HomeMy WebLinkAboutAGENDA REPORT 2003 0903 CC REG ITEM 10JMoorpark City Council
Agenda Report
ITEM 10 • T.
To: The Honorable City Council
From: Kenneth C. Gilbert, Director of Public Works
Date: August 20, 2003 (Council Meeting 9 -3 -03)
Subject: Consider Approving an Increase to the Estimated Cost for
the Flinn Avenue Realignment Project (Project 8037] and
Adoption of a Resolution Amending FY 2003/2004 Budget
for Said Purpose
BACKGROUND
Last May the City Council approved the award of contract, in the
amount of $539,865, to Nativ Engineering for the construction of
the subject project. That action included the approval of a ten
percent (100) construction contingency in the amount of $53,987.
DISCUSSION
A. Summary of Proposed Change
It is requested that an additional $127,680 be approved for
the Project to cover certain unforeseen costs, most of which
are related to conflicts with underground utilities which
were previously unknown.
B. Added Work
Subsequent to the Notice to Proceed, the contractor was
directed to construct certain improvements not included in
the original design. This added work calls for the
installation of conduits to the west side of Spring Road, to
enable the City to, at some point in the future, provide
irrigation water to landscaped parkways to be constructed on
the west side of the street. The estimated cost for this
added work is summarized as follows:
Description Est. Amt. ($)
Change Order 4A: Conduit from median to West Parkway 5,600.00
Change Order 413: Conduit across Second Street 4.000.00
Total 9,600.00
flinn amnd
Flinn Avenue Realignment: Revise Contingency
August 20, 2003
Page 2
B. Additional Quantities
The actual quantities for certain bid items will exceed the
Engineer's Estimate, resulting in actual costs exceeding the
bid amounts. A summary of these added costs is as follows:
Description Bid Qty. Est. Actual Qty. Added Cost ($)
Item 3: Excavation 1,521 CY 2,270 CY 20,972.00
Item 13E: 5" Conduit 145 LF 298 LF 11.622.00
Total 32,594.00
C. Change Order Summary
The nature of the work has required staff to approve, or
consider approving, a number of Contract Change Orders,
generally summarized as follows:
Description
Est. Amt. ($)
1
Move Bus Stop
0
2a
Add conduit to street light not shown on SCE plans
6,500
2b
Revise design for Fire Hydrant relocation to avoid telephone conduits
11,300
2c
Revise design for Storm Drian lateral to avoid telephone conduits
13,500
2d
Revise design for SCE Conduit on Minor St. to avoid telephone conduits
4,400
2e
Relocate Water Air Vac
5,400
3
Excavation in Rear Yards required to bore street light conduit
10,000
4g SCE conflict with Telephone [Old Flinn Avenue]
Sub - total: Approved to Date
51,100
4a
Conduits to west side parkway
5,600
4b
Conduits crossing Second Street
4,000
4c
Additional boring to accommodate Adelphia conduit
6,400
4d
SCE conflict with Storm Drain box at Second Street
7,740
4e
SCE conflict with Storm Drain box: three street lights
3,000
4f
Relocate Signal pole - conflict with wall foundation
1,000
4g
SCE conflict with Telephone [Old Flinn Avenue]
1,500
Total
80,340
D. Substructure Conflicts
A number of the above listed Change Orders were generated
when the Contractor encountered a number of conflicts between
the improvements being constructed and existing
underground
structures and facilities. A list of the above Change Orders
caused by substructure conflicts is as follows:
Description
Est. Amt. ($)
2b Revise design for Fire Hydrant relocation to avoid telephone conduits
11,300
2c Revise design for Storm Drian lateral to avoid telephone conduits
13,500
2d Revise design for SCE Conduit on Minor St. to avoid telephone conduits
4,400
3 Excavation in Rear Yards required to bore street light conduit
10,000
4d SCE conflict with Storm Drain box at Second Street
7,740
4e SCE conflict with Storm Drain box: three street lights
3,000
4f Relocate Signal pole - conflict with wall foundation
1,000
4g SCE conflict with Telephone [Old Flinn Avenue]
1,500
52,440
flinn_amnd
(f
V C -, ..
