HomeMy WebLinkAboutAGENDA REPORT 2022 0302 CCSA REG ITEM 10DCITY OF MOORPARK, CALIFORNIA
City Council Meeting
of March 2, 2022
ACTION APPROVED STAFF
RECOMMENDATION.
BY A. Hurtado.
D. Consider Professional Services Agreement with FCG Consultants to Provide
Construction Management and Inspection Services for the Princeton Avenue
Improvement Project (C0020), Specification No. MPK 21-03. Staff
Recommendation: 1) Award Professional Services Agreement for Construction
Management and Inspections Services for the Princeton Avenue Improvement
Project (C0020) to FCG Consultants, Inc. for an amount not-to-exceed
$1,455,483.65; and 2) Authorize the City Manager to sign the Agreement, subject
to final language approval by the City Manager; and 3) Authorize the City Manager
to amend the Agreement for additional work in an amount not-to-exceed
$145,548.00 (10% of the amount of the Agreement). (ROLL CALL VOTE
REQUIRED) (Staff: Daniel Kim, City Engineer/Public Works Director)
Item: 10.D.
MOORPARK CITY COUNCIL
AGENDA REPORT
TO: Honorable City Council
FROM: Daniel Kim, City Engineer/Public Works Director
DATE: 03/02/2022 Regular Meeting
SUBJECT: Consider Professional Services Agreement with FCG Consultants to
Provide Construction Management and Inspection Services for the
Princeton Avenue Improvement Project (C0020), Specification No.
MPK 21-03
DISCUSSION
On October 6, 2021, the City Council approved the Plans and Specifications for the
Princeton Avenue Improvement Project and authorized staff to advertise the project to
obtain construction bids and a Request for Proposals for Construction Management and
Inspection Services. On December 1, 2021, shortly after receiving Project Authorization
from Federal Highway Administration (FHWA), a Request for Proposals was published
on the City’s website with a submission deadline on January 13, 2022. The Request for
Proposals was also published in the Ventura County Star on December 4, 2021, and
December 14, 2021.
On February 16, 2022, City Council awarded a construction contract to Security Paving
Company, Inc., and a Professional Services Agreement for Construction Administration
Services to Stantec Consulting Services, Inc., and further, fully funded the construction
phase of the project. Although the functions sound similar and overlapping,
Construction Administration Services is provided by the Project Engineer of Record and
is primarily an administrative function to support construction activities as it relates to
design documents. The selected consultant for Construction Management and
Inspection Services will be responsible for the coordination of the entire construction
phase of the project, manage project controls and schedule, ensure compliance and
conformance to the Project Plans and Specifications, provide quality control and
materials testing, serve as the lead coordinator between the general contractor and the
Engineer of Record, and ensure that all federal requirements are met for federal funding
reimbursements for participating costs.
Item: 10.D.
82
Honorable City Council
03/02/2022 Regular Meeting
Page 2
On January 13, 2022, staff received four proposals from qualified engineering firms to
provide Construction Management and Inspection Services: Anser Advisory, LLC; FCG
Consultants Inc.; Filippin Engineering, Inc.; and MNS Engineers, Inc. A consultant
selection panel was formed to review and evaluate the technical proposals and to
interview the prospective firms. The consultant selection panel comprised of current
and former Public Works staff members who are familiar with the City’s needs,
knowledge of the project scope of work, and understand the importance of the project’s
successful completion and delivery. The proposals were evaluated based on the
requirements set forth in the Request for Proposals, project understanding, experience
working on similar projects, consultant and sub-consultant qualifications, and
understanding of Federal and State requirements on federally funded projects. Based
on the review and evaluation of the technical proposals and consultant interviews, the
final ranking for consultant selection is as follows:
1. FCG Consultants, Inc.
2. MNS Engineers, Inc.
3. Filippin Engineering, Inc.
4. Anser Advisory, LLC
FCG Consultants Inc. (FCG), and their sub-consultant team, has the experience and
expertise to provide the City with Construction Management and Inspection Services for
the Princeton Avenue Improvement Project. FCG is an engineering firm that specializes
in project and construction management on large highway improvement projects and
have a successful track record on delivering federally funded projects throughout
Southern California. The FCG team has demonstrated their project understanding and
key construction issues, understanding of the City’s needs and their roles and
responsibilities for the project, and commitment to the City for the successful completion
of the project.
Attachment 1 contains the draft professional services agreement for Construction
Management and Inspection Services. Staff is requesting City Council’s consideration
and approval of the professional services agreement with FCG Consultants, Inc. for
Construction Management and Inspection Services for the Princeton Avenue
Improvement Project.
FISCAL IMPACT
FCG Consultants, Inc. fee proposal for Construction Management and Inspection
Services is $1,455,483.65. This fee amount is approximately 10% of the construction
contract value and is within reason for a project of this scale. The City Council already
appropriated funding for the construction phase of the project on February 16, 2022, so
there is no fiscal impact from awarding this contract.
83
Honorable City Council
03/02/2022 Regular Meeting
Page 3
COUNCIL GOAL COMPLIANCE
This action does not support a current strategic directive for the Fiscal Years 2021-2023
Goals and Objectives. However, the City Council has made the Princeton Avenue
Improvement Project a priority for many years.
STAFF RECOMMENDATION
1. Award Professional Services Agreement for Construction Management and
Inspections Services for the Princeton Avenue Improvement Project (C0020) to
FCG Consultants, Inc. for an amount not-to-exceed $1,455,483.65; and
2. Authorize the City Manager to sign the Agreement, subject to final language
approval by the City Manager; and
3. Authorize the City Manager to amend the Agreement for additional work in an
amount not-to-exceed $145,548.00 (10% of the amount of the Agreement).
Attachment: Professional Services Agreement with FCG Consultants Inc.
84
PROFESSIONAL SERVICES AGREEMENT BETWEEN
THE CITY OF MOORPARK AND
FCG CONSULTANTS INC. FOR
CONSTRUCTION MANAGMEMENT AND INSPECTIONS SERVICES FOR
THE PRINCETON AVENUE IMPROVEMENT PROJECT,
SPECIFICATION NO. MPK 21-03
THIS AGREEMENT, made and effective as of this _____ day of
________________________, 2022, between the City of Moorpark, a municipal corporation
(“City”) and FCG Consultants Inc., a corporation (“Consultant”). In consideration of the
mutual covenants and conditions set forth herein, the parties agree as follows:
WHEREAS, City has the need for Construction Management and Inspections
Services for the Princeton Avenue Improvement Project, Specification No. MPK 21-03;
and
WHEREAS, Consultant specializes in providing such services and has the proper
work experience, certifications, and background to carry out the duties involved; and
WHEREAS, Consultant has submitted to City a Proposal dated January 13,
2022, which is attached hereto as Exhibit C; and
WHEREAS, Consultant has submitted to City a Cost Proposal dated
February 16, 2022, which is attached hereto as Exhibit D; and
NOW, THEREFORE, in consideration of the mutual covenants, benefits, and
premises herein stated, the parties hereto agree as follows:
1.TERM
The term of this Agreement shall be from the date of execution to July 8, 2025,
unless this Agreement is terminated or suspended pursuant to this Agreement.
2.SCOPE OF SERVICES
City does hereby retain Consultant, as an independent contractor, in a
contractual capacity to provide Construction Management and Inspections Services, as
set forth in Exhibits C and D. In the event there is a conflict between the provisions of
Exhibit C, Exhibit D, and this Agreement, the language contained in this Agreement
shall take precedence.
Consultant shall perform the tasks described and set forth in Exhibit C.
Consultant shall complete the tasks according to the schedule of performance which is
also set forth in Exhibits C and D.
Compensation for the services to be performed by Consultant shall be in
accordance with Exhibit D. Compensation shall not exceed the rates or total contract
value One Million, Four Hundred Fifty-Five Thousand, Four Hundred Eighty-Three
ATTACHMENT
85
FCG Consultants Inc. Page 2 of 16
dollars and Sixty-Five cents ($1,455,483.65) as stated in Exhibit D, without a written
Amendment to the Agreement executed by both parties. Payment by City to Consultant
shall be in accordance with the provisions of this Agreement.
3.PERFORMANCE
Consultant shall at all times faithfully, competently and to the best of their ability,
experience, standard of care, and talent, perform all tasks described herein. Consultant
shall employ, at a minimum, generally accepted standards and practices utilized by
persons engaged in providing similar services as are required of Consultant hereunder
in meeting its obligations under this Agreement.
4.MANAGEMENT
The individual directly responsible for Consultant’s overall performance of the
Agreement provisions herein above set forth and to serve as principal liaison between
City and Consultant shall be Abdallah Fakhouri, P.E., and no other individual may be
substituted without the prior written approval of the City Manager.
The City’s contact person in charge of administration of this Agreement, and to
serve as principal liaison between Consultant and City, shall be the City Manager or the
City Manager’s designee.
5.PAYMENT
Taxpayer ID or Social Security numbers must be provided by Consultant on an
IRS W-9 form before payments may be made by City to Consultant.
The City agrees to pay Consultant monthly, in accordance with the payment
rates and terms and the schedule of payment as set forth in Exhibit D, based upon
actual time spent on the above tasks. This amount shall not exceed One Million, Four
Hundred Fifty-Five Thousand, Four Hundred Eighty-Three dollars and Sixty-Five cents
($1,455,483.65) for the total term of the Agreement unless additional payment is
approved as provided in this Agreement.
Consultant shall not be compensated for any services rendered in connection
with its performance of this Agreement, which are in addition to those set forth herein,
unless such additional services and compensation are authorized, in advance, in a
written amendment to this Agreement executed by both parties. The City Manager, if
authorized by City Council, may approve additional work not to exceed ten percent
(10%) of the amount of the Agreement.
Consultant shall submit invoices monthly for actual services performed. Invoices
shall be submitted on or about the first business day of each month, or as soon
thereafter as practical, for services provided in the previous month. Payment shall be
made within thirty (30) days of receipt of each invoice as to all non-disputed fees. Any
expense or reimbursable cost appearing on any invoice shall be accompanied by a
receipt or other documentation subject to approval of the City Manager or the City
86
FCG Consultants Inc. Page 3 of 16
Manager’s designee. If the City disputes any of Consultant’s fees or expenses, City
shall give written notice to Consultant within thirty (30) days of receipt of any disputed
fees set forth on the invoice.
6.TERMINATION OR SUSPENSION WITHOUT CAUSE
The City may at any time, for any reason, with or without cause, suspend, or
terminate this Agreement, or any portion hereof, by serving upon the Consultant at least
ten (10) days prior written notice. Upon receipt of said notice, the Consultant shall
immediately cease all work under this Agreement, unless the notice provides otherwise.
If the City suspends or terminates a portion of this Agreement, such suspension or
termination shall not make void or invalidate the remainder of this Agreement.
The Consultant may terminate this Agreement only by providing City with written
notice no less than thirty (30) days in advance of such termination.
In the event this Agreement is terminated or suspended pursuant to this Section,
the City shall pay to Consultant the actual value of the work performed up to the time of
termination or suspension, provided that the work performed is of value to the City.
Upon termination or suspension of the Agreement pursuant to this Section, the
Consultant will submit an invoice to the City pursuant to this Agreement.
7.DEFAULT OF CONSULTANT
The Consultant’s failure to comply with the provisions of this Agreement shall
constitute a default. In the event that Consultant is in default for cause under the terms
of this Agreement, City shall have no obligation or duty to continue compensating
Consultant for any work performed after the date of default and can terminate or
suspend this Agreement immediately by written notice to the Consultant. If such failure
by the Consultant to make progress in the performance of work hereunder arises out of
causes beyond the Consultant’s control, and without fault or negligence of the
Consultant, it shall not be considered a default.
If the City Manager or his/her designee determines that the Consultant is in
default in the performance of any of the terms or conditions of this Agreement, he/she
shall cause to be served upon the Consultant a written notice of the default. The
Consultant shall have thirty (30) days after service upon it of said notice in which to cure
the default by rendering a satisfactory performance. In the event that the Consultant
fails to cure its default within such period of time, the City shall have the right,
notwithstanding any other provision of this Agreement, to terminate this Agreement
without further notice and without prejudice to any other remedy to which it may be
entitled at law, in equity or under this Agreement.
8.LIQUIDATED DAMAGES
There are no liquidated damages under this Agreement.
87
FCG Consultants Inc. Page 4 of 16
9.OWNERSHIP OF DOCUMENTS
Consultant shall maintain complete and accurate records with respect to sales,
costs, expenses, receipts, and other such information required by City that relate to the
performance of services under this Agreement. Consultant shall maintain adequate
records of services provided in sufficient detail to permit an evaluation of services. All
such records shall be maintained in accordance with generally accepted accounting
principles and shall be clearly identified and readily accessible. Consultant shall provide
free access to the representatives of City or the City’s designees at reasonable times to
such books and records; shall give the City the right to examine and audit said books
and records; shall permit City to make transcripts therefrom as necessary; and shall
allow inspection of all work, data, documents, proceedings, and activities related to this
Agreement. Notification of audit shall be provided at least thirty (30) days before any
such audit is conducted. Such records, together with supporting documents, shall be
maintained for a period of three (3) years after receipt of final payment.
Upon completion of, or in the event of termination or suspension without cause of
this Agreement, all original documents, designs, drawings, maps, models, computer
files, surveys, notes, and other documents prepared in the course of providing the
services to be performed pursuant to this Agreement shall become the sole property of
the City and may be used, reused, or otherwise disposed of by the City without the
permission of the Consultant. With respect to computer files, Consultant shall make
available to the City, at the Consultant’s office and upon reasonable written request by
the City, the necessary computer software and hardware for purposes of accessing,
compiling, transferring, and printing computer files.
10.INDEMNIFICATION AND HOLD HARMLESS
Indemnity for professional liability: When the law establishes a professional
standard of care for Consultant’s Services, to the fullest extent permitted by law,
Consultant shall indemnify, protect, defend and hold harmless City and any and all of its
officials, employees, and agents (“Indemnified Parties”) from and against any and all
losses, liabilities, damages, costs and expenses, including legal counsels’ fees and
costs to the extent same are caused in whole or in part by any negligent or wrongful act,
error or omission of Consultant, its officers, agents, employees or subconsultants (or
any agency or individual that Consultant shall bear the legal liability thereof) in the
performance of professional services under this Agreement.
Indemnity for other than professional liability: Other than in the performance of
professional services and to the full extent permitted by law, Consultant shall indemnify,
protect, defend and hold harmless City, and any and all of its officials, employees, and
agents from and against any liability (including liability for claims, suits, actions,
arbitration proceedings, administrative proceedings, regulatory proceedings, losses,
expenses or costs of any kind, whether actual, alleged or threatened, including legal
counsels’ fees and costs, court costs, interest, defense costs, and expert witness fees),
where the same arise out of, are a consequence of, or are in any way attributable to, in
whole or in part, the performance of this Agreement by Consultant or by any individual
88
FCG Consultants Inc. Page 5 of 16
or agency for which Consultant is legally liable, including but not limited to officers,
agents, employees or subcontractors of Consultant.
Consultant agrees to obtain executed indemnity agreements with provisions
identical to those set forth here in this Section from each and every subcontractor, or
any other person or entity involved by, for, with, or on behalf of Consultant in the
performance of this Agreement. In the event Consultant fails to obtain such indemnity
obligations from others as required here, Consultant agrees to be fully responsible
according to the terms of this Section. Failure of City to monitor compliance with these
requirements imposes no additional obligations on City and will in no way act as a
waiver of any rights hereunder. This obligation to indemnify and defend City as set forth
here is binding on the successors, assigns, or heirs of Consultant and shall survive the
termination of this Agreement or this Section.
City does not and shall not waive any rights that it may have against Consultant
by reason of this Section, because of the acceptance by City, or the deposit with City, of
any insurance policy or certificate required pursuant to this Agreement. The hold
harmless and indemnification provisions shall apply regardless of whether or not said
insurance policies are determined to be applicable to any losses, liabilities, damages,
costs, and expenses described in this Section.
11.INSURANCE
Consultant shall maintain prior to the beginning of and for the duration of this
Agreement insurance coverage as specified in Exhibit A attached hereto and
incorporated herein by this reference as though set forth in full.
12.INDEPENDENT CONSULTANT
Consultant is and shall at all times remain as to the City a wholly independent
Contractor. The personnel performing the services under this Agreement on behalf of
Consultant shall at all times be under Consultant’s exclusive direction and control.
Neither City nor any of its officers, employees, or agents shall have control over the
conduct of Consultant or any of Consultant’s officers, employees, or agents, except as
set forth in this Agreement. Consultant shall not at any time or in any manner represent
that it or any of its officers, employees, or agents are in any manner officers or
employees, or agents of the City except as set forth in this Agreement. Consultant shall
not incur or have the power to incur any debt, obligation, or liability against City, or bind
City in any manner.
No employee benefits shall be available to Consultant in connection with the
performance of this Agreement. Except for the fees paid to Consultant as provided in
the Agreement, City shall not pay salaries, wages, or other compensation to Consultant
for performing services hereunder for City. City shall not be liable for compensation or
indemnification to Consultant for injury or sickness arising out of performing services
hereunder.
89
FCG Consultants Inc. Page 6 of 16
13.LEGAL RESPONSIBILITIES
The Consultant shall keep itself informed of local, state, and federal laws and
regulations which in any manner affect those employed by it or in any way affect the
performance of its service pursuant to this Agreement. The Consultant shall at all times
observe and comply with all such laws and regulations, including but not limited to the
Americans with Disabilities Act and Occupational Safety and Health Administration laws
and regulations. The Consultant shall comply with and sign Exhibit B, the Scope of
Work Requirement for Professional Services Agreements Compliance with California
Government Code Section 7550, when applicable. The City, and its officers and
employees, shall not be liable at law or in equity occasioned by failure of the Consultant
to comply with this Section.
Should the Scope of Services include work that is considered a public work to
which prevailing wages apply, the public work project is subject to compliance
monitoring and enforcement by the California Department of Industrial Relations (DIR).
Consultant agrees to comply with and be bound by all applicable terms, rules and
regulations described in (a) Division 2, Part 7, Chapter 1 (commencing with Section
1720) of the California Labor Code, including without limitation Labor Code Section
1771 and (b) the rules and regulations established by the DIR implementing such
statutes, as though set forth in full herein, including any applicable amendments made
thereto during the term of this Agreement. For every subcontractor who will perform
work on this project, Consultant shall be responsible for subcontractor’s compliance with
(a) and (b), and Consultant shall take all necessary actions to ensure subcontractor’s
compliance. Labor Code Section 1725.5 requires all contractors and subcontractors to
annually register with the DIR before bidding or performing on any public work contract.
14.ANTI DISCRIMINATION
Neither the Consultant, nor any subconsultant under the Consultant, shall
discriminate in employment of persons upon the work because of race, religious creed,
color, national origin, ancestry, physical disability, mental disability, medical condition,
genetic information, marital status, sex, gender, gender identity, gender expression,
age, sexual orientation, or military and veteran status; or any other basis protected by
applicable federal, state, or local law, except as provided in Section 12940 of the
Government Code. Consultant shall have responsibility for compliance with this Section.
90
FCG Consultants Inc. Page 7 of 16
15.UNDUE INFLUENCE
Consultant declares and warrants that no undue influence or pressure is used
against or in concert with any officer or employee of the City in connection with the
award, terms, or implementation of this Agreement, including any method of coercion,
confidential financial arrangement, or financial inducement. No officer or employee of
the City will receive compensation, directly or indirectly from Consultant, or any officer,
employee, or agent of Consultant, in connection with the award of this Agreement or
any work to be conducted as a result of this Agreement. Violation of this Section shall
be a material breach of this Agreement entitling the City to any and all remedies at law
or in equity.
16.NO BENEFIT TO ARISE TO LOCAL EMPLOYEES
No member, officer, or employee of the City, or their designees or agents, and no
public official who exercises authority over or responsibilities with respect to the
Services during his/her tenure or for one year thereafter, shall have any interest, direct
or indirect, in any agreement or sub-agreement, or the proceeds thereof, for work to be
performed in connection with the Services performed under this Agreement.
17.CONFLICT OF INTEREST
Consultant covenants that neither they nor any officer or principal of their firm
have any interests, nor shall they acquire any interest, directly or indirectly, which will
conflict in any manner or degree with the performance of their services hereunder.
Consultant further covenants that in the performance of this Agreement, they shall
employ no person having such interest as an officer, employee, agent, or subconsultant.
Consultant further covenants that Consultant has not contracted with nor is performing
any services directly or indirectly, with the developer(s) and/or property owner(s) and/or
firm(s) and/or partnership(s) and/or public agency(ies) owning property and/or
processing an entitlement application for property in the City or its Area of Interest, now
or within the past one (1) year, and further covenants and agrees that Consultant and/or
its subconsultants shall provide no service or enter into any contract with any
developer(s) and/or property owner(s) and/or firm(s) and/or partnership(s) and/or public
agency(ies) owning property and/or processing an entitlement application for property in
the City or its Area of Interest, while under contract with the City and for a one (1) year
time period following termination of this Agreement.
18.NOTICE
Any notice to be given pursuant to this Agreement shall be in writing, and all such
notices and any other document to be delivered shall be delivered by personal service
or by deposit in the United States mail, certified or registered, return receipt requested,
with postage prepaid, and addressed to the party for whom intended as follows:
91
FCG Consultants Inc. Page 8 of 16
To: City Manager
City of Moorpark
799 Moorpark Ave.
Moorpark, CA 93021
To: Abdallah Fakhouri, P.E.
Secretary
FCG Consultant Inc.
22885 Savi Ranch Road, Suite G
Yorba Linda, CA 92887
Either party may, from time to time, by written notice to the other, designate a
different address or contact person, which shall be substituted for the one above
specified. Notices, payments and other documents shall be deemed delivered upon
receipt by personal service or as of the third (3rd) day after deposit in the United States
mail.
19.CHANGE IN NAME
Should a change be contemplated in the name or nature of the Consultant's legal
entity, the Consultant shall first notify the City in order that proper steps may be taken to
have the change reflected in the Agreement documents.
20.ASSIGNMENT
Consultant shall not assign this Agreement or any of the rights, duties, or
obligations hereunder. It is understood and acknowledged by the parties that Consultant
is uniquely qualified to perform the services provided for in this Agreement.
21.LICENSES
At all times during the term of this Agreement, Consultant shall have in full force
and effect, all licenses required of it by law for the performance of the services in this
Agreement.
22.VENUE AND GOVERNING LAW
This Agreement is made, entered into, and executed in Ventura County,
California, and any action filed in any court or for arbitration for the interpretation,
enforcement or other action of the terms, conditions, or covenants referred to herein
shall be filed in the applicable court in Ventura County, California. The City and
Consultant understand and agree that the laws of the state of California shall govern the
rights, obligations, duties, and liabilities of the parties to this Agreement and also govern
the interpretation of this Agreement.
92
FCG Consultants Inc. Page 9 of 16
23.COST RECOVERY
In the event any action, suit or proceeding is brought for the enforcement of, or
the declaration of any right or obligation pursuant to this Agreement or as a result of any
alleged breach of any provision of this Agreement, the prevailing party shall be entitled
to recover its costs and expenses, including attorneys’ fees, from the losing party, and
any judgment or decree rendered in such a proceeding shall include an award thereof.
24.ENTIRE AGREEMENT
This Agreement and the Exhibits attached hereto contain the entire
understanding between the parties relating to the obligations of the parties described in
this Agreement. All prior or contemporaneous agreements, understandings,
representations, and statements, oral or written, are merged into this Agreement and
shall be of no further force or effect. Each party is entering into this Agreement based
solely upon the representations set forth herein and upon each party’s own independent
investigation of any and all facts such party deems material.
25.CAPTIONS OR HEADINGS
The captions and headings of the various Articles, Paragraphs, and Exhibits of
this Agreement are for convenience and identification only and shall not be deemed to
limit or define the content of the respective Articles, Paragraphs, and Exhibits hereof.
26.AMENDMENTS
Any amendment, modification, or variation from the terms of this Agreement shall
be in writing and shall be effective only upon approval by both parties to this Agreement.
27.PRECEDENCE
In the event of conflict, the requirements of the City’s Request for Proposal, if
any, and this Agreement shall take precedence over those contained in the Consultant’s
Proposal.
28.INTERPRETATION OF AGREEMENT
Should interpretation of this Agreement, or any portion thereof, be necessary, it is
deemed that this Agreement was prepared by the parties jointly and equally, and shall
not be interpreted against either party on the ground that the party prepared the
Agreement or caused it to be prepared.
29.WAIVER
No waiver of any provision of this Agreement shall be deemed, or shall
constitute, a waiver of any other provision, whether or not similar, nor shall any such
waiver constitute a continuing or subsequent waiver of the same provision. No waiver
shall be binding unless executed in writing by the party making the waiver.
93
FCG Consultants Inc. Page 10 of 16
30.AUTHORITY TO EXECUTE
The person or persons executing this Agreement on behalf of the Consultant
warrants and represents that he/she has the authority to execute this Agreement on
behalf of the Consultant and has the authority to bind Consultant to the performance of
obligations hereunder.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be
executed the day and year first above written.
CITY OF MOORPARK FCG CONSULTANTS INC.
__________________________________ __________________________________
Troy Brown, City Manager Maha Fakhouri, President
Attest: __________________________________
__________________________________
Abdallah Fakhouri, Secretary
Ky Spangler, City Clerk
94
FCG Consultants Inc. Page 11 of 16
Exhibit A
INSURANCE REQUIREMENTS
Prior to the beginning of and throughout the duration of Work, Consultant will maintain
insurance in conformance with the requirements set forth below. Consultant will use
existing coverage to comply with these requirements. If that existing coverage does not
meet requirements set forth here, Consultant agrees to amend, supplement, or endorse
the existing coverage to do so. Consultant acknowledges that the insurance coverage
and policy limits set forth in this section constitute the minimum amount of coverage
required. Any insurance proceeds available to the City in excess of the limits and
coverage required in this Agreement and which is applicable to a given loss, will be
available to the City.
Consultant shall provide the following types and amounts of insurance:
Commercial General Liability Insurance using Insurance Services Office (ISO)
“Commercial General Liability” policy form CG 00 01 or the exact equivalent. Defense
costs must be paid in addition to limits. There shall be no cross liability exclusion for
claims or suits by one insured against another. Limits are subject to review but in no
event less than $1,000,000 per occurrence for all covered losses and no less than
$2,000,000 general aggregate.
Business Auto Coverage on ISO Business Auto Coverage form CA 00 01 including
symbol 1 (Any Auto) or the exact equivalent. Limits are subject to review, but in no
event to be less than $1,000,000 per accident. If Consultant owns no vehicles, this
requirement may be satisfied by a non-owned auto endorsement to the general liability
policy described above. If Consultant or Consultant’s employees will use personal autos
in any way on this project, Consultant shall provide evidence of personal auto liability for
each such person.
Workers’ Compensation on a state-approved policy form providing statutory benefits as
required by law with employer’s liability limits no less than $1,000,000 per accident or
disease.
Professional Liability or Errors and Omissions Insurance as appropriate shall be written
on a policy form coverage specifically designed to protect against acts, errors or
omissions of the Consultant and “Covered Professional Services” as designated in the
policy must specifically include work performed under this Agreement. The policy limit
shall be no less than $1,000,000 per claim and in the aggregate. The policy must “pay
on behalf of” the insured and must include a provision establishing the insurer’s duty to
defend. The policy retroactive date shall be on or before the effective date of this
Agreement.
Excess or Umbrella Liability Insurance (Over Primary) if used to meet limit
requirements, shall provide coverage at least as broad as specified for the underlying
coverages. Coverage shall be provided on a “pay on behalf” basis, with defense costs
95
FCG Consultants Inc. Page 12 of 16
payable in addition to policy limits. Policy shall contain a provision obligating insurer at
the time insured’s liability is determined, not requiring actual payment by the insured
first. There shall be no cross liability exclusion precluding coverage for claims or suits by
one insured against another. Coverage shall be applicable to the City for injury to
employees of Consultant, subconsultants, or others involved in the Work. The scope of
coverage provided is subject to approval by the City following receipt of proof of
insurance as required herein. Limits are subject to review but in no event less than
$2,000,000 aggregate.
Insurance procured pursuant to these requirements shall be written by insurers that are
admitted carriers in the State of California and with an A.M. Bests rating of A- or better
and a minimum financial size of VII.
General conditions pertaining to provision of insurance coverage by Consultant.
Consultant and the City agree to the following with respect to insurance provided by
Consultant:
1.Consultant agrees to have its insurer endorse the third party general liability
coverage required herein to include as additional insureds the City, its officials,
employees, and agents, using standard ISO endorsement CG 2010 and CG
2037 with edition acceptable to the City. Consultant also agrees to require all
contractors and subcontractors to do likewise.
