HomeMy WebLinkAboutAGENDA REPORT 1999 0721 CC REG ITEM 10DAGENDA REPORT
CITY OF MOORPARK
72.S. i r
ITEM 10• D.
CITY OF MOORPARK, CALIFORNIA
City Council Meeting
of 1 f -�)iGi q
ACTION:�'nV�?Ct 6'
mm6n c b bCn MI A ,
iii ♦.i� ;�.I�
TO: The Honorable City Council ;C��
FROM: Kenneth C. Gilbert, Director of Public Worksl
DATE: July 9, 1999 (Council Meeting 7- 21 -99)
SUBJECT: Consider Adding Landscape Improvements to the Design for
the Los Angeles East Improvement Project
OVERVIEW
This report discusses the cost impacts of adding landscaping to the
design for the approved block retaining walls, as well as adding
raised landscaped medians to the design for the proposed street
realignment and reconstruction.
BACKGROUND
On June 2, 1999, the City Council heard a presentation on a number
of alternative retaining wall designs for the project and directed
staff to proceed with the project design using a "Keystone" type
concrete block for the retaining walls to be constructed. At that
meeting questions were raised about the feasibility and cost of
adding landscaping to the wall design. Questions were also raised
about the feasibility and cost of adding a landscaped median to the
design for the proposed street improvements.
DISCUSSION
A. Retaining Walls
1. Construction Costs: At the June 2 meeting,. the City Council
was advised that the estimated cost for the construction of
the required retaining walls using the Keystone block
design, was approximately $875,000 (estimated square footage
of wall face: 30,000 s.f.) .
000020
L A East Project: Landscaping
July 9, 1999
Page 2
2. Landscaping: As mentioned above, the City Council asked that
staff prepare a full analysis of the cost impacts of
revising the wall design to include landscaping.
3. Additional Easement Width: No additional easement width will
be required if landscaping is added.
4. Landscaping / Irrigation - Design: The additional design
costs for adding landscaping to the wall design is
approximately $6,000. The final design for the wall
landscaping will be developed with assistance from the block
manufacturer. Design options range from scattered landscaped
bowls constructed into the wall, to landscaped terraced
shelves. Although drought tolerant plants will be used, it
will be necessary to install and maintain an irrigation
system, most likely a drip system.
5. Landscaping / Irrigation - Construction: The estimated added
construction costs for adding landscaping and irrigation to
the retaining wall design is estimated to be approximately
$75,000 [$2.50 x 30,000sf = $75,0001.
6. Annual Landscape Maintenance Costs: It is estimated that the
annual maintenance cost for the wall landscaping will be
approximately $5,000 [4000 LF x 1' wide = 4,000 sf x two
(2.5) rows = 10,000 sf $.025 /sf /mo = $250 /mo x 12 mos. _
$3,000, plus contingency plus extra costs = $5,000.1
7. Maintenance Requirements: Due to the height and location of
some of the landscaped areas, the project will very likely
require special equipment (ladders) and training (safety).
Although the full extent of such needs has not yet been
determined, the cost estimate noted above is believed to be
sufficient to fully fund such efforts.
8. Cost Summary (Walls only):
Plus Additional 5,000
Annual Maint.Costs
* ** Wall design is provided by the manufacturer for little
or no cost.
L A East4 LS
-- - 000021
Retaining
Wall Costs
($)
Current
Revised
Description
Estimate
Change
Estimate
Design
* **
6,000
* **
Construction
875,000
75,000
950,000
Inspection
60,000
5,000
65,000
Total
935,000
86,000
1,015,000
Plus Additional 5,000
Annual Maint.Costs
* ** Wall design is provided by the manufacturer for little
or no cost.
L A East4 LS
-- - 000021
L A East Project: Landscaping
July 9, 1999
Page 3
B. Median
1. Background: Some time ago the City Council approved the
alignment and conceptual design for the re- alignment and
widening of the subject segment of Los Angeles Avenue
[East] . The scope of work for that project included the
addition of pavement width to accommodate two twelve feet
(121) wide travel lanes, one fourteen feet (141) wide paved
center median, eight feet (81) of pavement beyond the side
line in each direction for pedestrians and bicycles and
gravel shoulders. Said improvements were to be constructed
within an eighty -eight feet (881) right -of -way - a corridor
wide enough to accommodate two lanes in each direction
should future needs require.
2. Landscaping: As mentioned above, the City Council recently
asked that staff prepare a full analysis of the cost impacts
of revising the design to include a raised and landscaped
center median.
