To: The Honorable City Council
From: Kenneth C. Gilbert, Director of Public Works
Date: November 5, 1998 (Council Meeting 11- 18 -98)
c r�cl keS�
Subject: Notice of Completion for the 1998 Slurry Seal Project
L�
BACKGROUND
On May 6, 1998, the City Council awarded a contract to Valley
Slurry Seal for slurry sealing various streets throughout the
City.
DISCUSSION
A. Project Scope, Purpose and Design
Slurry sealing protects the existing pavement from the
effects of the sun and elements, thus extending the life of
the pavement. A slurry sealing contract typically also
includes the removal and replacement of problem asphalt
areas, the placement of a leveling course (where required),
the application of crack filler as required and the re-
striping of the street.
The goal of the City's Slurry Seal Program is to apply slurry
seal to approximately one -third of the minor and collector
streets every other year. This will allow each street to be
resurfaced about once every six years.
The 1998 Slurry Seal Project provided for the placement of
approximately 2,300 tons of asphalt covering approximately
twenty -two miles of streets. In addition, a number of
parking lots were also resurfaced.
coo
Slurry Seal 1998: Completion
November 6, 1998
Page 2
B. Change Orders
Two Change Orders were issued for this project, generally
described as follows:
• Change Order No. 1 [Cost: $ -0 -]: This Change Order added
three areas to the surfaces being slurry sealed. In that
the cost for this work was included in the total
quantities paid, there was no need for a separate cost.
The areas added by this Change Order are described as
follows:
a) the west end of the Arroyo Vista Community Park
access road;
b) Lassen Avenue west of Park Lane; and,
c) the east end of Second Street.
• Change Order No. 2 [Cost: $ -0 -1: This Change Order deleted
from the contract Mountain Trail Court, located just east
of Mountain Meadow Drive at the north side of Mountain
Meadow Park. After the award of contract it was determined
that the condition of the street warranted the
construction of an asphalt overly. Accordingly, this
street segment has been added to the streets to be
included in the 1999 A/C Overlay Project.
C. Quantity Adjustment
Invariably with Public Works projects the final actual
quantity for each of the items required to complete the
project will differ somewhat from the engineer's estimate of
quantities set forth in the bid documents. This means that
the final contract cost will differ somewhat from the bid
price, based upon the actual quantity of items constructed.
Many times the final contract cost is slightly more than the
bid price. This time the final contract cost, based on actual
quantities required, was less than the bid price. A
comparison of the bid price to the final actual contract cost
is as follows:
• Bid Price: $302,688.30
• Less Actual Final Contract Cost: ($286,025.66)
Amount Less Than Bid 16,662.64
D. Final Inspection and Acceptance
The City Engineer has completed a final inspection of the
project and has found the work to be acceptable. At this
time it would be appropriate for the City Council to accept
the project as completed, direct the City Clerk to file a
Notice of Completion and authorize release of the retention.
Slry98 cmp
UUU k-
Slurry Seal 1998: Completion
November 6, 1998
Page 3
E. Work Funded by Developer
The slurry sealing and related improvements done to Cedar
Spring Street and Mountain Meadow Drive in the vicinity of
the Mirabella / Villagio community, was done at the request
of, and was funded by, California Community Builders (CCB). A
summary of the costs and payments for this work is as
follows:
Construction Costs:
Slurry Seal:
$5,525.00
100
Striping:
$2,585.00
210: Parks
Construction Cost:
210: Parks
$8,110.00
Administration:
Inspection
$1,550.00
Contract Admin.
$1,590.00
$3,140.00
Total Cost
$11,250.00
Less Amount Paid by CCB
($11,250.00)
Balance Due
$0
F. Parking Lots
In the May 6th staff report to the City Council regarding the
award of contract, it was mentioned that the costs for the
application of slurry seal to certain City -owned parking lots
could not be charged to the funding sources restricted to
street maintenance. That report mentioned that upon
completion of the project, it would be necessary to calculate
the cost of the re- surfacing of the parking lots and to
transfer those costs to the budgets provided for such
maintenance. The May 6th report estimated those costs to be as
follows:
Parkinq Lot Location
City Hall
Peach Hill Park (2 lots)
Mountain Meadow Park
Sub -total
Metro Link Lots
Total
Slry98 cmp
Fund
Division
100
703: Facilities
100
210: Parks
100
210: Parks
204 201: Transit
Est. Cost
3,156
2,590
1,570
7,316
12,160
19,476
(. " S ,, Q 0
Slurry Seal 1998: Completion
November 6, 1998
Page 4
The scope of work, cost and suggesting funding source for the
parking lot resurfacing efforts is summarized as follows:
Notes: a: 33% of cost to be paid by MUSD per terms of License Agreement.
