B. Consider Agreement with Southern California Edison for Energy Efficiency-Light
Fixture Replacement Rate. Staff Recommendation: Authorize the City Manager
to sign the Schedule LS-1 Option E, Energy Efficiency-Light Emitting Diode
(LED) Fixture Replacement Rate Agreement, subject to final language approval
of the City Manager. (Staff: Shaun Kroes)
Item: 9.B.
MOORPARK CITY COUNCIL
AGENDA REPORT
TO: Honorable City Council
FROM: Shaun Kroes, Program Manager
DATE: 12/02/2020 Regular Meeting
SUBJECT: Consider Agreement with Southern California Edison for Energy
Efficiency-Light Fixture Replacement Rate
BACKGROUND AND DISCUSSION
On November 30, 2018, the City executed an Agreement with Siemens Mobility, Inc.
(Siemens), for streetlight turnkey services for the purpose of acquiring streetlights from
Southern California Edison (SCE) and then converting them from high pressure sodium
(HPS) to light emitting diode (LED) fixtures. The first phase of the service was to
perform a system-wide field audit to identify which poles could be purchased from SCE.
Eventually, the City acquired 2,229 SCE poles, with a combined 2,363 fixture heads
(including decorative lights on High Street, single-mast poles and double-mast poles).
Conversion of the City-owned streetlights occurred in late spring/early summer, with the
lights along High Street pending final fixture selection and installation.
The City has the ability to request that the remaining lights (approximately 158) owned
by SCE be converted to LED through SCE’s LS-1 Option E program. The LS-1 Option
E program enables SCE to estimate the capital cost of converting the HPS light to LED
on a per-light basis. The City does not pay any additional costs to participate in the
program and SCE’s capital costs are recovered over a 20-year period through energy
cost savings which will be rolled into the existing rate schedule. SCE has estimated that
the conversion of 158 Edison-owned streetlights from HPS to LED will cost
approximately $59,100 (or $374.04 per light). The cost recovery will be spread over the
course of 20 years, paid for with energy savings. The SCE Agreement specifies;
however that SCE does guarantee that any energy or bill savings will accrue to the City
as a result of the LED Fixture replacement; however, by participating in the LS-1 Option
E program the City will be able to establish a more uniform streetlight look throughout
the City.
The City has the option of selecting a 3000 Kelvin degrees (3000k) color temperature
light or a 4000 Kelvin degrees (4000k) color temperature light. The 3000k color
temperature light is considered a “warm white” and the 4000k color temperature light is
between warm and cool on the spectrum. The City selected 3000k color temperature
Item: 9.B.
47
Honorable City Council
12/02/2020 Regular Meeting
Page 2
lights for City-owned streetlights and staff recommends that 3000k color temperature
lights be selected for the LS-1 Option E program.
FISCAL IMPACT
There is no fiscal impact associated with entering into the Agreement with SCE as the
City will pay no upfront costs for the conversion. SCE estimates that the City will see a
cost savings of $1,310 per year during the 20-year repayment period and a $4,265 per
year cost savings after 20 years.
COUNCIL GOAL COMPLIANCE
This action is consistent with City Council Strategy 5, Goal 2, Objective 3 (5.2.3):
“Complete Purchase and Convert Streetlights.”
STAFF RECOMMENDATION
Authorize the City Manager to sign the Schedule LS-1 Option E, Energy Efficiency-Light
Emitting Diode (LED) Fixture Replacement Rate Agreement, subject to final language
approval of the City Manager.
Attachment: Southern California Edison Agreement
48
ATTACHMENT
Southern California Edison Original Cal. PUC Sheet No. 57074-E
Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.
