TO: The Honorable City Council
FROM: Kenneth C. Gilbert, Director of Public Works 1 �^
DATE: April 18, 2002 (Council Meeting 5 -1 -02)
SUBJECT: Notice of Completion for the New Los Angeles Avenue
Bridge Widening Project
T)T grTTQfiT0TsT
A. Project Scope: The project widened the New Los Angeles Avenue
bridge across the Arroyo Simi, briefly summarized as follows:
1. South Side Widening: The project called for the widening of
the bridge structure on the south side of the street
[downstream side of the bridge] , shifting the centerline to
the south.
2. Bridge Width: The outside dimension of the bridge was
widened from 82' to a width of 1171.
3. Six Lanes: The project resulted in the re- striping of the
street to provide three travel lanes in each direction.
These six lanes now extend from the freeway to Spring Road.
4 Median: The striping also included provisions for a 14' wide
painted median, with left -turn lanes where required.
5 Sidewalks: Sidewalks were added to both sides of the bridge.
There are now sidewalks on both sides of the street between
Spring Road and Science Drive /Miller Parkway.
6 Street Lights: The project also included the installation of
street lights on the north side of the street.
New L A Brg_cmp
New Los Angeles Avenue Bridge Widening: Completion
April 18, 2002
Page 2
B. Other Project Requirements: Other project requirements include:
1. Environmental Clearance: The project was found to be
Categorically Exempt.
2. Right -of -Way Acquisition: A small piece of right -of -way
[190sf] was required near the southwest corner of the
bridge. The City obtained a Right -of -Entry Permit to allow
project construction to proceed on schedule. The City is
proceeding with the actual acquisition of that parcel. When
obtained, that parcel will be conveyed to Caltrans.
3. Permits: Certain permits and approvals were required.
Project administration included efforts to assure compliance
with all permit requirements. A list of the required permits
is as follows:
a) U. S. Army Corp of Engineers: An Environmental Consultant
was retained by the City to obtain this permit.
b) California Fish & Game Department: An Environmental
Consultant was retained by the City to obtain this
permit.
c) Regional Water Quality Control Board: The City retained
an Environmental Consultant to obtain this permit.
d) VCFCD: Staff obtained a permit from the Ventura County
Flood Control District (VCFCD).
e) Caltrans: A Caltrans Encroachment Permit was issued for
this project.
C. Quantity Adjustment
Invariably with Public Works projects the final actual
quantity for each of the bid items differs from the
engineer's estimate of quantities set forth in the original
bidding documents. The final contract cost will differ from
the bid price, based upon the actual quantities required.
The
final quantities required
for this
project were more than
the
engineer's estimate.
The cost
of the
additional
quantities was $159,481.71. A
summary of the more
significant
deviations
from the engineer's
estimate
is as follows:
Description Est. Cost ($)
Actual Cost ($)
Delta Cost ($)
a.
Temporary fencing
2,748
5,192
2,444
b.
Traffic Control
24,965
46,110
21,145
c.
Striping
6,046
9,735
3,689
d.
Misc. Concrete
14,620
34,361
19,741
e.
Pavement
27,076
81,916
54,840
f.
Piles
118,996
165,131
46,135
g.
Bank Rock Protection
19,698
29,670
9,972
other
1,516
Total
159,482
New L A Brg_cmp `^ * -%'%r'
New Los Angeles Avenue Bridge Widening: Completion
April 18, 2002
Page 3
D. Change Orders
There were two (2) Change Orders for the project. However,
each change order covers several tasks. A summary of the
extra work directed by these Change Orders is attached as
Exhibit 1. The amount of the Change Orders is as follows:
Description Total ($)
Change Order #1 71,324.19
Change Order #2 49,245.00
Total 120,569.19
E. Right -of -Way
The construction of the project required the acquisition of a
small piece of right -of -way near the southwest corner of the
bridge. A right -of -entry permit was obtained from the
property owner to allow construction to proceed during
acquisition efforts. Staff, with the assistance of the City's
Property Acquisition consultant, is still working with the
property owner to obtain the property. It is the intent of
staff to then have the property conveyed to Caltrans.
F. Fiscal Impact
1. Construction Costs: The total final construction costs are
summarized as follows:
Description
Total ($)
Bid Amount
1,414,921.10
Quantity Adjustment
159,481.71
Change Orders
120,569.19
Total 1,694,972.00
2. Design: The design
was prepared by Charles Abbott &
Associates. The total
design fee was $162,216.
3. Design Support: Certain design support expenses are
summarized as follows:
Description
Total ($)
Permit Consultant
14,737.82
Permits
2,989.90
Printing, Etc.
