HomeMy WebLinkAboutAGENDA REPORT 2021 1103 CCSA REG ITEM 10MCITY OF MOORPARK,
CALIFORNIA
City Council Meeting
of November 3, 2021
ACTION APPROVED STAFF
RECOMMENDATION.
BY K. Spangler.
M. Consider the Award of Contract to F.S. Contractors, Inc. for the 2021 Sidewalk
Rehabilitation Project (Project No. M0050). Staff Recommendation: Approve
Amendment No. 1 to Agreement between the City of Moorpark and F.S.
Contractors, Inc. for the 2021 Sidewalk Rehabilitation Project (M0050),
Specification No. MPK 21-01, in the amount of $30,269.80 and authorize the City
Manager to sign the Amendment subject to final language approval of the City
Manager. (Staff: Daniel Kim, City Engineer/Public Works Director)
Item: 10.M.
MOORPARK CITY COUNCIL
AGENDA REPORT
TO: Honorable City Council
FROM: Daniel Kim, City Engineer/Public Works Director
DATE: 11/03/2021 Regular Meeting
SUBJECT: Consider the Award of Contract to F.S. Contractors, Inc. for the 2021
Sidewalk Rehabilitation Project (Project No. M0050)
DISCUSSION
On April 29, 2020, the City Council authorized staff to allocate remaining funds
associated with the Tax Allocation Bond issued in 2006 to undertake Capital
Improvement Projects that benefit the former Redevelopment Agency (RDA) Project
Area. One of the approved and appropriated project allocations was in the amount of
$273,324 for sidewalk rehabilitation within the RDA Project Area. On September 1,
2021, the City Council awarded a construction contract to F.S. Contractors, Inc. in the
amount of $220,001.00, plus a 10% project contingency amount of $22,000.10, for a
total contract amount of $242,001.10.
The Plans and Specifications for the 2021 Sidewalk Rehabilitation Project proposed
14,000 square feet of sidewalk replacement. Because the total contract award amount,
including the 10% contingency amount, is less than the appropriated project allocations,
staff is recommending to increase the total quantity of sidewalk replacement at the bid
unit price.
The project will be funded from Account No. 3005-311-M0050-55200. After taking into
consideration the cost for legal advertisement for bid solicitation ($1,053.10) and the
construction contract, the available remaining budget for the project is $30,269.80.
Account No. 3005-311-M0050-55200 $273,324.00
Legal Advertisement ($1,053.10)
Construction Contract ($242,001.10)
Budget Remaining $30,269.80
Item: 10.M.
449
Honorable City Council
11/03/2021 Regular Meeting
Page 2
Staff is recommending to increase the proposed quantity of sidewalk replacement from
14,000 square feet to 16,751.8 square feet. The additional 2,751.8 square feet of
sidewalk replacement, at the bid unit price of $11.00 per square feet, is $30,269.80 and
will be covered by the remaining budget amount. Amendment No. 1 to the current
Agreement with F.S. Contractors, Inc. will increase the total contract amount to
$272,270.90.
FISCAL IMPACT
None.
COUNCIL GOAL COMPLIANCE
This action does not support a current strategic directive.
STAFF RECOMMENDATION
Approve Amendment No. 1 to Agreement between the City of Moorpark and F.S.
Contractors, Inc. for the 2021 Sidewalk Rehabilitation Project (M0050), Specification
No. MPK 21-01, in the amount of $30,269.80 and authorize the City Manager to sign the
Amendment subject to final language approval of the City Manager.
Attachment: Amendment No. 1
450
ATTACHMENT
AMENDMENT NO. 1
AGREEMENT BETWEEN THE CITY OF MOORPARK AND
F.S. CONTRACTORS, INC. FOR THE 2021 SIDEWALK REHABILITATION PROJECT
(M0050), SPECIFICATION NO. MPK 21-01
This Amendment No. 1 to the Agreement between the City of Moorpark, a
municipal corporation (“City”), and F.S. Contractors, Inc., a corporation (“Contractor”),
for construction services (“Agreement”), is made and entered into on this ___ day of
____________________, 2021.
RECITALS
WHEREAS, on September 28, 2021 the City and Contractor entered into an
Agreement to have the Contractor provide construction services related to sidewalk
repair and rehabilitation; and
WHEREAS, the City and Contractor now desire to amend the Agreement for an
additional period; and
WHEREAS, the City and Contractor now desire to amend the Agreement to
increase the compensation for services to be performed by Contractor from Two
Hundred Forty-Two Thousand One Dollars and Ten Cents ($242,001.10) by a value of
Thirty Thousand Two Hundred Sixty-Nine Dollars and Eighty Cents ($30,269.80) for a
total contract value of Two Hundred Seventy-Two Thousand Two Hundred Seventy
Dollars and Ninety Cents ($272,270.90), and document said agreement to amend by
jointly approving Amendment No. 1 to the Agreement.