Flinn Avenue Realignment: Revise Contingency
August 20, 2003
Page 3
E. Cost Estimates
The amounts noted for the above Change Orders are estimates.
Actual costs will be determined upon completion of the work.
F. Electrical Undergrounding and Street Lighting Cost
The approved project included costs related to the
installation of an underground electrical system and new
street lights. Many of the above noted change orders relate
to these components of the work. A revised summary of these
costs is as follows:
Description
Est. Amt. ($)
Direct costs to SCE
61,625
Bid Price [Item #13] plus additional quantity ( #13E)
150,898
Sub -Total
212,523
Change Orders:
2a Add conduit to street light not shown on SCE plans
6,500
2d Revise design for SCE Conduit on Minor St. to avoid telephone conduits
4,400
4d SCE conflict with Storm Drain box at Second Street
7,740
4e SCE conflict with Storm Drain box: three street lights
3,000
4g SCE conflict with Telephone [Old Flinn Avenue]
1,500
Total
235,663
G. Added Contract Time
The extra work encountered by the Contractor has required
staff to add contract days to the contract.
H. Additional Construction Engineering Costs
The added contract time will require more contract
administration hours, increasing the cost for this consultant
contract from $70,000 to $91,000.
I. Fiscal Impact
1. Revised Construction Cost Estimate: Based on the above
described changes, the revised estimated construction
costs are as follows:
Bid Amount
Change Orders to date [Est.]
Extra Quantities to Date
Contingency (10 %)
Total
Amount ($)
539,865.00
80,340.00
32,594.00
Subtotal 652,799.00
53,986.50
706,785.50
flinn_amnd
,,± p
Flinn Avenue Realignment: Revise Contingency
August 20, 2003
Page 4
2. Total Project Cost Estimate: The revised total project
costs are summarized as follows:
Description
Design
Design Support
Right -of -Way
Construction Contract ( +10 %)
SCE Undergrounding Direct Costs
Inspection / Contract Admin.
Total
Amount ($)
60,000
500
2,000
707,000
61,625
91,000
922,125
3. Budget Amendment: The attached Resolution provides for an
amendment to the Budget to reflect the revised costs
described herein. That Resolution is summarized as
follows:
Descri t
Design
Fund
2501 L A AOC
2902 MRA
Current Budget ($
12,945
12,945
25,890
Change ($) Revised
0
0
0
12,945
12,945
25,890
Construction 2501
L A AOC
302,160
53,340
355,500
* > 2605
Gas Tax
16,000
-
16,000
*` > 2602
TDA Art. 3
41,805
-
41,805
2902
MRA
302,160
53,340
355,500
662,125
106,680
768,805
Inspection 2501
L A AOC
35,000
10500
45,500
2902
MRA
35,000
10500
45,500
Total FY 02/03 758,015 127,680 885,695
Plus Prior Year Costs 39,610 0 39,610
Total Project Budget 797,625 127,680 925,305
** Campus Park Medians
* ** Portion of Spring Rd. Widening
STAFF RECOMMENDATION (Roll Call Vote)
1. Approve the revised project costs as set forth in this
report.
2. Adopt Resolution NO. 2003- amending the Budget for this
project.
Attachments:
Exhibit 1: Resolution
flinn amnd
Exhibit 1
RESOLUTION NO. 2003-
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF MOORPARK, CALIFORNIA, AMENDING THE FY
03/04 BUDGET TO REVISE THE AMOUNTS OF THE
APPROPRIATIONS AND BUDGET FOR PROJECT 8037:
FLINN AVENUE REALIGNMENT [L. A. AVE. AOC FUND
(FUND 2501); MRA AREA 1 OPERATIONS FUND (FUND
2902)]
WHEREAS, on June 18, 2003, the City Council adopted the
Budget for Fiscal Year 2003/04; and
WHEREAS, a staff report has been presented to the City
Council requesting a budget increase in the aggregate amount of
$127,680); and
WHEREAS, Exhibit "A ", attached hereto and made a part hereof,
describes said budget amendment and its resultant impacts to the
budget line item(s).
