Loading...
HomeMy WebLinkAboutAGENDA REPORT 2000 0105 CC REG ITEM 11HCity of Moorpark Agenda Report To: The Honorable City Council From: Kenneth C. Gilbert, Director of Public ITEM /I• /f _o CITY OF 1.10ORPARK, C:ALIF01UNIA City Council NTeefing of 15 0 BY: ✓ Works 7l Date: December 10, 1999 (Council Meeting 1 -5 -2000) Subject: Consider Notice of Completion for the Miscellaneous Curb, Gutter and Sidewalk Construction Project DISCUSSION A. Background On August 18, 1999, the City Council authorized staff to advertise for receipt of bids for the subject project. On October 6, 1999, the City Council awarded the construction contract for the project. B. Project Scope The location of each concrete repair or construction site is identified on the map attached as Exhibit 1. A general description of the scope of work to be performed at each of those sites is attached as Exhibit 2. C. Project Completion The project has been completed and it is now appropriate for the City Council to accept the improvements and approve the Notice of Completion. D. Fiscal Impact 1. Construction Contract Summary: A summary of the final construction contract costs is as follows: Bid Price Quantity Adjustment Sub -Total Change Orders Amount $ 61,830.75 (929.25) 60,901.50 3,713.00 Total 64,614.50 Conc99_cmp 000323 Miscellaneous Concrete: Complete December 10, 1999 Page 2 2. Change Orders: Project Change Orders are listed as follows: No. Description Amount ($) 1 Rebar: Reinforcing steel bars in slab at Public 0 the various elements of the Works Yard [no extra cost]. contract, is as 2 Harvard St.: Mobilization costs only for work 223.00 Fund 2602 related to the removal and replacement of curb 2903 Total Code / Street Gen. Fund SE-821 and gutter at 6516 Harvard Street. Other costs Gas Tax ($) MRA ($) A related to this work [totally $4011 were paid via an adjustment to final quantities. B 3 Spring Road: Mobilization and related costs for 623.00 changes to the driveway at 555 Spring Road. Poppyglen Other costs related to this work [$709] were 100% D paid via an adjustment to final quantities. 4 Poindexter Drain: Costs related to installation 2,617.00 Vista Del Valle of drain line per a revised design (the original design was not constructed). These Sosna Ct. costs were more than offset by the deletion of K the bid item [$2,850] for the original design. The net savings was $233. L 5 Mobilization: Mobilization required for re -saw 250.00 cutting on Dorothy Avenue. Other costs were Tierra Rejada 45% paid via an adjustment to final quantities. 100% G Total 3,713.00 3. Total Project Costs: A summary of total estimated project costs incurred by both the MUSD and the City is as follows: Element Estimated Costs ($) Design 12,066 Construction 64,615 Inspection ** 7,300 Total 83,981 ** Total Not to Exceed figure. Actual final costs to be less. 4. Funding Source Breakdown: A summary of the funding sources for the various elements of the subject contract, is as follows: Fund 1000 Fund 2602 Fund 2605 Fund 2903 Total Code / Street Gen. Fund SE-821 ($) Gas Tax ($) MRA ($) A Dorothy B McFadden C Poppyglen 100% 100% D Spring Road E Vista Del Valle J Sosna Ct. K Collins /Hearon L Harvard F Tierra Rejada 45% 55% 100% G City Hall 100% 100% H Public Wks Yard 50% 50% 100% I Poindexter Drain 100% 100% conc99_cmp 000329 j @@a�te j Tye Miscellaneous Concrete: Complete December 10, 1999 Page 3 5. Final Construction Cost Allocation: A breakdown of the final construction costs by funding source is as follows: Funding Source 1000 General Fund 2602 TDA Article 3 2605 Gas Tax Sub -Total City 2903 MRA Total Percent of Total Total Cost ($) 7.0% 4,497.00 13.7% 8,853.64 75.3% 48,646.86 61,997.50 4.0% 2,617.00 100% 64,614.50 6. Total Project Funding Allocation: A breakdown of the total final funding for the project is as follows: 7. TDA Article 3 (SB -821): A Bicycle / Pedestrian Facilities grant, in the amount of $18,000, funded a portion of the costs for the sidewalk and related improvements constructed on the south side of Tierra Rejada Road just west of Spring Road. The actual total cost of those improvements was $11,507. The surplus grant monies will be carried over to a future TDA Article 3 grant project. If the City is not a recipient of such a grant in the next cycle, the monies will be credited toward a future SB -821 grant project. 