NOW, THEREFORE, it is mutually agreed by and between the parties to the
Agreement as follows:
I.Section 1, TERM, is amended by replacing this section in its entirety as follows:
“The term of the Agreement shall be from the date of execution until
completion of the work identified in the Scope of Services and in
conformance with Exhibit C and D, unless this Agreement is terminated or
suspended consistent with Section 6 of this Agreement.”
II.Section 2, SCOPE OF SERVICES, is amended by replacing this section in its
entirety as follows:
“City does hereby retain Contractor in a contractual capacity to
provide construction services related to sidewalk repair and rehabilitation,
as set forth in Exhibit C: Contractor’s Bid Proposal, dated July 30, 2021,
which exhibit is attached hereto and incorporated herein by this reference
as though set forth in full and hereinafter referred to as the “Proposal” and
as set forth in Exhibit C, which include (i) Standard Specifications; (ii)
Special Provisions; (iii) Workers’ Compensation Insurance Certificate
(Labor Code 1860 and 1861); (iv) Payment and Performance Bonds; and
(v) Insurance Certificate for General Liability and Automobile Liability,
attached hereto and incorporated herein by this reference as though set 451
Amendment No. 1 to Agreement between City of Moorpark and F.S. Contractors, Inc. Page 2
forth in full and hereinafter referred to as Exhibit C. Where said Scope of
Services as set forth in Exhibit C is modified by this Agreement, or in the
event there is a conflict between the provisions of said Scope of Services
and this Agreement, the language contained in this Agreement shall take
precedence.
Contractor shall perform the tasks described and set forth in Exhibit C,
Exhibit D, and Specification No. MPK 21-01. Contractor shall complete the
tasks according to the schedule of performance which is also set forth in
Exhibit C and Exhibit D.
Compensation for the services to be performed by Contractor shall be in
accordance with Exhibit C and Exhibit D. Compensation shall not exceed
the rates or total value of Two Hundred Twenty Thousand One Dollars
($220,001.00) as stated in Exhibit C, plus a ten percent (10%) contingency
of Twenty-Two Thousand Dollars and Ten Cents ($22,000.10), plus Thirty
Thousand Two Hundred Sixty-Nine Dollars and Eighty Cents ($30,269.80)
as stated in Exhibit D, for a total contract value of Two Hundred Seventy-
Two Thousand Two Hundred Seventy Dollars and Ninety Cents
($272,270.90), without a written amendment to the agreement executed
by both parties. Payment by City to Contractor shall be as referred to in
this Agreement.
City and Contractor acknowledge that this project is a public work to which
prevailing wages apply, and that a public work project is subject to
compliance monitoring and enforcement by the California Department of
Industrial Relations (DIR). Contractor agrees to comply with and be bound
by all the terms, rules and regulations described in (a) Division 2, Part 7,
Chapter 1 (commencing with Section 1720) of the California Labor Code,
including without limitation Labor Code Section 1771 and (b) the rules and
regulations established by the DIR implementing such statutes, as though
set forth in full herein, including any applicable amendments made thereto
during the term of this Agreement. For every subcontractor who will
perform work on this project, Contractor shall be responsible for
subcontractor’s compliance with (a) and (b) and Contractor shall take all
necessary actions to ensure subcontractor’s compliance. Labor Code
Section 1725.5 requires all contractors and subcontractors to annually
register with the DIR before bidding or performing on any public work
contract.”