2.No liability insurance coverage provided to comply with this Agreement shall
prohibit Consultant, or Consultant’s employees, or agents, from waiving the right
to subrogation prior to a loss. Consultant agrees to waive subrogation rights
against the City regardless of the applicability of any insurance proceeds, and to
require all contractors and subcontractors to do likewise.
3.All insurance coverage and limits provided by Contractor and available or
applicable to this Agreement are intended to apply to the full extent of the
policies. Nothing contained in this Agreement or any other agreement relating to
the City or its operation limits the application of such insurance coverage.
4.None of the coverages required herein will be in compliance with these
requirements if they include limiting endorsement of any kind that has not been
first submitted to the City and approved in writing.
5.No liability policy shall contain any provision or definition that would serve to
eliminate so-called “third party action over” claims, including any exclusion for
bodily injury to an employee of the insured or of any contractor or subcontractor.
6.All coverage types and limits required are subject to approval, modification, and
additional requirements by the City, as the need arises. Consultant shall not
make any reductions in scope of coverage (e.g. elimination of contractual liability
or reduction of discovery period) that may affect the City’s protection without the
City’s prior written consent.
96
FCG Consultants Inc. Page 13 of 16
7.Proof of compliance with these insurance requirements, consisting of certificates
of insurance evidencing all of the coverages required and an additional insured
endorsement to Consultant’s general liability policy, shall be delivered to city at or
prior to the execution of this Agreement. In the event such proof of any insurance
is not delivered as required, or in the event such insurance is canceled or
reduced at any time and no replacement coverage is provided, the City has the
right, but not the duty, to obtain any insurance it deems necessary to protect its
interests under this or any other Agreement and to pay the premium. Any
premium so paid by the City shall be charged to and promptly paid by Consultant
or deducted from sums due Consultant, at the City’s option.
8.Certificate(s) are to reflect that the insurer will provide thirty (30) days notice to
the City of any cancellation or reduction of coverage. Consultant agrees to
require its insurer to modify such certificates to delete any exculpatory wording
stating that failure of the insurer to mail written notice of cancellation or reduction
of coverage imposes no obligation, or that any party will “endeavor” (as opposed
to being required) to comply with the requirements of the certificate.
9.It is acknowledged by the parties of this Agreement that all insurance coverage
required to be provided by Consultant or any subcontractor, is intended to apply
first and on a primary, non-contributing basis in relation to any other insurance or
self-insurance available to the City.
10.Consultant agrees to ensure that subcontractors, and any other party involved
with the Work who is brought onto or involved in the Work by Consultant, provide
the same minimum insurance required of Consultant. Consultant agrees to
monitor and review all such coverage and assumes all responsibility for ensuring
that such coverage is provided in conformity with the requirements of this
section. Consultant agrees that upon request, all agreements with subcontractors
and others engaged in the Work will be submitted to the City for review.
11.Consultant agrees not to self-insure or to use any self-insured retentions or
deductibles on any portion of the insurance required herein and further agrees
that it will not allow any contractor, subcontractor, Architect, Engineer, or other
entity or person in any way involved in the performance of Work contemplated by
this Agreement to self-insure its obligations to the City. If Consultant’s existing
coverage includes a deductible or self-insured retention, the deductible or self-
insured retention must be declared to the City. At that time, the City shall review
options with the Consultant, which may include reduction or elimination of the
deductible or self-insured retention, substitution of other coverage, or other
solutions.
12.The City reserves the right at any time during the term of the Agreement to
change the amounts and types of insurance required by giving the Consultant
ninety (90) days advance written notice of such change. If such change results in
substantial additional cost to the Consultant, the City will negotiate additional
compensation proportional to the increased benefit to the City.
97
FCG Consultants Inc. Page 14 of 16
13.For purposes of applying insurance coverage only, this Agreement will be
deemed to have been executed immediately upon any party hereto taking any
steps that can be deemed to be in furtherance of or towards performance of this
Agreement.
14.Consultant acknowledges and agrees that any actual or alleged failure on the
part of the City to inform Consultant of non-compliance with an insurance
requirement in no way imposes any additional obligations to the City nor does it
waive any rights hereunder in this or any other regard.
15.Consultant will renew the required coverage annually as long as the City, or its
employees or agents face an exposure from operations of any type pursuant to
this Agreement. This obligation applies whether or not the Agreement is canceled
or terminated for any reason. Termination of this obligation is not effective until
the City executes a written statement to that effect.
16.Consultant shall provide proof that policies of insurance required herein expiring
during the term of this Agreement have been renewed or replaced with other
policies providing at least the same coverage. Proof that such coverage has
been ordered shall be submitted prior to expiration. A coverage binder or letter
from Consultant’s insurance agent to this effect is acceptable. A certificate of
insurance and/or additional insured endorsement as required in these
specifications applicable to the renewing or new coverage must be provided to
the City within five days of the expiration of coverage.
17.The provisions of any Workers’ Compensation or similar act will not limit the
obligations of Consultant under this Agreement. Consultant expressly agrees not
to use any statutory immunity defenses under such laws with respect to the City,
its employees, officials and agents.
18.Requirements of specific coverage features or limits contained in this section are
not intended as limitations on coverage, limits, or other requirements nor as a
waiver of any coverage normally provided by any given policy. Specific reference
to a given coverage feature is for purposes of clarification only as it pertains to a
given issue, and is not intended by any party or insured to be limiting or all-
inclusive.
19.These insurance requirements are intended to be separate and distinct from any
other provision in this Agreement and are intended by the parties here to be
interpreted as such.
20.The requirements in this section supersede all other sections and provisions of
this Agreement to the extent that any other section or provision conflicts or
impairs the provisions of this section.
98
FCG Consultants Inc. Page 15 of 16
21.Consultant agrees to be responsible for ensuring that no contract used by any
party involved in any way with the Work reserves the right to charge the City or
Consultant for the cost of additional insurance coverage required by this
Agreement. Any such provisions are to be deleted with reference to the City. It is
not the intent of the City to reimburse any third party for the cost of complying
with these requirements. There shall be no recourse against the City for payment
of premiums or other amounts with respect thereto.
22.Consultant agrees to provide immediate notice to City of any claim or loss
against Consultant arising out of the work performed under this Agreement. The
City assumes no obligation or liability by such notice, but has the right (but not
the duty) to monitor the handling of any such claim or claims if they are likely to
involve the City.
99
FCG Consultants Inc. Page 16 of 16
Exhibit B
CITY OF MOORPARK
Scope of Work Requirement for Professional Services Agreements
Compliance with California Government Code Section 7550
Consultant shall sign and include this page in any document or written reports prepared by
Consultant for the City of Moorpark (City) to which California Government Code Section 7550
(Government Code § 7550) applies. Government Code §7550 reads:
“(a) Any document or written report prepared for or under the direction of a state
or local agency, that is prepared in whole or in part by nonemployees of the
agency, shall contain the numbers and dollar amounts of all contracts and
subcontracts relating to the preparation of the document or written report; if the
total cost for the work performed by nonemployees of the agency exceeds five
thousand dollars ($5,000). The contract and subcontract numbers and dollar
amounts shall be contained in a separate section of the document or written
report.
(b) When multiple documents or written reports are the subject or product of the
contract, the disclosure section may also contain a statement indicating that the
total contract amount represents compensation for multiple documents or written
reports.”
For all Professional Services Agreement with a total dollar value in excess of $5,000, a signed
and completed copy of this form must be attached to all documents or completed reports
submitted to the City pursuant to the Scope of Work.
Does the dollar value of this Professional Services Agreement exceed $5,000?
Yes No
If yes, then the following information must be provided in compliance with
Government Code § 7550:
1.Dollar amount of Agreement/Contract: $ ____________
2.Dollar amount of Subcontract:$ ____________
3.Does the total contract amount represent compensation for multiple
documents or written reports? Yes No
I have read the foregoing Code section and will comply with Government Code §7550.
__________________________________ ______________________
Date
100
PROPOSAL
to provide
Construction Management and Inspection
for
Princeton Avenue Improvement Project
CIP No. MPK 21‐03
Federal Project No. HSIPL‐5436(018)
Prepared for the
City of Moorpark
Prepared for the
City of Moorpark
January 13, 2022
Exhibit C
Scope of Services
101
TABLE OF CONTENTS
Construction Management and Inspection Services
For the Princeton Avenue Improvement Project
Spec No. MPK 21-03
Federal-Aid No. HSIPL-5436(018)
Section 1: Cover Letter ................................................................................................................................................... 1
Section 2: Statement of Project Understanding ....................................................................................................................... 2
Project Background ...................................................................................................................................... 3
Technical Understanding .............................................................................................................................. 3
Approach ........................................................................................................................................................ 7
Project Goals ................................................................................................................................................. 7
Understanding City of Moorpark Needs ...................................................................................................... 7
Previous Work Experience ........................................................................................................................... 7
City Policies and Procedures ....................................................................................................................... 7
Scope of Services .......................................................................................................................................... 7
Special Considerations and Project Challenges ........................................................................................ 8
Constructability Review of Plans and Specifications .............................................................................. 10
Section 3: Statement of Qualifications .................................................................................................................................... 12
Firm Profile / Qualifications ........................................................................................................................ 12
Similar Projects and References ................................................................................................................ 14
Section 4: Organization and Staffing ....................................................................................................................................... 21
Organizational Chart ................................................................................................................................... 21
Team Resumes ............................................................................................................................................ 22
Section 5: Scope of Work .......................................................................................................................................................... 34
Section 6: Person Hours by Task ............................................................................................................................................. 47
Construction Management Task Activity Schedule ................................................................................. 48
Section 7: Project Schedule ......................................................................................................................................... 49
Section 8: Certificates and Exhibits ............................................................................................................................. 50
Section 9: Cost Proposal .............................................................................................................................................. 64
Appendix: Addenda Acknowledgement ...................................................................................................................... 65
102
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 1: COVER LETTER
January 13, 2022
Attn: Mr. Daniel Kim, P.E.
City Engineer/Public Works Director
City of Moorpark – Engineering/Public Works Department
799 Moorpark Avenue
Moorpark, CA 93021
Subject: Construction Management and Inspection Services for the Princeton Avenue Improvement Project, Spec
No. MPK 21-03, Federal-Aid No. HSIPL-5436(018)
Dear Mr. Kim:
FCG Consultants, Inc. (FCG) is pleased to commit our services to the City of Moorpark (City) to provide Construction Management
and Inspection Services for the Princeton Avenue Improvement Project. FCG is a firm with extensive roadway and traffic signal
improvement experience committed to providing the highest level of service in the most cost-effective manner possible. We will
provide the City with the most experienced and motivated team that will produce the highest quality work and will become part of the
City team in every aspect.
We are committed to quality work, efficiency in staffing and budgeting, and successfully delivering this project. Our team has been
selected based on availability and relevant experience, full understanding of the scope of services, and knowledge of the needs of
the stakeholders. The key staff proposed for this project have managed numerous projects like this and will apply this knowledge
and experience to hit the ground running. The individuals proposed have the availability, the qualifications, and in many cases the
cross-training for both office and field positions to cost-effectively solve problems at any level. Our team has extensive experience
working on public works projects that utilize Caltrans standards and procedures and the Local Assistance Procedures Manual.
FCG is no stranger to providing construction management and inspection services on federally funded projects located throughout
California and has successfully serviced these projects to our clients’ satisfaction. We are committed to this project and propose a
team that is available and local. Quality, safety, and a can-do attitude are key elements that will make this project a success. FCG
is committed to quality work, safety in every instance, and an attitude that believes anything is possible. Our employees are familiar
with the various standards and how to use them to bring about a successful project. Standards of quality are a priority for our staff
and are thoroughly discussed, including the expectations of the Resident Engineer and requirements of the specifications, plans,
and Construction Manual. Proper inspection and testing of the materials will yield expected quality materials and workmanship. Our
contact information is as follows:
FCG Consultants Inc. - DBE
Contact: Maha Fakhouri, President & CEO, (714) 312-0317, maha.fakhouri@fcgconsultants.com
Address: 22885 Savi Ranch Parkway, Suite G, Yorba Linda, CA 92887
FCG is a woman-owned California corporation and certified Small Business Enterprise (SBE) and Disadvantaged Business
Enterprise (DBE) focused on providing client-driven solutions to assist clients in successfully delivering infrastructure projects.
Founded in 2009, FCG is headquartered in Yorba Linda, California, with a staff of 23 fully dedicated personnel providing construction
engineering, construction management, and construction inspection services to clients throughout California. The firm specializes in
project and construction management and inspection for various types of public works clients utilizing assorted standards such as
Caltrans Local Assistance Procedures Manual, FHWA, Greenbook, and AWWA. FCG staff are highly experienced with inspection
of roadway improvements, traffic signals, drainage systems, utilities, ADA ramps, retaining walls, MSE walls, soil nail walls, asphalt
concrete (AC), Portland cement concrete (PCC) pavement, flood control channels, railroad construction, electrical, landscape,
SWPPP, and safety. FCG will perform construction management, contract administration, construction inspection, daily reporting,
coordination with stakeholders, review labor compliance reports, and quality assurance testing and acceptance,
Mr. A.B. Fakhouri, PE, QSD, is our proposed Project Manager / Resident Engineer and will be assigned for the duration of the
project. He is a former Resident Engineer of Caltrans District 7 with more than 26 years of project management, design, and construction
experience on transportation infrastructure, water infrastructure, and various other public works projects. He gained his experience
working for Caltrans, county departments of transportation, transportation authorities, and local cities. His project management
experience includes contract administration and on-site management involving multiple contractors, and he is highly experienced
with the Caltrans Construction Manual and Local Procedures Assistance Manual. He will provide quality control over construction
inspection services and will manage the contract and the budget.
Page 1 103
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 1: COVER LETTER
Subconsultants
WSP USA, Inc.
Contact: Derich Sukow, PE, Vice President/Construction Services District Manager, (714) 721-4229, derich.sukow@wsp.com
Address: 1100 Town and Country Rd. #200, Orange, CA 92868
(WSP) a corporation, founded in 1933 as an engineering and professional services consulting firm. WSP provides Project
management; structures and roadway inspections; scheduling; administrative support; OE, environmental support, constructability
review, claims, disputes.
Twining Testing Laboratory, Inc.
Contact: Jeff Tawakoli, PE, Ventura Branch Manager, (805) 644-5100, jtawakoli@twininginc.com
Address: 1879 Portola Road, Suite G, Ventura, CA 93003
Twining Testing Laboratories offers comprehensive geotechnical/asphalt/concrete/soil consulting, inspection, and material testing
services during construction. Their services are applied in planning, design, and construction of municipal and public works
throughout Southern California. Twining has broad geotechnical and materials testing experience throughout Southern California.
Twining’s service includes quality assurance and compaction testing during grading and backfill, sampling and testing aggregate
base; HMA; and PCC.
Wagner Engineering & Survey, Inc.
Contact: Paul Wagner, PE, Sr. Vice President, (818) 892-6565, paulw@wesinc.org
Address: 17134 Devonshire Street, Suite 200, Northridge, CA 91325
Wagner Engineering and Survey, Inc. (WES), a WBE/DBE/SBE/CBE Los Angeles firm is a dedicated to providing quality survey,
mapping, land planning and civil engineering services in a cost effective and ambitious manner. Their services include providing
design, aerial mapping & surveying processes. WES is well known for the quality of their deliverables — detailed topographic
surveys, and vast swaths of aerial mapping. The horizontal control and drawing software used for CADD production are the latest
versions of AutoCAD, AutoCAD Civil 3-D, MicroStation and Inroads.
Hernandez Environmental Services, Inc.
Contact: Juan Hernandez, Principal Biologist, (909) 772-9009, juan@hernandezenvironmental.com
Address: 17037 Lakeshore Drive, Lake Elsinore, CA 92530
HES’s expertise is in developing dynamic solutions to assist our clients through the environmental, biological, and regulatory
compliance requirements of their projects. The HES staff has over three decades of experience in providing biological and regulatory
permitting services. HES has provided environmental compliance and biological construction monitoring services for urban
development, utility, and infrastructure projects throughout southern California.
Proposal Terms and Conditions
FCG acknowledges examination of the RFP and accepts the terms and conditions as described in the RFP. We also acknowledge
Addendum No. 1 dated December 23rd, 2021, and Addendum No. 2 dated January 7th, 2022. Our team has reviewed the RFQ and
all addenda for this procurement and together our team will provide City of Moorpark with the consulting services you deserve.
FCG understands the importance of this project to the City of Moorpark. The City can be assured that FCG is dedicated to proposing
professional team members that have the qualifications, experience, and skills necessary to successfully complete the scope of work
on schedule and within budget. Having completed numerous roadway and traffic signal improvement projects in Los Angeles County,
our public works experienced staff is available, ready to assist on this assignment, and able to handle several active projects concurrently
should the need arise.
Disadvantages Business Enterprise (DBE) Goal
FCG meets the DBE participation goal of 11% by proposing a team of certified DBEs, bringing DBE utilization to 100%. We appreciate
the opportunity to be considered for this contract. If you have any questions, or require additional information, please do not hesitate
to contact me. I may be reached at 22885 Savi Ranch Parkway, Suite G, Yorba Linda, California 92887, Office: 714.312.0317, Fax:
714.312.0793, Cell: 714.883.8068 or maha.fakhouri@fcgconsultants.com with any questions you may have.
Sincerely,
Maha Fakhouri, President & CEO
Page 2 104
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Project Background
The City of Moorpark is requesting proposals for Construction
Management, Inspection, Materials Testing, and Contract
Administration services for the Princeton Avenue Improvement
Project (Specification No. MPK 21-03). The project will utilize
federal funds for participating costs, federal aid number HSIPL-
5436(018). The City of Moorpark is proposing to perform various
improvements on Princeton Avenue. Princeton Avenue, within
the proposed project limit, is a two-lane, east-west, arterial road
that provides the primary link for local traffic between the center
of the City and the Campus Park/Moorpark College area.
Princeton Avenue is also an alternative and bypass route to
State Highway 118, with a segment located within State right-of-
way that crosses below State Highway 118. The adjacent land
uses along Princeton Avenue include residential neighborhoods, light industrial, retail/commercial, and office business parks. In
general, the roadway within the project limit is characterized by a reverse curve with two vehicle travel lanes, a limited unpaved
shoulder area, and an unimproved pedestrian path along the southside. There are several single-family residential homes that take
access directly from Princeton Avenue The proposed scope of work consists of the reconstruction of approximately 3,600 feet of
Princeton Avenue, between east of Spring Road and Condor Drive. The proposed improvements include retaining wall structures,
screen walls, graded slopes, and storm drainage facilities to accommodate the widening of Princeton Avenue for 8-foot bike lanes,
12-foot vehicle travel lanes (one in each direction), 14-foot left-turn lane, and pedestrian sidewalks.
Technical Understanding
The FCG Team includes former Caltrans engineers who are highly qualified to provide the scope of services required for the Project.
Based upon the duties and responsibilities stated in the RFP, we are providing this work plan to manage the city’ construction Project.
Although the plans do not include staging plans, the FCG Team believes the best way to construct this project shall be as follows:
Stage 1 - Westbound Princeton Avenue
a.Striping and Traffic Control – The project consists of
removal of the existing striping and portions of existing
asphalt and drainage improvements. As detailed in TCP
option 1, the approach the Contractor shall take, is to make
the south side of Princeton, the first phase of work. The
point to this is to get the south side improvements complete
and get the pedestrian traffic onto these new
improvements. The Contractor could then focus on the
north side of Princeton and gear up for the retaining walls
and other improvements. The FCG Team will coordinate all
efforts with the City, Caltrans and the Contractor to ensure
full compliance to requirements of MUTCD, WATCH
Manual, and project specifications.
b.Grading – The project consists of existing roadway
removal. The removals consist of existing asphalt and
concrete along with curb, gutter and sidewalk. There are
20K CYS of cut/fill with 10K CYS of export. The Plans also
call for 12.5K tons of C.A.B along with 7100 tons of A/C and
400 tons of Rubberized A/C.
c.Drainage / Waterline Improvements – The project consists of the installation of a new RCP storm drain systems from 18”
to 42” diameter pipe. Other storm drain improvements consist of Inlets, collars, headwalls, manholes, catch basins, junction
structures and wall gutters. There are approximately 3,220 LF of new waterline, which includes new fire hydrants, water service
reconnections, blow offs and air vac valves. Landscape irrigation is also part of the Contract. The FCG team will conduct a
utility meeting to ensure compliance to requirements set forth and collaboration by all utility companies and the Contractor.
Page 3 105
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
d. Civil Improvements – The project consists of removal of
existing concrete and asphalt, curb, metal beam guard rail,
fencing, ret. wall, bollards, signage and steel framework.
Most of the removals will be replaced with new items of
work. New A/C and rubberized A/C, concrete curbs, new
signage and striping, new driveways and curb ramps. The
driveways and ramps shall always remain open to
pedestrians. The FCG Team have extensive experience
with construction of such facilities and will make sure the
Contractor lays out the work in advance to meet all
pertinent requirements especially ADA requirements. In
addition, the FCG Team will coordinate proper materials
sampling and testing of soil, concrete, and asphalt work to
ensure quality of materials used for the project.
e. Electrical – The project consists of installation of new
traffic rated boxes and Cobra lighting fixtures. There are
also new power poles to be coordinated with SCE. The
FCG Team has extensive experience working with all
relevant electrical work and will ensure the Contractor
adheres to all required guidelines.
f. Landscape – The project consists of installation of a new
irrigation system with mainline and lateral piping, valves,
flow sensors and bubblers; The inspection of the irrigation
system is to be coordinated with the City’s landscape
representative. Landscaping consists of ivy, vines, bushes and lilacs. The FCG Team has extensive experience with such work
and Mr. Fuentes, our proposed Landscape Architect/Inspector will ensure compliance of all requirements for all work including
inspection of plant materials at the nurseries.
g. Structural Components – The FCG team provides Dragan Buha, PE, Structure Representative, as a lead for any structure
related submittals, RFI’s, change order requests and related items. Dragan has over 30 years of construction management
experience and he has worked on the SR-23/SR-118 Connector project completed in the early 90s and inspected the
construction of the structural work on this segment including the Arroyo Simi Bridges and Princeton Ave. Undercrossing Bridges.
Dragan has experience in all aspects of bridge and retaining wall construction under Caltrans and Greenbook standards and
will provide his services on this project only when required. Field inspection work will be done by the on-site roadway/bridge
inspector and Special Inspector and Material Testers (when needed). Any unusual geotechnical conditions observed will be
brought up to the Designer and Geotech Engineer of Record in order to verify that they are acceptable.
First order of work for our team is to review the project plans and specification, record any ambiguities that may require
clarifications and discuss these items with the designer. We also review background information that would help us better
understand designs constraints, permits, overall requirements and most important stakeholders’ involvement.
Structural work on this project includes several retaining walls (RW) to be constructed in order to accommodate roadway
widening. The project specific RW are labeled as “Type 1” to “Type 8” and they consist of CMU block stem walls supported on
cast in place (CIP) spread footings while the Type 9 RW consists entirely of an cast-in-place concrete stem wall supported on
24-inch Cast in Drilled Hole (CIDH) reinforced concrete piles with pile cap foundation. Based on the information provided in soils
report, we still need to clarify with the designer if any over excavation under the spread footings is required and to which depth.
Before starting the RW work, the contractor must provide submittals for materials to be used in the work for approval
(reinforcement, concrete, CMU blocks, mortar, grout, joint fillers), as well as specify methods of construction to be used. The
FCG Team together with the Engineer of Record (EOR) will review and approve all submittals before the work can start.
Contractor is required to positively identify all utilities before excavation for the foundations (Dig-Alert marked utilities), as well
as any existing/future drainage in potential conflict with the new foundations. Typical cross sections show that the existing slopes
could be laid back at 1:1 ratio, which in turn indicates that no shoring will be required. If any temporary shoring is required
Page 4 106
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
selected contractor will have to provide shoring design submittal for review and approval. Once each wall is staked by the
contractor’s surveyor, FCG Team will review staking notes and discuss wall transitions with the contractor to make sure all
stakes are clearly marked and in accordance with the project plans.
Once the RW foundation excavation start, inspector and material tester will verify elevation quantities and track them daily, test
compaction and verify depth of aggregate base under the foundation (if any specified). Excavation must be always protected,
and adequate signing placed for safety of pedestrians and motorist. Reinforcing steel placement and footing dimensions are
verified before the concrete is placed (we will also confirm that the approved concrete mix is used) and tested for quality
assurance. Placement of additional reinforcement, masonry blocks with mortar, grouting will be monitored daily and testing of
mortar and grout is performed at specified intervals for quality control. All tests are logged and tracked in project files; any failed
tests require correction before the work is approved.
Construction of CIDH piles (as part of the foundation for CIP concrete EW) require drilling 24-inch diameter holes, verification
that holes are plumb within tolerance with no caving and of adequate depth, inspection of reinforced steel cage with spacers
before it is placed in the ground and placement of approved concrete mix. Soils reports indicate presence of sandy soil which
will require use of temporary casing during placement of concrete. In case that the groundwater is encountered (several borings
indicate presence of groundwater), the contractor must propose the method of construction for review and approval (casing and
dewatering or wet placement method). Concrete placed under wet placement method (if needed), requires gamma/gamma
testing for verification of soundness of placed concrete.
Given the number of retaining walls, as well as the number of different types of RW, we will ensure that the proper type of wall
is being constructed on the correct location and the segment of the wall. Several of the RW on the project consist of multiple
transition withing short distances between different types that have different reinforcement and even block size. One such
example is Retaining Wall “B” which transitions between five different Types of RWs. Another example is Retaining Wall “A”
which consists of four different Types of RWs that transition between different types in distances as short as 9 feet. FCG
inspection staff will always have required detailed specific information from project plans onsite and discuss the details with the
contractor in order to avoid any errors or misunderstandings. Significant portion of the work on this project (walls “G” and “J”)
include installations of over 300 24-inch CIDH piles. According to the local geology of the area and likelihood of existence of
shallow bedrock, there is a potential that a significant amount of CIDH piles could potentially encounter bedrock prior to 50-foot
embedment, which according to the contract plans will require a 15-foot rock socket drilling and embedment in bedrock. We will
discuss this with the contractor at the preconstruction meeting and request that they have adequate drilling equipment on site
to avoid potential delays. These piles are spaced at 6-foot intervals (3 pile diameter) and the contractor will have to consider
pile placing sequence in their workplan in addition to proposed methods of installation.
Retaining Walls - This project contains an extensive number of retaining walls to be constructed. After reviewing the provided
plans, we understand there are 8 retaining walls that total a combined length of approximately 0.85 miles and consist of 9
different project specific retaining wall types. The project specific retaining walls are labeled Type 1 to 8 which consist of CMU
block stem walls supported on CIP spread footings with the 9th type of retaining wall consisting entirely of an CIP stem wall
supported on 24-inch CIDH piles. These nine different types of retaining walls are not Caltrans Standard Specification “Type”
of walls, but rather project specific.
Given the number of retaining walls as well as the number of types of retaining walls, one challenge will be to ensure that the
proper Type of wall is being constructed on the correct retaining wall. Several of the retaining walls on the project consist of
multiple types which transition within short distances back and forth between different types. One such example is Retaining
Wall “B” which transitions between 5 different Types of retaining walls. Another example is Retaining Wall “A” which consists
of 4 different Types of retaining walls that transition between different Types in distances as small as 9 feet.
To ensure the proper Type of wall is constructed, our structures staff will tabulate every top of wall and top of footing stated on
the contract plans, review them prior to each work shift, and bring to the attention of the Structure Representative any
discrepancy that is encountered so the contractor does not get to far in construction if a potential correction is necessary. This
level of proactiveness is the core of minimizing schedule impacts as well as controlling project cost. Our team has already put
together two tables to assist in our complete understanding of which wall requires which type of wall, see below:
Page 5 107
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
We have identified several challenges, including
Retaining Wall “J”, which has a wall layout line approximately 8 feet from SR-118 Bridge Bent 6L as well as the CIDH
support pile approximately 11 feet from the Bridge Bents location. Given that the CIDH have the potential of having rock
sockets, drilling activities may require monitoring equipment to be placed on SR-118 Bridge Bent 6L to ensure excessive
vibrations do not impact the existing bridge foundation or column. See Exhibit S- 1.
With a new 30-inch RCP storm drainage pipe being installed under Retaining Wall “B”, coordination between drainage and
structures construction field staff in relation to the proposed 30-inch RCP storm drain line at CL station 19+60 approximately
1 foot below bottom of footing will be critical to ensure no schedule delays in retaining wall construction. See Exhibit S-2.
With an existing 42-inch storm drain line under proposed Retaining Wall “C”, proper identification, verification of depth, and
location of existing 42-inch storm drain line approximately 4 feet below bottom of footing on Retaining Wall “C” at CL Station
16+00 will be necessary during excavation activities for retaining wall footing. See Exhibit S-3.
