TO:
FROM:
DATE:
SUBJECT:
MOORPARK
MEMORANDUM
The Honorable City Council
Steven Kueny, City Manager J>C}
August 11, 1988
STEVEN KUENY
City Manager
CHERYLJ.KANE
City Attorney
PATRICK RICHARDS, A.l.C.P.
Director of
Community Development
R. DENNIS DELZEIT
City Engineer
JOHN V. GILLESPIE
Chief of Police
Proposed Improvements of Unimproved Medians
and Parkways
The City Council recently requested a status report on planned
jmprovements for certain medians and related work. In attached
Exhibits "A" and "B" I have provided a list of medians and parkways,
respectively, that are in need of improvement and accompanying status
of each project. Also included are those locations that are totally or
partially improved and require City reimbursement to a developer. The
Council may also be aware of other locations not on the attached
lists. It would be helpful to add them to the list and incorporate the
complete list to the City's Capital Improvement Plan for construction
as funds become available.
In addition to the two AOC and developer financing, the City has
included funds in AD 84-2 to improve a portion of the unimproved areas
each year. The amount available in 1988/89 is $15, 000. In 1987 /88,
the City, along with the Marlborough Homeowners Association (HOA),
jointly improved the parkway at the southwest corner of Peach Hill and
Spring Road. The total cost was about $7, 500 with the HOA committed
for $3, 500. The Council should consider developing a priority list for
the unfunded projects it desires to have improved or at least designate
the project ( s) to be constructed with the $15, 000 from AD 84-2 for
1988/89. Staff feels that consideration should be given to the parkway
on the east side of Peach Hill Road extending north from Peach Hill
Park and the Princeton Avenue median and parkways. The first
location, to at least Westgate Road, would complement the recent
improvements installed as part of the park construction. The second
location would improve a primary entrance to a major area of the City.
799 Moorpark Avenue Moorpark, California 93021 (805) 529-6864
The Honorable City Council
August 11, 1988
Page 2
Staff Recommendation
Determine priority use for $15,000 of AD 84-2 funds for median and/or
parkway improvements and, further, direct Staff concerning other
portions of this report .
SK:sc
cm.88111
Attachments
EXHIBIT 'A'
MEDIANS
1. Description
Tierra Rejada Road west of Peach Hill Road to PC-3 (Warmington
Tracts 3019 and 3525).
Status
To be funded by Tierra Rejada/Spring Road AOC. Developer has
installed median curb and partially installed irrigation system
and is entitled to reimbursement for completed work. Landscape
plans have been submitted to the City for review. An accurate
estimate for reimbursement is not available. No time estimate as
to when sufficient AOC funds will be available to complete work or
to reimburse the developer.
2. Description
Tierra Rejada Road east of Peach Hill Road to 550 feet west of
Spring Road (Tract 2865 Pacifica and Pardee).
Status
Funded by special assessment of $367. 00 on each of the 622 lots
within Tract 2865 as part of AD 84-2 over a four year period
($91. 70 per year). This tract did not pay into the AOC. Total
estimated cost of $228,000 ($156,000 for median and $72,000 for
hardscape). This included AC paving adjacent to the median. To
date the City has paid $27,834 to Pacifica and $56,068 to Pardee
for a total of $83,902. It is planned that design and final cost
estimates for the landscaping and irrigation be prepared in
1988/89 with construction in 1989/90. The assessments for the
fourth year (1989/90) are planned to be adjusted based on the
final cost estimate.
3. Description
Tierra Rejada Road from Spring Road to 550 feet west of Spring
Road (LDM 11 and PD 1062 and 1063 Embassy).
Status
AOC funded. If constructed by developer of LDM 11 and PD 1062 and
PD 1063, they would be reimbursed from AOC.
Exhibit "A"
Medians
Page 2
4. Description
Tierra Rejada Road from Spring Road to east City limits.
Status
AOC funded. No scheduled construction.
5. Description
Spring Road from Tierra Rejada Road to Arroyo Simi.
Status
AOC funded. No scheduled construction.
6. Description
Princeton Avenue from Los Angeles Avenue (Highway 118) to Campus
Park Drive.
Status
Unfunded.
7. Description
Campus Park Drive from Julliard to 200 feet east of Marquette
Street
Status
To be constructed by Griffin Homes within the next few months.
This would complete the planned median improvements the entire
length of Campus Park Drive.