A comparison of the prior estimates and the final costs for
parking lot resurfacing is as follows:
Prior Est. Actual
• General Fund: 7,316 5,034
• Transit Fund: 12,160 6,922
• MRA Property 0 561
The reallocation of project costs to the appropriate funding
sources is discussed below.
G. Fiscal Impact
1. Construction Contract Cost Summary: A summary of the
total construction contract costs is as follows:
Element Total ($)
Bid Price 302,688.30
Quantity Adjustment (16,662.64)
Change Orders 0.00
Total 286,025.66
Slry98 cmp
000rpu !
Final Cost
{$)
Parking Lot
Location
Slurry
Striping
Total
Charge to Dept.
City Hall
2,040
377
2,417
100.703:
City Hall
Arroyo Vista
408
95
(a) 503
100.200:
Parks
Park Entry
Peach Hill Park
1,200
165
1,365
100.210:
Parks
(two Lots)
Mountain Meadow
578
171
749
100.210:
Parks
Park
Sub -total
4,226
808
5,034
18 High Street
459
102
561
401.501:
MRA
MetroLink Lots
5,207
1,715
6,922
204.201
Transit
Total
9,892
2,625
12,517
Notes: a: 33% of cost to be paid by MUSD per terms of License Agreement.
A comparison of the prior estimates and the final costs for
parking lot resurfacing is as follows:
Prior Est. Actual
• General Fund: 7,316 5,034
• Transit Fund: 12,160 6,922
• MRA Property 0 561
The reallocation of project costs to the appropriate funding
sources is discussed below.
G. Fiscal Impact
1. Construction Contract Cost Summary: A summary of the
total construction contract costs is as follows:
Element Total ($)
Bid Price 302,688.30
Quantity Adjustment (16,662.64)
Change Orders 0.00
Total 286,025.66
Slry98 cmp
000rpu !
Slurry Seal 1998: Completion
November 6, 1998
Page 5
2. Total Project Cost Summary: A summary of the total
estimated cost for the subject project is as follows:
Element
FY 97/98
FY 1998/99
Total
Design
6,929
0
6,929
Construction
51,449
234,577
286,026
Admin / Insp.
7,970
41,830
49,800
Total
66,348
276,407
342,755
3. Net City Costs: As discussed above, costs associated with
the resurfacing of the parking lot at 18 High Street
(Building / Engineering Offices) is to be funded by MRA
property maintenance funds. These costs are to be paid
from an existing account [410.510.0000.000.9101]
established for such purposes. The MRA costs and the net
FY 1998/99 cost to the City is shown as follows:
Design ($)
Total Project 6,929
Less MRA
Net to City 6,929
Less Prior Year (6,929)
Total FY 1998/99 0
Less Pd by CCB
Net City FY 98/99
Constr ($)
286,026
(561)
285,465
(51,449)
234,016
Insp ($)
49,800
49,800
(7,970)
41,830
Total ($)
342,755
(561)
342,194
(66,348)
275,846
(11,250)
264,596
4. Current Budget Summary: The current status of the budget
for this project [400.801.8037.xxx.xxx] is as follows:
Slry98 cmp
000.r. o;;4
FY 1998/99
Element
FY 97/98
Carryover
FY 1998/99
Total
Total {$}
Design
6,929
0
0
0
6,929
Construction
51,449
281,509
20,000
301,509
352,958
Admin /
7,970
43,331
1,000
44,331
52,301
Insp.
Total
66,348
324,840
21,000
345,840
412,188
Slry98 cmp
000.r. o;;4
Slurry Seal 1998: Completion
November 6, 1998
Page 6
5. Budget Amendment: In that some of the work included the
resurfacing of certain parking lots, it is necessary to
amend the FY 1998/99 Budget to reflect the correct funding
sources. The Budget Amendment described below also lowers
the total appropriations for this project to reflect the
final actual costs. The recommended budget adjustment is
summarized as follows:
FY 1998/99 Budget / Appropriation
Current Revised
Account Number Budget ($) Change ($) Total ($)
Budget
400.801.8037.802.9102
Design
400.801.8037.804.9903
Construction
400.801.8037.808.9102
Inspection
Total
Appropriations
Fund 100:
General Fund
Fund 203: Local
Transportation Fund
Fund 204: Transit
Total FY 98/99
Plus Prior Year Exp.
