CITY OF MOORPARK
CITY COUNCIL AGENDA REPOR
TO: The Honorable City Council
FROM: Mary K. Lindley, Director of Community Services ���
DATE: April 12, 2002 (CC Meeting of May 1, 2002)
SUBJECT: Consider Approval of Plans and Specifications,
Award a Contract, and Adopt a Budget Resolution
for the Construction of the
Restroom /Concession /Storage Facility at Arroyo
Vista Community Park
SUMMARY
The City Council is being asked to approve the plans and
specifications for the AVCP Phase II restroom /concession/
storage facility; award a contract to Tasco Construction,
Inc., to perform the work; and to adopt a Resolution
(Attachment A) appropriating an additional $171,000 towards
the project. The project is being funded by the Community
Zone of the Park Improvement Fund.
BACKGROUND
On December 6, 2000, the City Council approved the
appropriation of $120,000 for design of the building and
utilities (water, sewer, and electrical) and preliminary
site work. This appropriation did not include construction
costs. The December 6, 2000, Agenda Report stated that
staff would return to the Council to request an
appropriation for construction at the conclusion of the bid
process. At that time, the initial cost estimate for the
project was $460,000. As previously reported, a percentage
of the $460,000 may be attributable to other future
projects, specifically the aquatics facility and AVCP Phase
II. As a result, when budgets for those projects are
developed, proportionate charges for the construction of
the utility services and connection charges will be
0 A;
MAMLindley\PARKS \Park Projects \AVCP Restrooms \award RR buildling construction ccagd.doc
AVCP Restroom Contract Award
Page 2
transferred, thereby lowering the overall cost of the
restroom facility.
Due to delays experienced in the design of the restroom
building, the project was split in two: utility extension
and building. On February 6, 2002, the City Council awarded
a contract to J & H Engineering General Contractors, Inc.
for the extension of the water, sewer, and electrical
utility services to the AVCP Phase II restroom facility and
appropriated an additional $169,000 towards the project.
This appropriation, combined with the initial project
budget of $120,000 for design services, brought the total
project budget to $289,000, where it stands to date.
Construction of the utility extension phase of the project
is close to completion.
The City conducted the bid process on the construction of
the restroom building, which concluded on April 25. The
apparent successful low bidder is Tasco Construction, Inc.
from Camarillo.
DISCUSSION
Project Plans and Specifications
Brent Schneider Architects prepared the design and
specifications for the restroom facility. The facility
includes a 450 square foot restroom and a 285 square foot
concession stand. Both of these components are similar in
size and design to the existing restroom facility at the
softball fields. Additionally, the facility includes a 965
square foot storage room to be shared by the youth sports
organizations based at AVCP. The storage space is twice the
size as the existing storage area.
The Council is being asked to approve the aforementioned
plans and specifications. A full set of plans and
specifications for the project were provided to the City
Council under separate cover.
Contract Award
The bid closing for the construction of the building was
April 25. The City received 3 bids. The Council is being
asked to award a contract to Tasco Construction, Inc., the
lowest qualified bidder, at a cost of $263,538. The other
M: \MLindley \PARKS \Park Projects \AVCP Restrooms \award RR buildling construction
ccagd.doc (-� 4-,^+^
C r"
lI � . ., v
AVCP Restroom Contract Award
Page 3
two bids received are as follows: SBS
$345,157 and QCM Construction at $391,000.
It has been determined that the apparent
qualified to perform the work. Tasco C
confirmed that their bid is valid and
prepared to proceed with the construction of
Corporation at
low bidder is
instruction has
that they are
the project.
Project Budget
Additionally, the Council is being asked to adopt the
attached budget resolution appropriating funds for the
construction of this phase of the project. As stated
previously, to date the Council has appropriated $289,000.
Of the amount appropriated to date, approximately $197,000
has allocated to various project tasks. To complete the
project, an additional $171,000 is needed to bring the
total project budget to $460,000.
RECOMMENDATION (Roll Call Vote)
Approve the plans and specifications for the construction
of the restroom facility; award a contract to Tasco
Construction, Inc., for $263,538; and adopt Resolution No.
2002 -_, appropriating an additional $171,000 to the
project from the Park Improvement Fund - Community Zone.
Attachments: (A) Resolution
(B) Project Budget
M: \MLindley \PARKS \Park Projects \AVCP Restrooms \award RR buildling construction "
ccagd.doC
AVCP Restroom Contract Award
Page 4
RESOLUTION NO. 2002-
ATTACHMENT A
RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF MOORPARK, CALIFORNIA, AMENDING
THE FY 2001/02 BUDGET BY TRANSFERRING
$171,000 FROM THE COMMUNITY PARK
IMPROVEMENT ZONE RESERVE FUND (2100) TO
THE RESTROOM /CONCESSION /STORAGE FACILITY
PROJECT AT ARROYO VISTA COMMUNITY PARK
(2100.7800.7018)
WHEREAS, on June 20, 2001, the City Council adopted
the budget for Fiscal Year 2001/02; and
WHEREAS, a staff report has been presented to said
Council requesting a budget amendment by transferring
$171,000 from the Community Park Improvement Fund Reserve
balance for the design and construction of a restroom,
concession, and storage facility at Arroyo Vista Community
Park; and
WHEREAS, Exhibit "A" hereof describes said budget
amendment and its resultant impacts to the budget line
item(s).
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF
MOORPARK DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. A budget amendment
from the
described
approved.
General Fund Reserve as
in Exhibit ` %A" attached
allocating $171,000
more particularly
hereto is hereby
SECTION 2. The City Clerk shall certify to the
adoption of the resolution and shall cause a certified
resolution to be filed in the book of original Resolutions.
PASSED AND ADOPTED this lst day of May, 2002.
ATTEST:
Patrick Hunter, Mayor
Deborah S. Traffenstedt, City Clerk
\ \mor pri sere \home folders \MLindley \PARKS \Park Projects \AVCP Restrooms \award
RR buildling construction ccagd.doc
AVCP Restroom Contract Award
Page 5
Resolution No. 2002-
EXHIBIT A
Budget Revision
A. Fund Allocation:
Fund No.
Fund Name
Amount
2100.5500
Community Park Improvement Fund -
$171,000
$171,000
$460,000
B. Budget Appropriation:
BUDGET NUMBER
BUDGETED
REVISION
NEW BUDGET
2100.7800.7018.9620
$289,000
$171,000
$460,000
Approved to Form:
Cn•n.��c
\ \mor pri sery \home_folders \MLindley \PARKS \Park Projects \AVCP Restrooms \award
RR buildling construction ccagd.doc
AVCP Restroom Contract Award
Page 6
ATTACHMENT B
AVCP RESTROOM /STORAGE /CONCESSION FACILITY
PROJECT BUDGET
REVISED
AVCP RESTROOM /STORAGE /CONCESSION
FACILITY
PROJECT
BUDGET EST.
Building Design
$ 10,000
Civil Design
$ 27,000
Electrical Design
$ 2,000
Soils & Geotech. Testing
$ 4,000
Project Management
$ 6,000
Construction (Utilities)
$125,000
Construction (Building)
$264,000
Permits & Fees
$ 3,000
Inspection
$ 10,000
7% Contingency
$ 9,000
Total Estimate
$460,000