8. Description
Tierra Rejada Road from Arroyo Simi north 710 feet.
Status
To be constructed as part of the Tierra Rejada Road Bridge project
at an approximate cost of $26, 000 from the Los Angeles Avenue
AOC. The landscaping and irrigation improvements must be designed
and installed. These improvements would also be funded by the Los
Angeles Avenue AOC.
9. Description
Los Angeles Avenue
A. Tierra Rejada Road to Spring Road.
B. Tierra Rejada Road to west City limits.
Exhibit "A"
Medians
Page 3
C. Condor Drive south to Condor Drive north.
D. High Street to Condor Drive South.
Status
A. AOC funded. No scheduled construction.
B. Unfunded. Due to existing right-of-way constraints may
not be feasible.
C. AOC funded. No scheduled construction.
D. Unfunded. Due to existing right-of-way and physical
constraints may not be feasible.
10. Description
New Los Angeles Avenue -Spring Road to Freeway 23.
Status
AOC funded. No scheduled construction.
11. Description
Tierra Rejada Road within PC-3.
Status
Previously improved by Urban West Communities (UWC). This is
Tierra Rejada/Spring Road AOC funded so UWC is entitled to
reimbursement. The reimbursement amount has not been determined.
AOC funds are not currently available for reimbursement.
cm. 88112
EXHIBIT I B"
PARKWAYS
1. Description
Princeton Avenue -Both sides from Los Angeles Avenue (Highway
118) to Campus Park Drive.
Status
Unfunded.
2. Description
Campus Park Drive -west of Princeton Avenue to its terminus
adjacent to Tract 2453.
Status
Unfunded.
3. Description
4.
5.
Campus Park Drive -south side from Princeton Avenue east to Penn
Street.
Status
Unfunded.
Description
Peach Hill Road -east side from Peach Hill Park north to Mesa
Verde Drive.
Status
Unfunded.
Description
Peach Hill Road from Mesa Verde Drive to Rolling Knoll Road
(portions of both sides of street excluding the north side between
Bella Vista and Vista Del Valle).
Exhibit "B"
Parkways
Page 2
Status
Unfunded.
6. Description
Tierra Rejada Road -north side from Peach Hill Road east to 550
feet west of Spring Road (Tract 2865 Pacific and Pardee).
Status
The Pardee portion of the parkway will be landscaped at the time
the meandering sidewalk is installed. These improvements have
been designed by the City as part of the AD 84-2 assessments for
Tract 2865 at a cost of about $1, 000. Pardee will install the
improvements in the near future. Installation is being delayed
until after scheduled installation of a water line adjacent to
this area. No improvements to the Pacifica portion are currently
planned.
7. Description
Rolling Knoll Road -west side from Peach Hill Road to 300 feet
north of Peach Hill Road.
Status
Unfunded.
8. Description
Spring Road west side from Arroyo Simi to Peach Hill Road (Tree
well cutouts provided, but no provision to provide trees or
irrigation system).
Status
Unfunded.
9. Description
Poindexter Avenue -south side of Sierra Avenue.
Status
Unfunded.
Exhibit "B"
Parkways
Page 3
10. Description
Poindexter Avenue -north side adjacent to railroad right of way.
Status
Unfunded.
11. Description
Second Street and Roberts Street at Spring Road -entrance to the
Tract.
Status
Unfunded.
12. Description
Millard Street at Los Angeles Avenue (Highway 118) -entrance to
the Tract.
Status
Unfunded.
13. Description
Los Angeles Avenue south side, west of Tierra Rejada Road
(existing planter adjacent to Tract 2817 -Griffin).
Status
Unfunded.
14. Description
Los Angeles Avenue south side, east of Tierra Rejada Road,
adjacent to Tract 2817.
Status
Planting street trees is responsibility of Griffin Homes.
Currently awaiting approval of Cal Trans and/or alternative plan
approved by Cal Trans and City.
15. Description
Los Angeles Avenue -north side Gabbert Road/Tierra Rejada Road,
east to Maureen Lane, adjacent to Industrial Park.
Exhibit "B"
Parkways
Page 4
Status
Developer has agreed to install meandering sidewalk and
landscaping. Awaiting final approval by Cal Trans.
16. Description
Moorpark Avenue (Highway 23) -both sides -High Street to Charles
Street.
Status
Unfunded.
17. Description
Various City entry monuments.
Status
Unfunded.
cm.88113