Moorpark City Council
Agenda Report
The Honorable City Council
Kenneth C. Gilbert, Director of Public Works
June 20, 2003 (Council Meeting 7 -2 -03)
TN__
SUBJECT: Notice of Completion for the 2002 Curb Ramp Project
BACKGROUND
In February of 2003, the City Council awarded a contract for the
construction of the subject project. The purpose of the project
was to install curb ramps at certain "T" intersections, in order
to improve handicap access.
DISCUSSION
A. Project Scope
The location of the thirty -two (32). new curb ramps is
illustrated on the map attached as Exhibit 1.
B. Quantity Adjustment
In the construction of a Public Works project, it is not
uncommon for the final actual quantity for given bid items to
differ from the engineer's estimate of quantities set forth in
the original bid documents. The final contract cost will
differ from the bid price, based upon the actual quantities
required.
The final quantities required for this project were more than
the engineer's estimate. The cost of the additional quantities
required was $5,003.15.
Curb ramp_cmp
Curb Ramp Project: Notice of Completion
June 20, 2003
Page 2
C. Change Orders
There was one Change Order required for the project, in the
amount of $2,128.95.
D. Fiscal Impact
1. Construction Cost: A summary of the final construction
costs is as follows:
Description Cost Est. ($)
Bid Amount 42,382.21
Quantity Adjustments 5,003.15
Change Orders 2.128.95
Total 49,514.31
2. Total Project Costs: Project 8030 is funded by
TDA Article
3 (SB -821) grant monies [Fund 2602],
with the
local share
costs coming from
Fund 2603:
TDA Article 8 (Local
Transportation Fund).
An estimate
of the
total final
project costs, allocated to
funding sources, is as
follows:
Proiect 8030
Fund 2602
Fund 2603
Description
SB -821 ($)
LTF ($)
Total
FY 02/03
Design
5,591.00
5,591.00
11,182.00
Construction
24,757.15
24,757.16
49,514.31
Inspection
1,000.00
1.000.00
2,000.00
FY02103 Sub -Total
31,348.15
31,348.16
62,696.31
Plus Prior Year Design Costs
207.00
207.00
Total
31,348.15
31,555.16
62,903.31
3. Budget Surplus: The
projected
budget surplus for this
project is as follows:
Project 8030
Estimated
Projected
Description
Budget ($)
Actual ($)
Surplus ($)
Fund 2603: LTF
Design
20,000.00
5,591.00
14,409.00
Construction
77,000.00
24,757.16
52,242.84
Inspection
15,000.00
1,000.00
14,000.00
Sub -Total
112,000.00
31,348.16
80,651.84
Fund 2602: SB -821 Grant
Design
5,700.00
5,591.00
109.00
Construction
35,800.00
24,757.15
11,042.85
Inspection
1,500.00
1,000.00
500.00
Sub -Total
43,000.00
31,348.15
11,651.85
Total
155,000.00
62,696.31
92,303.69
Curb ramp_cmp
Curb Ramp Project: Notice of Completion
June 20, 2003
Page 3
4. Reallocation of Fund 2602 Suzplus: The City Council
recently awarded a contract for the Flinn Avenue
Realignment Project [Project 8037]. That project included
the widening of Spring Road to accommodate new Bike Lanes.
A portion of the cost of that street widening is funded by
SB -821 bicycle / pedestrian facilities grant money (SB -821
- Fund 2602).
It is the intent of staff to
action, the above cited Fund
Flinn Avenue project.
E. Final Inspection and Acceptance
transfer, via administrative
2602 surplus [$11,652] to the
The City has completed a final inspection of the project and
has found the work to be acceptable, less minor "punch- list"
items. At this time it would be appropriate for the City
Council to accept the project as complete and direct the City
Clerk to record the Notice of Completion to start the final
lean period, upon completion of correction of the "punch -
list" items. Absent the receipt of any Stop Notices from
subcontractors or suppliers, the ten percent retention will
be released thirty -five (35) days after the date of the
recordation of that notice.
STAFF RECOMMENDATION
Accept the work as complete.
Attachments: