HomeMy WebLinkAboutAGENDA REPORT 1999 0818 CC REG ITEM 11LTo:
From:
Date:
CITY OF MOORPARK
AGENDA REPORT
The Honorable City Council
ITEM // • /- •
CITY OF MOORPARK, CALIFORNIA
City Council Meeting
oil i qq
ACTION: 1)L2 J 4 02Ca I UM
Kenneth C. Gilbert, Director of Public Works
August 6, 1999 (Council Meeting 8- 18 -99)
M11
Subject: CONSIDER RESOLUTION NO. 99- AMENDING THE FY
1999/2000 BUDGET TO ADD A PROJECT FOR THE
CONSTRUCTION OF PAVEMENT REHABILITATION AND RELATED
WORK ON LOS ANGELES AVENUE BETWEEN SPRING ROAD AND
THE ROUTE 118 FREEWAY
OVERVIEW
This requests
rehabilitation
east and west
approval of
and drainage
of the Los
improvement project (see map
a project to construct pavement
improvements on Los Angeles Avenue
Angeles Avenue East widening and
attached as Exhibit 1).
DISCUSSION
A. Los Angeles Avenue East Widening Project
The City is in the process of developing the final design for
a project to widen Los Angeles Avenue from a point east of
Spring Road, easterly to Condor Drive (see Exhibit 1). The
scope of the project includes the acquisition of additional
street right -of -way. It is anticipated that the project design
and right -of -way acquisition for this project will be
completed in approximately two years.
B. Highway Relinquishment
Two recently executed Agreements between the City and Caltrans
provide for the relinquishment to the City of those portions
of Spring Road and Los Angeles Avenue which used to serve as
the alignment of Route 118 prior to the construction of the
Freeway Connector Project. One pre- requisite of relinquishment
is the upgrading of the condition of the roadway to a minimum
L_A_rehabl 0004%"J- S
Los Angeles Avenue Rehabilitation Project
August 6, 1999
Page 2
ten -year life. Caltrans has or will meet that condition in the
following manner:
• The Spring Road Relinquishment Agreement provides for
Caltrans funding of a future City project to construct
pavement rehabilitation and related street improvements on
this street segment. The estimated cost of that project is
$530,000, with Caltrans funding not to exceed $750,000.
Payment to the City will be made when the City advertises
for receipt of bids for this construction project (discussed
below) .
• The Los Angeles Avenue relinquishment Agreement has Caltrans
paying the City $1,116,000 in -lieu of constructing any
improvements. This option was selected because of the
expected delay in constructing the Los Angeles Avenue East
Widening and Reconstruction Project. Caltrans payment of
this sum is expected within two months.
C. Spring Road Rehabilitation
The FY 1999/2000 Budget includes Project 8021 providing for
the construction of pavement rehabilitation and related street
improvements on Spring Road between New Los Angeles Avenue and
High Street. It is the intent of staff to proceed in the very
near future with the design and construction of that project.
As stated above, costs for this project will be reimbursed by
Caltrans.
D. Subject Los Angeles Avenue Rehabilitation Project
The subject project consists of two components generally
described as follows:
• The construction of a storm drain to correct a drainage
problem on the south side of the street at the concrete
batch plant; and,
• The construction of an asphalt overlay east and west of
the future Los Angeles Avenue East Widening Project.
A more detailed description of the two elements of the subject
projects is as follows:
1• Storm Drain: The curb outlet on the south side of the
street at the concrete batch plant, is connected to a
concrete "V- ditch" which runs easterly to Ventura County
Flood Control District (VCFCD) box culvert. In that the
"V- ditch" does not function, the street floods. It was
mutually agreed by the City and Caltrans, to include in
the cost of rehabilitation, the construction of a new
storm drain pipe to replace the "V- ditch." It is
recommended that the City proceed immediately with the
design and construction of this storm drain.
0004E�9
L_A_rehabl
Los Angeles Avenue Rehabilitation Project
August 6, 1999
Page 3
2. Asphalt Overlay: Pavement east and west of the future Los
Angeles Avenue East Widening Project is in very poor
condition. It is recommended that the City not wait to
rehabilitate this pavement with the future widening
project. It is recommended that this rehab work be done as
a part of the Spring Road rehabilitation project. Rehab
costs for each of these street segments will be segregated
for cost accounting purposes [Projects 8021 and 80241. The
project may also include work other than pavement
rehabilitation required in order to address other
deficiencies identified in the pre - relinquishment needs
survey.