Total Project Costs
Less Revenue from CCB
Net Total City Project Costs
Slry98 cmp
0 0 0
301,509 (67,493) 234,016
44,331 (2,501) 41,830
345,840 (69,994) 275,846
0 5,034 5,034
345,840 (81,950) 263,890
0 6,922 6,922
345,840 (69,994) 275,846
66,348
342,194
(11,250)
330,994
Slurry Seal 1998: Completion
November 6, 1998
Page 7
RECODMMATIONS [Roll Call Vote]
Staff recommends that the City Council take the following
actions:
1. Adopt Resolution 98 - approving an amendment to the
FY 1998/99 Budget by revising the appropriation and budget
for the subject project as follows: General Fund [Fund
100]: $5,034 increase; Local Transportation Fund [Fund
203]: $81,950 decrease; and Transit Fund [Fund 204]:
$6,922 increase (net total decrease: $69,994);
2. Accept the work as completed;
3. Instruct the City Clerk to file the Notice of Completion
for the project; and,
4. Authorize the release of the retention upon satisfactory
clearance of the thirty five (35) day lien period.
Slry98 cmp
000,04
RESOLUTION NO. 98 -
A RESOLUTION OF THE CITY
OF MOORPARK, CALIFORNIA,
AMENDMENT TO THE FISCAL
BUDGET TO ADJUST THE FI
SLURRY SEAL PROJECT [FUN
FUND 1001
COUNCIL OF THE CITY
APPROVING A BUDGET
YEAR 1998/99 ADOPTED
JNDING FOR THE 1998
D 204, FUND 203 AND
WHEREAS, on June 17, 1998, the City Council adopted the Budget
for Fiscal Year 1998/99; and,
WHEREAS, a staff report has been presented to the City Council
requesting a budget amendment for a net reduction in the aggregate
amount of $69,994 ; and,
WHEREAS, Exhibit "A," attached hereto and made a part hereof,
describes said budget amendment and its resultant impacts to the
budget line item(s) and projected year end fund balance(s).
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK,
CALIFORNIA, DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. That an amendment to the FY 1998/99 Budget amount
for the 1998 Slurry Seal Project, as well as the appropriations for
said project, is hereby approved for a net reduction in the amount
of $69,994, as more particularly described in the aforesaid Exhibit
"A," is hereby approved.
PASSED AND ADOPTED this 18h day of November, 1998.
Patrick Hunter, Mayor
City of Moorpark, California
ATTESTED:
Deborah S. Traffenstedt, City Clerk
000'0
Resolution No. 98 -
Exhibit "A"
ADDITIONAL APPROPRIATIONS FOR
PROJECT 8037 (SLURRY SEAL)
FUND
ACCOUNT NUMBER
APPROPRIATION
TO ACCOUNT NUMBER
ACTUAL
EXPENDITURES
General Fund
REQUEST
$0
General Fund
100.000.0000.000.5100
$5,034.00
400.801.8037.000.3992
Reserve
$81,950
$(263,890)
Transit
Transit Fund
204.000.0000.000.5100
$6,922.00
400.801.8037.000.3992
Reserve
$301,509
$(345,840)
$69,994
TOTAL TRANSFERS
$11,956.00
FROM RESERVES:
$44,331
$(2,501)
$41,830
SUMMARY OF TRANSFERS IN / (OUT) BY FUND
FUND
ACCOUNT NUMBER
(All To Be Applied to
#400.801.8037.xxx.xxxx)
CURRENT
BUDGET
REQUESTED
CHANGED
ACTUAL
EXPENDITURES
General Fund
100.801.8037.000.9801
$0
$(5,034)
$(5,034)
LTF
203.801.8037.000.9801
$(345,840)
$81,950
$(263,890)
Transit
204.201.8037.000.9801
$0
$(6,922)
$(6,922)
Total
$301,509
$(345,840)
$69,994
$(275,846)
DISTRIBUTION OF APPROPRIATIONS TO EXPENSE ACCOUNT NUMBERS
ACCOUNT
CURRENT
SUBJECT
REVISED
NUMBER
APPROPRIATION
APPROPRIATION
APPROPRIATION
/ (REDUCTION)
400.801.8037.802.9102
$0
$0
$0
Design
400.801.8037.804.9903
$301,509
$(67,493)
$234,016
Construction
400.801.8037.808.9102
$44,331
$(2,501)
$41,830
TOTALS:
$3451840
$(69,994)
$275,846
c1o0�0t)