Retaining Walls “G” and “J” are supported on 24-inch CIDH piles with embedment length requirements that have the
potential of 15-foot-deep rock sockets into bedrock based on the local area geology. With 320 CIDH piles combined
between the two walls, the potential schedule delays could have a significant impact to schedule. We understand the
importance to provide adequate documentation for assistance in potential change order work or disputes in the future,
successful documentation of drill rates, soils encountered, and communication with the City or Caltrans will be required.
With the various Types of walls and multiple transitions within one wall, constructability issues may be present with
longitudinal continuous reinforcement that is required to continue through these transitions. One example is a Type 5 wall
transitioning into a Type 8 wall, which consists of a transition from 16” CMU block to 12” CMU block. See Exhibit S-4.
CIDH Piles - This project has extensive foundation installations including cast-in-drilled-hole (CIDH) piles. For retaining walls
“G” and “J”, there are more than (320) 24-inch CIDH piles supporting the retaining walls that require installation. According to
the local geology and potential shallow bedrock, there is a potential that a significant amount of CIDH piles could potentially
encounter bedrock prior to 50-foot embedment which according to the plans will require a 15-foot rock socket installation.
Wall Wall Type Height, FT CL Stations Total Length, FT Foundation
A4, 5, 6, 84 to 14 1+56.63 to 5+00.62 328 Spread Footing
B1, 4, 5, 6, 84 to 12 5+79.48 to 15+48.41 996 Spread Footing
C1A, 1B, 74 to 715+76.80 to 21+96.15 641 Spread Footing
D1422+25.92 to 23.88.97 175 Spread Footing
E1, 63.5 to 524+19.01 to 33+87.54 925 Spread Footing
GCIP Stem and Footing 6 to 18 9+25.73 to 17+66.69 824 24" CIDH
H2, 37 to 9 5+24.65 to 8+99.73 355 Spread Footing
JCIP Stem and Footing 6 to 18 18+42.69 to 19+26.69 120 24" CIDH
PROJECT WALL TYPES CMU BLOCK SIZE (IN)
18
28
38, 12
48, 12
58, 12, 16
68
712
88, 12
Exhibit S‐1
Exhibit S‐2
Exhibit S‐3
Exhibit S‐4
Page 6 108
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
In addition, the 24-inch CIDH piles are to be installed at 6 feet off center from each other. Careful consideration of pile installation
sequence will be required during installation to not disturb fresh concrete of adjacent CIDH that were placed the previous day
or two. Under the Caltrans SR's direction, our staff will review the contractor's pile installation plan for conformity to project
requirements, special provisions, and Caltrans Standard Specifications. During construction, our inspection staff will monitor
drill rates, start and stop times of drill rigs, rock socket drill rates, drill rig down time, and other necessary information in order to
assist the agency in any potential future claims or change orders. Prior to starting the work, we will review the pile placement
plan and verify the outline of the contractor’s method for sequence of placement, the methods of installation, and a mitigation
plan are acceptable. From there, we will make recommendations to the Structures Representative if any changes are required
to be contract compliant. Once the work begins, our team has the experienced staff to inspect and watch for during CIDH pile
construction. Our experienced structures inspection team has a deep understanding of the contract requirements, has expertise
in this type of pile installations, and will verify the work is completed in accordance with contract requirements.
Stage 2 - Eastbound Princeton Avenue
a.Striping and Traffic Control – The project consists of removal of the existing striping that conflicts with project details;
installation of temporary striping for placement of k-rail and crash cushions on the shoulders of the 133 freeway and in the center
median. The plans include a detour plan but do not include traffic control or staging plans, however, the Contractor will most likely
close lanes during the allowed hours per the project specifications for erection and removal of falsework. The FCG Team
anticipates that the Contractor will perform various operations at night due to availability of full closure especially for work over
through lanes. The FCG Team will coordinate all efforts with the City and Contractor to ensure full compliance to requirements
of MUTCD, WATCH Manual, and project specifications.
b.Drainage / Waterline Improvements – The project consists of the installation of new electrical conduits, irrigation conduits
and existing copper pipe removal and capping. The project plans include construction of a new 10” drainage system atop a
concrete v ditch and then backfilled with lean concrete. There are also at grade light fixtures located on the project. The FCG
Team will conduct a utility meeting to ensure compliance to requirements set forth by all utility companies and the Contractor.
c.Civil Improvements – The project consists of various freeway, road and trail improvements, including, but not limited to,
removal of existing concrete and asphalt, and restoration of facilities at the end of the project. New PCC paving, new minor
concrete paving and asphalt paving. The FCG Team have extensive experience with construction of such facilities and will make
sure the Contractor lays out the work in advance to meet all pertinent requirements especially ADA requirements. In addition,
the FCG Team will coordinate proper materials sampling and testing of soil, concrete, and asphalt work to ensure quality of
materials used for the project.
d.Electrical – The project consists of installation of new conduit and light fixtures for the bridges and trails. An un-metered panel
will be built and at grade lighting fixtures will be included from the bridge to Novel Park. The FCG Team has extensive experience
with working with all relevant electrical work and will ensure full compliance to requirements for all work.
e.Landscape – The project consists of installation of a new irrigation system; construction of hardscape; and installation of new
plants. The FCG Team has extensive experience with such work and Mr. Fuentes, our proposed Landscape Architect/Inspector
will ensure compliance of all requirements for all work including inspection of plants at the nurseries.
Stage 3 – Pavement and Delineation
a.Pavement – The project consists of installation of a new irrigation system; construction of hardscape; and installation of new
plants. The FCG Team has extensive experience with such work and Mr. Fuentes, our proposed Landscape Architect/Inspector
will ensure compliance of all requirements for all work including inspection of plants at the nurseries.
b.Striping – The project consists of installation of a new irrigation system; construction of hardscape; and installation of new
plants. The FCG Team has extensive experience with such work and Mr. Fuentes, our proposed Landscape Architect/Inspector
will ensure compliance of all requirements for all work including inspection of plant materials at the nurseries.
c.Demobilization – The project consists of installation of a new irrigation system; construction of hardscape; and installation of
new plants. The FCG Team has extensive experience with such work and Mr. Fuentes, our proposed Landscape
Architect/Inspector will ensure compliance of all requirements for all work including inspection of plant materials at the nurseries.
Page 7 109
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Approach
The FCG Team’s strives to anticipate or diminish potential conflicts/issues before they arise through continual review of project plans,
specifications, contractor’s schedule, and other contract documents. Our team is adept at:
Anticipating job site conflicts/issues
Calling job site conflicts/issues to the Project Manager’s and /or contractor’s attention
Offering constructive recommendations and achieving cooperation from the contractor
Dealing with issues in a professional, straightforward fashion
Our approach to issues resolution is to:
Obtain and document the facts surrounding the issue
Develop reasonable solutions in conjunction with the contractor and City Project Manager
Respond quickly and effectively so that job progress and quality to not suffer
Project Goals
The FCG Team has had two primary objectives since our inception in 2010:
Ensuring the success of our clients and delivery of projects.
Enhancing communities and providing the best project.
Working steadily toward these goals we gained a notable reputation for project understanding, technical excellence, cost
effectiveness, and client responsiveness. It is these attributes that our construction management and inspection team bring to each
project. To these goals, we add individual project-oriented goals that include:
Ensure Safety and compliance to Plans, Specifications, SWPPP, MUTCD, and all others.
Continuous communication with City staff, contractor, and design team.
Impeccable recordkeeping and reporting.
Budget Control – Minimizing change orders and applying value engineering where applicable.
Schedule Control – keeping the project moving while resolving design, contractor, or other project challenges.
Understanding City of Moorpark Needs
The FCG Team understands the importance of this project to the City as it has been anticipated to start construction for a long time
now. As the City of Moorpark staff strive and work hard to improve the lives of the residents of the City of Moorpark, project such as
this provide a great deal to the City in terms of improving infrastructure and traffic flow. The FCG Team understands the needs of
the City of Moorpark due to the following:
Previous Work Experience
FCG successfully completed Construction Management and Inspection on the Asphalt Overlay of Spring Road, Princeton Avenue,
Poindexter Avenue, and Gabbert Road Project; City Project No. MPK 15-03, Federal Project No. STPL-5436 for the City of Moorpark,
October 2017 through March 2018. This project was very important to the City as it required administration per the Caltrans Local
Assistance Procedures Manual (LAPM), coordination with residents and business, and coordination with Caltrans especially at
Westbound SR-118 at Princeton Avenue which ended at the limits of this project. The FCG Team successfully delivered project to
the City without any claims or issues and the City received full reimbursements of federal funds under the leadership of our proposed
Project Manager / Resident Engineer Mr. A.B. Fakhouri.
City Policies and Procedures
As stated earlier, FCG has successfully completed a federally funded project with the City of Moorpark during which FCG executed
all administration of the project alongside of the City utilizing LAPM and City procedures and formats of documents. Such documents
included, but not limited to; daily inspection reports, progress pay estimates, and more. As the project started, Caltrans
Construction/Local Assistance Liaison conducted a Pre-Construction Review of the project documents where FCG had all
documents prepared properly to the satisfaction of the City and Caltrans per the City and Caltrans requirements.
Scope of Services: The FCG Team has prepared a thorough and specific Scope of Services something in Section 6.
Page 8 110
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
Special Considerations and Project Challenges
FCG learned a great deal about working with the City of Moorpark in terms of enforcement and ensuring Contractor compliance
during construction. The FCG Team understands the City ordinances and requirements pertaining to construction projects as the
proposed project may be the largest of its kind at the City. and this is when the FCG Team can step in and ensure compliance. Our
Resident Engineer will ensure the Contractor is aware of all this at the Pre-Construction Meeting and will remind the Contractor of
this every day and in every meeting and will make sure the inspector is enforcing this daily in the field. Other challenges that will
impact construction are, but not limited to, are as follows:
CHALLENGE RECOMMENDED SOLUTIONS
Safety
Safety is the most important thing on any construction project, including but not limited to,
pedestrians, motorists, bicyclists, contractor workers, inspectors, city and agency staff, and
anyone in the vicinity of the project. The FCG inspector will always enforce safety.
Maintaining Traffic Flow
The FCG Team understands the need to enforce starting work hours at 8:30 a.m. and ending
at 4:30 p.m. and lane closures at signalized intersections within 200 feet of a signal is limited
to 9:00 a.m. and 3:00 p.m. Such requirements will limit the production of the Contractor’s work,
not to mention the limited workspace on Princeton Avenue work limits, and it may cause the
Contractor to try to start work earlier and not schedule to complete daily work by 4:30 p.m.
Electrical Equipment Lead Time
Procurement of electrical equipment has caused delays prior to the start of construction and
during construction due to the high demand of such equipment. It is recommended that the
Contractor submit all long lead items before the Pre-Construction meeting to meet the deadline.
Coordination with Utility Companies
Typically, coordination with utility companies takes time, especially with Southern California
Edison (SCE). The FCG Team will ensure coordination is done timely to maintain the project
schedule by conducting a utilities meeting immediately after the Pre-Construction Meeting.
Flagging Typical payment for traffic control does not specifically include flagging costs. We recommend
including specific language for flagging as part of traffic control if flagging is needed.
Construction Schedule We suggest adding language to the specifications to include a timeline for review and response
to the baseline schedule and submittal of monthly schedule updates.
Page 9 111
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Constructability Review of Plans and Specifications
The FCG Team has worked on several similar projects and learned a great deal during construction of such projects as many of th e
team members have experience working as Designers, Contractors, Construction Managers, and Inspectors. The FCG Team has
noticed some issues of concern and provided recommended solutions as shown in the following table:
ISSUES AND RECOMMENDED SOLUTIONS
PROJECT PLANS
CIDH Piles
CIDH piles should be addressed more clearly: minimum to none details of requirements for
CIDH piles construction including workplan submittal and possibility to have wet hole concrete
placement. Pile length is not defined which can create increased cost of this item to the city
(contractor will bid conservatively, or it will create potential claim). Retaining wall sheets refer to
the Geotech Reports and these should be made available to the contractors bidding the project.
CDIH Pile Clearance
CIDH pile bottom clearance should be 3”
not 2” as shown on detail for 24” CIDH
Concrete Pile
CDIH inspection Tubes
CIDH inspection tubes: CIDH pile shows inspection tubes that are required for wet hole concrete
placement, is there a chance to hit underground water? Geotech report should addressed that.
CIDH pile depths:
CIDH pile depths: CIDH pile depth is undefined on the plans? It is given as 50 foot if no bedrock
and embedded to the bedrock 15 feet. There is a potential that most piles will be f=different
length preventing the contractor from making rebar cages in advance. Typically drilled holes
should be filled ASAP after frilling with concrete and rebar.
Retaining Wall
Retaining Wall specifications (piles, foundations, block walls, concrete walls) are not sufficient
in details, suggest adopting Caltrans requirements at least for CIDG piles if not all elements.
Rebar Specify distance from rebar to interior block wall, wall Type 7 (and others).
Backfill Specify height of permeable backfill material behind RW 7. (CT SS has it).
Retaining Wall Blocks
Specify location of the rebar in reference to the inside wall of the block, not outside. With gravel
size 3/8- 1/2-inch, this rebar should be at least 0.5-0.75 inch away from the inside surface, so it
is encased in grout. It should be shown on the detail.
Gap Areas
Plans should address gap area shown
between larger and smaller size block
shown as triangle? See below. Is it grout,
mortar or just backfill?
Bridge details BO-3
Plans should address Caltrans “Bridge Details BO-3”: sheet (page 34 of 69 plans) should be
referenced for all walls. Each wall cross section should be labeled with appropriate details.
Retaining Wall Cap
Top of RW has cap: no details what type
of cap is it? If mortar cap, it should be
shaped to shed water. If not, in some
locations it must be drilled (?) for cable
railing post (detail should be provided).
Page 10 112
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 2: STATEMENT OF PROJECT UNDERSTANDING
PROJECT SPECIFICATIONS
Overtime Inspection Overtime inspection should be clearly defined: define overtime in excess of 8 regular hours daily
and weekend work and provide an hourly rate to be charged back i.e., $140 per hour.
Schedule updates
The Contractor to submit a weekly look-ahead schedule and monthly project schedule updates
along with updated As-Builts with monthly progress payments.
Water Improvements
City should double check the agreement and permitting process during construction to ensure
that the Princeton Avenue Contractor is allowed to perform the various work as some water
agencies require that their specialty contractors perform the works; project specs should clearly
define the scope of water matched with the plans; and explain the permitting process and who
is responsible for what and costs.
Specifications References The specs have a few references in CT Permit about Lead Compliance Plan, no reference
seen in the SP.
HEPA The specs should address HEPA; Caltrans also commented on use of HEPA filters for
vacuuming stripe removals, no reference seen in the SP.
Submittals
Need to be approved before contractor can start work. Suggestion is CPM schedule, SWPPP,
obtain permits, (provide LS items breakdown or Schedule of Values SOV).
Surveying issues Surveying is to be done by the contractor, include sentence in SP that the contractor’s Surveyor
shall provide survey notes and reports available to the CM 24 hours after completing the staking.
LS measured items
At some point the contractor should provide itemized item breakdown for LS items to facilitate
monthly payments. It is preferred that this be provided with the bids, in order to help evaluate
and compare them. The Designer probably has breakdown of quantities for these items, but we
can only list descriptions and let the contractor show their quantities and unit prices.
SWPPP Provide guidelines for SWPPP prepared by the contractor.
Buy America More details on Buy America: Buy America requirements are mentioned in SP but without many
details. It should reference spec that explains it in more detail.
Page 11 113
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
FIRM PROFILE / QUALIFICATION
FCG Consultants, Inc. (FCG) a woman-owned California Corporation and Certified Small
Business (SBE) and Disadvantaged business Enterprise (DBE), is focused on providing client-
driven solutions to assist clients in navigating through a very challenging economy. FCG,
founded in 2009, is headquartered in Yorba Linda, California with a staff of twenty three fully
dedicated personnel providing Construction Engineering, Construction Management, and
Construction Inspection to clients throughout California. The firm specializes in Project and
Construction Management and Inspection for various types of public works clients utilizing
assorted standards such as Caltrans, Local Assistance Procedures Manual, FHWA,
Greenbook, and AWWA. FCG staff are highly experienced with inspection of roadway
improvements, drainage systems, utilities, ADA ramps, retaining walls, MSE walls, soil nail
walls, Structural Steel/Bolting/Welding, pedestrian/bikeways, wet CIDH pile, stainless steel,
electrical, landscape, SWPPP, and Safety.
FCG serves its clients from two locations, Yorba Linda and Norwalk. With twenty-three
employees in both locations, we are able to cover a larger geographic market to better serve
our clients. FCG’s construction engineering and inspection team provides a full scope of
services, from project development through project closeout, by providing cost-effective and
functional solutions. The FCG Team carefully plans and tailors the scope for each assignment,
specific to the client and project needs. We are fully dedicated to achieving every project
and client goal and standard.
Financial Condition: FCG is financially sound and has no bankruptcy, pending litigation,
planned office closures, or impending mergers. FCG is not prohibited from professional practice or working with any Federal, State,
local or public agency.
We firmly believe that with each passing year and the completion of each job for our various clients, the satisfaction of our clients will
begin to further reflect the condition of our company as well as our ability to provide our clients with the professionalism and superior
customer service they deserve.
Similar and Government Agency Experience: FCG has a strong working relationship and rich history with our subconsultant team.
Our previous experience, mutual trust, and ability to mobilize quickly and keep the project momentum moving forward allows us to
present City of Moorpark with a quality team that can work together to deliver a project successfully and on-time. The FCG Team
members have extensive experience with construction management services for City of Moorpark, Caltrans, and a myriad of other
clients and agencies. Each of us is familiar with construction management and inspection contracts and understands the importance
of assembling a solid team. For this effort, we have nine (9) highly qualified key staff, and additional as-needed staff, working together
as a team to ensure City of Moorpark is getting the highest quality candidates and service to successfully complete the project on-
time. In this proposal, FCG will discuss several successfully delivered projects that are similar to this project.
Our people are our greatest strength and therefore our greatest asset. Our success is based on our hiring the best people in the
industry to produce the highest quality results at the most reasonable price. This practice continues throughout our internal
comprehensive training program that can get inspectors up to speed on any work assignment and in any work environment, concluding
with our quality maintenance process. Our employees and subconsultants have a depth of knowledge and experience that sets
us apart from our competitors.
Our personnel are highly qualified and experienced in their respective disciplines. Each of their qualifications illustrate multiple
projects, past and present, they have worked on. We are proposing a sum of experienced candidates with the appropriate experience,
as per the city’s requirements and the RFQ, who are ready and available to be deployed. This pursuit is a team effort and FCG is
committed to ensuring City of Moorpark receives the highest quality service from the appropriate candidates regardless if they are
prime or subconsultant.
Our Construction Manager, Mr. Fakhouri, will work closely with the subs to ensure unity, uniformity, and continuity between the
subconsultants and the City of Moorpark and deliver the highest quality service to City of Moorpark. You can expect seamless
integration with the current construction personnel.
Firm Information
Firm Location:
22885 Savi Ranch Pkwy, Suite G
Yorba Linda, California 92887
Form of Organization:
California S Corporation
Number of Employees:
20 Full-time employees
3 Part-time employees
Registration
DIR # 1000018164
DBE # 46140
Federal ID # 27-3911217
Page 12 114
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Many of our employees are externally trained in Caltrans test methods, various OSHA safety trainings, HAZMAT environmental
training, SWPPP QSD, SWPPP QSP, ACI, as well as a myriad of other training certifications. More than the certifications they hold,
our team has a “can-do” attitude and motivation that makes our presence known and helps develop our business at every level and
with every client. In addition to hiring the best and the brightest in the industry, we provide internal training to each of our employees.
From inspection, safety, SWPPP, office engineering, labor compliance, to materials testing and more, FCG provides their staff with
continued training and support in every area of their career. Over the years, FCG has developed a significant amount of training
material related to construction and project management and inspection which is and will continue to be a benefit across all areas of
our business.
Our relevant project experience is a demonstration of the different projects we have worked on from bridge widening to Caltrans right-
of-way, utility relocation, traffic signals, building and widening ramps, building retaining walls, traffic control, night work, and 55-hour
closures. We have completed this work enforcing different specifications, including Caltrans Standard Plans and Specifications,
Greenbook Standard Plans and Specifications, SWPPP, Safety, Cal-OSHA, Caltrans Safety Requirements, and Caltrans Structures
Safety Requirements. Each of us have worked around environmentally sensitive areas, near bodies of water, challenging interchanges
surrounded by businesses and residences as well as congested interchanges, freeways and live traffic. In-fact, many of us have
worked on the 60 freeway itself, performing the same kind of work. We have done this work not only in Orange County, but also in
Riverside, and Los Angeles counties, as well as other parts of the state. As a result, we understand the special needs of these types
of projects and can bring that knowledge and understanding to this project.
The following table shows some of the recent projects FCG and the Project Manage / RE:
Differentiator: FCG staff has the ability to efficiently staff projects with the most committed, experienced and knowledgeable staff
with relevant experience to each project. The FCG Team can provide large business service with a team of multi-discipline
professionals; however, what differentiates our firm from others is having the ability to provide a small business, client-focused, and
customer-service approach to deliver each client the one-on-one attention needed to specifically tailor cost-effective solutions and
solve unique project needs.
Agency Project Role Start/End Dates
Construction Management and Inspection
City of Whittier/Caltrans D7 Whittier Greenway Trail Extension Gap Closure
Project PM/RE 02/2021 – 02/2022
City of Downey/Caltrans D7 Telegraph Road Traffic Throughput & Safety
Enhancement Project – Federal Funds PM/RE 05/2021 – 01/2022
City of Norwalk/Caltrans D7 Traffic Signal Improvements on Rosecrans Ave.
Project – Federal Funds PM/RE 03/2021 – 09/2021
City of Norwalk/Caltrans D7 Traffic Signal Improvements on San Antonio Dr.
Project – Federal Funds PM/RE 03/2021 – 09/2021
City of Downey/Caltrans D7 Stewart & Grey Fiber Optic Traffic Signal Project
– Federal Funds
PM/RE 08/2020 – 07/2021
City of Downey/Caltrans D7 Imperial Highway Traffic Signal Upgrades
Project – Federal Funds PM/RE 08/2020 – 07/2021
City of Irwindale/Caltrans D7 Irwindale Park Improvements Project, Phase III PM/RE 03/2020 – 02/2021
City of Burbank/Caltrans D7 Burbank Channel Bikeway Project – Federal
Funds PM/RE 08/2019 – 02/2021
City of Irwindale/Caltrans D7 I-605/Live Oak Ave. Ramp Widening &
Improvement – Federal Funds PM/RE 10/2018 – 02/2020
City of Norwalk/Caltrans D7 Foster Road Side Panel Replacement Project –
Federal Funds PM/RE 11/2017 – 05/2019
City of Moorpark/Caltrans D7 AC Overlay on Various Streets – Federal Funds PM/RE 10/2017 – 02/2018
City of Whittier/Caltrans D7 Beverly Blvd. Traffic Safety & Lighting
Improvements – Federal Funds PM/RE 12/2016 – 07/2017
City of Norwalk/Caltrans D7 Alondra Boulevard Street Improvements –
Federal Funds PM/RE 07/2015 – 05/2016
Norwalk/Downey/Caltrans D7 Firestone Blvd. Bridge Replacement – Federal
Funds PM/RE 05/2014 – 11/2015
City of Delano/Caltrans D6 Woollomes Ave Interchange Improvements
Project PM/RE 01/2012 – 03/2014
Page 13 115
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SIMILAR PROJECT AND REFERENCES
Whittier Greenway Trail East Extension & Lambert Rd. Signal Synchronization | City of Whittier, CA - FCG
Client City of Whittier Contact Isaac Bravo; Civil Engineering Assistant
13230 Penn Street
Whittier, CA 90602
(562)567-9518
ibravo@cityofwhittier.org
Project Description
This Federally Funded Project consists of a 2.7mile long
easement into a 15-foot-wide walking trail along Union Pacific
Railroad. Work includes the construction of bicycle and pedestrian
path, installation of fencing along the corridor, pedestrian crossings
and walking paths, wayfinding sinage, and storm drain
modifications. The Lambert Road Traffic Signal Synchronization
will include coordination of traffic signal timing and detection,
upgrading traffic signals and grade signal crossings.
Scope of Services
FCG staff will perform construction management and inspection
services per Caltrans LAPM and Caltrans Construction
Manaual. Work included traffic control, removals, concrete and asphalt paving, curb and gutter, ADA ramps, sidewalk, street
lighting, traffic signals, Edison service connections, drainage, landscape, and striping. Duties included management and
inspection of various items of work, office engineering, conducting meetings, reviewing submittals and RFIs, CCOs, daily diaries
and quantities, daily photos, coordinating materials testing and lane closures, filing documents, and preparing as-builts
Dates 02/2021 – 02/2022 Cost $ 9 Million
Staff FCG Staff: A.B. Fakhouri, Project Manager; Don Lewis, Construction Inspector, and Samar Alfakhouri, Office
Engineer.
Telegraph Road Traffic Throughput & Safety Enhancement Project | City of Downey, CA – FCG & HES
Client City of Downey Contact Edwin Norris, PE – Project Manager
11111 Brookshire Avenue
Downey, CA 90241
(562) 904-7110
enorris@downeyca.org
Project Description
This Federally Funded Project consisted of construction of raised
median islands with landscaping and irrigation, reconstruction of the
existing asphalt pavement, traffic signal modifications and signage
and striping.
Scope of Services
FCG is performing construction management and inspection
services per Caltrans LAPM and Caltrans Construction Manaual.
Work includes traffic control, removals, concrete and asphalt paving,
curb and gutter, ADA ramps, sidewalk, street lighting, traffic signals,
fiber optics, Edison service connections, drainage, landscape, and striping. Duties include management and inspection of various
items of work, office engineering, labor compliance, conducting meetings, reviewing submittals and RFIs, CCOs, daily diaries and
quantities, daily photos, coordinating materials testing and lane closures, filing documents, and preparing as-builts.
Dates 05/2021 – 01/2022 Cost $7 Million
Staff FCG Staff: A.B. Fakhouri, Project Manager; Tony Alfakhouri, Inspector; Jasmine Alfakhouri, Office Engineer.
HES Staff: Juan Hernandez, Principal Biologist; Shawn Gatchel-Hernandez, Principal Regulatory Specialist; Elizabeth
Gonzalez, Associate Biologist; Hallie Hernandez, Associate Biologist; Sarah Gulyas, Associate Biologist; Sarah
Vasquez, Associate Biologist.
Page 14 116
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Burbank Channel Bikeway Project BS-1481 | City of Burbank, CA - FCG
Client City of Burbank Contact Omar moheize – Principal Civil Engineer
150 North Third Street
Burbank CA 91502
(818) 238-3915
omoheize@burbankca.gov
Project Description
This Federally Funded Project consists of 0.79-mile bike and
pedestrian path that is being constructed adjacent to the Burbank
Western Channel. Work includes activities required to ensure that
construction is performed in accordance with permit requirements,
Federal and State regulations, and the approved plans and
specifications.
Scope of Services
FCG performed construction management and inspection services
per Caltrans LAPM and Caltrans Construction Manaual. Work
included traffic control, removals, concrete and asphalt paving, curb
and gutter, ADA ramps, sidewalk, street lighting, traffic signals,
Edison service connections, drainage, landscape, and striping. Duties included management and inspection of various items of
work, office engineering, conducting meetings, reviewing submittals and RFIs, CCOs, daily diaries and quantities, daily photos,
coordinating materials testing and lane closures, filing documents, and preparing as-builts.
Dates 10/2019 – 2/2022 Cost $8 Million
Staff FCG Staff: A.B. Fakhouri, Project Manager; Sami Hamamdeh, Inspector; Anthony Moussa, Inspector.
Fairway Drive / SR-60 Lemon Avenue Interchange | City of Industry, CA - WSP
Client San Gabriel Valley Council of
Governments (SGVCOG)
Contact Charles Tsang, PE – Project Manager
4900 Rivergrade Road, Suite A120
Irwindale, CA 91706
(626) 962-9292
ctsang@sgvcog.org
Project Description
WSP is providing full CM for the $150M Fairway Drive Grade
Separation project located in the City of Industry and
unincorporated area of Los Angeles County, crossing the UPRR
Los Angeles Subdivision and Metrolink (Riverside Line) at UPRR
milepost (MP) 23.40. This project eliminates the existing at-grade
crossing at this location through construction of a combination of
railroad flyover and roadway underpass just north of SR 60. Work
includes constructing a four-lane roadway underpass and a new
four-track, 80’-wide railroad bridge. Business Parkway and Walnut
Drive North will be lowered at their intersections with Fairway Drive.
Scope of Services
The scope includes constructing 7,000 feet of retaining walls up to 30’high to support raised UPRR and Metrolink tracks, a new
structural steel railroad bridge, and reconstruction of several freight siding and lead tracks for adjacent businesses. Scope also
includes earth retaining structures, soil stabilization system (Geopier®), pump station, grading, storm drain realignment, culverts,
sewer siphon with airline, relocation of Verizon and MCI lines, waterline installation, utility casings, street lighting, signals
modification, signing and striping, protection and/or relocation of existing dry and wet utilities, and ADA-compliant curb, gutter and
sidewalk, landscaping and irrigation. Temporary work consists of railroad shoring systems conforming to BNSF/UPRR
requirements, excavation support systems and traffic control features. The entire project includes a total of 200,000 cubic yards of
roadway excavation and 18,200 cubic yards of retaining wall.
Dates On-going Cost $159 Million
Staff WSP Staff
Page 15 117
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Gerald Desmond Bridge Replacement | City of Long Beach, CA - WSP
Client Port of Long Beach Contact Duane Kenagy, PE – Project Manager
415 W. Ocean Blvd.
Long Beach, CA 90802
(562) 283-7068
Duane.Kenagy@polb.com
Project Description
The GDB will be the first cable-stayed vehicular bridge to be
constructed in the state of California. The existing bridge has
developed maintenance problems and safety issues, and the Port of
Long Beach, its owner, has determined that it is more economical to
replace it with a new bridge with 200 feet of vertical clearance over
the Ports’ Main Channel, 45 feet more than the original structure.
Construction will include approaches, ramps and connectors to
Ocean Boulevard and the I-710 Long Beach Freeway. The proposed
alignment will be approximately 140 feet north of the existing bridge,
centerline to centerline. The bridge will be a cable-stayed design with
two towers approximately 500 feet in height. Excluding approach
structures, the bridge will be approximately 2,000 feet long, with the main span approximately 1,000 feet long from tower to tower.
Scope of Services
WSP was selected by the Port of Long Beach to provide program management and construction management (PM/CM) services
for the design-build Gerald Desmond Bridge (GDB) Replacement Project. Utility relocation was one of the most significant efforts.
Major utilities impacted will include high-pressure gas, water, sewer, telephone, electrical, storm drain, and oil pipelines. Once the
new bridge is in service, the existing GDB will be demolished.
Dates Ongoing Cost $1.47 Billion
Staff WSP Staff: Chris Okerstrom, Scheduler
I – 15 Express Lanes Design-Build Project, Riverside County, CA – WSP and FCG
Client Caltrans District 8 Contact Siong Yap, PE – Resident Engineer
464 West 4th Street
San Bernardino, CA 92401
(951) 232-3922
Siong.yap@ca.dot.com
Project Description
WSP is providing independent quality assurance (IQA) services as
part of the project/ construction management team for this $600M
design-build project for Caltrans D8 and Riverside County
Transportation Commission (RCTC). Additionally, many of our
subconsultant firms are presently supporting the Caltrans contract.
The Project adds two express lanes in each direction for
approximately 14-miles across five cities in Riverside County.
Responsibilities include supervising a team of IQA staff
responsible for inspection and verification of the quality assurance
(QA) teams, adherence to the approved Quality Management Plan
(QMP) during inspection and documentation of constructed items
of the project for final acceptance; as well as review and response to submittals, requests for information (RFI’s), notices of design
change (NDCs) and nonconformance records (NCRs) issued during the project.
Scope of Services
WSP’s proactive staff demonstrated our ability to commuinicate requirements well with the contractor and resolve potential field
issues at the lowest level to facilitate quality work while keeping the project on schedule.
Dates Ongoing Cost $600 Million
Staff WSP Staff
FCG Staff: AB Fakhouri, PE as Independent Quality Assurance Inspector
Page 16 118
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
2020 Annual Pavement Overlay and Slurry Program | City of Thousand Oaks, CA - Twining
Client City of Thousand Oaks Contact Mike Tohidian, PE - Senior Civil Engineer
2100 Thousand Oaks Boulevard
Thousand Oaks, CA 91362
(805) 449-2516
mtohidian@toaks.org
Project Description
The City of Thousand Oaks is responsible for maintaining
approximately 380 miles of streets and is a leader in exploring the
use of innovative pavements with emphasis towards utilizing
recycled crumb rubber in asphalt concrete pavements.
Since 2010, Thousand Oaks has engaged the services of Twining
to assist in review and revision of the community’s pavement
rehabilitation specifications, perform materials design studies,
implement quality assurance programs, perform construction
inspection and testing, and perform pavement destructive testing
and assist with pavement deflection testing for future pavement
designs. The City used Terminal Blend rubberized emulsion
aggregate slurry seal, using black rock source. The black rock will help the slurry seal to retain its black color for a longer period
and the rubberized emulsion will add to the durability of the slurry seal product.
Scope of Services
Twining has provided annual materials certifications and labor compliance interviews throughout the projects per Caltrans LAPM
and Caltrans Construction Manaual.
Dates 05/2020 – 09/2020 Cost $8 Million
Staff Twining Staff: Jeff Tawakoli, PE, Branch Manager; Amir Ghavibazoo, PhD, Pavement Engineer; Brandan Mathis,
Inspector; Rachel Stuff, Inspector
Yerba Buena Road South Resurfacing | County of Ventura, CA - Twining
Client County of Ventura Contact Matt Ehret – Project Director
800 South Victoria
Ventura, CA 93009
(805) 643-0446
matthew.ehret@ventura.org
Project Description
The 2020 project consists of providing quality assurance during
pavement resurfacing of Yerba Buena Road south per Specification
RD19-03 from State Route 1 to Post Mile 3.28. The project scope
included asphalt-rubber aggregate membrane, asphalt rubber hot mix
placements, pavement widening, polymer modified bitumen placement,
miscellaneous paving, and construction of new catch basins, and asphalt
concrete berms.
Scope of Services
Twining provided batch plant and field coverage for compaction testing
of soils, base, and asphalt per Caltrans LAPM and Caltrans
Construction Manaual.
Dates 03/2020 – 05/2020 Cost $2.2 Million
Staff Twining Staff: Jeff Tawakoli, PE, Project Manager; Amir Ghavibazoo, PhD, Pavement Engineer; Brandan Mathis,
Inspector
Page 17 119
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
East Mountain Drive Bridge | Montecito, CA - Twining
Client County of Santa Barbara Contact Brent Clavin, PE, QSD, QSP – Civil Engineer
123 East Anapamu Street, Suite 1
Santa Barbara, CA 93101
(805) 568-3003
bclavin@cosbpw.net
Project Description
Destroyed because of debris flow in 2018, East Mountain Drive Bridge
is currently being replaced in Montecito. The new bridge construction
will include caisson foundation installations and new abutments and
wingwalls construction.
Scope of Services
Twining provided quality assurance material testing. Their involvement
included providing compaction testing of the wall backfills, concrete
sampling, and laboratory testing of selected materials per Caltrans
LAPM and Caltrans Construction Manaual.
Dates 12/2020 – 01/2021 Cost $500,000
Staff Twining Staff: Jeff Tawakoli, PE, Project Manager
Lockheed Martin Aeronautics Palmdale Photovoltaic Solar Expansion Project | Los Angeles County, CA - HES
Client Burns & McDonnell Contact Tara Krahe
617 W. 7th Street, Suite 202
Los Angeles, CA, 90017
tkrahe@burnsmcd.com
Project Description
The project consists of construction of 24 MW Palmdale Photovoltaic
Solar Expansion Project located at Lockheed Martin’s Plant 10 in
Palmdale, California. The project and its related components were
constructed within a 140-acre project site and would tie into the
existing Southern California Edison grid associated with the Plant 10
complex to the north of the site.
Scope of Services
HES performed construction monitoring on the project site. HES
biologists monitored the removal, relocation, and avoidance of
western Joshua trees (Yucca brevifolia), ensuring the project
remained in compliance with the project avoidance and protection
plan and provided guidance when adjustments to the original plan were needed. HES had a biological monitor present on site to
observe all construction activities that involved clearing and grubbing to ensure no take occurred on any state and federal listed
plant and animal species. Once all clearing and grubbing activities were complete HES biologists performed biweekly site visits to
ensure all trees protected-in-place had not been impacted by project activities and the avoidance fencing remained intact during
the duration of construction. HES provided monthly reports with biologists daily observations.
Dates 9/2021 – 01/2022 Cost $4,983
Staff HES Staff: Juan J. Hernandez, Principal Biologist; Shawn Gatchel-Hernandez, Principal Regulatory Specialist; Hallie
Hernandez, Associate Biologist; Elizabeth Gonzalez, Associate Biologist.
Page 18 120
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Burrtec Facility in Yucca Valley | San Bernardino County, CA - HES
Client Burrtec Facility in Yucca Valley Contact Gary Koontz
Burrtec Waste & Recycling Services
41575 Eclectic Street
Palm Desert, CA, 92260
gkoontz@burrtec.com
Project Description
The project consisted of the relocation of the existing Burrtec Waste
and Recycling facility and all operations. The project included
development of a truck terminal for Burrtec Waste and Recycling
Services’ collection fleet and an approximately 16,200 square foot solid
waste transfer station. Additional improvements included landscape
frontages on Indio Avenue and Sunnyslope Drive, a maintenance shop,
a fueling station, an operations facility, in-ground truck scales, a
stormwater detention basin, and associate parking.
Scope of Services
HES performed preconstruction nesting bird surveys that included the
entire Yucca Valley Burrtec Waste Transfer Facility project site and a 250-foot buffer around the perimeter of the site. Biologists
performed walking transects up to 100 feet apart for 100 percent coverage of the site. HES biologists informed the project manager
of active nests and implemented a 250-foot buffer around the nests until the birds left the nest. Reports updating the client of the
status of the nests were submitted until it was determined the nests were inactive. HES had a biological monitor present on site to
observe all construction activities that involved clearing and grubbing to ensure no take occurred on any state and federal listed
plant and animal species.
Dates 7/2020 – 08/2020 Cost $1.5M
Staff HES Staff: Juan J. Hernandez, Principal Biologist; Shawn Gatchel-Hernandez, Principal Regulatory Specialist; Hallie
Hernandez, Associate Biologist; Elizabeth Gonzalez, Associate Biologist; Cruz Hernandez, Biological Aide
Ventura Boulevard Sidewalk Improvements, Studio City, CA - WES
Client City of Los Angeles Contact Abdullah Sadozai – Engineering Associate
City of L.A. Dept. of Public Works
1149 S. Broadway
Los Angeles, CA 90015
(213) 485-4652
abdullah.sadozai@lacity.org
Project Description
Wagner Engineering & Survey, Inc. (WES) performed Civil Engineering
Design services for 5 locations of sidewalk improvements for current
ADA compliance along Ventura Boulevard. One location at Ventura
Boulevard and Fairway Avenue included street improvements and
retaining wall design all to B-Permit standards. The project involved
pavement designs, sidewalk designs, curb & gutter designs and
coordination and meetings with City staff.
Scope of Services
WES performed topographic surveys and construction staking.
Dates 06/2017 – 03/2018 Cost $100K
Staff WES Staff
Page 19 121
SECTION 3: STATEMENT OF QULIFICATIONS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
6th Street Viaduct Replacement Project, Los Angeles, CA - WES
Client City of Los Angeles Contact Choice Sterling Skanska USA
City of L.A. Dept. of Public Works
1149 S. Broadway
Los Angeles, CA 90015
(323) 852-4233
Choice.sterling@skanska.com
Project Description
The Sixth Street Viaduct, also known as the Sixth Street Bridge, is located
between Boyle Heights and the Downtown Art District in Los Angeles,
California, US. The viaduct will be demolished and replaced with a new
bridge under the Sixth Street Viaduct replacement project.
The bridge links the Los Angeles River, Metrolink tracks, Union Pacific
Railroad tracks, Santa Ana Freeway, Golden State Freeway, and other
local streets. It is maintained by the City of Los Angeles and the California
Department of Transportation (Caltrans).
Scope of Services
Wagner Engineering & Survey, Inc. (WES) provided services on multiple
contracts for this project. From 2010-2012 WES performed services to provide preliminary title reports. In July of 2013 WES
performed land surveying and mapping. In 2015 WES started working on the construction phase of the project. We are currently
performing construction survey services. The surveys are challenging due to height and safety precautions.
Dates 2015 - Ongoing Cost $588M
Staff WES Staff
Metro Gold Line I-210 Barrier Replacement Project, Los Angeles, CA - WES
Client Metro Contact Andy Nowak – Jacobs Engineering
1 Gateway Plaza
Los Angeles, CA 90012
(949) 224-7957
Andy.nowak@jacobs.com
Project Description
Project included cross-section surveys of the HOV lanes, No. 1 lanes and
6.2-mile length on both sides of the median at 50-foot intervals. 13 freeway
bridge/street under-passes were surveyed. Topographic surveys were
performed in the underpass areas. The cross-section surveys were added
to the base maps. All surveys conformed to the Caltrans Survey Manual
and work was performed within the Caltrans Safety Manual specifications.
All aerial surveys were delivered with Caltrans photogrammetry oversight
through District 7 and the State photogrammetry division.
Scope of Services
Wagner Engineering & Survey, Inc (WES) is performing multiple tasks on this project. A Horizontal and Vertical Control Network
was established. The existing Caltrans control was densified to produce secondary mainline control at 4,000-foot intervals.
Approximately 20 secondary control stations along the project corridor were set. For aerial control and mapping, 19 aerial targets
were set, and 32 color exposures produced at 1″ = 300' scale were used to produce aerial mapping of 1″=50' with 2' contour levels.
The final color ortho-photography was produced at .25’-pixel resolution. The mapped area was all freeway Right-of-Way area.
Dates 2018 - 2019 Cost $425M
Staff WES Staff
Page 20 122
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
ORGANIZATIONAL CHART
FCG has assembled an in-house team of experienced construction management and inspection professionals that will successfully
deliver this project on time and within budget. The organizational chart below shows our project team and the lines of communication
between team members.
Backup Electrical/Construction Inspectors (as needed)
Mamon Subeh – Civil Inspector Anthony Moussa – Electrical Inspector Iman Sabiri, PE – Office Engineer
Tyler Haddadin – Civil Inspector David Molino – Electrical Inspector Majed Moussa – Office Engineer
Mark Korando – Civil Inspector Timmy To – Electrical Inspector Samar Alfakhouri – Office Engineer
Office Engineer
Jasmine Fakhouri FCG
Material Testing
Twining Laboratory Staff
The key personnel proposed for this project will be available to the extent proposed for the duration of the required services. No person
designated as “key” will be removed or replaced without the prior written concurrence of the City of Moorpark.
City of Moorpark
Daniel Kim, PE
City Engineer/Public Works Director
Project Manager/Resident Engineer
A.B. Fakhouri, PE, QSD FCG
Structures Representative
Dragan Buha, PE WSP
Construction Inspector Scheduler
Don Lewis - Civil FCG
Leon Fuentes - Electrical FCG Chris Okerstrom WSP
Surveying
Wagner Engineering Staff
Environmental
Hernandez Environmental Staff
Page 21 123
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
TEAM RESUMES
A.B. FAKHOURI, PE, QSP
Project Manager
Mr. Fakhouri is a Registered Professional Engineer licensed in the State of California, and
a former Resident Engineer of Caltrans District 7, Los Angeles, CA. He has worked on
various interchange projects of similar nature that included bridge demolition and
widening, interchange widening, relocation of utilities, electrical, 55-hour closures, and
more. As a Project Manager, duties included, but were not limited to, interfacing with
clients, managing and training personnel, managing subconsultants, performing
construction management, and construction inspection. As a Resident Engineer, duties
included identifying problems and recommending solutions, ensuring compliance with
safety requirements and contract provisions, preparing calculations, reports, and
correspondence, reviewing submittals and RFI’s, change orders, conducting meetings,
coordination, overseeing inspection, ensuring compliance to safety, SWPPP and labor
laws. Mr. Fakhouri has the ability to satisfy the client with high-performance, high-
quality staff at a moment’s notice.
RELEVANT EXPERIENCE
Telegraph Road Traffic Safety Enhancements Project – City of Downey, CA
Project Manager|Resident Engineer: This Federally Funded project consisted of
various improvements on Telegraph Road. Duties: Included construction management
and inspection of various work items; overseeing field interviews and conducting field reviews of certified payroll; office engineering;
conducting meetings; reviewing submittals and Requests for Information (RFIs), Construction Change Orders (CCOs), daily diaries
and quantities, and daily photos; coordinating materials testing and lane closures; reviewing contractor as-builts. Duration: 05/2021 –
02/2022. Cost: $7 Million.
Stewart & Gray Road and Imperial Highway Traffic Signal Upgrades and Enhancements Projects – City of Downey, CA
Project Manager|Resident Engineer: These Federally Funded projects consisted of various improvements on Stewart & Gray and
Imperial. Duties: Included construction management and inspection of various work items; overseeing field interviews and conducting
field reviews of certified payroll; office engineering; conducting meetings; reviewing submittals and Requests for Information (RFIs),
Construction Change Orders (CCOs), daily diaries and quantities, and daily photos; coordinating materials testing and lane closures;
reviewing contractor as-builts. Duration: 08/2020 – 11/2021. Cost: $4 Million.
Rosecrans Avenue and San Antonio Drive Traffic Signal Improvements Projects – City of Norwalk, CA
Project Manager|Resident Engineer: These Federally Funded project consisted of various improvements on Telegraph Road.
Duties: Included construction management and inspection of various work items; overseeing field interviews and conducting field
reviews of certified payroll; office engineering; conducting meetings; reviewing submittals and Requests for Information (RFIs),
Construction Change Orders (CCOs), daily diaries and quantities, and daily photos; coordinating materials testing and lane closures;
reviewing contractor as-builts. Duration: 03/2021 – 01/2022. Cost: $2.5 Million.
I-605/Live Oak Avenue Ramp Widening & Improvements Project – City of Irwindale, CA
Project Manager|Resident Engineer: This Federally Funded project consisted of a ramp widening and various improvements within
Caltrans and City right-of-way. Duties: Included construction management and inspection of various work items; overseeing field
interviews and conducting field reviews of certified payroll; office engineering; conducting meetings; reviewing submittals and Requests
for Information (RFIs), Construction Change Orders (CCOs), daily diaries and quantities, and daily photos; coordinating materials
testing and lane closures; reviewing contractor as-builts. Duration: 11/2018 – 07/2019. Cost: $2 Million.
AC Overlay on Gabbert Rd, Poindexter Avenue, Spring Road and Princeton Avenue - City of Moorpark, Moorpark, CA
Project Manager|Resident Engineer: This Federally funded project consisted of various improvements on Gabbert Road. Duties:
Included construction management and inspection of various work items; overseeing field interviews and conducting field reviews of
certified payroll; office engineering; conducting meetings; reviewing submittals and Requests for Information (RFIs), Construction
Change Orders (CCOs), daily diaries and quantities, and daily photos; coordinating materials testing and lane closures; reviewing
contractor as-builts. Duration: 11/2017 – 02/2018. Cost: $500,000.
Education and Licensing
Education
M.S. Civil Engineering, CSULB-
1998.
B.S. Civil Engineering, CSULB-
1996.
Years With Current Firm
11 Years.
Licensing
PE License # C60844.
Page 22 124
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
DONALD LEWIS
Construction Inspector
Mr. Lewis has over 27 years of experience in the heavy civil construction industry. He has
been involved as a Project Engineer, Quality Control Manager, Superintendent and Project
Manager. He has worked on freeways, highways, railroads, underground utilities, pump
stations and bridges. Experience includes inspection of underground sewer, water and
drainage lines. Inspection in excavations, backfill and grading. Inspection of bridge
construction from pile driving, footings, bents, abutments, soffits and deck. He has most
recently been involved in concrete paving from set up to hand and machine paving. Others
areas of inspection and quality control include curbs, ramps, sidewalks and driveways. Mr.
Lewis has extensive experience with Caltrans, flood control districts and various City and
County projects.
RELEVANT EXPERIENCE
Whittier Greenway Trail Extension Gap Closure Project, City of Whittier, CA
Construction Inspector: Project consisted of developing a 2.7-mile-long easement into a
15 ft wide walking trail along Union Pacific Railroad owned property in the City of Whittier,
CA. This project also includes the Lambert Road Traffic Signal Synchronization Project.
Work also included assisting the Resident Engineer with filing, public relations, produce
daily diaries and photos, monitor contractor progress, and produce pay estimates, conduct
employee interviews, review Change Orders, and correspondences.
SR-210 Widening and Rehabilitation Project, Caltrans District 7, Sylmar, CA
Construction Inspector: Project consists of 10 miles of concrete pavement rehab and replacement. Work includes, but not limited to,
traffic control, mass excavation, median barrier removal and replacement, electrical, drainage, overhead signage, grading, asphalt and
concrete pavement and striping. Duties include field inspection of all work performed, SWPPP oversite, producing daily reports,
including photos. Inspection of traffic control and equipment. Tracking and recording daily quantities. Safety oversight and
implementation, including production of the Job Hazard Analysis. Coordination with testing firm for batched concrete and aggregates.
LAX / APM, Los Angeles World Airports, Los Angeles, CA
Construction Inspector: Project consists of a 3-mile elevated light rail from CONRAC (Consolidated Rental Car Facility) to Tom
Bradley International Terminal. Duties included but were not limited to the following: Inspection of and coordination with QA personnel
on work being performed. Coordinate material orders, deliveries, and placement. Assist with 60% and 90% plan reviews for accuracy
and constructability. Met with LAWA personnel on upcoming work and conducted meetings on critical topics in relation to road closures
and possible impacts to travelers. Inspected pothole activities and coordinated existing conditions with the designers. Coordinated and
conducted meetings between the demolition contractor and LAWA personnel.
Raymond Bridge Grade Separation, Fullerton, CA
Construction Inspector: Project consisted of the following: Construction of two bridges that allowed Raymond Ave to pass under the
BNSF railway and Valencia Blvd. Utility relocations including water, storm drain, gas, sewer and fiber. Inspection of soil excavation
and logging and documentation of hazardous material. Organized manifests and created logs for the City of Fullerton. Coordinated the
construction of the bridge structures and material testing. Attended weekly progress meetings. Organized extra work documentation
and discussed with Agency personnel. Inspected jobsite for SWPPP BMP’s and relayed information to the QSP. Relayed progress
with local neighbors and businesses and addressed any issues. Conducted JHA paperwork.
I-5 Camp Pendleton Pavement Rehab and Replacement, CA
Construction Inspector: Project consisted of twelve miles of two-lane complete replacement in both directions, including individual
slab replacements. Served as aggregate quality control manager at the batch plant. Built and maintained daily production logs of
concrete paving. Insured crews were performing work of high quality and in a safe manner. Project also included shoulder widening
with new base and asphalt structural sections. Verified excavation limits were accurate as area was in Coastal Commission
boundaries. Produced daily diaries of work performed and logged daily photos.
Education and Licensing
Education
BS Criminal Justice, CSULB, CA-
2000.
Santa Ana College, Various
Engineering Classes-2020.
Years With Current Firm
1 Years.
Licensing
CTM 125; Defensive Driving and
Cal/OSHA – 10 Hour Safety
Certified.
Page 23 125
SECTION 4: ORGANIZATION AND STAFFING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
LEON FUENTES
Construction Inspector - Electrical
Mr. Fuentes has over 25 years of construction experience which includes Construction
and Electrical Inspection. He has worked for construction contractors and private
consulting firms on a large variety of heavy civil, public works, and development projects.
Duties also included field inspection, producing daily reports and quantities calculations,
reviewing and monitoring schedule of work, enforcing compliance with plans and
specifications, reviewing shop drawings, reviewing and negotiating change orders,
reviewing submittals and RFI’s, enforcing safety compliance, performing walkthrough and
preparing final punch list, preparing and reviewing as-built plans, and assisting with project
acceptance.
RELEVANT EXPERIENCE
Dam Reconstruction and Improvement Project, County of LA, CA
Construction Inspector: Project consists of Removing 1.7 million Cubic yards of
sediment from the reservoir and establish a permanent stormwater maintenance area that
allows for the creation of 70 acres of enhanced habitat and recreational opportunities for
local communities. Duties included inspection of construction work, coordinating with all field staff, producing daily dairies and
quantities, assist the RE with office work and coordination in the field per Caltrans Standards.
Various City Maintenance of Electrical Facilities, Crosstown Electrical, Inc., Los Angeles, CA
Construction Inspector: In charge of various crews performing various work activities as part of the maintenance of electrical facilities
for various cities in Los Angeles County such as Downey, Norwalk, Santa Fe Springs, and more. Duties included inspection and repairs
to various facilities, producing daily reports, producing daily quantities, producing look-ahead schedules, producing progress reports,
and maintaining record of all materials and repairs.
Foster Road Side Panel Improvements Project, City of Norwalk, CA
Construction Inspector: This federally funded project will provide a safe walking and bike route to school between Studebaker Road
and Pioneer Boulevard. Duties included inspection of traffic control, striping, concrete removal and paving, slab replacement, shoulder
backing, shoulder paving, drainage, clean-outs, safety, and SWPPP.
AC Overlay Project, City of Moorpark, CA
Construction Inspector: Project consisted of grind and overlay asphalt paving, curb ramps, and electrical loops within the City of
Moorpark. Duties included inspection of Traffic Control, Striping, HMA removal and paving, JPCP removal and paving, shoulder paving,
drainage, barriers, clean-outs, ADL removals, Safety, and SWPPP. Duties also included inspection of all electrical work.
I-15 / Base Line Interchange Reconstruction Project, Caltrans District 8, City of Fontana, CA
Construction Inspector: Project consisted of expanding and reconfiguring the I-15 at Base Line Road Interchange and the intersection
of Base Line Road and East Avenue to improve safety and relieve traffic congestion. Duties included monitoring and construction of
electrical work, temporary and permanent lighting, installation of vaults, traffic signals, installation of sign and street lighting, installation
of traffic and service cabinets, installation of permanent fiber optic lines, ramp metering and traffic monitoring systems.
Education and Licensing
Education
High School Diploma
IBEW Apprentice Program
Page 24 126
SECTION 4: ORGANIZATION AND STAFFING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
JASMINE FAKHOURI
Office Engineer
Ms. Fakhouri has more than 2 years of experience as an Office Engineer on public works
projects for public works agencies and construction contractors. Her responsibilities
include, but are not limited to, reviewing certified payroll, employee interviews, maintaining
accurate and complete project records and files; maintaining contract records; assisting
the Project Manager with change orders, submittals, and RFIs; assisting in preparing
quantity calculations and cost estimates; coordinating with various agencies; reviewing
and preparing correspondence; preparing and updating spreadsheets; converting working
files to PDF; and preparing various reports. Ms. Fakhouri has extensive experience
working on federally funded projects that utilize FHWA and Local Assistance Procedures
Manual requirements for documentation and filing, verifying certified payroll of contractors,
and producing documentation and reports accordingly.
RELEVANT EXPERIENCE
Imperial Highway Traffic Signal Upgrades and safety Enhancement Project, City of
Downey, CA
Office Engineer/Labor Compliance: This Federally Funded Project consists of construction of a fiber optic traffic signal
communication system on Stewart & Gray Road. Duties included, but were not limited to, verifying the contractor’s certified payroll,
preparing and maintaining project files, performing document control, creating and updating correspondence log, preparing and
updating submittal logs, maintaining logs, preparing progress reports, assisting the Resident Engineer with reviewing CCO and pay
estimate requests, and collecting inspector reports and quantities.
Stewart & Gray Road Fiber-Optic Traffic Signal Project, City of Downey, CA
Office Engineer/Labor Compliance: This Federally Funded Project consists of construction of a fiber optic traffic signal
communication system on Stewart & Gray Road; Duties included, but were not limited to, verifying the contractor’s certified payroll,
preparing and maintaining project files; performing document control; creating and updating correspondence logs, preparing and
updating submittal logs; maintaining logs; preparing progress reports; assisting the Resident Engineer with reviewing CCO and pay
estimate requests; and collecting inspector reports and quantities.
Telegraph Road Traffic Throughput & Safety Enhancement Project, City of Downey, CA
Office Engineer/Labor Compliance: This Federally Funded Project consisted of construction of raised median islands with
landscaping and irrigation, reconstruction of the existing asphalt pavement, traffic signal modifications and signage and striping.
Duties included, but were not limited to, verifying the contractor’s certified payroll, preparing and maintaining project files, performing
document control; creating and updating correspondence logs, preparing and updating submittal logs, maintaining logs, preparing
progress reports, assisting the Resident Engineer with reviewing CCO and pay estimate request, and collecting inspector reports and
quantities.
