Loading...
HomeMy WebLinkAboutAGENDA REPORT 2002 0116 CC REG ITEM 10AITEM /O- A, AGENDA REPORT CITY OF MOORPARK TO: The Honorable City Council FROM: Walter Brown, City Engineer DATE: January 4, 2002 (Council Meeting 1- 16 -02) . 1 1. _, i �yorz HU(Qt6--a AaB- ) SUBJECT: Consider Approval of the Re- design of the Retaining Walls for the Los Angeles East Improvement Project [Project 8012] BACKGROUND On June 2, 1999, the City Council considered a number of alternative design concepts for the required retaining walls. The option selected was a "Keystone" type concrete block (see Exhibits 1 - A and B). On July 21, 1999, the City Council revised that design by directing that "tiered" landscaping be incorporated into the wall design. MWMARY The use of reinforced concrete soil nailed simulated rock cut walls in lieu of Keystone walls offers advantages in: • Appearance, shown by comparing exhibits 1, 3 and 4. • Cost, saving approximately $308,000 as shown in the tables in the `Discussion' section of this report. • Ease of construction and reduced disturbance of adjacent properties. The recommendation of this change to the project was initiated as a result of a value and constructability analysis of the retaining walls. The analysis required the plans to be brought to a high level of detail. DISCUSSION The retaining walls required for the subject project range in height from four feet (4') to twenty -seven feet (27'). The earth behind most of the walls will continue to slope upward from the top of the L— A— East5 —wa112 000238 L A East Project: Retaining Wall Re- Design January 4, 2002 Page 2 walls. The optimal design for the retaining walls should provide attractive appearance and stable slopes at the least cost and not disturb existing buildings or require extensive removal and re- compaction of the hillside. During the design process, as the level of detail of the Los Angeles Avenue East construction plans increased, the need to provide shoring to protect one of the adjacent residences during construction of a retaining wall fronting became apparent. The shoring was needed to support the building during the construction of both Keystone and conventional type retaining walls. As a matter of cost control design alternatives that would eliminate the need for shoring were considered. The soil nailing, some times called tie -back, option was originally considered for only the support of the residence. When the costs to mobilize the equipment and tradesmen used for soil nailing were considered and the cost - effectiveness of reinforced concrete soil nailed retaining walls were calculated it became evident that concrete soil nailed retaining walls are a viable choice for this project. Alternative wall designs and their ability to achieve the design objectives are discussed in the following sections. A. Keystone Wall Design Examples of the Keystone retaining wall system are shown on Exhibits 1 - A and B. This type of retaining wall relies on the installation of patented concrete blocks retained in place by 18" horizontal layers of compacted soil and "construction fabric ". The Keystone wall concrete blocks use layers of construction fabric to anchor the wall to the retained earth. The installation of the construction fabric requires the removal of earth to create a 1 to 1 (horizontal to vertical) slope to assure the stability of the slope during construction. Additionally the sloped earthen face needs to be excavated back from the wall approximately 8 feet for each 10 feet of wall height to allow for the installation of the construction fabric. The above described removal and re- compaction of the retained slope will result in more disturbance to the existing hillside than is necessary for the construction of vertical reinforced concrete retaining walls or soil nailed walls. The excavation will require temporary shoring of some existing buildings (see Exhibits 2 - A and B). The shoring is expensive and carries some risk of damage, or claims of damage, to the shored buildings. The estimated construction cost for the Keystone retaining walls, including excavation, landscaping, right -of -way and other costs directly attributable to the Keystone wall, is $1,540,000. The costs associated with shoring and repairing potential damage to the buildings affected by the installation are not included in the estimated amount. A summary of costs follows: L_A_East5_wa112 0 02 439 L A East Project: Retaining Wall Re- Design January 4, 2002 Page 3 A V=im Ctnn= Wall Wall: 2,870 x 13.00 = 37,310 SF @ $17.00 /SF = $634,270 x Excavation: 2,870 x 15.59 = 44, 743 C @ $5.00 /CY = $223,717 x Leveling Pad 2,870 x 0.14 = 399 C @ $12.50 /CY = $4,983 x Backfill: 2,870 x 11.13 = 31,943 CY @ $5.00 /CY = $159,716 x Right-of-Way 2,870 x 10.90 = 31, 283 SF @ $7.50 /SF = $234,623 x Landscape 2,870 x 21.80 = 62, 566 SF @ $4.44 /SF = $277,793 6.59% Desi n $0 x 6.29% _ $0 TOTAL: _ $1,181,606= $31.67/S.F TOTAL: $1,535,100= $41.14 /S.F. B. Reinforced Concrete Cantilevered Retaininq Wall Reinforced concrete cantilevered retaining walls use the weight of the wall and the soil over the footing of the wall to counter balance the forces of the soil retained by the wall. The installation of the reinforced concrete wall requires the removal of earth to create a 1 to 1 (horizontal to vertical) slope to assure the stability of the slope during construction (see Exhibits 2 - A and C) . This wall type would not include the cascading or tiered wall landscaping which was to be incorporated into the Keystone wall. The wall would have a flat surface with no decorative features. The estimated construction cost for "standard" reinforced concrete retaining walls, including excavation, landscaping, right -of -way and other costs directly attributable to the retaining wall for this project is $ $1,180,000. A summary of costs follows: R r."+- il=c=c Rctaininn Wall Concrete: 2,870 x27.8/27= 2,955CY @$229.00/CY = $676,703 Rebar: 2,870 x 67.00 =192, 290 LB@ $0.53 /LB= $101,914 Excavation: 2,870 x 10.77 = 30,910CY@ $5.00 /CY = $154,550 Backfill: 2,870 x 5.67 = 16,273CY@ $5.00 /CY = $81,365 Right-of-Way 2,870 x 2.00 = 5,740SF@ $7.50 /SF= $43,050 Landscape 2,870 x 4.00 = 11,480SF@ $4.44 /SF= $50,971 Design $1, 108,552x 6.59% _ $73,054 TOTAL: _ $1,181,606= $31.67/S.F C. Reinforced Concrete Cantilevered Retaining Wall with Simulated Quarried Rock Facing There is no structural difference between the "standard" reinforced concrete retaining walls and the reinforced concrete L A East5 wa112 000 240 L A East Project: Retaining Wall Re- Design January 4, 2002 Page 4 cantilevered retaining wall with simulated quarried rock facing. The installation of this wall requires the removal of earth to create a 1 to 1 (horizontal to vertical) slope to assure the stability of the slope during construction (see Exhibits 2 - A and C) . The thickness of the wall is increased by the depth of the pattern. The simulation of quarried rock is achieved by the use of rubber or Styrofoam lined forms that mold the concrete into the shape of the selected pattern. After the concrete has set, it is etched and stained with a weather resistant dye. Several patterns of stonework are available. This wall type would not include the cascading or tiered wall landscaping which was to be incorporated into the Keystone wall. Some examples of aesthetic wall treatments that can be applied are attached as Exhibits 3 - A and B. The surface treatment recommended by staff is Sedona. The addition of a simulated quarried rock facing to a standard cantilever retaining wall will increase the cost of the wall by approximately $13.00 per square foot of wall surface. The estimated construction cost for reinforced concrete retaining walls with simulated quarried rock facing, including excavation, landscaping, right -of -way and other costs directly attributable to the retaining wall for this project is $1,580,000. A summary of costs follows: r rmn+ -i 1 avar Tlannrati va Ratai ni nff Wal 1 Concrete: 2,870 x 27 . 8/27 = 2, 955 CY @ $229.00 /CY= $676,703 Rebar: 2,870 x 67.00 = 192,290LB@ $0.53 /LB= $101,914 Stone -Crete Decorative Finish 2,870 x 13.00 = 37,310SF@ $10.00 /SF= $373,100 Excavation: 2,870 x 10.77 = 30, 910CY@ $5.00 /CY = $154,550 Backfill: 2,870 x 5.67 = 16,273CY@ $5.00 /CY = $81,365 Right-of-Way 2,870 x 2.00 = 5, 740 SF@ $7.50 /SF= $43,050 Landscape 2,870 x 4.00 = 11, 480 SF@ $4.44 /SF= $50,971 Design $1, 481,652x 6.29% _ $93,196 TOTAL: _ $1,574,848 = $42.21/S.F D. Reinforced Concrete Soil Nailed Simulated Rock Cut Wall The reinforced concrete soil nailed simulated rock cut wall is actually a vertical concrete slab attached to the soil and retained with corrosion resistant steel anchors. The soil nails are installed as the soil is excavated. This allows the wall to be constructed while minimizing the disturbance of the area behind the wall. The anchors are inserted into drilled holes which are then pressure grouted. The design is widely used in Europe and has seen increased use in the United States over the L_A— East5_wa112 000241L L A East Project: Retaining Wall Re- Design January 4, 2002 Page 5 past few years. The simulation of a rock cut is achieved by hand sculpting of the concrete into realistic native rock shapes. The concrete can be colored with integral color and /or, after the concrete has set, etched