Sheet 1
SCHEDULE LS-1 OPTION E,
ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED) FIXTURE REPLACEMENT
RATE AGREEMENT
Form 14-965
(To be inserted by utility) Issued by (To be inserted by Cal. PUC)
Advice 3241-E R.O. Nichols Date Filed Jun 30, 2015
Decision 14-10-046 Senior Vice President Effective Jun 1, 2016
1P8 Resolution
49
SOUTHERN CALIFORNIA EDISON COMPANY
SCHEDULE LS-1 OPTION E, ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED)
FIXTURE REPLACEMENT RATE AGREEMENT
Form 14-965
06/2016
1
This Schedule LS-1 Option E, Energy Efficiency-Light Emitting Diode (LED) Fixture Replacement Rate
Agreement (Agreement), effective this day of _,
_(Effective Date), is entered into between Southern California Edison Company (SCE)
and __________________________, an SCE customer taking service on Schedule LS-1
(Applicant), referred to collectively as "Parties," and individually as "Party." This Agreement provides
for SCE, at Applicant’s request, to replace the existing street lighting fixtures serving Applicant’s
premises with Light Emitting Diode (LED) street lighting fixtures to achieve energy efficiency benefits for
Applicant, as set forth in Special Condition 14, Option E, Energy Efficiency-Light Emitting Diode (LED)
Fixture Replacement, of Schedule LS-1.
The Parties agree as follows:
1. LED FIXTURES
SCE shall install, own, operate, and maintain LED Fixtures for Applicant as set forth in Exhibit "A"
attached hereto and incorporated herein by this reference. The LED Fixtures provided hereunder
shall at all times remain the property of SCE.
2. LED FIXTURE REPLACEMENT COSTS
2.1 The replacement costs of the LED Fixtures provided hereunder shall be borne by
Applicant.
2.2 Applicant shall pay the charge for the LED Fixtures Replacement rate, which includes an
Energy Efficiency Premium Charge (EEPC) and a Base LED Charge, under Option E of
Schedule LS-1. Applicant elects Option E in lieu of an upfront, one-time payment of the
replacement costs.
2.3 SCE does not guarantee that any energy or bill savings will accrue to Applicant as a result
of the LED Fixture replacements.
3. COMMENCEMENT OF SERVICE
The Parties agree that SCE has the right to charge Applicant, and Applicant has an obligation to
pay SCE, for the charges set forth in Schedule LS-1, Option E, commencing on the date SCE
begins serving the LED Fixtures installed pursuant to this Agreement.
4. TERM AND TERMINAT ION
4.1 This Agreement shall be effective as of the Effective Date and shall continue for a term of
twenty (20) years from the commencement of service as specified in Section 3 above
(Term).
4.2 Applicant may terminate this Agreement at any time during the Term upon a thirty (30) -
day advance written notice, provided that Applicant, prior to or within the 30-day advance
notice period, assigns the Agreement to any New Party In (NPI) that owns, rents or
leases the premises served by the street lighting fixtures replaced under this Agreement
and will take service under Option E of Schedule LS-1 effective as of the date of
termination; otherwise, Applicant shall pay a one-time termination charge equal to the
present value of the balance of the EEPC of Option E over the remaining Term. The
present value is determined based on SCE’s authorized rate of return on rate base, or
discounted rate of 7.90%.
50
SOUTHERN CALIFORNIA EDISON COMPANY
SCHEDULE LS-1 OPTION E, ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED)
FIXTURE REPLACEMENT RATE AGREEMENT
Form 14-965
06/2016
2
5. AMENDMENTS; ASSIGNMENTS
5.1 Any changes or amendments to this Agreement must be in writing and must be executed
by the Applicant and SCE and, if required, be approved by the California Public Utilities
Commission (Commission).
5.2 Applicant shall not assign this Agreement without the prior written consent of SCE;
provided, however, that Applicant may assign the Agreement pursuant to the terms and
conditions of Section 4.2 above, and the NPI must assume all rights and obligations
under this Agreement for the remaining Term. Any assignment and assumption shall be
in a form acceptable to SCE.