Irwindale Park Improvements Project, Phase III, City of Irwindale, CA
Office Engineer/Labor Compliance: This project consists of demolition of existing concrete walks, planters, existing tennis courts,
and retaining walls. Work also included electrical, architectural / structural, Irrigation, landscape, and permit work. Duties included,
but were not limited to, verifying the contractor’s certified payroll, conducting employee interviews, preparing and maintaining project
files; performing document control; creating and updating correspondence logs; preparing and updating submittal logs; maintaining
submittals logs, RFI logs, Contractor Change Order logs, and testing logs; preparing progress reports; assisting the Resident Engineer
with reviewing CCO and pay estimate requests; and collecting inspector reports and quantities.
Burbank Channel Bikeway Project, City of Burbank, CA
Office Engineer/Labor Compliance: This Federally Funded project consists of 0.79-mile bike and pedestrian path that is being
constructed adjacent to the Burbank Western Channel. Duties included, but were not limited to, verifying the contractor’s certified
payroll, conducting employee interviews, preparing and maintaining project files; performing document control; creating and updating
correspondence logs; preparing and updating submittal logs; maintaining submittals logs, RFI logs, Contractor Change Order logs,
and testing logs; preparing progress reports; assisting the Resident Engineer with reviewing CCO and pay estimate requests; and
collecting inspector reports and quantities.
Education and Licensing
Education
B.S. Civil Engineering-2020.
Licensing
Engineer in Training in progress.
Page 25 127
SECTION 4: ORGANIZATION AND STAFFING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
DRAGAN BUHA, PE, QSD
Project Manager/Structures Representative
Dragan has over 30 years of experience in civil engineering, construction, and project
management that includes an emphasis on civil/structural engineering infrastructure
projects. He has over 14 years of experience working with the California Department of
Transportation (Caltrans) Structure Construction (District 59), District 7 (Los Angeles)
Project Management, and District 7 (D-7) Construction. Dragan’s experience includes
work on new or the modification of existing interchanges, including construction of new
roads, drainage facilities, bridges, bridge retrofits, Caltrans maintenance facilities, and
planning and design oversight for D-7 Caltrans Transportation Management Center (TMC)
in Glendale. His experience also includes managing the construction for local agencies’
sponsored improvement projects on Caltrans right-of-way and within city and railroad
limits, as well as managing on-call construction inspection contracts for Caltrans and/or
local agencies. Dragan has performed constructability reviews and value engineering for
various outside clients including San Bernardino Association of Governments (SANBAG),
Orange County Transportation Authority (OCTA), and local cities. Current responsibilities
include leading and supporting transportation pursuits in Southern California, managing
several on-going on-call contracts, supervising assigned staff, and being a resource to
other functional units.
RELEVANT EXPERIENCE
On Call Construction Engineering and Inspection - Three Contracts - 07A3910,
07A4704 & 07A4783, Caltrans D-7, CA
Project Manager: Dragan took over as Consultant Contract Manager in the East/West
area (07A3910 contract) of Los Angeles County. Provided office engineers and roadway
and electrical inspectors and schedulers to Caltrans on a task order (T.O.), as-needed basis. The contract included completion of a
total of 23 T.O.s, totaling 20+ people deployed. Dragan’s responsibilities included selecting staff resumes, drafting T.O. budgets,
tracking expenses, providing monthly invoices, managing subconsultants, preparing monthly projections, and processing T.O.
amendments. He also implemented improvements to the invoice procedure and after being six months behind in invoicing, client was
able to catch up within one year. This contract led to winning and managing two more contracts with D-7 between 2019 and 2021.
Ventura County On-Call, (Contract 07A4378), Caltrans D-7, CA
Project Manager: Dragan worked as the Subconsultant Contract Manager.
On Call Construction Engineering and Inspection in San Bernardino and Riverside Counties, (Contract 08A3022), Caltrans
District 8, CA
Project Manager: Dragan took over as Consultant Contract Manager for this project which is scheduled to complete at the end of
2021 with a total budget of $15.1M. Currently there are 27 T.O.s on this contract with multiple amendments.
I-5 Widening and Construction Support Management Project, OCTA, CA
Project Manager: Dragan was the Project Manager responsible for CM support on the subcontract with HDR.
Lost Hills, Calabasas Interchange Improvement Project, City of Calabasas, CA
Resident Engineer/Structures Rep.: Dragan served as Resident Engineer, Structure Representative, and Assistant Project
Manager with responsibility to oversee the design firm preparing plans, specifications, and estimates (PS&E) under Caltrans D-7
oversight. He was also responsible for CM and contract administration. The project is locally funded by Metro Measure R.
SR-126/Commerce Center Drive Interchange Project, Los Angeles County, CA
Structures Rep: to provide CM services to augment County staff in delivering this project. Dragan was responsible for overseeing
all structure work on the project consisting of a new bridge and several MSE, retaining, and sound walls.
Education and Licensing
Education
M.S., Civil Engineering, Vanderbilt
University – 1990
B.S., Civil Engineering, Belgrade
University – 1985
Years of Experience
30 Years.
Licensing
Professional Civil Engineer: CA,
51368
Qualified Storm Water Pollution
Prevention Plan
Developer/Practitioner
(QSD/QSP)
Page 26 128
SECTION 4: ORGANIZATION AND STAFFING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
CHRIS OKERSTROM
Construction Scheduler
Chris has professional experience in the construction industry, with a particular focus on
project management, project controls, project scheduling, claims mitigation and resolution,
and cost estimating and monitoring systems. For a broad range of public agency
construction projects, he has provided project schedule analysis, efficiency analysis, and
overall construction management (CM) for rail, bridge, highway, airport, pier, waterway,
and manufacturing/energy projects. Chris has been assigned as project engineer/manager
on several complex public works programs and has successfully supported owners and
operators, as well as architecture, engineering, and construction firms.
RELEVANT EXPERIENCE
I-5 Segment 3 CM, Orange County Transportation Authority (OCTA), Orange County,
CA
Project Scheduler: Chris serves as project scheduler responsible for review and analysis
of the contractor’s monthly schedule submittals. WSP, as a subconsultant, is providing CM
services to OCTA on this project to widen I-5 from Alicia Parkway to El Toro Road.
Design and Program Management Services, Orange County Toll Roads Transportation, Orange County, CA
Project Scheduler: Chris serves as project scheduler responsible for review and analysis of the contractor’s monthly schedule
submittals. WSP, as managing partner of this joint venture, is providing program management and engineering design services for
Orange County’s entire 51-mile toll-road program.
Gerald Desmond Bridge Replacement, Port of Long Beach, Long Beach, CA
Project Scheduler: These Federally Funded Chris serves as the project scheduler for this project’s CM team. His responsibilities
include review of the contractor’s schedule, drafting correspondence, and analysis of claim impacts. Also, for three years (09/2012—
03/2015), Chris served as the project controls manager for the project CM team. WSP is providing program management for the
replacement of the Gerald Desmond Bridge connecting Long Beach to Terminal Island. The replacement will be California’s first
cable-stayed vehicular bridge and the second tallest cable-stayed bridge in the U.S. The project scope includes construction
management, utilities coordination, specialty materials testing, submittals management, surveying, community outreach, project
controls, document control, cost estimating and scheduling, funding and grants support, and traffic engineering. The project also
includes a multi-million-dollar design-build contract for the bridge’s replacement. The 8,800-foot-long bridge includes a 2,000-foot
main cable stayed span with a 200-foot vertical clearance, 515-foot-tall towers, drilled shafts, cast-in-place post-tensioned decks, and
approach superstructures constructed using both moveable scaffolding systems and traditional falsework.
California High-Speed Rail Construction Package 2-3, California High-Speed Rail Authority, Central Valley, CA
Deputy Oversight Manager: Chris served as deputy oversight manager on this project, responsible for the construction management
team, including oversight of right-of-way, engineering, third-party utilities, CM, project controls, and document control staff on a 65-
mile segment of the high-speed rail alignment in the Central Valley of California.
Positive Train Control Design-Build Global Positioning System Based Software Project, Metrolink, Los Angeles, CA
Project Controls Manager: Project Controls Manager. Chris served as project controls manager on this project, responsible for the
project CM team.
Education and Licensing
Years of Experience
30 Years.
Page 27 129
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
STEPHANIE A. WAGNER, PE, PLS, LEED®AP, FACEC
Principal Surveyor/Engineer
Ms. Wagner is a well-known leader in the civil engineering and land surveying professions.
She is the dedicated founder of her firm and has managed civil design and construction
surveys for LAUSD, CALTRANS, Metro, Alameda Corridor East, City and County of Los
Angeles and numerous other municipalities. She has a diverse project and task
management background with over 40 years of experience. She has led a civil design
team for 30 years with Wagner Engineering & Survey, Inc. (WES) and stresses sustainable
design for all projects. Her knowledge in mapping and field survey formats, boundary
establishments, datum compatibility, design and construction methods is an invaluable
asset.
RELEVANT EXPERIENCE
City of Los Angeles 6th Street Viaduct Replacement Project, LA, CA
Principal Surveyor/Engineer: Ms. Wagner managed the survey services on multiple
contracts for this project. From 2010-2012 the team performed services to provide
preliminary title reports, in 2013 the team performed survey and mapping services and in
2015 the team started work on the construction phase of the project. Ms. Wagner and the
WES survey team are currently performing construction survey services which are
challenging due to the height and safety precautions.
Metro Orange Line Northern Canoga Extension EIR/PE, San Fernando Valley, CA
Principal Surveyor/Engineer: Ms. Wagner managed the survey and right-of-way portion
of the project, including a 4-mile bike path. She managed the photogrammetric field
surveying, aerial mapping and right-of-way engineering for the 4-mile northern extension
of the existing Orange Line from the Canoga Station to the Chatsworth Metrolink Station.
The mapping & digital terrain models delivered to Metro, certified to exceed National Mapping Accuracy Standards. Ms. Wagner
supervised the 10 topographic station surveys along the route and the legal descriptions and plats of the design-identified acquisition
areas.
Metro Mid-City Exposition Light Rail Transit Project Segment 1, LA, CA
Principal Surveyor/Engineer: Ms. Wagner oversaw design surveys and construction staking of this design-build light rail project from
the 7th Street/Metro Center Station west to Venice Boulevard in Culver City. She oversaw accurate construction staking of 8.6 miles
of the light rail project. Site-specific surveys at 5 station areas were delivered.
Orange County Transportation Authority (OCTA) Program Management Support, Widening of SR57, Orange County, CA
Principal Surveyor/Engineer: Ms. Wagner oversaw the team as Task Manager. The team participated on 3 task orders for this project
including review of misalignments reported between the existing and proposed substructures in 5 bridges, Bastanchury, Rolling Hills,
Associated Road, Birch and Brea. Detailed reports were prepared and delivered. The WES survey team has analyzed 3 grade
separations including Orangethorpe and Lakeview.
Alameda Corridor East, San Gabriel Trench, Construction Management Project, San Gabriel, CA
Principal Surveyor/Engineer: Alameda Corridor East (ACE) is now the San Gabriel Valley Council of Governments (SGVCOG). Ms.
Wagner supervised the field verification services, right-of-way and boundary staking of this ongoing construction management project.
The San Gabriel Trench will result in the lowering of a 1.4-mile section of the Union Pacific Railroad through the City of San Gabriel
with bridges constructed at Ramona Street, Mission Road, Del Mar Avenue and San Gabriel Boulevard. The Southern California
Chapter of the Construction Management Association of America has recognized SGVCOG with a Project Achievement Award for
this project.
Education and Licensing
Education
BS Civil Engineering, Nicholls
State University, LA – 1974
Years of Experience
30 Years.
Licensing
1990 Registered Civil Engineer CA
#46979, 1990 & LA #20270, 1987
Licensed Land Surveyor CA
#5752, 1986 CA 1989 Lifetime
Instructor Credential, Engineering,
Community College System
2004 LEED® Accredited
Professional
Page 28 130
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
KIERAN DOHERTY, PLS
PLS Party Chief
Mr. Doherty is an experienced land surveyor of 32 years. He is adept at construction
management, construction staking, topographic, and control and boundary surveys. He
has performed GPS control surveys for aerial mapping and centerline establishments. He
is knowledgeable in the use of various field surveying, coordinate geometry and CADD
software. His knowledge of TDS Star Net least square and Leica GPS adjustment software
is invaluable in the production of accurate and cost effective deliverables. Mr. Doherty has
performed surveys for large land development projects as well as over 100 miles of
freeways and rail corridors in Southern California.
RELEVANT EXPERIENCE
Alameda Corridor Transportation Authority, North End, Los Angeles, CA
Party Chief: as the Certified Party Chief and as part of the construction management
team, Mr. Doherty performed surveying to ensure accuracy on reinforced concrete and
steel bridges, track-work, and infrastructure.
Alameda Corridor East, San Gabriel Trench, Construction Management Project, San
Gabriel Valley, CA
Party Chief: Alameda Corridor East (ACE) is now the San Gabriel Valley Council of
Governments (SGVCOG). Mr. Doherty, Certified Party Chief, is providing survey services
including boundary staking for this ongoing construction management project. The project
will result in the lowering of a 1.4-mile section of the Union Pacific Railroad through the
City of San Gabriel with bridged construction at Ramona Street, Mission Road, Del Mar
Avenue and San Gabriel Boulevard. The Southern California Chapter of the Construction
Management Association of America has recognized SGVCOG with a Project Achievement Award for this project.
Metro Red Line, Segments II/III, Los Angeles, CA
Party Chief: Mr. Doherty’s duties included that of Certified Party Chief and Office Surveyor for 10 miles of subway construction. For
Segment II, Mr. Doherty performed Construction Management Quality Control surveys for a 2-year period on the tunnel and station
construction, settlement monitoring, and track work least squares adjustments of horizontal control. For Segment III, Mr. Doherty
successfully accomplished all construction staking for the new track work.
Metro Mid-City/Exposition Light Rail Transit Design/Build Project, Los Angeles, CA
Party Chief: Mr. Doherty was the Chief of Parties for the Exposition Project Phase I, in charge of office calculations and QA/QC of the
survey construction package. His duties included coordination with the designer, contractor and other sub-consultants to ensure
accurate construction staking of 8 miles of a new light rail project, retaining walls, bridge structures and utility relocations.
Metro Crenshaw-LAX Light Rail Transit Corridor Project Environmental, ACE, Preliminary Engineering, Design Bid Support
and Design Services during Construction Phases of this Project, Los Angeles, CA
Party Chief: Under the Advanced Conceptual Engineering Phase, the GPS control network surveys, topographic surveys, and
centerline surveys were performed under Mr. Doherty’s supervision for this 8-mile corridor for a new light rail system. The GPS survey
network was used to control over 15 miles of study area for the 1” = 40’ design-level aerial mapping and color ortho-photography. The
center line survey was used in the establishment of the existing right of way corridor including street and rail road rights of way.
Education and Licensing
Education
BS in Civil Engineering,
University College
Cork, Ireland
AS in Surveying, Rancho
Santiago College
Rancho Santiago, CA
Years of Experience
20 Years.
Licensing
1992 Licensed Land Surveyor CA
#6768
AutoCAD Certification
GPS Post-Processing Certification
Page 29 131
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
JEFF TAWAKOLI, PE
Project Manager
Jeff Tawakoli, PE, is a professional engineer with over 33 years of experience in geotechnical
and construction materials engineering, Jeff’s areas of expertise include subsurface
investigation, engineering analysis, preparation of soils reports, building and roadway
inspection program management and engineering, project management, and geotechnical
engineer for bridges, commercial, industrial, military facilities, roadways, and mid-rise
buildings.
RELEVANT EXPERIENCE
East Mountain Drive Bridge, County of Santa Barbara, CA
Project Manager: Previously destroyed as a result of debris flow in 2018, East Mountain
Drive Bridge is currently being replaced in Montecito. The new bridge construction will include
caisson foundation installations and new abutments and wingwalls construction. Twining is
providing quality assurance material testing. Jeff is serving as the project manager,
overseeing the delivery all of our services, dispatching inspectors, reviewing all reports, and
acting as the single point of contact for the project team.
County of Ventura, Yerba Buena Road South Resurfacing: Santa Monica, CA.
Project Manager: The 2020 project consists of providing quality assurance during pavement
resurfacing of Yerba Buena Road south per Specification RD19-03 from State Route 1 to
Post Mile 3.28. The project scope included ARAM, ARHM placements, pavement widening,
PMB placement, miscellaneous paving, and construction of new catch basins, and AC berms.
Twining provided batch plant and field coverage for compaction testing of soils, base, and
asphalt.
City of Santa Barbara, Watermain Replacement Project FY19 A & B: City of Santa Barbara, CA.
Project Manager: The FY19A project was completed in April of 2020 and featured the replacement of aging water mains in various
locations of the City. The focus for FY19A was the beach area and Funk Zone, including a new water main on Cabrillo Boulevard from
State Street to Bath Street. Additional locations were in the San Roque neighborhood, and a segment of piping on Las Positas Road
north of U.S. Highway 101. The FY19B project was completed in June of 2020 and featured the replacement of approximately 2.9
miles of water main pipes in various parts of the City including North Milpas Street, East Haley Street, and West Cabrillo Boulevard.
Twining provided soils compaction material testing and inspection services as part of our on- call contract with the City. Contract
administration support to the Resident Engineer, inspection of 72+ lane miles of JPCP and /or JPCP-RSC, HMA, traffic control,
drainage related items, correspondence letter to the contractor, photo documentation and reports, preparation of quantity sheets,
update of project files, review and verification of material submittals, weekly status reports, and preparation of monthly pay estimates.
Education and Licensing
Education
B.S. Civil Engineering, University
of Utah.
Years of Experience
33 Years
Licensing
Professional Civil Engineer, CA
PE 51883
ICC Reinforced Concrete
ICC Structural Masonry
ICC Fireproofing.
Page 30 132
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
BRANDAN MATHIS
Material Tester
Brandan Mathis brings over 19 years of technical experience to Twining. His experience
encompasses all aspects of testing and inspection with special emphasis in concrete and
welding inspection.
RELEVANT EXPERIENCE
Lost Hill Road Bridge Interchange, City of Calabasas, CA
Material Tester: This project included increasing the bridge width from two to five lanes and
rerouting the left turn traffic to a loop on-ramp. The new bridge also added two bike lanes
and a pedestrian sidewalk. The bridge was elevated four feet to meet Caltrans height
requirements, with added width to allow for the future improvements of the 101 to add HOV
lanes. Twining provided material testing and inspection services. Brandan provided quality
control and concrete inspections.
East Mountain Drive Bridge, County of Santa Barbara, CA.
Material Tester: Previously destroyed as a result of debris flow in 2018, East Mountain Drive
Bridge is currently being replaced in Montecito. The low water crossing that was destroyed
during the debris flow was replaced with a temporary bridge but is now being upgraded to a
permanent bridge. The new bridge construction will include caisson foundation installations
and new abutments and wingwalls construction. Twining is providing quality assurance
material testing. Our involvement includes providing compaction testing of the wall backfills,
concrete sampling, and laboratory testing of selected materials. Brandan provided quality
control inspections.
Annual Pavement Rehabilitation: City of Thousand Oaks, CA.
Material Tester: Since 2010, Thousand Oaks has engaged the services of Twining to assist
it in the review and revision of its pavement rehabilitation specifications, perform materials
design studies, implement quality assurance programs, perform construction inspection and testing, and perform pavement destructive
testing and assist with pavement deflection testing for future pavement designs. Brandan served as a public works inspector and
provided asphalt testing and inspection.
Certifications:
Education and Licensing
Years of Experience:
19 Years.
Licensing
ACI Field Testing Technician
Grade I
AWS Certified Welding Inspector
ICC Structural Steel and Welding
Legacy
ICC Reinforced Concrete
ICC Spray-Applied Fireproofing
Caltrans Certifications: 125 (BIT),
125 (GEN), 125 (HMA), 231, 375,
504, 518, 539, 540, 543,
556, 557.
Page 31 133
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 4: ORGANIZATION AND STAFFING
JUAN J. HERNANDEZ
Biologist
Mr. Hernandez has over thirty years of experience in biology, regulatory permitting,
environmental review, project management, and ten years in business administration. Mr.
Hernandez manages projects and assists clients in obtaining necessary approvals from
city, county, state, and federal agencies. Mr. Hernandez manages the biology department
and oversees all biological studies conducted and reports prepared by Hernandez
Environmental Services biologists. As an employee for Chambers Group Inc., Lilburn
Corporation, and LSA Associates, Mr. Hernandez managed projects through the planning
and regulatory permitting process. Mr. Hernandez performed biological assessments,
desert tortoise presence/absence surveys, jurisdictional delineations, obtained wildlife
regulatory permits, managed sub consultants in air quality, traffic, noise, geotechnical, and
cultural studies, and secured new contracts. Mr. Hernandez focused on solving client
needs and making projects come in on time and within budget. As an employee with the
California Department of Fish and Game, Mr. Hernandez was responsible for
administering and implementing the Streambed Alteration Agreement Program for western
San Bernardino and Riverside counties. He was in charge of issuing 1602 permits for
projects that would have substantial impacts on State riparian resources. Mr. Hernandez
also conducted numerous biological studies including presence/absence surveys for
Santa Ana sucker (Catostomus santaanae) and for the desert tortoise (Gopherus
agassizii), artificial reef studies in southern California, commercial and sport fishing
studies, and wild trout presence/absence studies in southern California streams. Mr.
Hernandez is also an experienced wetland delineator and has a unique understanding of
the regulatory permitting process.
RELEVANT EXPERIENCE
Brown Field Airport Runway Rehabilitation Project, Burrowing Owl Surveys, Biological Monitoring, and Regulatory
Compliance, San Diego, CA
Biologist: The Brown Field Airport Runway Rehabilitation Project consisted of the rehabilitation of the westernmost and easternmost
portions of Runway 8L/26R. HES conducted 30-Day, 3-Day, and 24-Hour Surveillance Surveys for burrowing owl prior to the
commencement of construction activities. HES also coordinated with CDFW and City staff on biological construction monitoring
requirements. HES attended pre-construction meetings, advised City staff and construction personnel on the presence of biological
resources within the project areas, and prepared Pre-construction Monitoring and Monitoring Reports for the project.
Rose Canyon Truck Sewer Joint Repair Project, Biological Resources Study; Jurisdictional Delineation; Regulatory Strategy,
San Diego, CA
Biologist: The Rose Canyon Trunk Sewer Joint Repair Project proposes to repair approximately 4.5 miles of the 4.7-mile long trunk
sewer. HES prepared a Biological Resources Study and Jurisdictional/Wetland Delineation for the Rose Canyon Trunk Sewer Joint
Repair Project. Advised City of San Diego Public Works Department staff on the potential requirements for the USACE Section 404
Permit, CDFW Section 1602 Streambed Alteration Agreement, and RWQCB Section 401 Water Quality Certification permitting process
Sewer Group Job 787 Emergency Point Repair Project, Biological Monitoring and Nesting Bird Surveys, San Diego, CA
Biologist: The Sewer Group Job 787 consisted of the emergency replacement of a broken pipeline encasement located within an
unnamed drainage, HES conducted Biological Monitoring and Nesting Brid Surveys for the Sewer Group 787 Emergency Point Repair
Project. HES also attended pre-construction meetings, advised City staff and construction personnel on the presence of biological
resources within the project area and requirements of the MMRP, and prepared Pre-construction Monitoring and Final Monitoring
Reports for the Project.
Sewer and Water Group Job 694, Biological Monitoring and Nesting Bird Surveys San Diego, CA
Biologist: Sewer and Water Group Job 694 consisted of the replacement of several sections of existing sewer mains; installation of
new sewer main; rehabilitation of existing sewer main; and installation of curb ramps, pavement resurfacing, and all other incidental
work and appurtenances. HES conducted Biological Monitoring and Nesting Bird Surveys for the Sewer and Water Group Job 694 in
compliance with the MMRP prepared for the Project.
Education and Licensing
Education
B.A., Biology, California State
University, Humboldt-1991.
Licensing
CDFW Environmental Scientist
Regulatory Specialist.
Project Management Training,
2013.
Desert Tortoise Training, Desert
Tortoise Council, November 2008.
Trained in Global Mapper GIS,
2007.
Wetland Delineation Training,
Wetland Training Institute. April
2003.
Page 32 134
SECTION 4: ORGANIZATION AND STAFFING
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
ELIZABETH K. GONZALEZ
Associate Biologist
As an associate biologist for Hernandez Environmental Services Ms. Gonzalez has
conducted biological studies, including presence/absence surveys for nesting birds,
burrowing owl (Athene cunicularia), desert tortoise (Gopherus agassizii), and for the least
Bell’s vireo (Vireo belli pusillus), vegetation sampling, and jurisdictional delineations. Ms.
Gonzalez also has experience preparing biological assessment reports, constraints
analyses, Western Riverside County Multiple Species Habitat Conservation Plan
(MSHCP) compliance documents, and regulatory permitting applications.
RELEVANT EXPERIENCE
Burrtec Facility in Yucca Valley, San Bernardino County, CA
Associate Biologist: Performed preconstruction nesting bird surveys that included the
entire Yucca Valley Burrtec Waste Transfer Facility project site and a 250-foot buffer
around the perimeter of the site. Performed walking transects up to 100 feet apart for 100
percent coverage of the site. Informed the project manager of active nests and
implemented a 250-foot buffer around the nests until the birds left the nest. Submitted
Reports updating the client of the status of the nests were until it was determined the nests
were inactive. Monitored all construction activities that involved clearing and grubbing to
ensure no take occurred on any state and federal listed plant and animal species.
Telegraph Road Traffic Throughput and Safety Enhancements Project, Los Angeles
County, CA
Associate Biologist: Performed weekly nesting bird surveys surveying all vegetation or structures that provided nesting opportunities
for nesting birds. Used GPS devices to mark the location of any nests found during the surveys and determined whether nests were
active or inactive. Submitted daily logs and reports for every survey performed identifying the findings of the surveys and created maps
showing the location of any nests observed. Continued to monitor inactive nests during the duration of the nesting bird season to
ensure no birds later occupied the nests and were impacted by project activities.
Lockheed Martin Aeronautics Palmdale Photovoltaic Solar Expansion Project, Los Angeles County, CA
Associate Biologist: Scheduled field visits for the project and organized all monitoring reports and made sure they were submitted
on time. Kept in regular contact with the project managers to ensure monitors were available when they were needed. Monitored and
directed the removal of western Joshua trees (Yucca brevifolia) and the installation of avoidance fencing around Joshua trees that
were to be preserved-in-place. Provided guidance to ensure all construction activities were in compliance with the Avoidance and
Protection Plan, the project specific incidental take permit, and the City of Palmdale Native Desert Vegetation Ordinance.
Education and Licensing
Education
B.S. Biology, California State
University, San Diego-2015.
Licensing
Wetland Delineation Training,
Wetland Training Institute, 2020.
24 Hour Mine Safety Training
Course, 2020 .
MSHCP Consultant Training,
Regional Conservation Authority,
2019.
Page 33 135
SECTION 5: SCOPE OF WORK
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SCOPE OF WORK
Scope of Services
Our construction management services focus on coordination, review, tracking, reporting, public outreach, cost control, and field
inspections to ensure the quality of the work complies with applicable federal funding requirements, LAPM, and the contract
documents. The RE and inspector(s) will coordinate and work proactively to assist the general contractor’s construction efforts and
maintain fluid channels of communication with the City’s design consultants to technically support the construction effort and the
efforts of the City in achieving a successful completion with minimum complications.
The FCG Team’s team is unique in that it has a natural quality assurance/control system. Through its structure as an integrated unit
with close communication between team members and interlocking responsibilities that provide good coverage of all elements of
construction engineering, it incorporates minimal overlap of duties to avoid misunderstandings and reduces costs.
The RE is responsible for daily decisions and assignments of specific duties while monitoring the success and completion of project
construction. The resident engineer has specific administrative duties that include review of field activities. He will institute a system
of periodic reviews of the field file for conformance with The FCG Team’s in-house filing system and LAPM. The inspectors will have
specific assignments and move the products of their reporting to the resident engineer/construction manager. This bi-level approach
has proved effective because the likelihood of a missed or incorrect item is essentially eliminated with this multi-level control.
Additionally, our team will maintain a project first philosophy with the contractor. When this is achieved, construction is easy, straight
forward, and accomplished with a minimum of issues. We are a team; and right is right and wrong is wrong for all parties. When this
is established, it creates a fair environment for all, and project success is achieved.
Task 1 Pre-Construction Services
Our Construction Manager (CM), AB Fakhouri, will start work on the Project immediately after the Notice to Proceed (NTP). AB
will develop the tasks that need to be accomplished and assist in bid review, Project scheduling, and with City of Moorpark’s
concurrence, assign staff duties to the appropriate members.
a.Constructability Review – The FCG Team will review the plans and special provisions during design for errors and
constructability issues, report those findings to City of Moorpark, and will coordinate with the design team to eliminate such
issues. By being active during design, these findings typically provide for accurate and concise bids that eventually reduce
RFI’s, changes or claims during construction. Most importantly, bid items in the Special Provisions must be clear as they
describe the work, measurement of the work, and what is included in the payment of each item.
b.Schedule – The CM will work with City of Moorpark to review the baseline schedule, look for issues, and make
recommendations to City of Moorpark as appropriate. Such recommendations will be based on logic and a realistic
schedule. Our CM will propose enhancements based on sequence and number of working days, milestones, and key dates
to ensure development of an efficient and well managed Project.
c.Budget – The FCG Team will review the contractors’ bids and provide comments and recommendations to City of
Moorpark to ensure proper expenditure of funds to control Project costs.