1,421.59
Other
308.17
Total 19,457.48
New L A Brg_cmp
New Los Angeles Avenue Bridge Widening: Completion
April 18, 2002
Page 4
4. Construction Engineering: A consultant was retained to
provide construction engineering (contract administration
and construction inspection). The cost of these services
was $218,800.
5. Total Project Costs: The estimated total project costs are
summarized as follows:
Description
Total ($)
Construction
1,694,972.00
Right -of -Way
7,490.00
Design Effort Since July 2000
50,115.52
Design Support
19,947.48
Construction Administration
218,800.00
Sub -total
1,991,325.00
Design Costs Prior to July 2000
112,100.00
Total
2,103,425.00
6. Funding Sources : The subject project is totally funded by
the Los Angeles Avenue AOC Fund.
7. Total Project
Budget Adjustment: The adjustment
to the
current total
appropriations required to fund
project
expenses since
July 1999 is summarized
as follows:
73,530
(70,063)
Total Current
Proposed Total
Required
Description
Appropriations ($)
Change ($) Appropriations
($)
Design
73,530
(3,467)
70,063
R -O -W
0
7,490
7,490
Construction
1,556,414
138,558
1,694,972
Inspection
185,500
33,300
218,800
Total
1,815,444
175,881
1,991,325
8. PY01 102 Budget: The current project budget is summarized as
follows:
New L A Brg_cmp
Total
Less Expenses
FY01 /02
Description
Appropriations ($)
Prior Years ($)
Budget ($)
Design
73,530
(70,063)
3,467
R -O -W
0
0
0
Construction
1,556,414
(1,261,610)
294,804
Inspection
185,500
(143,116)
42,384
Total 1,815,444
(1,474,789)
340,655
New L A Brg_cmp
New Los Angeles Avenue Bridge Widening: Completion
April 18, 2002
Page 5
9. Budget Amendment: As indicated in section F -7 above,
expense exceeded the total appropriations. The attached
resolution amends the budget to fully fund project expenses
since July 1999. A summary of the recommended budget change
is as follows:
G. Final Inspection and Acceptance
The City has completed a final inspection of the project and
has found the work to be acceptable. The project has also
been accepted by Caltrans and by the Ventura County Flood
Control District. At this time it would be appropriate for
the City Council to accept the project as completed and
direct the City Clerk to record the Notice of Completion to
start the final lean period.
H. Release of Retention
If the recommended action is taken, the Notice of Completion
will be forwarded to the County Recorder for recordation.
Absent the receipt of any Stop Notices from subcontractors
or suppliers, thirty -five (35) days after the date of the
recordation of the Notice of Completion, the ten percent
(10 %) retention will be paid.
RECOMMENDATIONS (ROLL CALL VOTE
Accept the work as completed and adopt Resolution 2002-
Attachments:
Exhibit 1:
Exhibit 2:
New L A Brg_cmp
Change Order Summary
Resolution
FY 01/02
Revised FY 01 /02
Description
Budget ($)
Change ($)
Budget ($)
Design
3,467
(3,467)
0
R -O -W
0
7,490
7,490
Construction
294,804
138,558
433,362
Inspection
42,384
33,300
75,684
Total 340,655
175,881
516,536
G. Final Inspection and Acceptance
The City has completed a final inspection of the project and
has found the work to be acceptable. The project has also
been accepted by Caltrans and by the Ventura County Flood
Control District. At this time it would be appropriate for
the City Council to accept the project as completed and
direct the City Clerk to record the Notice of Completion to
start the final lean period.
H. Release of Retention
If the recommended action is taken, the Notice of Completion
will be forwarded to the County Recorder for recordation.
Absent the receipt of any Stop Notices from subcontractors
or suppliers, thirty -five (35) days after the date of the
recordation of the Notice of Completion, the ten percent
(10 %) retention will be paid.
RECOMMENDATIONS (ROLL CALL VOTE
Accept the work as completed and adopt Resolution 2002-
Attachments:
Exhibit 1:
Exhibit 2:
New L A Brg_cmp
Change Order Summary
Resolution
Exhibit 1
Change Order Summary
April 18, 2002
Page 1
Chanae Order
1 Bridge Piling / Method of Connection
a Piling Changes: Additional work required as the result of the need for
piles 30% longer than those called for by the plans.
b Method of Connection: Change to the method of connection of the new
widened portion of the bridge deck to the exisitng bridge deck, as
directed by Caltrans.