and stained with a weather resistant dye. An example of a soil nailed simulated rock cut wall is located along the westerly side of I -405 adjacent to the Getty Museum. This wall is shown on Exhibits 4 - A and B. This is the surface treatment recommended by staff. This wall type would not include the cascading or tiered wall landscaping which was to be incorporated into the Keystone wall, however planting pockets can be incorporated into the wall to achieve a similar effect. The estimated construction cost for reinforced concrete soil nailed simulated rock cut wall, including excavation, landscaping, right -of -way and other costs directly attributable to the retaining wall for this project is $1,290,000. A summary of costs follows: n Rnil Nail Gniilntnd R,-taininQ Wall F. Re- Design Each of the wall types mentioned in items A through D is an individual design. The Keystone wall design is presently completed. Each of the wall types can be constructed within the area of the easement documents that are already prepared. The negotiations for acquisition of the easements may warrant the cost of preparation of new easements documents. Revisions to the wall easements, slope easements and construction easements along the north side of the street would require preparation of 47 000242 L A East5 wa112 2, 870 x 13. 00 = 37, 310 SF @ $32. 00 /CY = $1, 193, 920 Wall - Includes Tie- back bars (Supply, Drill, Grout, Test & Tension), Reinforcing, 8" Shot - Crete, Backdrain & Sculpting Face Excavation: 2,870 x 0.06 = 178CY@ $10.50 /CY = $1,868 Backfill: 2,870 x 0.06 = 178CY@ $3.50 /CY = $623 Right-of-Way 2,870 x 0.67 = 1, 923 SF@ $7.50 /SF = $14,422 Landscape 2,870 x 0.00 = 0SF@ $4.44 /SF = $0 Design $1,210,833 x 6.43% _ $77,857 TOTAL: _ $1,288,689= $34.54/S.F. F. Re- Design Each of the wall types mentioned in items A through D is an individual design. The Keystone wall design is presently completed. Each of the wall types can be constructed within the area of the easement documents that are already prepared. The negotiations for acquisition of the easements may warrant the cost of preparation of new easements documents. Revisions to the wall easements, slope easements and construction easements along the north side of the street would require preparation of 47 000242 L A East5 wa112 L A East Project: Retaining Wall Re- Design January 4, 2002 Page 6 descriptions and plat maps. The cost to prepare the descriptions and plat maps would be $37,600. Redesign efforts include the required changes to the plans. The redesign efforts are included in the estimated cost of the walls. The costs of the redesign efforts are based on a percentage of the estimated construction costs. G. Fiscal Impact 1. Wall Selection: A summary of the cost differentials of the retaining wall designs follows: Wall SE?1PCtion Cost Differentials Type of Wall Estimated Cost Change from To Date Future Total Cost Keystone Wall Keystone Wall $1,597,035 $0 Cantilever Retaining $1,181,606 - $415,429 Wall Cantilever Decorative $1,574,848 - $22,186 Retaining Wall (Adjusted for 2003 Construction Date & Soil Nail Sculpted $1,288,689 - $308,345 Retaining Wall 2. Current Total Project Cost Summary: A summary of the total estimated project costs [2003 construction costs] is as follows: Current Total Project Cost Summary Work Description Costs To Date Future Total Design $268,362 78,000 346,362 Right -of -Way - Preliminary Estimate, $0 1,500,000 1,500,000 No Appraisal Data Available Construction Using Soil Nail Wall (Adjusted for 2003 Construction Date & 0 3,460,000 3,460,000 with 15% Contingency) Construction Administration & 0 519,000 519,000 Inspection (15% of Construction Cost) Totals $268,362 $5,557,000 $5,825,362 STAFF RECOMMENDATION Approve the redesign of the retaining walls to provide for the construction of reinforced concrete soil nailed simulated rock cut wall. Use existing easement documents and defer preparation of new easement documents unless right -of -way costs exceed the cost of their preparation. L A East5 wa112 0002 Keystone Wall Exhibit 1 -A Keystone Wall Exhibit 1 -B Exhibit 2 -A Nll Nj off. It u TS �Ilk YX __tzt! u � 000246 Exhibit 2 -B w 6.5' z w 4.5, W U X SEE WALL AND `- HANDRAIL CETAIL 2% z orf ON SHEET 2 L J •y SEE DRAINAGE— PLANS i GEO —GRID PER Q, j KEYSTONE 00 WALL PLANS ALTERNATE 1 ECTION 2--2 N.T.S. LOT 1 1 5 00024'7 z Ln X LA-1 Lj a-, L. 60 Exhibit 2-C 6.5' ALTERNATE 2 SECTION 2-2 N.T.S. LOT 115 SEE WALL AND HANDRAIL DETAIL ON SHEET 2 M 000243 Cast Concrete Detail Exhibit 3 -A Sedona Pattern � yig g , A � r mill - Ni Sculpted Soil Nail Wall Exhibit 4 -A Wall along I -405 at the Getty Center Sculpted Soil Nail Wall Exhibit 4 -B Close -up of wall along I -405 at the Getty Center �-cTC• �r 3 ?flirt °'F";1 ?1. ?,�, �':',T ..- s�r'.'e'7 .1 ,A C- .�- �- �r -� >�r ITEM MINUTES OF THE CITY COUNCIL Moorpark, California December 20, 2001 An Adjourned Meeting of the City Council of the City of Moorpark was held on December 20, 2001, in the Community Center Conference Room of said City located at 799 Moorpark Avenue, Moorpark, California. 1. CALL TO ORDER: Mayor Hunter called the meeting to order at 6:05 p.m. Mayor Hunter announced that the adjourned meeting was called to discuss Item 9.A. which was continued from the December 19, 2001, regular meeting with the public hearing closed, due to lack of a voting quorum, and one closed session item. 2. ROLL CALL: Present: Councilmembers Harper, Mikos, Wozniak and Mayor Hunter. Absent: Councilmember Millhouse. Staff Present: Steven Kueny, City Manager and Deborah Traffenstedt, Assistant to the City Manager /City Clerk. 3. PUBLIC COMMENT: None. 9. PUBLIC HEARINGS: C. Consider the Status of Interim Prohibition of Wireless Telecommunications Facilities and Extension of Ordinance No. 272 and Amendment of Ordinance No. 273, Enacting a Moratorium on the Issuance of Permits for Construction or Placement of Wireless Telecommunications Facilities. Staff Recommendation: 1) Open the public hearing, take public testimony, and close public hearing; and 2) Adopt Ordinance No. 275, extending Ordinance No. 272 and amending Ordinance No. 273, enacting a moratorium on the issuance of permits for construction or placement of Wireless Communications Facilities in the City and declaring the urgency thereof. (4/5's vote required for adoption of ordinance) Continued from December 19, 2001, with Public Hearing Closed. MOTION: Councilmember Harper moved and Councilmember Mikos seconded a motion to approve the staff recommendation with a revised extension date for the moratorium from April 14, 2002, to April 18, 2002. The motion carried by voice vote of 4 -0, Councilmember Millhouse absent. 0002!k3 Minutes of City Council Moorpark, California Page 2 December 20, 2001 MOTION: Councilmember Harper moved and Councilmember Mikos seconded a motion to introduce Ordinance 275 for first reading and to waive full reading of the ordinance. The motion carried by voice vote of 4 -0, Councilmember Millhouse absent. MOTION: Councilmember Harper moved and Councilmember Wozniak seconded a motion to adopt Ordinance No. 275. The motion carried by voice vote of 4 -0, Councilmember Millhouse absent. 13. CLOSED SESSION: Mr. Kueny announced that the City Council would be going into closed session for discussion of Item 13.F. on the agenda. MOTION: Councilmember Harper moved and Councilmember Wozniak seconded a motion to adjourn to closed session for a discussion of Item 13.F. on the agenda. The motion carried by voice vote of 4 -0, Councilmember Millhouse absent. The time was 6:08 p.m. F. PUBLIC EMPLOYEE PERFORMANCE EVALUATION Title: Assistant City Manager, Assistant to City Manager /City Clerk, City Manager, City Attorney, City Engineer, Chief of Police, Director of Administrative Services, Director of Community Development, Director of Community Services, and Director of Public Works. Present in closed session were Mayor Hunter, Councilmember Mikos, Councilmember Harper, and Councilmember Wozniak; Steven Kueny, City Manager; and Deborah Traffenstedt, Assistant to the City Manager /City Clerk. The Council reconvened into open session at 6:12 p.m. Mr. Kueny stated that there was no action to report. 14. ADJOURNMENT: Mayor Hunter adjourned the meeting at 6:12 p.m. Patrick Hunter, Mayor ATTEST: Deborah S. Traffenstedt City Clerk 000254 MINUTES OF THE CITY COUNCIL Moorpark, California January 9, 2002 A Special Meeting of the City Council of the City of Moorpark was held on January 9, 2002, in the Community Center of said City located at 799 Moorpark Avenue, Moorpark, California. 1. CALL TO ORDER: Mayor Hunter called the meeting to order at 5:35 p.m. 2. ROLL CALL: Present: Councilmembers Harper, Mikos, Millhouse, Wozniak and Mayor Hunter. Staff Present: Steven Kueny, City Manager; Deborah Traffenstedt, Assistant to City Manager /City Clerk. 3. PUBLIC COMMENT: None. 4. PRESENTATION /ACTION /DISCUSSION: A. Consider Rejection of Claim: Robyn Tholander. Staff Recommendation: Reject the claim and direct staff to send a standard rejection letter to the claimant. MOTION: Councilmember Harper moved and Mayor Hunter seconded a motion to approve the staff recommendation. The motion carried by unanimous voice vote. 5. ADJOURNMENT: Mayor Hunter adjourned the meeting at 5:36 p.m. Patrick Hunter, Mayor ATTEST: Deborah S. Traffenstedt City Clerk 000255