1.Construction Bid and Award
The FCG Team will assist City of Moorpark in the construction bid procurements, including contract documents,
Federal and State requirements, Plans and Special Provisions, and permit requirements. We will perform all work as
per the Caltrans Construction Manual and Local Assistance Procedure Manual.
a.Construction Bid Documents – The FCG Team will review the bids for compliance with contract documents and
contract scope to avoid unbalanced bid items and to prepare tabulations of all bids. The CM will advise City of Moorpark’s
Project Manager, (on issuing the NTP based on review of apparent low bidder price and schedule. This allows for the
contractor to obtain all appropriate permits prior to construction.
b.Pre-Construction Meeting – Once the NTP is produced, the FCG Team will coordinate for the preconstruction meeting
by preparing a list of attendees, including, but not limited to, the contractor, designer, City of Moorpark, Caltrans, and utility
companies. Prior to the meeting, the CM will prepare for City of Moorpark review an agenda that identifies the following:
documents required from the contractor for supervision and safety, certified payroll requirements, materials sampling and
Page 34 136
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
testing criteria, and certificates of compliance for all materials. The attendees will receive meeting minutes, including a sign-
in sheet, for their records following the meeting.
c.Construction Contract Award – The CM will review all bids and will make a recommendation to City of Moorpark to
award to the lowest apparent responsive bidder. Additionally, we will develop a payment excel file, verify the contractor’s
references, licenses, insurances, and coordinate with the contractor for award.
d.Funding Documents – The FCG Team will assist the City with the following:
1.Send copy of notice of preconstruction meeting to Caltrans.
2.Prepare local agency contract award checklist.
3.Prepare detail estimate and summary and finance letter based upon low bid.
4.Obtain from contractor Local Agency Bidder – DBE Commitment (construction contracts) and Local Agency Bidder –
DBE Information (construction contracts) based upon low bid.
5.Prepare resident engineer’s construction contract administration checklist to help local agency with administration of
federal aid project.
6.Submit to Caltrans DLAE Item No. 2 through 5 along with City provided data for engineer’s final opinion of probable
construction cost, contractor’s bid, bid analysis, executed contract, and as advertised plans and specifications.
7.Prepare progress invoice at least every six months based upon contractor’s contract progress reports and submit to
Caltrans DLAE.
Task 2 Construction Management and Coordination
As the pre-construction phase comes to an end, we will begin staffing for construction management and inspection based on the
contractor’s actual schedule of activities and staging of the work. The staffing will parallel the contractor activities to ensure maximum
efficiency in expenditure of the construction management contract with City of Moorpark. When Project activity increases, we will
add additional field staff necessary. A staffing plan is included in the Proposed Staffing and Project Organization section of this
proposal. As we have demonstrated in the past, The FCG Team is committed to reducing the Project duration, which will result cost
savings to City of Moorpark.
Task 2.1 Meetings
The FCG Team will coordinate and conduct weekly progress
and field meetings with the City of Moorpark, the design team,
and Contractor. Our CM will prepare the meeting agendas,
which will include reviews of the Project schedules, a summary
of submittals and RFI’s, unresolved issues, and new issues
requiring follow-up. Our CM will produce meeting minutes of
each meeting. In addition, The FCG Team will coordinate and
meet with residents, business owners, utility firms, and other
agencies involved with this project.
Task 2.2 Communication and Coordination
Our CM, AB Fakhouri, PE, will act as the prime point of
contact between the contractor, City of Moorpark, and the
utility companies. FCG’s CM will ensure coordination with
property owners adjacent to the Project right-of-way to
develop timely communication regarding pre-condition
survey, during construction, and post construction
activities. Mr. Fakhouri will also maintain regular contact
with City of Moorpark’s Construction Manager and Project
Management team, keeping everyone informed as the
Project progresses. FCG’s construction management team
will maintain a close working relationship with all
stakeholders and cohesiveness within the FCG Team.
Page 35 137
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
The FCG Team will coordinate with the contractor during the entire Project including, but not limited to, ensuring full compliance with
permit requirements, procurement of early and/or long lead time items, and an excellent public outreach effort, which will be highly
sensitive to the many businesses surrounding the interchange and the traveling public in the surrounding community. This includes
emphasis on successfully implementing approved traffic control plans, nighttime and weekend lane closures, full road closures,
temporary drainage measures and making sure the WPCP or SWPPP BMPs are keeping up with the job as it changes. The FCG
Team is aware of the following list of projects that may be under construction simultaneously with this Project. The FCG Team will
diligently coordinate all efforts with the following, but not limited to, stakeholders:
a.City of Moorpark various departments.
b.Caltrans District 7; Los Angeles and Ventura Counties.
c.Residents.
d.Businesses.
e.Utility Companies.
f.Water Company.
g.School District.
h.Emergency Responders.
We will also coordinate with the activities of any other City of Moorpark construction Project in the vicinity that our Project may impact,
or that may have an impact our Project.
FCG has successfully worked with many public works contractors in Southern California and has developed strong working
relationships based on trust and respect. The FCG Team has the experience and capability of communicating and partnering with
the contractor and their sub-contractors. The FCG Team will always maintain a professional and a respectful relationship with the
contractor staff.
The Resident Engineer will send a daily e-mail report to the City Project Manager. This daily e-mail will provide the daily status, any
issues and photos. This service will efficiently keep the City Project Manager and others up to date on the project’s progress and
provide confidence in project progress in between site visits by the City of Moorpark.
Construction Coordination – The FCG’s CM will coordinate with the contractor as needed during the entire project to ensure
they are aware of permit requirements, long lead items that can potentially delay the project, and are sensitive to issues that affect
local businesses and the traveling public in the surrounding community. This includes emphasis on successfully implementing
approved traffic control plans, temporary drainage measures and making sure that the SWPPP BMP’s are keeping up with the job
as it changes. Additionally, we will coordinate with the activities of any other construction Projects in the vicinity that we could impact,
or that could impact our Project. These topics will be discussed at the pre-construction meeting, and subsequent progress meetings.
When necessary, required follow up meetings will be scheduled. The FCG Team has successfully worked with many public works
contractors in the counties of Ventura, Los Angeles, Orange, San Bernardino, Riverside, San Diego, and Imperial, and has developed
strong working relationships based on trust and respect. The FCG Team has the experience and capability of communicating and
working with the contractor. The FCG Team will continue to develop good working relationships while producing the desired product
for the City of Moorpark.
Utility Coordination – The FCG’s CM will manage the Project’s utility coordination efforts with the contractor and the local utility
companies. A critical factor for constructing any project is early partnering with utility companies within the project limits. Our CM and
the FCG Team will coordinate with each utility company and work diligently to communicate, schedule and achieve the timeline for
each relocation or new construction. Also included in the appendices section of this submittal is a list of the utility work to be performed
by others as shown on the plans (Table A). For utilities planned for relocation during construction, the FCG Team plans to initiate
coordination with the contractor and the respective utility to plan for USA Dig Alert, potholing, and scheduling of the relocation work
of the facilities. The CM will verify the Contractor incorporates work related to the utilities in the baseline schedule.
Page 36 138
SECTION 5: SCOPE OF WORK
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Task 2.3 Project Schedule and Cost Control
FCG’s CM will manage the Project’s schedule and budget and will set up an internet-based document controls system and Primavera
scheduling. The team will prepare independent monthly estimates for the Project duration, monitoring both the Project and
contingency budgets. Our report to City of Moorpark will include amount paid to contractor to date, previously paid amount to
contractor, percent complete of each bid item, executed change orders, and retention withheld from each pay estimate. Our intent
is to keep City of Moorpark fully informed of the financial status of the Project.
Pay item quantities will be measured daily and documented on daily reports.
Quantity Sheets will be prepared with each pay estimate, with backup calculations.
Change orders will be prepared, monitored, costs independently estimated and verified, and work documented daily on a
separate daily diary with tentative agreements (if force account (T&M)).
Our tracking system includes costs, including supplemental work and furnished materials.
The CM will monitor the Contractor’s schedule, beginning with a thorough review of the baseline schedule submittal, and following
with a review of the monthly schedule updates. The CM will identify any changes or deviations and discuss these issues with the
contractor to determine the causes for deviation.
Contract Change Orders and Claims
The FCG Team will work with the City of Moorpark during Construction Contract Award and Change Order process to assist City of
Moorpark in controlling the costs of the Project and controlling the factors that may escalate Project costs. The FCG Team will
receive, process, track and document Project requests for Contract Change Orders from the Contractor and a CCO log will be
established at the beginning of the Project and will be continuously maintained and updated by Mr. Fakhouri. To the delegated level
of approval, and under the City of Moorpark’s direction, the FCG Team will determine the need, merit, scope, estimated cost, and
schedule impacts to the project as a result of potential contract change orders. The FCG Team will also negotiate change orders
with Contractor as directed. Once merit is established, Mr. Fakhouri will prepare change orders based on the Contract Documents
and in close coordination with the Design Engineer and City Project Manager.
All contract change orders will include a transmittal memorandum that will identify the issue, provide background information,
determine merit and provide financial and schedule impacts. This transmittal memorandum is generally for City review only and is
not shared with the Contractor. All contract change orders will be reviewed with the City Project Manager. The FCG Team will work
with City of Moorpark’s Project Manager to establish levels of financial authority from the City Project Manager up the chain of
command to provide guidelines for change authorization. The FCG Team compile the monthly Project costs, including engineering
and management costs, and include it in the monthly report to City of Moorpark.
Cost Estimating - All change orders will be estimated independently of the contractor’s proposed cost prior to approval by our
CM, and submittal for approval to City of Moorpark. We will comply with the Caltrans Construction Manual and Local Assistance
Procedures Manual and change order calculations will be based on force account analysis outlined in the Handbook. The FCG Team
is comprised of highly qualified scheduling and claims avoidance experts that will produce and analyze schedules from the
perspective of an owner and a contractor. Our experts will ensure the contractor is complying with the requirements. Our approach
includes, but is not limited to, analysis of schedules on a weekly basis, inspector’s daily diaries, meeting minutes, and Project files
to provide City of Moorpark advance notice of any potential delays.
Claims Avoidance and Mitigation – The FCG Team’s renowned claims division and our claims experts have a proven track
record with Caltrans and other public agencies on similar projects. We will monitor all site records of events, labor, materials and
equipment for potential claims or delay issues. This data will be essential when analyzing contractor’s CPM schedule and claims.
Our team will address every issue that will contain all relevant RFI’s, change orders, correspondence, pictures, inspector’s dairies,
cost analysis and schedule analysis. Our objective will be to minimize misunderstandings by providing clear and concise analysis of
all major issues on the Project.
Our Resident Engineer and Structures Representative will establish an open communication plan with the Contractor to discuss all
project matters and will respond to all issues timely to minimize any potential for claims. Typically, claims arise from lack or shortage
of communication and delay in response to RFI’s and change order requests. The FCG Team will address all concerns, RFI’s, and
change order requests in a timely matter and will document all matters in case a claim is submitted. The FCG Team have experience
with reviewing and responding to claims along with representing clients in mediation or arbitration to resolve such matters.
Page 37 139
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
Task 2.4 Management
Advanced Planning and Project Plan Review – Preceding the first working day, the FCG’s Team will visit the project site and
revise the document existing confirm conditions are precisely as represented on the plans and will document all findings. During
construction, the FCG Team will work with the Contractor to review and respond to RFI’s, and if changes are necessary, the team
will handle the change orders in agreement with the contract documents. In addition, the job site will be photographed to document
the pre-construction conditions of existing facilities and utilities that can be damaged amid the construction process. Specific
consideration will be made to the potential work impacts to the local businesses and the travelling public during the construction.
Advanced planning by the FCG Team will ensure the following:
Verify construction limits; review field conditions; identify areas for storage of long lead items, parking, and project
site staging; identify utilities that within the project footprint, and their ultimate disposition; photographic and video
documentation of the project site; and proactive pre-planning to avoid project delays.
Funding Submittals – The FCG Team will assist the City of Moorpark with the following:
1.Send copy of notice of preconstruction meeting to Caltrans.
2.Prepare local agency contract award checklist.
3.Prepare detail estimate and summary and finance letter based upon low bid.
4.Obtain from contractor DBE Commitment and Local Agency Bidder – DBE Information based upon low bid.
5.Prepare resident engineer’s construction contract administration checklist to help local agency with administration of project.
6.Submit to Caltrans DLAE with City provided data.
7.Prepare progress invoice based upon contractor’s contract progress reports and submit to Caltrans DLAE.
Project Submittals – The FCG Team will provide the contractor a list of submittals as per the Special Provisions, then perform a
thorough, comprehensive review of the contractor’s submittals. We will work closely with City of Moorpark to determine which
submittals the design consultant will review, and which will be reviewed by the FCG Team. A Submittal log will be developed,
maintained, and tracked according to when they are received and returned to the contractor and a copy will be included with eac h
transmittal and at the weekly meetings. Materials releases and certificates of compliance will be kept in the appropriate filing
categories, and materials summary sheets will have a running total of materials used on the Project. Anticipated submittals include,
but are not limited to, baseline schedule, WPCP or SWPPP, shoring plans, falsework plans, bridge demolition plan, bridge materials,
concrete mix designs, HMA job mix, shop drawings, quality control plans, traffic handling plans, piling plans, health and safety plan,
lead compliance plan, temporary lighting plan, and temporary signals plan.
Safety – The FCG PM and CM will work diligently to ensure all team members comply with State of California Construction Safety
Orders and provisions of the Caltrans Construction Manual. In addition, all staff on the FCG Team will be provided the necessary
safety equipment as required by construction safety orders and regulations of the Project. These devices will be, but are not limited
to, hardhats, safety glasses, reflectorized vests, work boots, earplugs, etc., trucks with amber lights, and harnesses for fall protection
(personal protective equipment (PPE)).
Schedule Control – The FCG Team will produce and analyze schedules from the perspective of an owner and contractor to
ensure timely or early completion of the Project. We will ensure the contractor is complying with the requirements of the monthly
schedule updates as required in the special provisions and will closely monitor the critical path to avoid delays and subsequent
consequences. Our analysis of the contractor’s schedules will be done on a weekly basis in conjunction with inspector’s daily diaries,
meeting minutes, submittal logs, and other Project records. This schedule analysis approach will provide City of Moorpark with notice
of any potential delays prior to issuance by the contractor to allow time for appropriate response. The FCG Team will enforce the
scheduling requirements in the Special Provisions, which will be key to placing City of Moorpark in a positive position in case of
claims. It is recommended that the Special Provisions require the contractor to submit TIA’s, together with costs for any change
orders, including with time requirements when cost proposals are due.
Page 38 140
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
SWPPP Compliance – Our CM is a certified QSD and has
experience managing construction work under the MS4 and
new permit requirements. Mr. Leon Fuentes will be providing
weekly or as-needed monitoring of field conditions. It is our
practice to handle storm water compliance with the same level
of attention as safety. The FCG Team will review the
contractor’s WPCP or SWPPP to ensure compliance with the
Regional Water Quality Control Board (RWQCB) permit
requirements. We will conduct regular inspections of the site
with the contractor and upload reports and documents to the
SMARTS database. Our team will ensure the contractor
adheres to the approved SWPPP plan and installs and
maintains appropriate BMPs, including maintaining an approved
storage with the proper contractor-owner agreement. It is
recommended the Special Provisions include language directing the contractor not to stockpile any materials on the Project site,
whether active or not, to avoid erosion or discharge into inlets or the flood control channel.
Environmental Compliance Enforcement – The FCG Team will ensure compliance with the environmental and resource
agency requirements contained in the Project permit. Our team will create a log of requirements of the various permits to ensure all
permit conditions and mitigation measures are met. Our field personnel will ensure the contractor complies with the permit conditions,
and mitigations work will be tracked and reported on inspection reports with photos.
Additionally, the FCG Team is highly experienced in working with AQMD and will review and ensure compliance with AQMD
requirements per the Project permit. Our team will identify the requirements in the permit to ensure all conditions and mitigation
measures are met, including any required monitoring and tracking procedures. The Project includes removal of existing slopes at
both sides of the 133 for the construction of the proposed bridge. The existing soil may include Aerially Deposited Lead (ADL) that
must be addressed in the Project plans and special provisions, including method of removal, disposal, and payment. The FCG team
will ensure the contractor submits a Health and a Safety Plan as well as a Lead Compliance Plan.
Permit Tracking – The FCG team is currently providing these same types of services to Cities of Irwindale, Downey, Burbank,
and other municipalities and agencies throughout the state. The FCG Team utilizes a simple system for tracking of both building and
public works permit using a simple spreadsheet. This system is fairly simple and allows the permittee and City officials to view the
current budget and status of each permit.
Shoring – A shoring submittal will be reviewed by one of our qualified PE’s assigned to the Project. Mr. Dragan Buha, PE a
Structures Representative, has a great deal of experience reviewing and approving contractor’s falsework, shoring, guying, and
other structural submittals.
Traffic Control – The FCG Team, CM, and field staff will
continuously monitor traffic control measures, ensuring all
detours and construction signage are maintained, clean, and
clear to the traveling public, including nighttime review for
reflection and clarity. Our CM will discuss traffic control plans at
each weekly meeting and keep the City and City of Moorpark
informed of any traffic lane closures, ensuring strict compliance
with local permit and contract requirements.
Monthly Activity Summary Report – Our CM will plan and
submit a month-to-month activity summary report to the city of
Moorpark administration that will provide a precise status of the
project budget and plan. We can either take after the format
given by the city of Moorpark or utilize a report format
implemented on our past projects. In expansion to status
updates on the schedule, logs providing data on completed, ongoing and expected work, potential claims or delays, SWPPP issues,
RFI ND Change order logs, counting expected changes, estimated costs and contingency balance. The report will moreover contain
overhauls on any critical issues with the potential to influence the project.
Page 39 141
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
Budget Control and Tracking – Our PM/CM will prepare and submit a monthly budget report to City of Moorpark management
with an accurate status of the Project budget and schedule. This report will contain, but not be limited to, schedule status updates,
work operations, submittal, RFI and change order logs, and Project issues.
Partnering – The FCG Team is a firm believer in partnering and has actively participated in partnering sessions on numerous past
projects. We will again accept responsibility for coordinating partnering sessions for the Project team, including making arrangements
with City of Moorpark’s preferred Partnering Facilitator.
Quality Assurance Program – The FCG Team’s extensive Caltrans experience, beginning with the Resident Engineer, A.B.
Fakhouri, PE, and Structures Representative, Dragan Buha, PE, will oversee our team’s quality control efforts with materials
sampling and testing, survey staking and control, and construction inspection services. The FCG Team is committed to providing
the highest quality people and services to the City of Moorpark. To further emphasize our Quality Assurance (QA) program, the QA
team will conduct regular quality improvement sessions to train staff and provide continuous updates on industry practices, Caltrans
directives, and changes in standard plans and specifications. The FCG Team will continuously review the jobsite and documentation
produced by our staff to ensure compliance with the LAPM and Caltrans Construction Manual requirements and they will keep in
regular contact with City of Moorpark Project Manager to ensure City satisfaction.
Labor compliance – The FCG Team will perform the following:
1.If applicable, attend Contractor pre-bid conference to present general requirements of bid preparation for project.
2.Verify applicable wage determination 10 days prior t bid opening and document verification as required.
3.Verify eligibility of selected contractor and its subcontractors to receive contract awards by confirming current, active license
status with State of California Contractors License board and non-appearance on Federal List of Parties Excluded.
4.Conduct preconstruction conference to present federal labor compliance requirements to contractor.
5.Verify and document jobsite posting of wage rate information and labor compliance posters and perform field interviews.
6.Receive and review labor compliance documentation from public works observers or inspectors and compare with contractor
submitted documents. Monitor weekly payroll documentation on continuous basis, including certified payroll reports, fringe
benefits statements, apprenticeship documentation, and payroll deduction authorizations.
7.Follow up with contractor regarding required document submittals and payroll discrepancies.
8.Coordinate withholding of progress and/or retention payments with County staff if contractor fails to abide by labor compliance
requirements.
9.Receive, pursue, and document labor complaints and recommend special action to be taken if contractor continuously fails to
comply with requests and requirements.
10.Maintain content and format of federal labor compliance file in conformance with applicable requirements.
11.Coordinate project file reviews by authorized county, state, and federal agencies.
12.Submit complete federal labor compliance file to County for retention (federal labor compliance files are to be retained for period
of not less than three years).
Construction QA Surveys – Mr. Paul Wagner, PLS of Wagner
Engineering will serve as Survey Project Manager, providing field survey
personnel to perform, the following support services, as needed for the
Project: construction survey staking and calculations, grid grade data, open-
ended traverses and profile data sheets, three-line profiles, right-of way
lines, special design – data surveys, control survey, topographic surveys,
structures surveys and construction staking, and monumentation (as-
needed). All survey quality assurance inspection provided will be in
accordance with the Caltrans Right-of-Way and Survey Manuals, as well as
plans and specifications and the requirements of the RFP.
Biological Monitoring – Mr. Juan Hernandez will serve as Survey Project Manager, providing field biologists to perform, the
following support services, as needed for the Project: a pre-construction survey within 3 days prior to ground disturbance is
mandatory in suitable habitat areas for migratory nesting birds; exclusionary devices and nest prevention methods designed to
prevent birds from utilizing the overpass; survey the entire stretch of the project area on both sides of Princeton Avenue. All trees,
shrubs, and structures that may be potential nesting areas for migratory birds will be surveyed. All Biological Monitoring provided
will be in accordance with the Caltrans Right-of-Way and Survey Manuals, as well as plans and specifications and the requirements
of the RFP.
Page 40 142
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
Public Outreach – Even a project that is constructed safely, on time, and within budget can be perceived as a failure if public
relations are not handled professionally and proactively. The City’s projects may impact the public and require effective public
relations by the project team. The FCG Team will act as the primary contact during construction for the public to address concerns
related to the project. All public concerns will be listened to with an empathetic ear. Contact information will be gathered and logged
with the issues raised, and resolution of each issue will be proactively processed as acceptable to the City. If community outreach is
required for the project.
The FCG Team will:
1.Prepare and distribute informational flyers to residents and business owners within the project area prior to, at 50 percent, and
near project completion advising:
When and what will take place.
How much time it will take to complete work.
What impacts may occur throughout the area.
What precautions business owners and residents should take.
What traffic control measures taken minimize construction impacts to businesses and residents.
Where detours will be established – maps to be provided.
What construction operations may affect ingress and egress to properties.
2.Set up a 24-hour telephone number to receive complaints. Respond to complaints within 24 hours and notify the City within that
time of said resolution.
3.Hold informational meetings with area residents and business owners to include two meetings prior to construction and one
meeting during construction.
4.Maintain a log of telephone calls documenting complaints received and actions taken to resolve the complaint; provide the City
a weekly summary sheet documenting complaints/comments filed along with the action taken and resolution selected.
5.Ensure maintenance of detours and access to businesses and resolve any issues arising from detours.
Deliverables – The FCG Team will deliver the following before, during, and after construction:
1.Constructability Review. The FCG Team will provide requested reviews within 5 business days of the notice to proceed. Detailed
scope can be found in our proposal.
2.Preconstruction Meeting Agenda and Minutes. The FCG Team will provide the preconstruction minutes the day after the
preconstruction meeting.
3.Coordination Meetings with utilities, the public, and other agencies.
4.Review of submittals, RFI’s, change order requests, and inquiries.
5.Provide outreach support throughout the project to inform the public and stakeholders.
6.Setup electronic and hard copies of project files and utilize LAPM forms.
7.Inform Contractor of mandatory rules and city ordinances and enforce daily.
8.Daily Reports. The FCG Team inspection personnel will provide detailed daily logs at the end of each work week.
9.Daily Quantities of contract work of pay estimates.
10.Daily records of labor and hours for labor compliance enforcement including conducting employee interviews.
11.Progress meetings to discuss status of work and all other topics and issues.
12.Weekly report. Detailed weekly reports will be submitted at the end of each work week.
13.Monthly progress report. The required monthly report will be submitted with the monthly progress payment.
14.Progress payments. Payments will be submitted monthly and will include The FCG Team payment recommendations.
15.Pay estimate backup and documentation for reimbursement purposes.
16.Material Testing Results. Material testing field notes will be provided weekly basis and final reports will be submitted with the
monthly report.
17.Material testing logs of all test results for all materials.
18.BMP Reports. BMP reports will be submitted with the weekly reports.
19.Safety inspection reports on all work aspects for Prime and Subcontractors.
20.As Built Plans. As-Built plans will be provided on a weekly basis and the final plans will be submitted with 5 days after the
cessation of the work.
21.Final CM Files. Final CM file will be submitted with 15 days after the cessation of the work.
Page 41 143
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
As-Built Plans – The FCG Team will maintain as-built plans
on an on-going basis throughout the duration of the Project
along with reviewing the Contractor’s As-Built plans monthly
at the time of submission of the monthly pay estimate request
in order to match the work with the schedule and budget. The
redlined plans will show all changes made to the contract
plans, will present name of change approver, and CCO
number. We will also ensure the contractor is tracking as-
builts, and at the end of the Project, our construction
management team will combine all the information into one
accurate and complete set of drawings. At the end of the
Project, the Contractor will submit the final set of As-Built
plans for the City and the FCG Team to review and approve
and once the final set of plans are approved, the Engineer of
Record and Design Team will prepare the As-Builts and
provide the City with the signed plans along with the electronic copy of the plans for the City to archive. Finally, once the Project is
accepted and the Contractor is relieved from maintenance on the Project, the FCG Team will assist the City of Moorpark to transmit
the final copy of the As-Built plans to Caltrans District 7 and utility companies. The FCG Team has worked on many projects that
involve maintaining and reviewing As-Built plans and will ensure the Contractor complies with all requirements for submission.
Final Reports/Release of Permits – At the beginning of the Project, the FCG Team will prepare binders for hard copies of project
documents and a cloud-based filing system for web access of all documents. Such documents will be based on requirements set
forth by FHWA and LAPM which will be used throughout the project including, but not limited to, forms from Chapter 17 of the LAPM.
The FCG Team will complete all necessary forms from Chapter 17 of the LAPM and will assist the City with submission to Caltrans
for final reimbursement of federal funds.
The FCG Team will recommend to the City that final acceptance be issued to the contractor when all punch-list work is completed;
all issues and project walks are answered for the City. Finally, all as-builts will be inventoried and verified complete before the
contractor receives final acceptance and final payment is recommended. Once all closeout activities have been satisfied, a Report
of Completion will be prepared and forwarded to the City Project Manager with recommendation for acceptance of the work. The
report will verify the contractor's compliance with all contract specifications and drawings.
Task 3 Construction Inspection
Task 3.1 Meetings
The Resident Engineer will conduct weekly progress and field meetings with the contractor, City of Moorpark, as necessary and
appropriate, and the inspectors, Office Engineer, and other subconsultants will attend and participate in the discussions and
documentation of the meetings. The Resident Engineer will discuss issues with the Structures Representative, Field Inspectors, and
Office Engineer to ensure previous meeting minutes have been documented and distributed and an agenda with logs is prepared
for the current meeting to discuss project status and schedule.
Task 3.2 Communication
The Resident Engineer and Structures Representative will always communicate with the FCG Team including the subconsultants
and will make sure everyone is well informed and aware of construction activities and will identify all issues and discussions including,
but not limited to, change orders, delays, submittals, RFI’s, and notifying residents and businesses of activities especially closures.
The FCG Team will work as one to ensure proper coordination is done and all communication is shared and documented properly
including, but not limited, to design changes, special requests by the public, and or special requests by City departments. In addition,
the field inspectors will be heavily involved in coordination efforts with utility companies and other agencies because they will be
always present in the field and have knowledge of the work and activities and will participate in representing the FCG Team and
the City of Moorpark at occasions.
Page 42 144
SECTION 5: SCOPE OF WORK
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Task 3.3 Project Cost and Schedule
The Resident Engineer and Structures Representative will manage the Project schedule and finances and will ensure that field
inspectors and support team are aware of the upcoming work activities and costs. In addition, field inspectors will be involved with
gathering data and information to support reviewing construction and look-ahead schedules which will be documented int eh
inspector’s daily diaries. The inspector diaries will include, but not limited to, daily activities, daily quantities, and status of contract
work that will be used to compare to pay estimate requests, schedule submittals, and labor compliance.