3. Design Centerline: In order to lower costs, the design
centerline for the above described street improvements does
not coincide with the centerline of the ultimate eighty -
eight feet (881) right -of -way. The present design attempts
to lower costs by maximizing the use of the existing
roadbed. When and if the street were ever to be widened to
two lanes in each direction, at that time the centerline for
the street improvements would have been relocated to the
centerline for the street right -of -way.
4. Changed Centerline: If it is decided that the raised center
medians should be constructed with the initial street
improvements, it is recommended that the design be amended
to relocate the center line of the improvements to the
centerline of the street right -of -way. This change is
recommended in order to avoid the cost of the removal and
reconstruction of the raised medians at a later date when
and if the street is widened to four lanes. The added cost
for this change is summarized as follows:
• Design: $ 14,000
• Construction $197,000
• Inspection $ 0
$211,000
L_A_East4_LS
000022
L A East Project: Landscaping
July 9, 1999
Page 4
5. Hardscape Improvements: The estimated cost of constructing
the raised medians (median hardscape only) is as follows:
• Design: $ 7,000
• Construction
Median Hardscape $150,000
Less Pavement ($ 88,000)
Net Construction Costs $ 62,000
• Inspection $ 15,000
$ 84,000
6. Landscaping / Irrigation: The estimated cost of the median
landscaping is as follows:
• Design: $ 6,000
• Construction $ 75,000
• Inspection $ 5,000
$ 86,000
7. Annual Landscape Maintenance Costs: It is estimated that the
annual maintenance cost for the wall landscaping will be
approximately $12,000 [30,000 SF x $.025 /sf /mo = $750 /mo x
12 mos. = $9,000, plus contingency = $12,000.1
8. Cost Summary (Medians only): The total cost impact of adding
raised center medians to the proposed street improvements is
summarized as follows:
Median
Description
Costs
Realign Street
$211,000
Median Hardscape
$ 84,000
Median Landscape
$ 86,000
Sub -Total
$381,000
Plus Annual Median $ 12,000
Landscape Maint.
Costs
C. Cost Summary: Landscaped Wall & Median
The cost of adding landscaping to the wall and adding a center
landscaped median is summarized as follows:
Wall
Description Landscaping Median Total
Project Costs $86,000 $381,000 $467,000
Plus Annual $ 5,000 $ 12,000 $ 17,000
Maint.Costs
L A —East4 LS �7
000023
L A East Project: Landscaping
July 9, 1999
Page 5
D. Cost Summary: Total Project
Total estimated project costs are summarized as follows:
Description
Design
Right -of -Way
Constr: Street
Constr: Walls
Inspection
Sub -total
Subject Changes
Wall L/S
Medians
Sub -Total
Current
Estimate
$ 203,000
$1,790,000
$1,409,000
$ 862,000
$ 204,000
$4,468,000
Subj ect
Changes
A
B
C
D
E
0
Revised
Estimate
$4,468,000
$ 86,000 $ 86,000
$374,000 $ 374,000
$381,000 $ 381,000
Total $4,468,000 $381,000 $4,849,000
Plus Added Annual Maintenance Costs as noted above.
Notes: A. Design costs included in total costs noted below.
B. No additional easements or right -of -way required.
C. Cost changes included median costs noted below.
D. Wall costs without landscaping.
E. Added Inspection costs included in costs noted below.
E. Funding for Landscape Maintenance Costs
If approved for construction, either of the two above described
landscaped areas would be funded by the Citywide landscape
assessment levied by Assessment District AD84 -2. For the
immediate future, it appears that projected assessment revenues
are sufficient to fund these additional costs. However, it
should be noted that at some point in the future, as more areas
are added and /or the cost of maintaining existing facilities
increase, Citywide maintenance costs may exceed assessment
revenues. At that time the City would have to consider providing
funding from other sources and /or consider a Citywide Mail
Ballot for the approval of an increase to the assessment.
F. Summary
It is the view of staff that the added costs (see Section C) --
especially the annual maintenance costs -- of integrating
landscaping into the design for the retaining walls, would be
justified by the improved aesthetics of this option. However,
due to the rather significant cost of re- designing the street
improvements plans - and the significantly higher annual
maintenance costs - it is not recommended that the project
include landscaped medians.
L_A_East4_LS 000024
L A East Project: Landscaping
July 9, 1999
Page 6
STAFF RECOMMENDATION
Staff recommends that the City Council take the following actions:
1. Direct staff to add landscaping to the retaining wall design.
2. Direct staff to not revise the current design for the proposed
street improvements.
L_A_East4_LS
000025