TO: The Honorable City Council
FROM: Kenneth C. Gilbert, Director of Public Works
DATE: January 22, 2003 (Council Meeting 2 -5 -03)
SUBJECT: Consider Bids for the Construction of the 2002 Curb Ramp
Project
BACKGROUND
Staff conducted a survey of all City streets to review the degree
to which City streets and sidewalks accommodate handicap access.
We discovered that there were a number of "T" intersections which
did not provide a curb ramp on the "Thru- Street" side of the
intersection. That is, there were curb ramps at the two corners
of the side street, but there was no curb ramp across the street
from the side street.
The City Engineer's office prepared plans for the construction of
curb ramps at all identified deficient "T" intersections.
In December of 2002 the City Council approved the subject project
and authorized staff to advertise for receipt of bids the
construction of the project.
DISCUSSION
A. Project Scope
The locations of the curb ramps
the map attached as Exhibit 1.
the construction of thirty -two
B. Bid Results
to be constructed are shown on
The subject project calls for
(32) new curb ramps.
Bids for the subject project were received and opened on
January 21. The apparent low bidder is Sub Zero Excavating,
Inc., with a bid of $42,382.21. A summary of the bid results
is attached as Exhibit 2.
Curb ramp_awd
it
Curb Ramp Project: Award of Contract
January 22, 2003
Page 2
It has been determined that the apparent low bidder is
qualified to perform the work. Said bidder has confirmed that
their bid is valid and that they are prepared to proceed with
the construction of the project.
C. Fiscal Impact
1. Construction Cost Estimate: An estimate of construction
costs is as follows:
Description
Bid Amount
Contingency [15 %]
Total
2. Total Project Cost Estimate
project costs is as follows:
Description
Design
R -O -W
Construction
Inspection
Total
Construction
Cost Est. M
42,382.21
6,357.33
48,739.54
An estimate of the total
Total Project
Cost Est. M
11,214.00
0.00
49,000.00
3,000.00
63,214.00
3. Budget: The FY 02/03 Budget includes Project 8030 for the
construction of pedestrian / bicycle improvement projects
partially funded by TDA Article 3 [SB -821] grant monies
[Fund 2602]. It has been determined that the subject
project is eligible to be funded from this source.
Project 8030 shows local share matching monies funded by
TDA Article 8 (Local Transportation Fund) [Fund 2603].
A summary of
Proiect 8030
Description
Fund 2603: LTF
Design
Construction
Inspection
the budget for this project is as follows:
Projected Projected
Budget W Cost M Surplus
Sub -Total
Fund 2602: SB -821 Grant
Design
Construction
Inspection
Sub -Total
Total
Curb ramp_awd
20,000.00
5,700.00
14,300.00
77,000.00
24,500.00
52,500.00
15.000.00
1.500.00
13,500.00
112,000.00
31,700.00
80,300.00
5,700.00
5,700.00
0.00
35,800.00
24,500.00
11,300.00
1,500.00
1.500.00
0
43,000.00
31,700.00
11,300.00
155,000.00
63,400.00
91,600.00
Curb Ramp Project: Award of Contract
January 22, 2003
Page 3
It is the intent of staff to use the above projected
anticipated Fund 2602 surplus, plus certain additional
unappropriated Fund 2602 monies, to partially fund the
Spring Road Widening project (Project 8026), which
includes the construction of sidewalks and the addition of
Class 2 Bike Lanes.
D. Schedule
It is anticipated that construction of the project should
start in late February and be completed in March.
E. Administrative Actions
If the recommended action is taken by the City Council,
certain administrative actions will be undertaken by staff,
including the following:
• A contract agreement will be forwarded to Sub Zero
Excavating, Inc., for the construction of the subject
project, for the contract price of $42,382.21.
• When all of the contract documents are in order, the
agreement will be executed by the City Manager.
• A construction contingency of $6,357.33 (150) will be set
aside for the project.
STAFF RECOMMENDATION
Approve the award of a contract to Sub Zero Excavating, Inc. for
the construction of the subject project.
Attachments:
Exhibit 1: Map
Exhibit 2: Bid Results
Curb ramp_awd ®CC 1 81
a2� CITY OF MOORPARK
1--N-
City of Moorpark
Exhibit 2
Bid Results: 2002 Ramps @ "T" Intersections
Page l of 2
[File # Bid Results - 2002 Ramps]
Bidder » »>
Vendor I
Vendor 2
Bid Opening:
Name:
Engineer's Estimate
Sub "Zero Excavating
Newtech Eng. &
Construction
January 21, 2003
Address:
67 Erbs Road
30 N. Raymond
Avenue
Cit, State.
Thousand Oaks,
CA 91362
Pasadena, CA 91103
Tel. No.:
805- 494 -5013
(626) 583 -8370
Contact Person:
Est Qty Units
I LS
Lisa Fletcher
Sam Alfaisal
Item Description
Unit Cost
Total Bid
Unit Cost
Total Bid
Unit Cost
Total Bid
1 Mobilization
1,000.00
1,000.00
1,500.00
1,500.00
300.00
300.00
2 Traffic Control
1 LS
2,000.00
2,000.00
2,000.00
2,000.00
300.00
300.00
3 Type 5 Case A Ped Ramp
14 EA
432.93
6,061.02
789.80
11,057.20
500.00
7,000.00
4 Type l Case B Ped Ramp
18 EA
432.93
7,792.74
586.25
10,552.50
500.00
9,000.00
5 Remove Concrete
1 LS
3,100.00
3, lW00
750.00
750.00
6,400.00
6,400.00
6 Remove AC Pavement
l LS
400.00
400.00
500.00
500.00
1,026.00
1,026.00
7 Saw Cutting
873 LF
0.75
654.75
1.05
916.65
1.00
873.00
8 Curb & Gutter
684 LF
1 1.37
7,777.08
10.79
7,380.36
23.00
15,732.00
9 Sidewalk
510 SF
3.11
1,586.10
5.80
2,958.00
4.00
2,040.00
10 AC Pavement
4 TN
48.00
192.00
195.00
780.00
200.00
800.00
11 Clearing & Grubbing
1 LS
300.00
300.00
2,660.00
2,660.00
300.00
300.00
12 PED Signs
17 EA
300.00
5,100.00
65.50
1,113.50
275.00
4,675.00
13 Crosswalk Striping
5 LF
0.50
2.50
12.00
60.00
10.00
50.00
14 Paint Red Curbs
30 LF
2.00
60.00
5.10
153.00
9.00
270.00
15 Release
1 LS
1.00
1.00
1.00
1.00
1.00
1.00
Total
36,027.19
42,382.21
48,767.00
City of Moorpark
Exhibit 2
Bid Results: 2002 Ramps @ "T" Intersections
Page 2 of 2
[File # Bid Results - 2002 Ramps]
Bidder » »>
Vendor 3
Vendor 4
Vendor 5
Bid Opening:
Name:
Mendez Concrete,
Inc.
Nye & Nelson
Berry General Engineering
January 21, 2003
Address:
1210 E. Santa
Paula St.
1860 Eastman Ave.
[# 1081
P. O. Box 1457
Cit, State:
Santa Paula, CA
93060
Ventura, CA 93003
Ventura, CA 93002
Tel. No.:
805 -525 -8043
805- 654 -1682
805 -643 -7567
Contact Person:
Est Qty Units
1 LS
Manuel Mendez
Runic Nye
Dan Berry
Item Description
Unit Cost
Total Bid
Unit Cost
Total Bid
Unit Cost
Total Bid
1 Mobilization
3,888.29
3,888.29
7,500.00
7,500.00
8,038.00
8,038.00
2 Traffic Control
l LS
7,951.20
7,951.20
5,000.00
5,000.00
4,345.00
4,345.00
3 Type 5 Case A Ped Ramp
14 EA
1,246.75
17,454.50
1,150.00
16,100.00
820.00
11,480.00
4 Type 1 Case B Ped Ramp
18 EA
964.36
17,358.48
1,100.00
19,800.00
690.00
12,420.00
5 Remove Concrete
1 LS
7,951.20
7,951.20
5,000.00
5,000.00
21,675.00
21,675.00
6 Remove AC Pavement
I LS
950.40
950.40
3,000.00
3,000.00
1,675.00
1,675.00
7 Saw Cutting
873 LF
4.84
4,225.32
3.00
2,619.00
2.30
2,007.90
8 Curb & Gutter
684 LF
18.14
12,407.76
25.00
17,100.00
15.60
10,670.40
9 Sidewalk
510 SF
4.25
2,167.50
5.50
2,805.00
4.30
2,193.00
10 AC Pavement
4 TN
225.00
900.00
1,100.00
4,400.00
470.00
1,880.00
11 Clearing & Grubbing
1 LS
146.10
146.10
8,534.00
8,534.00
18,460.00
18,460.00
12 PED Signs
17 EA
215.73
3,667.41
200.0000
3,400.00
193.00
3,281.00
13 Crosswalk Striping
5 LF
29.22
146.10
34.00
170.00
26.65
133.25
14 Paint Red Curbs
30 LF
6.13
183.90
4.00
120.00
3.76
112.80
15 Release
i LS
1.00
1.00
1.00
1.00
1.00
1.00
Total
79,399.16
95,549.00
98,372.35