In addition, in case the Resident Engineer and City of Moorpark do not agree on a unit price or lump sum cost of a change order,
the field inspector will play a major role in terms of monitoring the work by the Contractor to determine merit of extra work, document
change order work daily, and supervise the Contractor work if the extra work is done under Time and Materials. When the extra work
is done under Time and Materials, the field inspector will document all pertinent information to the work including, but not limited to,
contractor staff names and classifications, equipment, and materials which will be used to verify the Contractor’s Extra Work Bills.
Task 3.4 Construction
The contractor will be required to provide Traffic Handling Plans, which will be reviewed and approved by the FCG Team in
coordination with City of Moorpark as necessary. We will also monitor this and if public safety is threatened, we will direct the
contractor to remedy the situation immediately.
a.Inspection Philosophy – Our work plan is to eliminate surprises to the City of Moorpark by being proactive in working with
the contractor to resolve issues as quickly as possible. A key to our success has been our ability to create a responsive
relationship with the contractor, and our client, resulting in a more efficiently run, and successful project. Our inspectors utilize
the CPM schedule to legitimately the construction advance the construction effort by looking ahead (Being observant of issues
that could delay), and by assisting the contractor in resolving the issues before they become problems. All phases of construction
and all work will be assessed for conformance with contract plans, specifications, and current specified and pertinent standards.
Inspection services, testing, and project-wide quality assurance will be in conformance with the Caltrans construction and local
assistance procedures manuals. The overriding objective for our inspectors will be to make sure beyond any doubt that the city
of Moorpark gets from the contractor what it is paying for, and what is required by the contractor drawings and specifications.
Our objective is to remain on track by doing it right in the first place eliminating time delaying corrective work and retrofitting.
Proactive approaches such as readiness reviews with the contractor’s personnel prior to a new construction activity starting, or
implementing traffic control measures such detours, have been instrumental in accomplishing the objective.
b.Field Staff Roles and Responsibilities – The FCG Team field personnel proposed for the Project are able to perform more
than one role on any project and are able to assist each other when needed. This provides efficiencies for City of Moorpark, as
the FCG Team possesses the versatility and technical knowledge of multiple aspects of heavy civil and structures construction.
Examples of this include our CM, SR, and Office Engineer who are well-versed in assisting with inspection as necessary.
c.Safety – The FCG Team is thoroughly familiar the state of California
Construction Safety Orders (CalOSHA) and traffic control Handbook practices
as indicated within the work area traffic control handbook (WATCH), as all as the
manual of uniform traffic control devices. The contractor will be required to
prepare and submit a safety plan for its operations. The safety plan will be
reviewed by the CM and the FCG Team. Deficiencies will be noted and
corrections the plan will presented. Public safety is extremely vital on the FCG
Team.
d.Traffic Management – The contractor will be required to provide the CM
with traffic handling plans, which will be reviewed and accepted by the
FCG Team in coordination with the city of Moorpark and Caltrans as
necessary. Our inspectors and CM will perform traffic handling plan to verify feasibility prior to implementation. We will
also monitor the implementation of this plan and any traffic control devices. If the public safety appears to be
compromised, we will direct the contractor to fix the situation immediately or cease the operations
Page 43 145
SECTION 5: SCOPE OF WORK
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
e.Inspection Disciplines – The FCG Team will provide
personnel to perform quality assurance inspection the
following Project elements that require specific
skill sets.
f.Roadway Inspection – Our work plan is to partner
with the contractor to resolve problems as quickly as
possible and at the lowest level possible. Key to our
success has been our ability to create a responsive
relationship with the contractor and our client,
resulting in a more efficiently run, successful project.
Our inspectors utilize the CPM and look-ahead
schedules to properly advance the construction effort.
All phases of construction and all work will be
inspected for conformance with contract plans,
specifications, and current specified and pertinent
standards. Inspection services, testing, and Project-
wide quality assurance will be performed in full
conformance with the Caltrans Construction and
Local Assistance Procedures Manuals. Our goal is to
stay on track by doing it right the first time and
eliminating time-delaying, corrective work. Proactive
approaches with the contractor’s personnel have
been instrumental in achieving this goal.
g.Structures Inspection – The FCG Team provides a
seasoned Structures Representative and an
experienced Structures Inspector with a wealth of
experience in bridge construction and inspection skill. Mr. Dragan Buha, PE possesses the skills to perform detailed
engineering analysis for falsework, shoring, use of transit, and builder’s level, to ensure the proposed line and
grades are met in the field, and digitally monitor the pre-stressing operation using a strain gage and load cell.
h.Electrical Inspection – Mr. Leon Fuentes, a seasoned field and electrical inspector, will provide electrical
inspection. He will administer the inspection and construction administration duties involved with the electrical
overhead signs, lighting, traffic signal and communications facilities (fiber optics).
i.Landscape Inspection – Our Landscape Inspector, Mr. Leon Fuentes, is knowledgeable and experienced with the
type of landscaping work associated with construction projects and can identify common plant diseases and pests
and provide recommendations.
j.Documentation – The FCG team will maintain a daily log that includes weather conditions, work status, location and
type of work performed, trade labor, equipment, and materials. Each inspector will take daily photos of work and
accurate measurement of quantities. The FCG team is highly experienced with documenting and maintaining project
files per the Caltrans LAPM. All project files will be kept and maintained by the PM|RE and OE regularly. The FCG
team will setup project folders for all hard copies of project documents and an online storage link to all files. The FCG
team will provide the City with a link to the online files and a directory to review and obtain project files as required.
FCG has had a successful strategy with providing field inspectors and project staff with means of performing inspection work
efficiently with minimal effort. Each inspector will have a laptop, smart phone, iPad, and field internet connection which will allow
each and every inspector to have access to emails, cloud-based filing system, and phone to communicate with the RE, Structures
Representative, City of Moorpark, Contractor, and all others. In addition, once the cloud-based systems is setup for everyone to use,
the inspector can use the iPad to perform daily work such as taking photos and directly saving them specific folders, write daily
diaries and document daily quantities on MS Excel and MS Word files.
Page 44 146
SECTION 5: SCOPE OF WORK
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
Task 3.5 Asphalt Plant Inspection
FCG Consultants (FCG) will schedule and coordinate materials sampling and testing and will develop the project Quality Acceptance
Plan (QAP) for off-site materials based on project specifications, and City requirements for City’s review and approval.
Typically, the RE or inspector, will request the Contractor submit a Materials Placement Notification that includes, but not limited to,
material to be placed, location, stations, mix design number, and time of batch at the plant and start time of placement at the jobsite.
Once this request is received, the RE or the inspector will forward the request to our Subconsultant Project Manager and Dispatch at
Twining requesting plant inspection prior to material placement to obtain required samples then follow to the jobsite to sample and
test placed materials. Twining will provide various reports including Batch Plant Inspection, Plant Materials Testing, Field Materials
Sampling, and Field Samples Testing, and any other pertinent reports that include information such as storage and reaction tank
temperatures, gradation, binder, compaction, and more.
Task 3.6 Materials Testing
The FCG Team member Twining will provide a Materials Testing Project
Manager as well as experienced personnel, equipment, and facilities to
perform quality assurance (QA) geotechnical and materials testing services for
this construction Project. Twining’s lab is located in the City of Ventura which
is very close to the City of Moorpark, which makes it easier to obtain samples
and perform timely tests and provide the contractor with faster test results.
Twining’s materials technicians will sample and test all materials in accordance
with the most current and appropriate California Test Methods (CTM’s), or
ASTM test methods when specified. Twining’s Caltrans certified laboratory,
which is only minutes from the Project site, and field technicians will be used
to ensure structure and roadway construction work conforms to Caltrans
standards, specifications, and special provisions for material quality and
workmanship. The test results will be transmitted immediately to the CM and
Office Engineer to expedite work. Hard copies will follow in the mail and the
FCG Team CM will ensure testing logs and summary sheets are developed and maintained for the various materials tests, and that
these logs also include resolution of any failed tests, to include re-tests. Turn-around times for testing will also be controlled by
proactive coordination between the CM and inspectors, and Twining’s field testers and lab personnel. Some of the tests to be
performed are nuclear gauge testing in accordance with CTM 375 for compaction at a rate of 10 tests per 500 tons; testing on the
conventional and ARHM asphalt mixture sampled in the field; and Stabilometer test on paving.
Task 4 – Caltrans/FHW Construction Contract Administration
a. Contract Administration – The FCG Team has provided Project staffing, managing several construction projects using the
Local Assistance Procedures Manual and Caltrans Construction Manual and contract administration procedures their entire
careers. AB Fakhouri (CM) is a former Caltrans Engineer, and Dragan Buha (SR) is a former Caltrans Senior and Structures
Representative, and both will provide City of Moorpark with a Construction Management team that has combined 60+ years of
construction and design experience specifically on Caltrans right-of-way (ROW), using the Greenbook and Caltrans Standards
and Specifications.
b. Progress Pay Estimates – The FCG Team will prepare monthly pay estimates based on field measurements of quantities
and as documented by our field inspection personnel. Materials logs will be kept ensuring items do not exceed quantities
previously released by inspection reports, certificates of compliance, or mill data. Our team will work with the contractor each
month to ensure accurate payment is made to match the work progress per measurement and payment provisions in the Special
Provisions.
Page 45 147
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 5: SCOPE OF WORK
c.Project Records and Filing System – The FCG’s CM and Office Engineer (OE) will establish and maintain a filing system
in hard copy as well as in electronic using the City of Moorpark filing categories as a standard to ensure compliance with all
requirements. All hard copy files will be scanned as PDF files and stored digitally on a server with a filing structure duplicating
the hard copies. Additionally, FCG’s OE will upload the electronic data documentation to City of Moorpark’s on-line file direct ory.
Submittal and RFI logs will be kept and tracked according to when they are received from and returned to the contractor together
with their approval or response status. Materials releases and certificates of compliance will be kept in the appropriate Caltrans
filing categories, and materials summary sheets will be developed to keep a running total of materials implemented on the Project.
All PCC and HMA tickets will be kept in separately identifiable boxes.
d.Federal Review - The FCG team has participated in several federal reviews with Caltrans and the Local Assistance Office and
presented the project documents impressively every time. The PM|RE is a former employee of Caltrans in Los Angeles and is
very experienced with documentation of construction projects per the LAPM. Mr. Fakhouri will ensure all project files are
maintained per the LAPM in project folders and in electronic form and will represent the City throughout the entire project, from
pre-construction, during construction, and through post-construction.
Our Resident Engineer, A.B. Fakhouri, has worked on several Federally Funded projects and participated in several
Project Reviews; Pre-Construction, Mid-Construction, and Post-Construction with representatives from Caltrans and
FHWA and he will ensure that all project documentation is per the Local Assistance Procedures Manual and FHWA
Requirements to ensure full compliance and proper finance management by the City. Mr. Fakhouri will provide the
Contractor with required documents to use on the project; LAPM and City of Downey forms to ensure compliance.
Task 5 Project Close-out and Acceptance
The FCG Team will provide the appropriate level of inspections to ensure all punch-list work is completed, safety issues are resolved,
final acceptance of the contract is granted, and all necessary paperwork and reports are completed:
a.Punch List – The punch list will be a living document throughout the life of the Project and the contractor will always be informed
as the progress to avoid dealing with a long list at the end of the Project. Our CM will arrange a walk through with the Contractor
and City of Moorpark. Once the field walk through is complete and work is approved, Project acceptance and sign off will be
completed.
b.Project Files and As-Builts – As each of the Project elements is completed, we will perform complete contract closeout
activities, including a walkthrough and a Punchlist. These activities will include, but are not limited to, verification of work
completion for each respective contract, final payments, and resolution of all change orders.
c.Final Reports – The FCG Team will recommend to City of Moorpark that final acceptance be issued to the contractor when all
punch-list work is completed, and all issues and Project walks are signed off by City of Moorpark, Caltrans, and Utility Companies.
Finally, all as-builts will be inventoried and verified complete prior to final acceptance and recommendation of final payment to
the contractor. The FCG Team will perform the project closeout as follows:
1.Prepare federal report of expenditures letter and report of expenditures checklist.
2.Prepare form to initiate Caltrans’ jobsite review and verification of project completion.
3.Prepare materials certificate for resident engineer’s signature to show that results of tests on acceptance samples indicate
materials incorporated in construction work and construction operations controlled by sampling and testing conformed with
approved plans and specifications.
4.Prepare final invoice, final detail estimate and summary, and change order summary Caltrans exhibit forms based upon
contractor’s final contract progress report.
5.Submit to Caltrans DLAE Item numbers 2 through 5 and attach Final Report – Utilization of DBE, First Tier Subcontractors
and DBE Certification Status Change to initiate timely project closure and payment.
6.Following receipt of final payment check from State Controller’s Office, include documents and submittals in federal funding
file, and make PDF formatted file on CD for City.
Page 46 148
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
SECTION 6: PERSON HOURS BY TASK
TASK TABLE
A task table is provided below which lists detailed tasks in rows, the individual assigned to each task, and the number of hours
associated with each task.
The FCG team has reviwed the plans and specs and put a Construction Management Schedule. Accordingly, the FCG team has
provided a task table by hours for the scope of work done by key staff which is also reflected in the Construction Management Task
Activities schedule as follows:
Page 47 149
City of Moorpark RFP for Construction Management and Inspection Services for Spec. No MPK 21‐03; HSIPL‐5436(018) Princeton Avenue Improvement Project SECTION 6: PERSON HOURS BY TASK CONSTRUCTION MANAGEMENT TASK ACTIVITY SCHEDULE The following table outlines the sequential activities that would be undertaken in completing the tasks for the FCG team.Page 48150
City of Moorpark RFP for Construction Management and Inspection Services for Spec. No MPK 21‐03; HSIPL‐5436(018) Princeton Avenue Improvement Project SECTION 7: PROJECT SCHEDULE PROJECT SCHEDULE The FCG Team put on their construction hard hats and assembled a list of major activities depicting on how Contractors will propose to build this project in the following Page 49151
SECTION 8: CERTIFICATIONS AND EXHIBITS
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
CERTIFICATES AND EXHIBITS
In compliance with Caltrans Local Assistance Procedures Manual (LAPM), FCG provides the certificates, forms, and exhibits on
the following pages which includes:
LAPM Exhibit 10-I, Notice to Proposers DBE Information
LAPM Exhibit 10-O1, Consultant Proposal DBE Commitment
LAPM Exhibit 10-O2, Consultant Contract DBE Commitment
LAPM Exhibit 10-Q, Disclosure of Lobbying Activities
LAPM Exhibit 15-H, Proposer/Contractor Good Faith Efforts
Non-Collusion Affidavit
Non-Lobbying Certification
Debarment and Suspension Certification
Page 50 152
Local Assistance Procedures Manual EXHBIT 10-I
Notice to Proposers DBE Information
Page 1 of 2
January 2020
EXHIBIT 10-I NOTICE TO PROPOSERS DBE INFORMATION
(Federally funded projects only)
The Agency has established a DBE goal for this Contract of 11%.
1.TERMS AS USED IN THIS DOCUMENT
x The term “Disadvantaged Business Enterprise” or “DBE” means a for-profit small business concern
owned and controlled by a socially and economically disadvantaged person(s) as defined in Title 49,
Code of Federal Regulations (CFR), Part 26.5.
x The term “Agreement” also means “Contract.”
x Agency also means the local entity entering into this contract with the Contractor or Consultant.
x The term “Small Business” or “SB” is as defined in 49 CFR 26.65.
2. AUTHORITY AND RESPONSIBILITY
A. DBEs and other small businesses are strongly encouraged to participate in the performance of
Contracts financed in whole or in part with federal funds (See 49 CFR 26, “Participation by
Disadvantaged Business Enterprises in Department of Transportation Financial Assistance Programs”).
The Consultant must ensure that DBEs and other small businesses have the opportunity to participate in
the performance of the work that is the subject of this solicitation and should take all necessary and
reasonable steps for this assurance. The proposer must not discriminate on the basis of race, color,
national origin, or sex in the award and performance of subcontracts.
B.Proposers are encouraged to use services offered by financial institutions owned and controlled by
DBEs.
3. SUBMISSION OF DBE INFORMATION
If there is a DBE goal on the contract, Exhibit 10-O1: Consultant Proposal DBE Commitment must be
included in the Proposal. In order for a proposer to be considered responsible and responsive, the proposer
must make good faith efforts to meet the goal established for the contract. If the goal is not met, the proposer
must document adequate good faith efforts. All DBE participation will be counted towards meeting the
contract goal; therefore, all DBE participation shall be collected and reported.
Exhibit 10-O2 Consultant Contract DBE Information must be included in best qualified consultant’s executed
consultant contract. Even if no DBE participation will be reported, the successful proposer must execute and
return the form.
4.DBE PARTICIPATION GENERAL INFORMATION
It is the proposer’s responsibility to be fully informed regarding the requirements of 49 CFR, Part 26, and the
Department’s DBE program developed pursuant to the regulations. Particular attention is directed to the
following:
A. A DBE must be a small business firm defined pursuant to 13 CFR 121 and be certified through the
California Unified Certification Program (CUCP).
B. A certified DBE may participate as a prime consultant, subconsultant, joint venture partner, as a vendor
of material or supplies, or as a trucking company.
C. A DBE proposer not proposing as a joint venture with a non-DBE, will be required to document one or a
combination of the following:
1. The proposer is a DBE and will meet the goal by performing work with its own forces.
2. The proposer will meet the goal through work performed by DBE subconsultants, suppliers or
trucking companies.
3. The proposer, prior to proposing, made adequate good faith efforts to meet the goal.
Page 51 153
Local Assistance Procedures Manual EXHBIT 10-I
Notice to Proposers DBE Information
Page 2 of 2
January 2020
D. A DBE joint venture partner must be responsible for specific contract items of work or clearly defined
portions thereof. Responsibility means actually performing, managing, and supervising the work with its
own forces. The DBE joint venture partner must share in the capital contribution, control, management,
risks and profits of the joint venture commensurate with its ownership interest.
E. A DBE must perform a commercially useful function pursuant to 49 CFR 26.55, that is, a DBE firm must
be responsible for the execution of a distinct element of the work and must carry out its responsibility by
actually performing, managing and supervising the work.
F. The proposer shall list only one subconsultant for each portion of work as defined in their proposal and
all DBE subconsultants should be listed in the bid/cost proposal list of subconsultants.
G. A prime consultant who is a certified DBE is eligible to claim all of the work in the Contract toward the
DBE participation except that portion of the work to be performed by non-DBE subconsultants.
5.RESOURCES
A. The CUCP database includes the certified DBEs from all certifying agencies participating in the CUCP. If
you believe a firm is certified that cannot be located on the database, please contact the Caltrans Office
of Certification toll free number 1-866-810-6346 for assistance.
B. Access the CUCP database from the Department of Transportation, Office of Civil Rights website.
1. Click on the link titled “Access the DBE Query Form”
2. Click on “Start DBE Firms Query” link
Searches can be performed by one or more criteria. Follow instructions on the screen.
6. materials or supplies purchased from dbes count towards the dbe goal under the following
conditions:
A. If the materials or supplies are obtained from a DBE manufacturer, count 100 percent of the cost of the
materials or supplies. A DBE manufacturer is a firm that operates or maintains a factory, or
establishment that produces on the premises the materials, supplies, articles, or equipment required
under the Contract and of the general character described by the specifications.
B. If the materials or supplies purchased from a DBE regular dealer, count 60 percent of the cost of the
materials or supplies. A DBE regular dealer is a firm that owns, operates or maintains a store,
warehouse, or other establishment in which the materials, supplies, articles or equipment of the general
character described by the specifications and required under the Contract are bought, kept in stock, and
regularly sold or leased to the public in the usual course of business. To be a DBE regular dealer, the
firm must be an established, regular business that engages, as its principal business and under its own
name, in the purchase and sale or lease of the products in question. A person may be a DBE regular
dealer in such bulk items as petroleum products, steel, cement, gravel, stone or asphalt without owning,
operating or maintaining a place of business provided in this section.
C. If the person both owns and operates distribution equipment for the products, any supplementing of
regular dealers’ own distribution equipment shall be, by a long-term lease agreement and not an ad hoc
or Agreement-by-Agreement basis. Packagers, brokers, manufacturers’ representatives, or other
persons who arrange or expedite transactions are not DBE regular dealers within the meaning of this
section.
D. Materials or supplies purchased from a DBE, which is neither a manufacturer nor a regular dealer, will
be limited to the entire amount of fees or commissions charged for assistance in the procurement of the
materials and supplies, or fees or transportation charges for the delivery of materials or supplies required
on the job site, provided the fees are reasonable and not excessive as compared with fees charged for
similar services.
Page 52 154
/RFDO $VVLVWDQFH3URFHGXUHV 0DQXDO([KLELW 2
&RQVXOWDQW3URSRVDO'%( &RPPLWPHQW
(;+,%,72&2168/7$17352326$/'%(&200,70(17
/RFDO $JHQF\ &RQWUDFW '%( *RDO
3URMHFW 'HVFULSWLRQ
3URMHFW /RFDWLRQ
&RQVXOWDQW
V 1DPH 3ULPH&HUWLILHG'%(
'HVFULSWLRQRI:RUN6HUYLFHRU 0DWHULDOV
6XSSOLHG
'%(
&HUWLILFDWLRQ
1XPEHU
/RFDO$JHQF\ WR &RPSOHWHWKLV6HFWLRQ
/RFDO $JHQF\ &RQWUDFW 1XPEHU
)HGHUDO$LG3URMHFW1XPEHU
3URSRVHG&RQWUDFW ([HFXWLRQ'DWH
&RQVXOWDQW¶V 5DQNLQJDIWHU(YDOXDWLRQ BBBBBBBBBBBBBBBBBBBBBBBBBB
/RFDO$JHQF\FHUWLILHV WKDW DOO '%( FHUWLILFDWLRQV DUHYDOLGDQGLQIRUPDWLRQRQ
WKLV IRUP LVFRPSOHWHDQGDFFXUDWH
'%(&RQWDFW ,QIRUPDWLRQ
727$/ &/$,0(''%(3$57,&,3$7,21
'%(
,03257$17 ,GHQWLI\DOO'%(ILUPVEHLQJFODLPHGIRU FUHGLW
UHJDUGOHVVRI WLHU:ULWWHQ FRQILUPDWLRQRI HDFK OLVWHG'%( LV
UHTXLUHG
3UHSDUHU
V 6LJQDWXUH 'DWH
3UHSDUHU
V 1DPH 3KRQH
3UHSDUHU
V 7LWOH
',675,%87,21 2ULJLQDO±,QFOXGHG ZLWKFRQVXOWDQW¶VSURSRVDOWRORFDO DJHQF\
$'$1RWLFH)RU LQGLYLGXDOVZLWKVHQVRU\ GLVDELOLWLHV WKLVGRFXPHQW LV DYDLODEOHLQDOWHUQDWHIRUPDWV )RU LQIRUPDWLRQFDOO RU 7''
RUZULWH5HFRUGVDQG)RUPV 0DQDJHPHQW 16WUHHW 06 6DFUDPHQWR &$
/33 3DJHRI
-DQXDU\
Construction Management and Inspection Services for Princeton Avenue Improvement Project
11%City of Moorpark
Princeton Avenue, between Spring Road and Condor Drive, in the City of Moorpark
✔FCG Consultants, Inc.
Construction Management & Inspection
Land Surveying Services
46140
9094
C0020
HSIPL-5436(018)
69.21
1.59
70.80
01/13/2022
714-312-0317Maha Alfakhouri
President / CEO
0DKD$OIDNKRXUL3UHVLGHQW)&*&RQVXOWDQWV
6DYL5DQFK3NZ\6XLWH*
<RUED/LQGD&$
6WHSKDQLH:DJQHU3UHVLGHQW:DJQHU(QJLQHHULQJ
'HYRQVKLUH6W6XLWH
1RUWKULGJH&$
3UHSDUHU
V 6LJQDWXUH
Page 53 155
/RFDO$VVLVWDQFH3URFHGXUHV0DQXDO([KLELW2
&RQVXOWDQW&RQWUDFW'%(&RPPLWPHQW
(;+,%,72&2168/7$17&2175$&7'%(&200,70(17
/RFDO$JHQF\ &RQWUDFW'%(*RDO
3URMHFW'HVFULSWLRQ
3URMHFW/RFDWLRQ
&RQVXOWDQW
V1DPH 3ULPH&HUWLILHG'%(7RWDO&RQWUDFW$ZDUG$PRXQW
7RWDO'ROODU$PRXQWIRU$//6XEFRQVXOWDQWV 7RWDO1XPEHURI$//6XEFRQVXOWDQWV
'HVFULSWLRQRI:RUN6HUYLFHRU0DWHULDOV
6XSSOLHG
'%(
&HUWLILFDWLRQ
1XPEHU
'%(&RQWDFW,QIRUPDWLRQ
'%(
'ROODU
$PRXQW
/RFDO$JHQF\WR&RPSOHWHWKLV6HFWLRQ
727$/&/$,0(''%(3$57,&,3$7,21
/RFDO$JHQF\&RQWUDFW
1XPEHU
)HGHUDO$LG3URMHFW1XPEHU
&RQWUDFW([HFXWLRQ
'DWH
/RFDO$JHQF\FHUWLILHVWKDWDOO'%(FHUWLILFDWLRQVDUHYDOLGDQGLQIRUPDWLRQRQ
WKLVIRUPLVFRPSOHWHDQGDFFXUDWH
/RFDO$JHQF\5HSUHVHQWDWLYH
V6LJQDWXUH 'DWH
/RFDO$JHQF\5HSUHVHQWDWLYH
V1DPH 3KRQH
/RFDO$JHQF\5HSUHVHQWDWLYH
V7LWOH
,03257$17,GHQWLI\DOO'%(ILUPVEHLQJFODLPHGIRUFUHGLW
UHJDUGOHVVRIWLHU:ULWWHQFRQILUPDWLRQRIHDFKOLVWHG'%(LV
UHTXLUHG
3UHSDUHU
V6LJQDWXUH 'DWH
3UHSDUHU
V1DPH 3KRQH
3UHSDUHU
V7LWOH
',675,%87,21 2ULJLQDO±/RFDO$JHQF\
&RS\±&DOWUDQV'LVWULFW/RFDO$VVLVWDQFH(QJLQHHU'/$()DLOXUHWRVXEPLWWR'/$(ZLWKLQGD\VRIFRQWUDFW
H[HFXWLRQPD\UHVXOWLQGHREOLJDWLRQRIIHGHUDOIXQGVRQFRQWUDFW
$'$1RWLFH)RULQGLYLGXDOVZLWKVHQVRU\GLVDELOLWLHVWKLVGRFXPHQWLVDYDLODEOHLQDOWHUQDWHIRUPDWV )RULQIRUPDWLRQFDOORU7''
RUZULWH5HFRUGVDQG)RUPV0DQDJHPHQW16WUHHW066DFUDPHQWR&$
3DJHRI
-XO\
Construction Management and Inspection Services for Princeton Avenue Improvement Project
City of Moorpark 11%
Princeton Avenue, between Spring Road and Condor Drive, in the City of Moorpark
FCG Consultants, Inc ✔TBD
C0020
HSIPL-5436(018)
01/13/2022
Maha Alfakhouri 714-312-0317
President / CEO
&RQVWUXFWLRQ0DQDJHPHQW ,QVSHFWLRQ
0DKD$OIDNKRXUL3UHVLGHQW)&*&RQVXOWDQWV
6DYL5DQFK3NZ\6XLWH*
<RUED/LQGD&$
/DQG6XUYH\LQJ6HUYLFHV
6WHSKDQLH:DJQHU3UHVLGHQW:DJQHU(QJLQHHULQJ
'HYRQVKLUH6W6XLWH
1RUWKULGJH&$
3UHSDUHU
V 6LJQDWXUH
Page 54 156
/RFDO$VVLVWDQFH3URFHGXUHV0DQXDO(;+%,74
'LVFORVXUHRI/REE\LQJ$FWLYLWLHV
(;+,%,74',6&/2685(2)/2%%<,1*$&7,9,7,(6
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352
1.Type of Federal Action:2.Status of Federal Action:3.Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post-award
d. loan For Material Change Only:
e. loan guarantee year ____ quarter _________
f. loan insurance date of last report __________
4.Name and Address of Reporting Entity 5.If Reporting Entity in No. 4 is Subawardee,
Enter Name and Address of Prime:
Prime Subawardee
Tier _______ , if known
Congressional District, if known Congressional District, if known
6.Federal Department/Agency:7.Federal Program Name/Description:
CFDA Number, if applicable ____________________
8.Federal Action Number, if known:9.Award Amount, if known:
10.Name and Address of Lobby Entity 11.Individuals Performing Services
(If individual, last name, first name, MI)(including address if different from No. 10)
(last name, first name, MI)
(attach Continuation Sheet(s) if necessary)
12.Amount of Payment (check all that apply)14.Type of Payment (check all that apply)
$ _____________ actual planned a. retainer
b. one-time fee
13.Form of Payment (check all that apply):c. commission
a. cash d. contingent fee
b. in-kind; specify: nature _______________e deferred
Value _____________ f. other, specify _________________________
15.Brief Description of Services Performed or to be performed and Date(s) of Service, including
officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 12:
(attach Continuation Sheet(s) if necessary)
16.Continuation Sheet(s) attached: Yes No
17.Information requested through this form is authorized by Title
31 U.S.C. Section 1352. This disclosure of lobbying reliance
was placed by the tier above when his transaction was made or
entered into. This disclosure is required pursuant to 31 U.S.C.
