TO: The Honorable City Council
FROM: Mary K. Lindley, Director of Community Services yt,
DATE: March 22, 2000 (CC Meeting of April 5, 2000)
SUBJECT: CONSIDER AUTHORIZING RECORDATION OF THE NOTICE OF
COMPLETION FOR THE CONSTRUCTION OF THE SENIOR
CENTER EXPANSION PROJECT
BACKGROUND
The total approved budget for design and construction of
the Senior Center Expansion Project, including ADA
enhancements to the Community Center, was $520,000. Of the
budgeted amount, all but $9,500 was funded by CDBG. The
$9,500 represents a General Fund expenditure for design
work for potential seismic retrofit work for the Citrus
Room, which the City Council later opted not to construct.
On October 20, 1999, the City
contract to Robert W. Stanhope
$360,964. Construction of the pi
pursuant to the approved plans
"minor punch" list items. There
Orders, summarized as follows:
awarded the construction
Company for a cost of
=oject has been completed
and specifications, less
were two project Change
Change Order ##1 (Cost - Add $2,329.71): Added a water line
shut -off valve, and rerouted electrical and water lines to
clear the Glue Lam Beam.
Change Order #2 (Cost - Add $5,147.90): Provided for
additional overexcavation and recompaction as a result of
the soils testing recommendations. Also added a door
between the Citrus Room and new room addition.
000,.9:
M: \MLindley \SENIORS \Sr. Center Notice of Completion.doc
Senior Center Notice of Completion
Page 2
Total Change Orders: $7,477.61
At the conclusion of the construction work, the total cost
of the construction contract awarded to Stanhope Company,
including the aforementioned Change Orders is $368,441.61.
With the Council's authorization to record the Notice of
Completion, the contractor will receive the balance of
payment due 35 days after the recordation and fulfillment
of all contractual obligations as determined by the City.
Additionally, the City Manager will be authorized to
release the project bonds after one year and in accordance
with the contract provisions.
In addition to construction, the Senior Center Expansion
project entailed design and construction plans, plan check
and building inspection, soils tests, project management,
and CDBG management and monitoring. The total estimated
final project cost, including all outstanding items and the
previously identified Change Orders, is approximately
$495,000, which is $25,000 under budget. Unrelated to
Stanhope's contract, staff is still completing the
replacement of the air conditioning unit over the Senior
Center kitchen, installation of the modular walls, and
replacement of the drinking fountain in the Senior Center.
The Council will be provided with a final cost report when
all outstanding work has been completed.
STAFF RECOMMENDATION
Staff recommends that the City Council:
1. Accept the work as complete;
2. Authorize the City Clerk to file the Notice of
Completion for the project;
3. Authorize the release of the balance of payment due
upon satisfactory clearance of the thirty -five (35) days
after Notice of Completion records and completion of close
out contractual obligations of contractor; and
4. Authorize the City Manager to release project bonds in
accordance with the contract provisions.