HomeMy WebLinkAboutAGENDA REPORT 2005 0615 CC REG ITEM 10CITEM 10- C-
CITY of MOORPARK, CALIFORNIA
City Counch (Mooting
of
ACTION:
:
Moorpark City Council BY
Agenda Report
To: The Honorable City Council
From: Kenneth C. Gilbert, Director of Public Works
Date: June 3, 2005 (Council Meeting 6- 15 -05)
Subject: Notice of Completion for the Construction of the Flinn
Avenue Realignment Project [Project 80371
BACKGROUND
A contract for the construction of the project was awarded to
Nativ Engineering in November of 2003. Construction was
substantially completed by the end of 2004, pending completion of
work related to the undergrounding of overhead utilities.
Recordation of a Notice of Completion for the project was delayed
pending resolution of a number of claims filed by certain
subcontractors and suppliers.
DISCUSSION
A. Scope of Work
The subject project included the following:
• construction of a new Flinn Avenue to intersect Spring
Road at Second Street;
• widening of the east side of Spring Road from Flinn Avenue
northerly to the rail crossing;
• construction of a raised center median (without
landscaping) in Spring Road from Flinn Avenue to the rail
crossing;
• construction of a traffic signal at the new intersection
of Spring Road, Flinn Avenue and Second Street;
• installation of conduits and vaults necessary to
underground the overhead utilities on Spring Road, Flinn
Avenue and Fitch Street in the vicinity of the Police
Station; and
• installation of colored, stamped concrete in the Campus
Park Drive median east of Collins Drive.
flinn cmp 0506
Flinn Avenue Realignment: Award Contract
June 15, 2005
Page 2
C. Changes
1. Quantity Adjustments: As is typical with public works
construction projects, the actual quantities required for
the job differed from the engineer's estimate. This
project required more quantities of certain bid items
resulting in additional costs of $6,920.58.
2. Change Orders: Ten (10) Change Orders approved for the
project, summarized as follows:
Change Order
Amount ($)
1. Move Bus Turn -out
0.00
2. Move fire hydrant, move S D, add conduit, relocate air vac
40,100.00
3. Extra work related to conduits
15,000.00
4. Reduction in Certain Unit Prices
0.00
5. Extra Irrigation and Conduit work
33,706.00
6. "Old" Flinn Avenue [cul -de -sac]
42,375.00
7. Price Change for A -C Work
16,844.00
8. Water Dist. Permit Costs
8,074.00
9. Changes to design for sewer connection
17,017.60
10. Litigation Resolution
(33,516.00)
139,600.60
K. Fiscal Impact
1. Unresolved Issues: Staff is still working with the
contractor to resolve certain unresolved matters. The
project costs noted herein are current estimates based on
knowledge to date.
2. Construction Contract Costs: The estimated total
construction contract costs are as follows:
........ ... ............_.._......................__..................................................................................................................................... ..........................................._ ...................
.._............,
Description Amount ($)
Bid Amount 533,491.00
:Additional Quantities 6,920.58
Change Orders 139.600.66
Total 680,012.24
. . . . . . . . . . . . . . . . . . . . . . ............. . ....... ........ . ......... . . . . . . . . . . . . . . ...................... . ............. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ........... . . . . . . . . . . . . . . . . .. . .. . .......... . . . . ........................... . . . . . . . . ........... . . . . . . . . . . . ............
3. Total Construction Costs: The estimated total
construction costs are estimated as follows:
flinn cmp 0506
�(i�f 2
Flinn Avenue Realignment: Award Contract
June 15, 2005
Page 3
4. Budget Recap Sheet: A Budget Re -cap Sheet is attached as
Exhibit 1. This chart shows the total appropriations and
current Budget amount for the project.
5. Budget Status: The currently estimated total
appropriations (Budget) for the subject project is broken
down as follows:
Description
Fund Appropriations
Total
($)
Est. Total Est.
Cost ($) Appropriations
Unexpended
($)
Design
2501 L A AOC
35,216
34,280.00
936
2902 MRA
35,217
14,517.00
20,700
70,433
48,797.00
21,636
Right -of -Way
2501 L A AOC
1,000
1,000.00
-
2902 MRA
1,000
1,000.00
-
2,000
2,000.00
-
Construction
2501 L A AOC
410,841
357,517.00
53,324
2605 Gas Tax
15,853
15,853.00
-
2602 TDA Art. 3
42,600
42,600.00
-
2902 MRA
410,842
348,166.00
62,676
880,136
764,136.00
116, 000.00
Inspection
2501 L A AOC
55,777
49,700.00
6,077
2902 MRA
55,778
51,000.00
4,778
111,555
100,700.00
10,855
Total
............ ........ ...