III. Section 3, PAYMENT, is amended by replacing the first paragraph of this section
in its entirety as follows:
“The City agrees to pay Contractor monthly, in accordance with the
terms and the schedule of payment as set forth in Exhibit C and Exhibit D,
attached hereto and incorporated herein by this reference as though set
forth in full, based upon actual time spent on the above tasks. This amount
shall not exceed Two Hundred Twenty Thousand One Dollars
($220,001.00) as stated in Exhibit C, plus a ten percent (10%) contingency
452
Amendment No. 1 to Agreement between City of Moorpark and F.S. Contractors, Inc. Page 3
of Twenty-Two Thousand Dollars and Ten Cents ($22,000.10), plus Thirty
Thousand Two Hundred Sixty-Nine Dollars and Eighty Cents ($30,269.80)
as stated in Exhibit D, for a total contract value of Two Hundred Seventy-
Two Thousand Two Hundred Seventy Dollars and Ninety Cents
($272,270.90), for the total term of the Agreement unless additional
payment is approved as provided in this Agreement.”
IV.Remaining Provisions:
Except as revised by this Amendment No. 1, all of the provisions of the
Agreement shall remain in full force and effect.
In Witness Whereof, the parties hereto have caused this Amendment to be
executed the day and year first above written.
CITY OF MOORPARK F.S. CONTRACTOR, INC,
_______________________________ _______________________________
Troy Brown
City Manager
Jose Angel Fierros
President
Attest:
_______________________________
Ky Spangler
City Clerk
453
CITY OF MOORPARK
JANICE S. PARVIN
Mayor
DR. ANTONIO CASTRO
Councilmember
CHRIS ENEGREN
Councilmember
DANIEL GROFF
Councilmember
DAVID POLLOCK
Councilmember
PUBLIC WORKS DEPARTMENT | 799 Moorpark Avenue, Moorpark, California 93021
Main City Phone Number (805) 517-6200 | Fax (805) 532-2555 | moorpark@moorparkca.gov
CHANGE ORDER NO.: 1 CONTRACTOR: FS Contractors, Inc.
PROJECT TITLE: 2021 Sidewalk Rehabilitation Project
Specification No. MPK 21-01
FEDERAL ID NO.: N/A
SUBJECT: Remove and Replace PCC Sidewalk
All work involved in this Change Order shall conform with the Public Works Standard
Specifications, Plans, General Provisions and Special Provisions. The following change is
hereby made to the Contract Documents:
Based on field measurements and existing site conditions, the City has
determined that an additional 2,751.8 square feet of removal and replacement
of PCC sidewalk will be added to the project scope of work. The Plans,
Specifications and Bid Schedule are hereby revised to include the additional
removal and replacement of PCC sidewalk at the contractor’s bid unit price of
$11.00 per square feet (Item No. 4).
The additional quantities are based on field measurements within the approved
project limits. No additional working days or time extensions are granted. The
total cost for this contract change order is not to exceed $30,269.80.
Item 4 – Remove and Replace PCC Sidewalk: ADD 2,751.8 square feet $30,269.80
END OF CHANGES
==================================================================
CHANGE TO CONTRACT PRICE
Amount
Original Contract Price $ 242,001.10
Plus approved quantity adjustments $ 0.00
Subtotal $ 242,001.10
Plus Change Orders to Date $ 0.00
Subtotal $ 242,001.10
This Change Order $ 30,269.80
Revised Contract Price $ 272,270.90
EXHIBIT D
454
Specification No. MPK 21-01
Change Order No. 1
Page 2
Number of
CHANGE TO CONTRACT TIME Working Days
By reason of this change order, the time for contract
completion will be adjusted as follows: 0
GENERAL PROVISIONS
Both Contractor and City agree and acknowledge that execution of this Change Order
constitutes a mutual accord and satisfaction as to the work and/or time extension covered
herein and Contractor specifically waives and releases any and all claims, rights or interest,
including but not limited to those for impact disruptions, loss of efficiency, ripple, or other
extraordinary or consequential costs arising directly or indirectly out of the work or time
extension described in this Change Order except as specifically included herein.
The contract is amended with respect to the above only and all other terms and conditions of
the original contract remain unchanged.
APPROVALS REQUIRED
Proposed by/
Concurrence by:
Jose Angel Fierros, President Date
FS Contractors, Inc.
Reviewed by:
Ariane Quizon, Assistant Engineer Date
Assistant Engineer
Recommended by:
Daniel Kim, P.E. Date
City Engineer/Public Works Director
Approved by:
Troy Brown, City Manager Date
455