3. Project Cost Estimate: It is recommended that the City
proceed immediately with the preparation of designs for
the Storm Drain project and the A/C Overlay project. It is
recommended that those design costs plus the storm drain
construction and inspection costs (Phase 1) be funded at
this time. The total estimated cost is as follows:
Element
Storm
A/C
Drain ($) Overlay ($) Total ($)
Phase 1:
Design
8,000
12,000
20,000
Construction
70,000
70,000
Inspection
10,000
10,000
Sub -Total
88,000
12,000
100,000
Phase 2
Construction
Est.
200,000
200,000
Inspection
18,000
18,000
Sub -Total
218,000
218,000
Total
88,000
230,000
318,000
4. Funding: As discussed
above, within
two months
it is
anticipated that Caltrans will pay the City the $1,116,000
required by the Los Angeles Avenue Relinquishment
Agreement. Those funds will be deposited into the Los
Angeles Avenue AOC Fund. It is recommended that the
subject project be funded by a portion of these monies.
5. Budget Amendment: The attached Resolution amends the
Budget to fund the subject project. The funds requested at
this time are sufficient to fund the Storm Drain project,
plus the design for the A/C Overlay project.
RECOMMENDATION (Roll Call Vote)
Staff recommends that the City Council take the following actions:
1. Adopt Resolution No. 99- amending the FY 1999/00
Budget to fund the subject project.
2. Direct staff to proceed with the design for both Phase 1
and Phase 2 improvements, as described in this report.
Attachments:
0004;
L A_rehabl
' I • Cr 2 CY)
j_ J • o
• Y
30NIad '
.•N ` •
a �
• •
N •
c+l •
•
•
•
•
1 •
•
•
•
•
Cn
Legend s
d
O
NL.A. East Project
■M M IL.A. Rehabilitation Project
mmkm Storm Drain
oo04GI
Cr
■
z ..o. ....•• •'
<
A
I
• '•
0 0
M
N
a ••
ti
v
o •
■
-.
■
RESOLUTION NO. 99 -
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
MOORPARK, CALIFORNIA, AMENDING THE FY 1999/2000
BUDGET BY ADDING PROJECT 8024 TO PROVIDE FOR THE
CONSTRUCTION OF PAVEMENT REHABILITATION AND RELATED
IMPROVEMENTS ON LOS ANGELES AVENUE BETWEEN SPRING
ROAD AND THE ROUTE 118 FREEWAY [REF. LOS ANGELES
AVENUE AOC FUND]
WHEREAS, on June 23, 1999, the City Council adopted the
Budget for Fiscal Year 1999/00; and
WHEREAS, a staff report has been presented to the City
Council requesting a budget increase in the aggregate amount of
$100,000; and
WHEREAS, Exhibit "A," attached hereto and made a part hereof,
describes said budget amendment and its resultant impacts to the
budget line item(s).
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK DOES
HEREBY RESOLVE AS FOLLOWS:
SECTION 1. That a Budget amendment is hereby approved to
allocate $100,000 from the Los Angeles Avenue AOC Reserve Fund and
appropriate said amount for the Los Angeles Avenue Rehabilitation
Project, as more particularly described in Exhibit "A" attached
hereto and made a part hereof.
SECTION 2. The City Clerk shall certify to the adoption of
this resolution and shall cause a certified resolution to be filed
in the book of original resolutions.
PASSED AND ADOPTED this 18th day of August, 1999.
Patrick Hunter, Mayor
ATTEST:
Deborah S. Traffenstedt, City Clerk
Attachments:
Exhibit 'A': Appropriation and Budget Detail
0004G:�,
Resolution No. 99-
EXHIBIT A
Budget Revision
A. Fund Allocation:
Fund No. Fund Name Amount
2501 Los Angeles Avenue AOC $100,000
B. Budget Appropriation:
Los Anaeles Aupmia
_..--
BUDGET NUMBER
---- ---- - --...-
BUDGETED
REVISION
NEW BUDGET
2501.8310.8024.9601:
$0
$20,000
$20,000
Design
2501.8310.8024.9640:
$0
$70,000
$70,000
Construction
2501.8310.8024.9650:
$0
$10,000
$10,000
Inspection
Total
$0
$100,000
$100,000
Approved to Form:'
0004;3