....................... ...................................................... .............. ...............................
1,064,124
...........................................................
915,633
......... ........... .._..
. 148,491
The above
cited amount for
unexpended
appropriations
will
be returned to sources when
the project is closed
out.
D. Final Inspection and Acceptance
The City has completed a final inspection of the project and
has found the work to be acceptable. At this time it would be
appropriate for the City Council to accept the project as
complete so that the City Clerk may record the Notice of
Completion to start the final lien period. Absent the
receipt of any Stop Notices from subcontractors or suppliers,
the ten percent retention will be released thirty -five (35)
days after the date of the recordation of that notice.
STAFF RECOMMENDATION
Accept the work as complete.
flinn cmp 0506
0 0(),2 7 -!
CITY OF MOORPARK
Capital Improvement Project
Budget Re -Cao Sheet
Exhibit: 1
Date: June 1, 2005
000'27
Department: Public Works MSGdl Tear-, r T U4/U5 Department: 8310
Project Title: Flinn Avenue Realig nment Project Number: 8037
Total Current A 3propriations
Fund
2501
2902
2501
2902
2501
2602
2605
2902
2501
2902
Project
Object
Code
9601
9601
9610
9610
9640
9640
9640
9640
9640
9640
Totals:
Account
Description
Design
Design
Total Design
Land
Land
Total Land
Construction
Construction
Construction
Construction
Total Constr.
Inspection
Inspection
Total Inspection
Total Prior
Years'
Expenses
$34,280
$33,147
$67,427
$1,000
$1,000
$2,000
$355,517
$42,600
$15,853
$346,166
$760,136
$49,681
$51,094
$100,775
$930,338
Current FY
Beginning Year
Budget
$671
$1,735
$2,406
$0
$0
$0
$8,058
$0
$147
$17,409
$25,614
$0
$0
$0
$28,020
Prior Budget
Changes This
FY
$265
$335
$600
$0
$0
$0
$47,266
$0
($147)
$47,267
$94,386
$6,096
$4,684
$10,780
$105,766
Current FY
Total Bud et
$936
$2,070
$3,006
$0
$0
$0
$55,324
$0
$0
$64,676
$120,000
$6,096
$4,684
$10,780
$133,7L6j
Total Approp.
To Date
$35,216
$35,217
$70,433
$1,000
$1,000
$2,000
$410,841
$42,600
$15,853
$410,842
$880,136
$55,777
$55,778
$111,555
$1,064,124
Requested Budget Amendment / Revised-To
al Appropriations
Object Account
Fund Code Description
2501 9601 Design
2902 9601 Design
xxxx 1 9610 R -O -W Ac q.
2501 9640 Construction
xxxx 9640 Construction
2902 9640 Construction
2501 9650 Inspection
2902 9650 Inspection
Project Totals:
Current FY
Total Budget
$936
$2,070
$0
$55,324
$0
$64,676
$6,096
$4,684
$133,786
Proposed
Budget Change
$0
$0
$0
$0
$0
$0
$0
$0
$0
Revised Current
FY Budget
$936
$2,070
$0
$55,324
$0
$64,676
$6,096
$4,684
$133,786
Previous Total
Appropr.
$35,216
$35,217
$2,000
$410,841
$58,453
$410,842
$55,777
$55,778
$1,064,124
Proposed
Revised Total
A pro .
$35,216
$35,217
$2,000
$410,841
$58,453
$410,842
$55,777
$55,778
$1,064,124
Pro ossed Revised
Funding mary
Fund
2501
2602 1
2605
2902
Fund Name
L A AOC
TDA Art. 3
as Tax
MRA
Total Prior
Years'
Expenses
$440,478
$42,600
$15,853
$431,407
Current FY
Beginning Year
Budget
$8,729
$0
$147
$19,144
Previously
Approved
Appropr. This
FY
$53,627
$0
$147
$52,286
Proposed
Additional
Appropr. This
Time
$0
$0
$0
$0
Proposed
Revised Total
Ap rop.
$502,834
$42,600
$15,853
$502,837
Project Totals:
$930,338
$28,020
$105,766
$0 1
$1,064,124
000'27