Total CCO #1
2 Miscellaneous Work
a Warped Wingwall: Additional removal and replacement of the warped
wingwall near Abutment #2 (SE).
b Obstructions: Removal of subsurface obstructions during installation of
sheet piling.
c Changeable Message Signs: Additional traffic control requried by
Caltrans.
d Method of Connection Credit: Credit adjustment to cost for Item b of
Change Order #1, pertianing to the method of connection to the existing
bridge deck.
e Street Lights: Installation of conduits for the added street lights on the
north side of the street.
f Added Work North Side Sidewalk: Additional work required for the
construction of the sidewalk on the north side of the street east and west
of the bridge.
g Restore Access Road: Placement of base material and other work
required by VCFCD to restore the north side access road between the
New L. A. Avenue bridge and the Spring Road bridge.
h Fencing: Additional fencing (in -lieu of guardrails) required by Caltrans.
I Fence Modification: Fence Height extension requried by VCFCD.
j Type A Joint Seal: Joint seal in sidewalks at ends of bridge deck,
required by Caltrans.
Total CCO #2
Total Change Orders
Amount ($)
55,994.40
15,329.79
71,324.19
7,304.35
3,228.82
4,665.69
(3,427.70)
12,123.37
4,960.22
9,465.00
7,216.25
1,294.00
2,415.00
49,245.00
120, 569.19
Ci.rorw�ar
.... �,...�
Exhibit 2
RESOLUTION NO. 2002 -
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF MOORPARK, CALIFORNIA, REVISING THE FY01 /02
BUDGET AND APPROPRIATIONS FOR PROJECT 8014 -
NEW LOS ANGELES AVENUE BRIDGE WIDENING [FUND
2501 - L A AOC FUND]
WHEREAS, on June 20, 2001, the City Council adopted the
Budget for Fiscal Year 2001/02; and
WHEREAS, a staff report has been presented to the City
Council requesting a budget increase in the aggregate amount of
$175,881; and
WHEREAS, Exhibit "A ", attached hereto and made a part hereof,
describes said budget amendment and its resultant impacts to the
budget line item(s).
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK DOES
HEREBY RESOLVE AS FOLLOWS:
SECTION 1. That a Budget amendment in the aggregate increase
of $175,881, as more particularly described in Exhibit "A ", is
hereby approved.
SECTION 2. The City Clerk shall certify to the adoption of
this resolution and shall cause a certified resolution to be filed
in the book of original resolutions.
PASSED AND ADOPTED this
ATTEST:
day of , 2002.
Patrick Hunter, Mayor
Deborah S. Traffenstedt, City Clerk
Attachment:
Exhibit 'A': Appropriation and Budget Detail
Resolution No. 2002 -
Exhibit "A"
REVISED
APPROPRIATIONS & BUDGET FOR
New Los Angeles Avenue Bridge Widening
[Project No. 80141
FUND
ACCOUNT NUMBER
APPROPRIATION REQUEST
L. A. Avenue AOC
2501.0000.0000.5500
$ 175,881
TOTALS: $ 175,881
FY 01/02 BUDGET RE -CAP
ACCOUNT NUMBER
CURRENT
SUBJECT
REVISED
REVISED
FY V, BUDGET
FY 2001/02
APPROPRIATION
FY 2001/02
$ (3,467)
BUDGET
/ (REDUCTION)
BUDGET
2501.8310.8046.xxxx
$ 340,665
$ 175,881
$ 516,536
TOTALS:
$ 340,655
$ 175,881,
$ 516,536
TOTAL APPROPRIATIONS RE -CAP
(Excluding Pre -FY 00 /01 Design Costs)
ACCOUNT NUMBER SUBJECT TOTAL
TOTAL PRIOR APPROPRIATION REVISED
APPROPRIATION / (REDUCTION) APPROPRIATION
2501.8310.8046.xxxx $ 1,815,444 $ 175,881 $ 1,991,325
TOTALS: $ 1,815,444; $ 175,8811 , $ 1,991,325
DISTRIBUTION OF APPROPRIATIONS TO EXPENSE ACCOUNT NUMBERS
ACCOUNT NUMBER
CURRENT
FY 01/02
BUDGET
SUBJECT
APPROPRIATION
/ (REDUCTION)
REVISED
FY V, BUDGET
2501.8310.8046.9601:
Design
$ 3,467
$ (3,467)
$
0
2501.8310.8046.9610:
R -O -W
$ 0
$ 7,490
$
7,490
2501.8310.8046.9640:
Const.
$ 294,804
$ 138,558
$
433,362
2501.8310.8046.9650:
Insp.
$ 42,384
$ 33,300
$
75,684
TOTALS:
$ 340,655
$ 175,881
$
516,536
Approved as to form: �,. d