FROM: Mary K. Lindley, Parks, Recreation, and Community
Services Director
DATE: July 12, 2005 (CC Meeting of 7/20/05)
SUBJECT: Consider Authorization of Recordation of the
Notice of Completion and FY 2005/06 Budget
Amendment for the Mountain Meadows Park
Playground Improvement Project
SUMMARY
On June 1, 2005, the City Council awarded a contract to
Premium Construction to perform playground improvements at
Mountain Meadows Park. The total cost of the contract was
$38,630. As of July 12, the project is substantially
completed with one Change Order in the amount of $4,175,
bringing the final construction contract cost to $42,805.
The City Council
recordation of the
attached Resolution
accommodate the one
DISCUSSION
is being asked to authorize the
Notice of Completion and adopt the
amending the FY 2005/06 budget to
Change Order.
The project consisted of the removal of the existing play
equipment and the purchase and installation of new
playground equipment. The completed improvements include
traditional playground equipment - two separate play
apparatuses, one designed for children 5 to 12 years of
age, a smaller apparatus for children 2 to 5 years of age,
and a new swing set that includes two bays of two
individual swings each (total of 4 swings), of which two
swings will accommodate toddler aged children.
111 :•
Honorable City Council
July 20, 2005
Page 2
Additionally, the improvements include a stand -alone play
apparatus called Supernova. The Supernova is a large
slanting ring that spins while children attempt to balance
on it. It is most similar to a traditional merry -go- round.
The Supernova is made by Kompan and sold by a company
called Three Wishes.
Also, the small circle playground to the east of the larger
playground area now contains a new climbing apparatus
called a "Space Ball ". The Space Ball is made by a German
playground company and it adds a unique feature to Mountain
Meadows Park not found in the City's other parks. All of
the equipment included in the design meets the current
California playground safety requirements.
The play surface in the large lot contains a mixture of
sand and "poured -in- place" rubber material. This meets the
ADA accessibility requirements. The surface in the small
round play lot with the Space Ball contains sand.
Notice of Completion
As stated above, construction of the Project has been
substantially completed pursuant to the approved plans and
specifications, less minor "punch" list items. There was
one Change Order for 50 tons of additional playground sand
for the amount of $4,175. At the completion of the
construction work, the total cost of the construction
contract awarded to Premium Construction was $42,805. With
the Council's authorization to record the Notice of
Completion, the Contractor will receive the balance of the
payment due, 35 days after the recordation and fulfillment
of all contractual obligations as determined by the City.
Additionally, the City Clerk's Office will be authorized to
release the project bonds in accordance with the contract
provisions.
Budget Amendment
The Mountain Meadows Park Playground Improvement budget is
currently $120,427. To cover the Change Order identified
above, the Council is being asked to adopt a resolution
amending the FY 2005/06 budget by appropriating an
additional $4,175 from the Park Improvement Zone 3 Fund
Balance, to the Mountain Meadows project budget. With the
project now complete, final expenditures total $124,602 and
are broken down as follows:
M: \MLindley \PARKS \Mountain Meadows \MM Park Notice of Completion Budget
Amendment ccagda 7- 20- 05.doc 000290
Honorable City Council
July 20, 2005
Page 3
Exoenditure Cost
Play equipment purchase $69,797
Play equipment install (includes CO #1) 42,805
Rubber ADA Surface 10,000
Project Coordinator 2,000
Estimated Total $124,602
STAFF RECOMMENDATION (Roll Call Vote)
Authorize the City Clerk to file the Notice of Completion
for the project, and authorize the release of the balance
of payment, due upon satisfactory clearance, thirty -five
(35) days after Notice of Completion records, release bonds
in accordance with the contract, and completion of closeout
contractual obligations on the part of contractor, and
adopt the attached Resolution No. 2005- ,amending the
project budget.
Attachment A - Resolution 2005-
M: \MLindley \PARKS \Mountain Meadows \MM Park Notice of Completion Budget
Amendment ccagda 7- 20- 05.doc 0 0 0 2 9'L
Honorable City Council
July 20, 2005
Page 4
RESOLUTION NO. 2005-
ATTACHMENT A
RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF MOORPARK, CALIFORNIA, AMENDING
THE FY 2005/06 BUDGET TO ALLOCATE $4,175
FROM THE PARK IMPROVEMENT ZONE 3 FUND
BALANCE (2113) TO THE MOUNTAIN MEADOWS
PLAYGROUND IMPROVEMENT EXPENDITURE BUDGET
WHEREAS, on June 15, 2005, the City Council adopted
the budget for Fiscal Year 2005/06; and
WHEREAS, a staff report has been presented to said
Council requesting a budget amendment allocating $4,175 to
the Mountain Meadows Playground Improvement expenditure
budget from the Park Improvement Zone 3 Fund Balance; and
WHEREAS, Exhibit "A" hereof describes said budget
amendment and its resultant impacts to the budget line
item(s) .
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF
MOORPARK DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. A budget amendment allocating $4,175 to
the Mountain Meadows Playground Improvement expenditure
budget from the Park Improvement Zone 3 Fund Balance as
more particularly described in Exhibit "A" attached hereto
is hereby approved.
SECTION 2. The City Clerk shall certify to the
adoption of this resolution and shall cause a certified
resolution to be filed in the book of original resolutions.
PASSED AND ADOPTED this 20th day of July, 2005.
Patrick Hunter, Mayor
ATTEST:
Deborah S. Traffenstedt, City Clerk
M: \MLindley \PARKS \Mountain Meadows \MM Park Notice of Completion Budget
Amendment ccagda 7- 20- 05.doc 000292
Honorable City Council
July 20, 2005
Page 5
Attachment: Exhibit A
Resolution No. 2005-
EXHIBIT A
Budget Revision
A. Fund Allocation:
Fund No.
Fund Name
Amount
2113.5500
Park Improvement Fund - Zone 3
$4,175
$4,175
$124,602
B. Budget Appropriation:
BUDGET NUMBER
BUDGETED
REVISION
NEW BUDGET
2113.7800.7810.9632
$120,427
$4,175
$124,602