8. Budget: A summary of the approved budget for the subject project is as follows: Budget Fund Amount ($) 1000: Gen. Fund 6,700 Design Constr. Inspection Total Funding Sources 2605: #9601 ($) #9640 ($) #9650 ($) ($) 1000 General Fund 7.0 845 4,497 511 5,853 2602 TDA Article 3 13.7 1,653 8,854 1,000 11,507 2605 Gas Tax 75.3 9,086 48,647 5,497 63,230 Sub -Total City 11,584 61,998 7,008 80,590 2903 MRA 4.0 482 2,617 292 3,391 Total 12,066 64,615 7,300 83,981 7. TDA Article 3 (SB -821): A Bicycle / Pedestrian Facilities grant, in the amount of $18,000, funded a portion of the costs for the sidewalk and related improvements constructed on the south side of Tierra Rejada Road just west of Spring Road. The actual total cost of those improvements was $11,507. The surplus grant monies will be carried over to a future TDA Article 3 grant project. If the City is not a recipient of such a grant in the next cycle, the monies will be credited toward a future SB -821 grant project. 8. Budget: A summary of the approved budget for the subject project is as follows: Budget Fund Amount ($) 1000: Gen. Fund 6,700 2602: SB- 821 18,000 2605: Gas Tax 70,000 Total City 94,700 Actual costs do not 2903: MRA (Project 8008) 50,000 exceed Budget amount. Total 144,700 Conc99_cmp 000330 Miscellaneous Concrete: Complete December 10, 1999 Page 4 STAFF RECOMMENDATIONS Staff recommends that the City Council take the following actions: 1. Accept the work as completed; 2. Instruct the City Clerk to record the Notice of Completion for the project; and, 3. Authorize the release of the retention upon satisfactory clearance of the thirty five (35) day lien period. 003 3:1 Conc99_cmp 0 0 0 C4 U N CITY OF MOORPARK u Exhibit 2: Project Description Page 1 of 2 A general description of the scope of work for the subject project is as follows: A. Dorothy Avenue: Removal and reconstruction of the curb and gutter (northwest side of the street) at the "knuckle" at the intersection of Dorothy Avenue and Millard Street to correct a poor drainage condition at this location. B. McFadden Avenue: Removal and reconstruction of the curb and gutter at the south end of McFadden Avenue to improve drainage. The work will include the construction of a ribbon gutter connecting the gutter on the street to a grate inlet in the alley just west of McFadden Avenue. C. Poppyglen Court: Re- construction of a portion of a driveway apron on the south side of the street near the end of Poppyglen Court. This work is being done to replace temporary asphalt installed when the subsided driveway was recently removed by City crews. D. Spring Road (South of Railroad) : Replacemei and driveways with concrete improvements Spring Road just south of the railroad. project, it is the intent of staff to construct concrete sidewalks on both sides the railroad crossing.] it of asphalt sidewalk on the west side of [Note: As a future pursue a project to of Spring Road across E. Vista Del Valle: Reconstruction of the curb and gutter on the west side of Vista Del Valle from a point just north of Vista Lavana Drive northerly to a point just north of Bonita Heights Street (approximately 3301), to correct drainage problems in this area. F. Tierra Rejada Road: Construction of a new curb, gutter and sidewalk on the south side of Tierra Rejada Road from Spring Road westerly to join with an existing sidewalk approximately five hundred feet (5001) to the west. This work is partially funded by an TDA Article 3 (SB -821) grant. G. City Hall: Construction of a handicap ramp at the walkway leading to the City Council Conference Room. This work is being done to improve handicap accessibility. Conc99_cmp 000333 Exhibit 2: Project Description Page 2 of 2 H. Public Works Yard: Re- construction of the concrete driveway and parking area in front of the Public Works Maintenance Yard. This work will include concrete surface along the south side of the building to improve the drainage and maintenance of this barricade and sign storage area. I. Poindexter outlet: The construction of a secondary outlet at the Catch basin on the south side of Poindexter Avenue just east of the rail spur crossing. The purpose of this work is to prevent flooding in the street when the "private" drain serving this catch basin does not function properly. The City possesses a flowage easement to allow water from the street to be conveyed to the adjacent industrial property. J. Driveway Apron on Sosna Court: Re- construction of the subsided driveway apron at 15286 Sosna Court. K. Curb at the Southwest Corner of Collins Drive and Hearon Drive: Reconstruct the curb (curb only - spandrel to remain) at the southwest corner of the intersection. L. Curb on Harvard: Reconstruct of the curb and gutter at 6516 Harvard Street. Conc99_cmp 000334