HomeMy WebLinkAboutAGENDA REPORT 1999 0915 CC REG ITEM 10CTo.
From
City of Moorpark
Agenda Report
- 725. 1q �
ITEM /0-
c .
CITY OF MOORPARK, CALIFORNIA
City Council Meeting
of t � l D;';Pi►']be //3 19�
ACTION:_�IYP,f.'lP
BY: Ja
The Honorable City Council
Kenneth C. Gilbert, Director of Public Works
Date: September 3,1999 (Council Meeting 9- 15 -99)
Subject: Spring Road Bridge Reconstruction Status Report
017F.RVTRW
This is in response to a request from the City Council for a report
on the history and status of the Spring Road Bridge Reconstruction
Project, to include a more in depth discussion of the following:
• Project History;
• Bidding Procedures; and
• Schedule Recovery Plan.
DISCUSSION
A. Project History
Attached as Exhibit 1 is a chronological summary of key actions
or benchmarks pertaining to the subject project.
B. Bidding Procedures
Questions have been raised about the qualifications of the
contractor and the selection process used by the City to select
that contractor. As the City Council is aware, the selection of
a contractor for any major public works project must be done in
accordance with the requirements of the Public Contracts Code of
the State of California. That Code requires that all major
projects be competitively bid and that the contract be awarded
to the lowest responsible bidder.
A responsible bidder is a bidder who: 1) has adequately
responded to all of the requirements set forth in the bid
documents [Responsive]; and 2) has been found to be qualified to
000291
Spring Road Bridge Replacement Project
September 3, 1999
Page 2
satisfactorily perform the required work [Qualified]. A
discussion of these two attributes is as follows:
• Responsive: It was determined by the City that the apparent
low bidder for the subject project (Sedcon) was not
responsive to the requirements of the bid documents. That
finding was made based upon a determination that said
contractor failed to comply with requirements relating to the
use of sub - contractors and /or suppliers who were registered
Disadvantaged Business Enterprises (DBE) . The bid from that
firm was rejected and the contract was awarded to the then
lowest responsible bidder, T M Engineering.
Qualified: Generally, any contractor is deemed to be
qualified to perform the required work if he possesses the
Contractor's License required for the type of work specified.
An agency is precluded from awarding a contract to a bidder
it believes is "more qualified." Again, any contractor who
can "satisfactorily" perform the work is deemed [by law] to
be qualified. In order for an agency to reject a bidder
because he is not qualified, that agency must state the
reasons for such a finding and allow the contractor an
opportunity to rebut those reasons. Typically, the only time
an agency is successful in rejecting a bidder on this basis
is when that agency has found evidence that the rejected
bidder failed to undertake and complete a prior contract
(most likely with another agency) in a satisfactory manner.
That is, the past performance was unsatisfactory. To be
successful the evidence of prior unsatisfactory performance
should be substantial.
From the references and other information provided in the bid
documents submitted by the selected contractor, staff found
no evidence of any prior unsatisfactory performance.
C. Recovery Plan
1. Problems: The contractor has encountered a number of problems
which have caused him to fall behind schedule. Those problems
include, but are not limited to the following:
a. delay in ordering, fabricating and driving indicator (test)
piles to confirm design for the depth of pile tips;
b. difficulty in driving piles to specified depth;
c. turn over of personnel (five superintendents to date);
d. numerous questions and /or requests for design changes to
address perceived "problems" asserted by contractor [The
remedies for most of those "problems" were in the
specifications. The Contractor chose to debate the problems
and /or specified solutions instead of implementing the
solutions provided in the specs.];
Spgbrg1S_hist 000292
Spring Road Bridge Replacement Project
September 3, 1999
Page 3
e. failure of water diversion facilities which led to flooding
of the work site;
f. damage to existing utilities [including telephone conduit
and overhead power line]; and
g. lapses in organization and control of the work site, sub-
contractors and suppliers.
2. Schedule: As discussed above, the contractor is approximately
three months behind schedule. Of particular concern to both
the Contractor and the City is the need for the contractor to
vacate the river bottom before the winter wet season. To that
end the Contractor recently developed a "Recovery Plan," a
copy of which is attached as Exhibit 2.
The attached Recovery Plan calls for the completion of the
construction of the bridge deck and the removal of the
falsework from the arroyo by the end of the first week of
December. This is a very ambitious schedule. In order to meet
this schedule, it will be necessary for the contractor to
assemble and deploy all of the resources (materials, supplies,
equipment and manpower) required to construct the project, in
a very concentrated and organized manner. In an effort to
facilitate those efforts, the City has granted the contractor
permission to:
• start work at 6:30 a.m.;
• work past the 7:00 p.m. deadline when necessary (provided
work does not extend past 10:oo p.m.);
• work on Saturdays and, in rare cases, Sunday if necessary).
It is the view of staff that the Contractor is about one week
behind the schedule outlined in the attached Recovery Plan.
Staff is advised that it is the intent of the contractor to
catch -up and be in position to commence construction of the
bridge deck falsework before the end of September.
It is the intent of staff to continue to monitor the efforts
of the contractor to meet the schedule called for by the
Recovery Plan.
RECOMMENDATIONS
Receive and file report.
Spgbrg15_hist 000253
Exhibit 1: Project History
September 3, 1999
Page 1
The following is a chronological summary of the more significant
milestones associated with the development and implementation of
the Spring Road Bridge Replacement Project
Date Action By: Description
04/02/92 City Council Authorize feasibility study of
possible bridge improvement project
12/15/93 City Council Approve bridge rehabilitation project
02/16/94 City Council Approve change from bridge widening
project to bridge replacement project
07/06 -94 City Council Approve Request for Proposals
07 -08/94 Staff Distribute RFP, review proposals from
several firms, conduct interviews,
evaluate and recommend selection
09/21/94 City Council Approve selection of DF&A (CAA) to
06/25/97 Staff
09/ - -/97 Staff
10/01/97 Staff
10/ - -/97
Spgbrg15_hist
Staff
Prepare report to City Council on
implementation schedule
Work with VCFCD on the design for the
Bike Path
Submit applications for permits from
Fish & Game, Water Quality Control
Board, etc.
Work with Ventura County Waterworks
Dist. #1 on utility relocation needs
and temporary sewer line
000204
prepare the design
06/21/95
City Council
Approve change to width of
bridge
06/01/95
Staff
Submit application for a
federal
grant for partial funding
07/19/95
City Council
Approve conceptual design
(alignment,
width, etc.)
03/19/97
City Council
Approve additional design
efforts /
costs
04/16/97
City Council
Adopt Resolution approving
Mitigated
Declaration for Project
06/25/97 Staff
09/ - -/97 Staff
10/01/97 Staff
10/ - -/97
Spgbrg15_hist
Staff
Prepare report to City Council on
implementation schedule
Work with VCFCD on the design for the
Bike Path
Submit applications for permits from
Fish & Game, Water Quality Control
Board, etc.
Work with Ventura County Waterworks
Dist. #1 on utility relocation needs
and temporary sewer line
000204
Exhibit 1: Project History
September 3, 1999
Page 2
Date Action By: Description
11/ - -/97 Staff Work with property owner northwest of
the bridge to obtain construction
easement
12/17/97 City Council Approve agreement with Pacific
Telephone to allow bridge construction
within Telephone easement
01/07/98 City Council Authorize advertise for bids
03/04/98
City
Council
Approve Agreement with State Fish &
Game Department
05/06/98
City
Council
Approve Supplemental
Agreement with
Caltrans re: Federal
grant
06/03/98
City
Council
Reject bids, request
information on
possible re- design
08/19/08
City
Council
Receive report on possible re- design,
approve project with
no re- design
08/26/98 Staff Follow -up Memo provided to the City
Council explaining that the project
was delayed in June 1996 due to
concerns over weather and traffic -
not re- design
11/04/98 City Council Approve revised Plans and authorize
re- advertising the project
O1/ - -/99 Staff & City Review bids, develop recommendation to
Attorney reject bid from apparent low bidder
for failure to comply with MBE
requirements
01/11/99 Carlsberg Spring Road closed to facilitate
roadway improvements south of the
bridge
02/03/99 City Council Award contract
03/18/99 Staff Issued Notice to Proceed: Contract
Time starts, first day road closure
required for bridge project
Sp9brg15_hist 0 0 O c 5 5
Exhibit 1: Project History
September 3, 1999
Page 3
Date Action By:
04/ - -/99 Contractor
05/01/99
06/14/99
Spgbrg15_hist
Contractor
Contractor
Description
Clearing Channel; construct box
culvert northwest of the bridge
Excavation for piles
First Test Pile driven: contractor
behind schedule
000250