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK DOES
HEREBY RESOLVE AS FOLLOWS:
SECTION 1. That a Budget amendment in the aggregate increase
of $127,680, as more particularly described in Exhibit "A ", is
hereby approved.
SECTION 2. The City Clerk shall certify to the adoption of
this resolution and shall cause a certified resolution to be filed
in the book of original resolutions.
PASSED AND ADOPTED this 3rd day of September, 2003.
Patrick Hunter, Mayor
ATTEST:
Deborah S. Traffenstedt, City Cler
Attachment:
Exhibit 'A': Appropriation and Budget Detail
Resolution No. 2003
Exhibit "A"
Revised Appropriations & Budget
For Project 8037: Flinn Avenue Realignment
A. Fund Allocation
Fund _ Account Number
L. A. Ave. AOC 1;2501.8310.8037.5500
2602.8310._8037.5500_ -
Gas Tax i2605.8310.8037.5500
RA -- ------ ___ --- — ----- — - --------- 12 _!� 0-2 . -n-f ��8 UTT.3_�----- - - - - --
M O
'rotai s 12 /, bdu
- - ---------- - _ -- - ------
B. FY 03/04 Budget Re-Cap
------ - - ------
_______._ - -- ------
Current Subject;
Revise
FY 03/0411 Appropriation' FY 03/04
Account Number Budget (Reduction), 1 Budget,
,2501.8310.8037.xxxx $ 350,105„ $ $ 63,840_; 413,945,
. .... ..... -------
--- --- - ----------- --- $--,--4 --- 1 0 $
— ---------- -------- - V $ 16,006 __
2605.8310.8037.xxxx
2902. ------- - -- - -- - ------
i8310.8037.xxxx 1 $ 350,1051 $ 63,840i $ 413,945
$- - -758, 0151 $ 127,6801
$ 885,695
C. Total Appropriations Re-Cap
— ------ - ---------- -- — -------- ----- - ------------
Revised,
i FY 03/04; Prior Years i Total,
'Account Number Budget: Expenditures! Approp iations!
1 '2 5 01.831 0 .8 03 7.x xX x $ 413, 945 $ 19,805! $ 433,750
7--_- - - -- -- - --- - -------- -. � 6 62A I 0 . 8037 x xx X $ 41, 805 $ T1,805
'
2605.8310.8037.X___XXx f $
I 16,000
$ 16, 000
-- -------- - ------ 433, 7-
- - - - --2.8M. 8037. xxxx $ 413,Y45 $ f 9,8 5 F 5U
$ 885,6951 $ 39,610 $ 925,305
----------- _ - - ----- ------ -
D. Distribution of Appropriations to Expense Accounts
Current Subjectl Revised
FY 03/04 Appropriation FY 03/04:1
,
IAccount Number Budget (Reduction) Budget
2501.8310.8037.9601: Design $ 12,945 1 .4 $ 0 $ 12,945
2902.8310.8037.9 6 0 _1 56-sign $ 12, 945 $ 0: $ - -12 , 9 4 5
$ 25,890 $ 0 $ 25,890
----------- - - ----- --------
��2602 8310_ - - - ------------ - ---- - ------ ---------
- - --
$ 41, 805
$ 0 $ 41,805
,2%_U5_.8310.8037.9640: Const i $ 16,000 $ 0 $ 16,000i
---------------------- - I
2501. 8310. 8037. --- n-st 1 $ 302, 5__3,_ -3 --- 4-0-1 $ 355,500i
355,500; --
10.8037.9650: C'o-n-'st $ 302,160 $ 53,340
$ 662,125 $ 106,680 $ 7668,805
2501 - .8310. 8037.9650: -- -- -- - --- _i_n_sp__.__;I ----- 35, 000 -- — $ --- -- 10,500 45,500:
Insp. 1 $35,000 $ 10,500 $ 45,500
70,000 $ 21,000 $ 91,000!
f6_t_a_f_Pr_o3_e_ct $ 758,015 $ 127,680 1 $ 885,695 1
Approved as to form: