HomeMy WebLinkAboutAGENDA REPORT 2001 1107 CC REG ITEM 09C ITEM
kU JA
of
ACT,:i7'�
MOORPARK CITY COUNCZ !
AGENDA REPORT
TO: The Honorable City Council
FROM: Kenneth C. Gilbert, Director of Public Works
DATE: October 22 , 2001 (Council Meeting 11-7-01)
SUBJECT: Consider Mitigated Negative Declaration / Environmental
Assessment for the Los Angeles Avenue Widening Project :
Spring Road to Moorpark Avenue [Project 80131
OVERVIEW
This presents for approval , at a public hearing, the Mitigated
Negative Declaration / Environmental Assessment for a project to
realign and widen Los Angeles Avenue from Moorpark Avenue easterly
to a point just east of Spring Road.
DISCUSSION
A. Background
1 . In August of 2000, the City Council approved the selection
of a consultant [Boyle Engineering] to prepare the design
for the subject project .
2 . In May of 2001, the City Council approved the conceptual
design for the project .
B. Project Scope & Description
Attached as Exhibit 1 is a description of the purpose and scope
of the project .
C. Mitigated Negative Declaration
A copy of the subject draft environmental document has been
provided to the City Council under separate copy.
LA_Spg_Mpk_negdec
Los Angeles Avenue Widening - Spring Road to Moorpark Avenue
Negative Declaration
October 22 , 2001
Page 2
D. Future Efforts
When Caltrans approval of the conceptual design is obtained,
the design consultant and/or City staff will proceed with
project implementation, which will include the following:
1 . Right-of-Way Legal Descriptions: The design consultant will
proceed with the preparation of legal descriptions for the
right-of-way parcels to be acquired.
2 . Preparation of Final Draft Design Plans and Specifications:
The design consultant will proceed with the preparation of
the final draft plans and specifications for the project .
3 . Utility Coordination / Relocation : The design consultant
and City staff will work with all affected utilities to
accomplish any needed utility relocations .
4 . Right-of-Way Acquisition: Staff will retain the services of
a consultant to assist City staff in the acquisition of the
required street rights-of-way. All of the acquired rights-
of-way will eventually be conveyed to Caltrans .
5 . Caltrans Permit: Staff will seek and obtain a Caltrans
Encroachment Permit for the project .
6 . Construction: When all of the above tasks have been
completed, the City will be in a position to advertise for
the receipt of bids for the construction of the project .
The City Council will be asked to approve the project plans
and authorize staff to advertise for bids .
E. Schedule
The estimated project schedule is as follows :
Description Start Complete
Caltrans Conceptual Approval In work 12 01
Plans and Specifications In Work 03/02
Right-of-way Acquisition 04/02 12/02
Final Caltrans Approval 09/02 12/02
Advertise for Receipt of bids 01/03 -- -
LA_Spg_Mpk_NegDec
Los Angeles Avenue Widening - Spring Road to Moorpark Avenue
Negative Declaration
October 22, 2001
Page 3
F. Public Review Period
The subject document was sent to the State Clearinghouse on
October 15, 2001 . The public review period will thus end on
November 15, 2001, subject to receipt of final comment closure
confirmation by the State Clearinghouse. It is recommended,
therefore, that action to certify the document be deferred to
the City Council meeting of December 5, 2001 .
G. Public Hearing
A notice of this public hearing was published on October 5,
2001 . On November 7, 2001, it would be appropriate to open the
pubic hearing, receive any public comment and then close the
public hearing.
STAFF RECOMMENDATION
Continue to December 5, 2001 .
Attachments :
Exhibit 1 : Project Description
LA_Spg_Mpk_NegDec ^.j�;{
Exhibit 1
Project Description
October 22, 2001
Page 1
A. General Project Scope
1 . Purpose: The purpose of the project is to widen Los Angeles
Avenue between Spring Road and Moorpark Avenue to
accommodate six (6) lanes of traffic .
2 . Project Limits : The limits of the project extend from
Moorpark Avenue easterly to a point approximately five
hundred feet (500' ) east of Spring Road. The total length
of the project is approximately 2300 feet .
3 . Existing Right-of-Way and Travel Lanes : The existing right-
of-way width along this segment of street varies from
eighty feet (801 ) to one hundred nine feet (109' ) . The
street is striped for four (4) twelve feet (12 ' ) wide
travel lanes, plus a fourteen feet (14 ' ) wide painted
median.
4 . Design Standard: The design standard for Los Angeles Avenue
calls for a curb-to-curb width of one hundred two feet
(1021 ) within a street right-of-way of one hundred eighteen
feet (1181 ) . Accordingly, the "half-street" dimensions
require fifty-one feet (511 ) from the centerline to the
curb face, within a "half street" right-of-way of fifty-
nine feet (59 ' ) .
