proposals come in under the original cost
estimate, the City Council would have the option of including any or all of those improvements in
the initial construction project. It is also possible that other funding sources (non City funds) may
be available, such as donations from the Moorpark Tennis Club and the United States Tennis
Association, which could be used to complete various desirable amenities (drinking fountain,
bleachers, benches, shelters, landscaping etc.). Additionally, there may be some minimal work
related to landscaping identified in Phase II which can to performed in -house using the City's park
maintenance staff.
In addition to the design of the tennis courts, the architect was also directed to evaluate potential
parking improvements that would yield additional parking spaces in the improved parking lot at
AVCP. The only direction in which the parking can be expanded is to the south. In order to gain
a sufficient number of new spaces to make the effort worthwhile; i.e., providing 20 or more
additional spaces, would require grading into the slope between the Park and Moorpark High
School. The architect estimates that a retaining wall of approximately 15 to 20 feet would be
needed to construct a parking lot expansion. Additionally, expanding the existing improved
parking lot to the south would impact the placement of at least one of the sets of courts (courts 5
and 6 on Attachment A) which would need to be relocated. Relocating a set of courts would
eliminate the symmetrical layout of the complex and expand the complex further west into the
park. Construction of the retaining wall alone would make the project cost prohibitive. Staff
recommends that the City not pursue expanding the improved parking lot in either Phase I or
Phase II of the project.
The next step in the process is for the City Council to approve the layout of the tennis courts and
the construction phasing plan. With this accomplished, the architect will develop construction
plans and specifications and further refine the construction cost estimates. Staff will then prepare
a bid document for distribution.
Recommendation
Staff recommends that the City Council approve the conceptual layout for the eight lighted tennis
courts as presented on Attachment A, approve the phasing plan, and direct staff to proceed with
design plans and specifications.
Attachments
C:\DOCS\ADMMCOLJRTDSG.AGD
OOCYO63
PD t J�r
h 4Rouo
MAf
AMA
Ull
-d
y war_ ��� n
cap
Attachment B
ARROYO VISTA COMMUNITY PARK TENNIS COURT COMPLEX
PRELIMINARY COST ESTIMATE - PHASE I
Tennis
Tennis Court w/Lights
8 Each
$32,500
Unit
Total
Description
Qty
Unit
Cost
Cost
Large Areas - Adjust /Cap
Allow
$1,000
Mobilization
Tie - Ins /Extend For D.F.
Allow
$2,500
$2,500
Demolition and Clearing
Service/Main Switch Board
Clear and Grub
84,000
S.F.
$0.05
$4,200
Grading and Drainage
$2,000
Grading
1,500
C.Y.
$3.25
$4,875
Catch Basin
1
Each
$1,000
$1,000
6" Drainline - P.V.C.
400
L.F.
$8
$3,200
Tennis
Tennis Court w/Lights
8 Each
$32,500
$260,000
Irrigation/Water
Automatic Irrigation System
Large Areas - Adjust /Cap
Allow
$1,000
$1,000
Tie - Ins /Extend For D.F.
Allow
$500
$500
Lighting/Electrical
Service/Main Switch Board
1 Allow
$6,000
$6,000
Security Light Conduits
4 Each
$500
$2,000
SUBTOTAL: $285,275
15.00% General Contractor Overhead and Profit: $42,791
-----------------------------------------------------------------------------------------------
GRAND TOTAL: $328,066
000065
Attachment B
ARROYO VISTA COMMUNITY PARK TENNIS COURT COMPLEX
PRELIMINARY COST ESTIMATE - PHASE II
Unit Total
Description Qty Unit Cost Cost
Mobilization
Demolition and Clearing
Clear and Grub
Site Features
Trash Receptacle
Tree Wells
Tree Grates - 4 ft.
Drinking Fountain
Picnic Shelter - 24 ft.
Picnic Table - steel w /vinyl coat
Bleachers - 3 rows
Bench
Hardscape
Concrete Paving - 4"
Seat Wall - 18" SFB
Landscaping
Soil Prep/Fine Grading
90 Day Maintenance Period
Trees - 24" box
Shrubs - 5 gal.
Shrubs - 1 gal.
Turf Hydroseed
Irrigation/Water
Automatic Irrigation System
Large Areas - Adjust /Cap
Small Areas
Lighting/Electrical
Security Walkway /Lights
Service/Main Switch Board
Allow $2,500 $2,500
5,000 S.F. $0.50 $2,500
4 Each $2,000 $8,000
1 Allow $6,000 $6,000
SUBTOTAL: $124,218
15.00% General Contractor Overhead and Profit: $18,633
-----------------------------------------------------------------------------------------------
GRAND TOTAL: $142,851
006066
Allow
$2,500
$2,500
10,760
S.F.
$0.05
$538
4
Each
$400
$1,600
7
Each
$150
$1,050
3
Each
$450
$1,350
2
Each
$2,500
$5,000
2
Each
$16,000
$32,000
8
Each
$850
$6,800
4
Each
$2,500
$10,000
16
Each
$400
$6,400
10,760
S.F.
$2
$21,520
120
L.F.
$38
$4,560
25,000
S.F.
$0.18
$4,500
25,000
S.F.
$0.06
$1,500
9
Each
$250
$2,250
100
Each
$14
$1,400
200
Each
$5
$1,000
25,000
S.F.
$0.05
$1,250
Allow $2,500 $2,500
5,000 S.F. $0.50 $2,500
4 Each $2,000 $8,000
1 Allow $6,000 $6,000
SUBTOTAL: $124,218
15.00% General Contractor Overhead and Profit: $18,633
-----------------------------------------------------------------------------------------------
GRAND TOTAL: $142,851
006066