6. NOTICE
Any notice either Applicant or SCE may wish to provide the other regarding this Agreement must
be in writing. Such notice must be either hand-delivered or sent by U.S. certified or registered
mail, postage prepaid, to the person designated to receive notice for the other Party below, or to
such other address as either may designate by written notice. Notices delivered by hand shall be
deemed effective when delivered. Notices delivered by mail shall be deemed effective when
received, as acknowledged by the receipt of the certified or registered mailing.
Applicant: SCE:
(Name)
Business Customer Division
(Title) Southern California Edison Company
2244 Walnut Grove Avenue
(Address) Rosemead, CA 91770
(City, State, Zip)
7. NONWAIVER
The failure of either Party to enforce any of the terms and conditions or to exercise any right or
privilege in this Agreement shall not be construed as a waiver of any such term and conditions or
rights or privileges, and the same shall continue and remain enforce and effect as if no such
failure to enforce or exercise had occurred.
8. SEVERABILITY
In the event that any of the provisions, or portions thereof, of this Agreement are held to be
unenforceable or invalid by the Commission, or any court of competent jurisdiction, the validity
and enforceability of the remaining provisions or any portion thereof shall not be affected.
9. APPLICABLE LAWS, RULES, AND REGULATIONS
This Agreement shall be subject to, and interpreted under the laws, rules, decisions and
regulations of the State of California, without regard to its conflict of laws principles, the
Commission, and SCE's Commission-approved tariffs.
51
SOUTHERN CALIFORNIA EDISON COMPANY
SCHEDULE LS-1 OPTION E, ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED)
FIXTURE REPLACEMENT RATE AGREEMENT
Form 14-965
06/2016
3
10. CALIFORNIA PUBLIC UTILITIES COMMISSION JURISDICTION
10.1 This is a filed form tariff agreement authorized by the Commission for use by SCE. No
officer, inspector, solicitor, agent or employee of SCE has any authority to waive, alter, or
amend any part of this Agreement except as provided herein or authorized by the
Commission. This Agreement is to be used in conjunction with Schedule LS-1 and
supplements the terms and conditions of the Applicant's electric service under Schedule
LS-1.
10.2 This Agreement shall at all times be subject to such changes or modifications by the
Commission as said Commission may, from time to time, direct in the exercise of its
jurisdiction.
10.3 Notwithstanding any other provisions of this Agreement, SCE has the right to unilaterally
file with the Commission, pursuant to the Commission's rules and regulations, an
application for change in rates, charges, classification, service, or rule or any agreement
relating thereto.
11. ENTIRE AGREEMENT
This Agreement, including SCE’s Commission-approved tariffs, constitutes the complete
agreement and understanding between the Applicant and SCE regarding the LED Fixtures
replacement costs. Prior agreements, representations, understandings, whether expressed or
implied, and communications, oral or written, between the Applicant and SCE shall not be
construed to be a part of this Agreement.
12. AUTHORIZATION SIGNATURE
In witness whereof, the Parties hereto have caused this Agreement to be signed by their duly
authorized representatives.
APPLIC ANT
BY:
NAME:
TITLE:
DATE SIGNED:
SOUTHERN CALIFORNIA EDISON COMPANY
BY:
NAME:
TITLE:
DATE SIGNED:
52
Form 14-965
06/2016
4
SOUTHERN CALIFORNIA EDISON COMPANY
EXHIBIT “A”
SCHEDULE LS-1 OPTION E,
ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED) FIXTURE REPLACEMENT
APPLICANT
CUSTOMER ACCOUNT NO.
SERVICE ACCOUNT NO.
(Additional account numbers/addresses may be attached hereto.)
SERVICE ADDRESS
APPLICANT REQUESTED READY TO SERVE DATE
ASAP
SCE READY TO SERVE DATE
DESCRIPTION OF LED FIXTURES/SCOPE OF WORK: SPECIFY HOW MANY STREET LIGHTING
FIXTURE REPLACEMENTS ARE BEING REQUESTED AND AGREED TO UNDER THIS
AGREEMENT AND OTHER RELEVANT DETAILS.
W.O. No(s):
53