5 . Project Objectives : The object of the project is to
construct full-width street improvements within the project
area, generally described as follows :
- one 14' painted median;
- six-12' travel lanes;
- two-8' emergency lanes (unpainted bicycle lanes) ;
- two-8' sidewalk / parkways; and
- free right turn lanes where necessary.
B. Shifted Centerline
Due to certain existing improvements along the north side of
the street west of Spring Road (see below for details) , the
Conceptual Plan calls for an eleven feet (111 ) shift of the
centerline to the south, between Spring Road and Millard
Street . East of Spring Road and west of Millard Street there
will be a tapered transition from the "shifted" centerline
back to the existing centerline at the east and west project
limits . The "shifted" centerline is necessary in order to
provide for the required fifty-one feet (51 ' ) dimension
between the centerline and the north curbface.
Exhibit 1
Project Description
October 22, 2001
Page 2
C. Project Constraints and Design Solutions
1 . North Side - West of Spring Road
a) Constraints :
• Half-street right-of-way width: fifty feet (50' ) ;
• Curb location: forty feet (40' ) from the center line;
• Existing Improvements :
- Existing residential rear yards;
- a ten feet (101 ) high block wall ;
- parkway landscaping; and
- power poles .
b) Design Solution: Due to the high cost of right-of-way
acquisition, and the removal and reconstruction of the
existing improvements on the north side of the street
just west of Spring Road, the Conceptual Plan calls for
all required street widening in this area to occur on
the south side of the street . To achieve the required
street width, the centerline will be shifted to the
south.
2 . South Side - East of Moorpark Avenue
a) Constraints : The south side of the street just east of
Moorpark Avenue has been improved to its full width
(fifty-one feet [511 ] from centerline to curb, within
fifty-nine feet [591 ] wide half-street right-of-way) .
There are substantial existing improvements in this
area, generally summarized as follows :
• existing properties already developed for multi-
family land use;
• decorative block walls and monument signs; and
• meandering sidewalks and parkway landscaping .
b) Design Solution: Due to the relative higher cost of
right-of-way acquisition and reconstruction along the
south side of the street in this area, the Conceptual
Plan calls for the centerline to remain at its present
location. Certain widening, relocation and improvement
will be required along the north side of the street in
this area.
D. Other Design Elements
1 . East-End Transition : As mentioned above, the centerline
will taper from the "shifted" centerline [eleven feet
(111 ) ] at the west side of Spring Road, back to the current
centerline to the east . The length of this transition will
be approximately five hundred feet (5001 ) . It will be
necessary to acquire additional street right-of-way and
reconstruct certain street and off-site improvements in
this area [Chevron Station and Bank of America] .
Exhibit 1
Project Description
October 22, 2001
Page 3
2 . West-End Transition: At Millard Street the centerline will
also transition from the "shifted" centerline back to the
existing centerline to the west. Here too the length of the
tapered transition will be approximately five hundred feet
(500' ) .
a) Additional street right-of-way will have to be acquired
on the north side of the street in the transition area,
ranging from zero at the Millard Street to nine feet
(91 ) wide at the west end of the transition.
b) The transition to the north will also require the
reconstruction of the curb, gutter and sidewalk in this
area.
3. North Side West of the Tapered Transition: In order to
achieve a fifty-nine feet (591 ) wide half-street west of
the westerly transition, it will be necessary to acquire an
additional nine feet (9' ) of street right-of-way and to
reconstruct street improvements in this area.
4 . Power Poles & Underground Utilities: The project will
require the relocation of the power poles and certain
modifications to some of the recently installed underground
utility vaults .
5. South Side R-O-W at 148 Los Angeles Avenue: There is an
existing residential structure located between the Le Club
Apartments and the Regal Condominiums . The street right-of-
way required at that location will probably require
acquisition of the entire property.
6. East-to-North Left-Turn Lane at Spring Road: The existing
double left-turn lane will be changed to a single left-turn
lane.
7 . West-to-South Left-Turn Lane at Moorpark Avenue: The
existing left-turn lane will be lengthened. The plans do
not call for a double left-turn lane at this location.
E. Right Turn Lanes
1 . Westbound at Moorpark Avenue: The Conceptual Plan calls for
an additional right-turn lane for Moorpark Avenue, to be
constructed west of Flory Avenue. It is anticipated that
the additional street right-of-way and street improvements
required for these improvements will be six feet (61 ) wide.
The design Engineer is seeking Caltrans approval of this
design feature.
e
Exhibit 1
Project Description
October 22, 2001
Page 4
2 . Eastbound at Spring Road: The Conceptual Plan also calls
for additional street widening on the south side of the
street just west of Spring Road, to provide for a free
right turn lane on to Spring Road. Once the additional
street width for this feature is determined by Caltrans,
the impacts of this design element on the off-site and on-
site improvements in the area will be assessed and a report
on this element of the project design will be presented to
the City Council .