1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any
person who fails to file the required disclosure shall be subject
to a civil penalty of not less than $10,000 and not more than
$100,000 for each such failure.
Signature: ________________________________________
Print Name: _______________________________________
Title: ____________________________________________
Telephone No.: ____________________ Date:___________
Authorized for Local Reproduction
Federal Use Only: Standard Form - LLL
Standard Form LLL Rev. 04-28-06
Distribution: Orig- Local Agency Project Files
Page 1
/330D\
Maha Alfakhouri
President / CEO
714-312-0317 1/13/22
1RW$SSOLFDEOH
plann
apply):
____
uation
ed
(la
Sheet(s) if nece
4.
Individu
includi
t name, fir
______________________
Page 55 157
/RFDO$VVLVWDQFH3URFHGXUHV0DQXDO(;+%,74
'LVFORVXUHRI/REE\LQJ$FWLYLWLHV
(;+,%,74',6&/2685(2)/2%%<,1*$&7,9,7,(6
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352
1.Type of Federal Action:2.Status of Federal Action:3.Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post-award
d. loan For Material Change Only:
e. loan guarantee year ____ quarter _________
f. loan insurance date of last report __________
4.Name and Address of Reporting Entity 5.If Reporting Entity in No. 4 is Subawardee,
Enter Name and Address of Prime:
Prime Subawardee
Tier _______ , if known
Congressional District, if known Congressional District, if known
6.Federal Department/Agency:7.Federal Program Name/Description:
CFDA Number, if applicable ____________________
8.Federal Action Number, if known:9.Award Amount, if known:
10.Name and Address of Lobby Entity 11.Individuals Performing Services
(If individual, last name, first name, MI)(including address if different from No. 10)
(last name, first name, MI)
(attach Continuation Sheet(s) if necessary)
12.Amount of Payment (check all that apply)14.Type of Payment (check all that apply)
$ _____________ actual planned a. retainer
b. one-time fee
13.Form of Payment (check all that apply):c. commission
a. cash d. contingent fee
b. in-kind; specify: nature _______________e deferred
Value _____________ f. other, specify _________________________
15.Brief Description of Services Performed or to be performed and Date(s) of Service, including
officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 12:
(attach Continuation Sheet(s) if necessary)
16.Continuation Sheet(s) attached: Yes No
17.Information requested through this form is authorized by Title
31 U.S.C. Section 1352. This disclosure of lobbying reliance
was placed by the tier above when his transaction was made or
entered into. This disclosure is required pursuant to 31 U.S.C.
1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any
person who fails to file the required disclosure shall be subject
to a civil penalty of not less than $10,000 and not more than
$100,000 for each such failure.
Signature: ________________________________________
Print Name: _______________________________________
Title: ____________________________________________
Telephone No.: ____________________ Date:___________
Authorized for Local Reproduction
Federal Use Only: Standard Form - LLL
Standard Form LLL Rev. 04-28-06
Distribution: Orig- Local Agency Project Files
Page 1
/330D\
1RW$SSOLFDEOHWR:6386$,QF
____________________________________
Derich Sukow, PE
Construction Services District Manager
(714) 721-4229 1/13/22
✔
Page 56 158
/RFDO$VVLVWDQFH3URFHGXUHV0DQXDO(;+%,74
'LVFORVXUHRI/REE\LQJ$FWLYLWLHV
(;+,%,74',6&/2685(2)/2%%<,1*$&7,9,7,(6
COMPLETE THIS FORM TO DISCLOSE LOBBYING ACTIVITIES PURSUANT TO 31 U.S.C. 1352
1.Type of Federal Action:2.Status of Federal Action:3.Report Type:
a. contract a. bid/offer/application a. initial
b. grant b. initial award b. material change
c. cooperative agreement c. post-award
d. loan For Material Change Only:
e. loan guarantee year ____ quarter _________
f. loan insurance date of last report __________
4.Name and Address of Reporting Entity 5.If Reporting Entity in No. 4 is Subawardee,
Enter Name and Address of Prime:
Prime Subawardee
Tier _______ , if known
Congressional District, if known Congressional District, if known
6.Federal Department/Agency:7.Federal Program Name/Description:
CFDA Number, if applicable ____________________
8.Federal Action Number, if known:9.Award Amount, if known:
10.Name and Address of Lobby Entity 11.Individuals Performing Services
(If individual, last name, first name, MI)(including address if different from No. 10)
(last name, first name, MI)
(attach Continuation Sheet(s) if necessary)
12.Amount of Payment (check all that apply)14.Type of Payment (check all that apply)
$ _____________ actual planned a. retainer
b. one-time fee
13.Form of Payment (check all that apply):c. commission
a. cash d. contingent fee
b. in-kind; specify: nature _______________e deferred
Value _____________ f. other, specify _________________________
15.Brief Description of Services Performed or to be performed and Date(s) of Service, including
officer(s), employee(s), or member(s) contacted, for Payment Indicated in Item 12:
(attach Continuation Sheet(s) if necessary)
16.Continuation Sheet(s) attached: Yes No
17.Information requested through this form is authorized by Title
31 U.S.C. Section 1352. This disclosure of lobbying reliance
was placed by the tier above when his transaction was made or
entered into. This disclosure is required pursuant to 31 U.S.C.
1352. This information will be reported to Congress
semiannually and will be available for public inspection. Any
person who fails to file the required disclosure shall be subject
to a civil penalty of not less than $10,000 and not more than
$100,000 for each such failure.
Signature: ________________________________________
Print Name: _______________________________________
Title: ____________________________________________
Telephone No.: ____________________ Date:___________
Authorized for Local Reproduction
Federal Use Only: Standard Form - LLL
Standard Form LLL Rev. 04-28-06
Distribution: Orig- Local Agency Project Files
Page 1
/330D\
______________________________________
Stephanie A. Wagner
President
818-892-6565 12/28/21
Page 57 159
Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort
EXHIBIT 15-H: PROPOSER/CONTRACTOR GOOD FAITH EFFORTS
Cost Proposal Due Date ___________________ PE/CE
Federal-aid Project No(s). _____________________ Bid Opening Date ___________________ CON
The established a Disadvantaged Business Enterprise (DBE) goal of
_____Bfor this contract. The information provided herein shows the required good faith efforts to meet or exceed
the DBE contract goal.
Proposers or bidders submit the following information to document their good faith efforts within five (5) calendar
days from cost proposal due date or bid opening. Proposers and bidders are recommended to submit the
following information even if the Exhibit 10-O1: Consultant Proposal DBE Commitments or Exhibit 15-G:
Construction Contract DBE Commitment indicate that the proposer or bidder has met the DBE goal. This form
protects the proposer’s or bidder’s eligibility for award of the contract if the administering agency determines that
the bidder failed to meet the goal for various reasons, e.g., a DBE firm was not certified at bid opening, or the
bidder made a mathematical error.
The following items are listed in the Section entitled “Submission of DBE Commitment” of the Special Provisions,
please attach additional sheets as needed:
A. The names and dates of each publication in which a request for DBE participation for this
project was placed by the bidder (please attach copies of advertisements or proofs of
publication):
Publications Dates of Advertisement
B. The names and dates of written notices sent to certified DBEs soliciting bids for this project and
the dates and methods used for following up initial solicitations to determine with certainty whether the
DBEs were interested (please attach copies of solicitations, telephone records, fax confirmations, etc.):
Names of DBEs Solicited Date of Initial Solicitation Follow Up Methods and Dates
Page 1 of 3
May 2020
01/13/2022
HSIPL-5436(018)
City of Moorpark
11.00%
Not Applicable. FCG Consultants, Inc. is DBE Certified
Not Applicable
Page 58 160
Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort
C. The items of work made available to DBE firms including those unbundled contract work items
into economically feasible units to facilitate DBE participation. It is the bidder's responsibility to
demonstrate that sufficient work to facilitate DBE participation in order to meet or exceed the DBE
contract goal.
Items of Proposer or Bidder Breakdown of Amount Percentage
Work Normally Performs Item Items ($) Of
(Y/N) Contract
D. The names, addresses and phone numbers of rejected DBE firms, the reasons for the bidder's
rejection of the DBEs, the firms selected for that work (please attach copies of quotes from the firms
involved), and the price difference for each DBE if the selected firm is not a DBE:
Names, addresses and phone numbers of rejected DBEs and the reasons for the bidder's rejection of
the DBEs:
Names, addresses and phone numbers of firms selected for the work above:
E. Efforts (e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining
information related to the plans, specifications and requirements for the work which was
provided to DBEs:
Page 2 of 3
May 2020
No 0.00%Mileage Costs
0.00%No
0.00%
No
Equipment Rental
0.00%Permit Fees
NoPlan Sheets
1RQH
1RQH
1RW$SSOLFDEOH
1RQH
Page 59 161
Local Assistance Procedures Manual Exhibit 15-H
Proposer/Contractor Good Faith Effort
F. Efforts (e.g. in advertisements and solicitations) made to assist interested DBEs in obtaining
bonding, lines of credit or insurance, necessary equipment, supplies, materials, or related assistance or
services, excluding supplies and equipment the DBE subcontractor purchases or leases from the prime
contractor or its affiliate:
G. The names of agencies, organizations or groups contacted to provide assistance in contacting,
recruiting and using DBE firms (please attach copies of requests to agencies and any responses
received, i.e., lists, Internet page download, etc.):
Name of Agency/Organization Method/Date of Contact Results
H. Any additional data to support a demonstration of good faith efforts:
Page 3 of 3
May 2020
1RW$SSOLFDEOH
1RW$SSOLFDEOH
1RW$SSOLFDEOH
Page 60 162
NON-COLLUSION AFFIDAVIT
(Title 23 United States Code Section 112 and
Public Contract Code Section 7106)
To the CITY of MOORPARK
DEPARTMENT OF PUBLIC WORKS
CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR SPEC NO.
MPK 21-03M, HSIPL-5436(018), PRINCETON AVENUE IMPROVEMENT PROJECT
In accordance with Title 23 United States Code Section 112 and Public Contract Code
7106 the bidder declares that the bid is not made in the interest of, or on behalf of, any
undisclosed person, partnership, company, association, organization, or corporation; that
the bid is genuine and not collusive or sham; that the bidder has not directly or indirectly
induced or solicited any other bidder to put in a false or sham bid, and has not directly or
indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put
in a sham bid, or that anyone shall refrain from bidding; that the bidder has not in any
manner, directly or indirectly, sought by agreement, communication, or conference with
anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit,
or cost element of the bid price, or of that of any other bidder, or to secure any advantage
against the public body awarding the contract of anyone interested in the proposed
contract; that all statements contained in the bid are true; and, further, that the bidder has
not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the
contents thereof, or divulged information or data relative thereto, or paid, and will not pay,
any fee to any corporation, partnership, company association, organization, bid
depository, or to any member or agent thereof to effectuate a collusive or sham bid.
Firm Name:
Signature:
Name and Title:
Date:
Notes: Providing false information may result in criminal prosecution or administrative
sanctions. The above certification is part of the Proposal.
FCG Consultants, Inc.
Maha Alfakhouri, President / CEO
1/13/2022
Page 61 163
NON-LOBBYING CERTIFICATION FOR FEDERAL-AID CONTRACTS
CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR SPEC NO.
MPK 21-03M, HSIPL-5436(018), PRINCETON AVENUE IMPROVEMENT PROJECT
The prospective participant certifies, by signing and submitting this bid or proposal, to the
best of his or her knowledge and belief, that:
(l) No federal appropriated funds have been paid or will be paid, by or on behalf of
the undersigned, to any person for influencing or attempting to influence an officer
or employee of any federal agency, a Member of Congress, an officer or employee
of Congress, or an employee of a Member of Congress in connection with the
awarding of any federal contract, the making of any federal grant, the making of
any federal loan, the entering into of any cooperative agreement, and the
extension, continuation, renewal, amendment, or modification of any federal
contract, grant, loan, or cooperative agreement.
(2) If any funds other than federal appropriated funds have been paid or will be paid
to any person for influencing or attempting to influence an officer or employee of
any federal agency, a Member of Congress, an officer or employee of Congress,
or an employee of a Member of Congress in connection with this federal contract,
grant, loan, or cooperative agreement, the undersigned shall complete and submit
Standard Form-LLL, "Disclosure of Lobbying Activities," in accordance with its
instructions.
This certification is a material representation of fact upon which reliance was placed when
this transaction was made or entered into. Submission of this certification is a prerequisite
for making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code.
Any person who fails to file the required certification shall be subject to a civil penalty of
not less than $10,000 and not more than $100,000 for each such failure.
The prospective participant also agrees by submitting his or her bid or proposal that he
or she shall require that the language of this certification be included in all lower tier
subcontracts, which exceed $100,000 and that all such sub recipients shall certify and
disclose accordingly.
Firm Name:
Signature:
Name and Title:
Date:
Notes: Providing false information may result in criminal prosecution or administrative sanctions. The
above certification is part of the Proposal.
FCG Consultants, Inc.
Maha Alfakhouri, President / CEO
1/13/2022
Page 62 164
DEBARMENT AND SUSPENSION CERTIFICATION
TITLE 49, CODE OF FEDERAL REGULATIONS, PART 29
CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES FOR SPEC NO.
MPK 21-03M, HSIPL-5436(018), PRINCETON AVENUE IMPROVEMENT PROJECT
The bidder, under penalty of perjury, certifies that, except as noted below, the bidder or
any other person associated therewith in the capacity of owner, partner, director, officer,
and manager:
Is not currently under suspension, debarment, voluntary exclusion, or
determination of ineligibility by any federal agency;
Has not been suspended, debarred, voluntarily excluded or determined ineligible
by any federal agency within the past three (3) years;
Does not have a proposed debarment pending; and
Has not been indicted, convicted, or had a civil judgment rendered against it by a
court of competent jurisdiction in any matter involving fraud or official misconduct
within the past three (3) years.
If there are any exceptions to this certification, insert the exceptions in the following space.
Exceptions will not necessarily result in denial of award, but will be considered in
determining bidder’s responsibility. For any exception noted above, indicate below to
whom it applies, initiating agency, and dates of action.
Firm Name:
Signature:
Name and Title:
Date:
Notes: Providing false information may result in criminal prosecution or administrative
sanctions. The above certification is part of the Proposal.
FCG Consultants, Inc.
Maha Alfakhouri, President / CEO
1/13/2022
Page 63 165
SECTION 9: COST PROPOSAL
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
COST PROPOSAL
The cost proposal is being provided in a separate envelope in printed copy and in digital copy.
Page 64 166
City of Moorpark RFP for
Construction Management and Inspection Services for
Spec. No MPK 21‐03; HSIPL‐5436(018)
Princeton Avenue Improvement Project
APPENDIX
ADDENDA ACKNOWLEDGEMENT
FCG acknowledges receiving Addendum No. 1 dated December 23rd, 2021, and Addendum No. 2 dated January 7th, 2022. The
signed acknowledgements are provided on the following pages.
Page 65 167
Page 66 168
FCG Consultants, Inc.
Maha Alfakhouri
Page 67 169
CITY OF MOORPARK
JANICE S. PARVIN
Mayor
DR. ANTONIO CASTRO
Councilmember
CHRIS ENEGREN
Councilmember
DANIEL GROFF
Councilmember
DAVID POLLOCK
Councilmember
PUBLIC WORKS DEPARTMENT | 799 Moorpark Avenue, Moorpark, California 93021
Main City Phone Number (805) 517-6200 | Fax (805) 532-2555 | moorpark@moorparkca.gov
January 7, 2022
ADDENDUM NO. 2
for Request for Proposals for Construction Management and Inspection Services
Specification No. MPK 21-03, HSIPL-5436(018)
Princeton Avenue Improvement Project
There is no change to the proposal due date January 13, 2022, at 3:00 p.m.
NOTICE IS HEREBY GIVEN to all prospective proposers that the following changes,
clarifications, and additions are made part of the Notice of a Request for Proposals for the above
referenced project and shall be taken into account in the preparation of all proposals and the
execution of all work. The changes, clarifications, and/or additions to the Request for Proposals
are as follows:
1. Addendum No. 2 for Specification No. MPK 21-03, HSIPL-5436(018), Princeton Avenue
Improvement Project, has been issued on the city’s website.
https://www.moorparkca.gov/bids.aspx?bidID=95
2. The following are responses to formal inquiries. The City will not be accepting any more
pre-proposal questions.
Question 1: Due to the COVID-19/Coronavirus pandemic, the anticipated spread of
Omicron, and related public health directives from state and local authorities,
and in light of recent challenges impacting the reliability of postal services,
will the City consider accepting electronic submissions only?
We have submitted similar cost proposals to other agencies where we
provide the cost proposal file as a password protected file where the
password can be provided upon request and can do the same if the City is
open to this option.
Will the City entertain an electronic submission for this project?
Response 1: The City is not accepting electronic only submissions. Please
submit both hard copies and the requested digital files.
[End of Changes]
Page 68 170
Princeton Avenue Improvement Project
Construction Management and Inspection Services
RFP Addendum No. 2
Page 2
This addendum shall be made part of the above referenced project. Full compensation for all
work and requirements of this addendum shall be considered as included in the appropriate
technical and cost proposals and no additional compensation will be allowed, therefore.
__
Daniel Kim, P.E., City Engineer/Public Works Director
Questions regarding this addendum may be directed to Daniel Kim at (805) 517-6255.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM BY ATTACHING A SIGNED COPY OF THIS
ADDENDUM WITH YOUR BID PROPOSAL. FAILURE TO DO SO MAY RESULT IN
DISQUALIFICATION OF YOUR BID.
Company Name:
Authorized Representative:
Signature of Authorized Representative: ___________________________________________
FCG Consultants, Inc.
Maha Alfakhouri, President / CEO
Page 69 171
22885 Savi Ranch Parkway, Suite G
Yorba Linda, California 92887
Tele | 714.312.0317
Fax | 714.312.0793
www.fcgconsultants.com
Grade Separations
Railroad
Transit
Highways
Freeways
Bridges
Water Lines
Sewer Lines
Wastewater
Street Lighting
Signalized Intersections
Fiber Optics
Landscape
Hardscape
Striping
SWPPP
Capital Improvements
Public Works
Transportation
Design‐Build
CMGC
Ports
Airports
School Districts
Trusted
Partner
for
Construction
Management
and Inspection
Services
172
FCG Consultants Inc. - DBE City of Moorpark
Construction Management & Inspection Services
Revised Cost Proposal - February 16, 2022
Classification Hours Hourly Rate Cost
Pre-construction Phase (40 Working Days)
Resident Engineer 80 231.68$ 18,534.12$
Office Engineer 40 97.55$ 3,901.92$
Subtotal 120 22,436.04$
Construction Phase (375 Days)
2022
Resident Engineer 750 231.68$ 173,757.38$
Construction Inspector - 1 1500 146.32$ 219,483.00$
Construction Inspector - 2 168 146.32$ 24,582.10$
Office Engineer 375 97.55$ 36,580.50$
2023
Resident Engineer 750 233.99$ 175,494.95$
Construction Inspector - 1 1500 147.79$ 221,677.83$
Construction Inspector - 2 176 147.79$ 26,010.20$
Office Engineer 375 98.52$ 36,946.31$
Subtotal 2,793 914,532.25$
Post-Construction Phase (40 Working Days)
Resident Engineer 80 233.99$ 18,719.46$
Office Engineer 40 98.52$ 3,940.94$
Subtotal 120 22,660.40$
Misc. Expenses Months Monthly Cost Total
Vehicles 18 -$ -$
Labtops 18 -$ -$
Cell Phones 18 -$ -$
Office Supplies 18 -$ -$
Field Office 18 -$ -$
Subtotal -$
FCG Total DBE %65.93%959,628.69$
Subconsultants
Structures Rep. & Scheduler - WSP 255,664.90$
Materials Testing - Twining 86,759.02$
Wagner Engineering (DBE) - Surveying DBE %1.76%25,562.99$
Bio. Monitoring - HES 127,868.05$
Subtotal 495,854.96$
1,455,483.65$
DBE Commitment Contract Goal 11.00%
FCG Commitment 67.69%
Limitations & Conditions:
Construction duration is estimated at 375 working days with time for preconstruction & time for closeout phase.10.28%
Inspectors will be fully equipped with vehicles, computers, and tools and equipment required to perform their tasks.
Overtime and Weekend work is not included. Overtime is to be charged at 1.5 the above rate.
Cost proposal is subject to pervailing wage rates, and prvailing wage rate change for inspectors.
Misceleanous expenses includes stationeries and other items needed for CM team.
All costs are subject to negotiations.
Total Cost (NOT TO EXCEED)
Princeton Avenue Widening Project
Exhibit D
Cost Proposal
173
Project Activities Project Manager|
Resident Engineer
Structures
Representative
Lead
Inspector
Electrical
Landscape Insp.Scheduler Office Engineer
Review Baseline Schedule and Monthly Schedule Updates 8 4
Review Project Budget including anticipated Change Orders 8 4
Perform a thorough Constructability Review prior to bid 8 4
Review advertising and bid documents and analyze results 8 4
Prepare and conduct Pre-Construction and utility meetings 8 4 8 8
Prepare construction contract administration documents 8 4
Setup coordination meetings with Contractor and utilities 8 4 8 8
Review Submittals During Move-in Period 8 4
Prepare progress payments documents and quantity sheets 8 4 4 4
Monitor spending and produce funding compliance reports 8 4
Setup and maintain project records and files 12 20
80 40 0 0 32 40
Review look-ahead and updates of schedule submittal for work
activities 24 24 160 24 158
Conduct field visits prior to construction of upcoming phases 40 24 160 24
Prepare a monthly status report to the City 40 24 120 24 20
Perform SWPPP inspection and report documentation 32 16 480
Perform daily field inspection and report documentation 40 24 360
Review Contractor certified payroll and DBE participation 40 530
Review Contractor As-Built plans monthly 60 24 200 24
Communicate with other agencies and coordinate work 40 24 200 24 60
Contact and coordinate with involved utility companies 80
Review Submittals, RFI’s, and Payment and CCO requests 400 64
Coordinate lane closures with Contractor and City 40 24 240 24
Perform quality assurance of all materials to be used 40 24 240 40
Perform Air and Water Quality testing (as needed)40
Coordinate materials sampling and testing 40 40 180 16 40
Inspect and enforce Safety measures and procedures 40 40 180 16
Review Final As-Built plans 24 40 120 16
Perform quality surveying verification 80 16 120 16
Document and Log materials test results and reports 80 60
Negotiate and process change orders 160
Perform monthly cost estimates for payment and CCO’s 80 40 120 56
Monitor changes to project and document for claims 80 24 120 40 40
1500 472 3000 344 158 750
Produce first, secondary, and final punch list to Contractor 20 12 12 24
Approve final As-Builts and deliver to the City 20 12 12 8
Perform the final walk-through and accept the project 20 8 8
Produce project files and closeout forms 20 8
80 40 0 0 24 40
Total Anticipated Hours 1660 552 3000 344 214 790
Pre-Construction Tasks
During Construction Tasks
Post Construction Tasks
174
Local Assistance Procedures Manual EXHIBIT 10-H1
Cost Proposal 2022
X Prime Consultant Subconsultant 2nd Tier Subconsultant
Consultant:
Project No. Contract No.Date 2/16/2022
Hours Actual Hourly Rate Total
830.00 95.00$ 78,850.00$
1500.00 60.00$ 90,000.00$
168.00 60.00$ 10,080.00$
415.00 40.00$ 16,600.00$
LABOR COSTS
195,530.00$
-$
c) TOTAL DIRECT LABOR COSTS [(a) + (b)]195,530.00$
INDIRECT COSTS
40.76%)e) Total Fringe Benefits [(c) x (d)]79,698.03$
15.15%) included g) Overhead [(c) x (f)]29,622.80$
65.79%)i) Gen & Admin [(c) x (h)]128,639.19$
121.70%
j) TOTAL INDIRECT COSTS [(e) + (g) + (i)]237,960.01$
FIXED FEE 10.00%k)TOTAL FIXED FEE [(c) + (j)] x fixed fee:43,349.00$
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary)
Quantity Unit Unit Cost Total
-$
-$
-$
l) TOTAL OTHER DIRECT COSTS -$
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary)
255,664.90$
86,759.02$
25,562.99$
127,868.05$
m) TOTAL SUBCONSULTANTS' COSTS 495,854.96$
n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)]495,854.96$
TOTAL COST [(c) + (j) + (k) + (n)]972,693.97$
NOTES:
1.
2.
3.
Page 1 of 3
Note: Mark-ups are Not Allowed
The cost proposal format shall not be amended. Indirect cost rates shall be updated on an annual basis in accordance with the consultant's
annual accounting period and established by a cognizant agency or accepted by Caltrans.
Subconsultant 4:
d) Fringe Benefits (Rate:
f) Overhead & G&A (Rate:
h) General & Admin (Rate:
Description of Item
Subconsultant 1:
FCG Consultants, Inc.
TBD
DIRECT LABOR - 2022
Jasmine Fakhouri
Construction Inspector - 1
Office Engineer
Construction Inspector - 2 Leon Fuentes
HSIPL-5436(018)
Classification/Title Name
Project Manager / RE A.B. Fakhouri, PE
Don Lewis
Subconsultant 2:
Subconsultant 3:
Key personnel must be marked with an asterisk (*) and employees that are subject to prevailing wage requirements must be marked with two
asterisks (**). All costs must comply with the Federal cost principles. Subconsultants will provide their own cost proposals.
Anticipated salary increases calculation (page 2) must accompany.
Biological Monitoring - HES
Structures Rep. & Scheduler - WSP
Material Testing - Twining
Wagner Engineering (DBE) - Surveying
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see page 2 for calculation)
175
Consultant
Project No. Contract No.Date 2/16/2022
1. Calculate Average Hourly Rate for 1st year of the contract (Direct Labor Subtotal divided by total hours)
Avg Hourly 5 Year Contract
Rate Duration
$ 195,530.00 =67.12324065 Year 1 Avg Hourly Rate
Avg Hourly Rate
Year 1 $67.12 += $67.79 Year 2 Avg Hourly Rate
Year 2 $67.79 += $68.47 Year 3 Avg Hourly Rate
Year 3 $68.47 += $69.16 Year 4 Avg Hourly Rate
Year 4 $69.16 += $69.85 Year 5 Avg Hourly Rate
Total Hours
per Year
Year 1 75.00%*=2184.8 Estimated Hours Year 1
Year 2 25.00%*=728.3 Estimated Hours Year 2
Year 3 0.00%*=0.0 Estimated Hours Year 3
Year 4 0.00%*=0.0 Estimated Hours Year 4
Year 5 0.00%*=0.0 Estimated Hours Year 5
Total 100%=2913.0
Year 1 $67.12 *=146647.5 Estimated Hours Year 1
Year 2 $67.79 *= $ 49,371.33 Estimated Hours Year 2
Year 3 $68.47 *= $- Estimated Hours Year 3
Year 4 $69.16 *= $- Estimated Hours Year 4
Year 5 *= $- Estimated Hours Year 5
= $ 196,018.83
= $ 195,530.00
= $488.83 Transfer to Page 1
NOTES:
1.
2.
3.
4.
Page 2 of 3
Direct Labor Subtotal
FCG Consultants, Inc.
CALCUATIONS FOR ANTICIPATED SALARY INCREASES
HSIPL-5436(018)TBD
per Cost Proposal per Cost Proposal
Total Hours
Calculations for anticipated salary escalation must be provided.
This is not the only way to estimate salary increases. Other methods will be accepted if they clearly indicate the % increase, the # of years of the contract, and a breakdown of
the labor to be performed each year.
An estimation that is based on direct labor multiplied by salary increase % multiplied by the # of years is not acceptable. (i.e. $250,000 x 2% x 5 yrs = $25,000 is not an
acceptable methodology).
This assumes that one year will be worked at the rate on the cost proposal before salary increases are granted.
Proposed Escalation
1%
1%
3. Calculate estimated hours per year (Multiply estimate % each year by total hours)
4. Calculate Total Costs including Escalation (Multiply Average Hourly Rate by the number of hours)
Total Hours
1%
2913.0
Total
1%
2913.0
Avg Hourly Rate Estimated hours
2913
2. Calculate hourly rate for all years (Increase the Average Hourly Rate for a year by proposed escalation %)
Estimated %
Cost per Year(calculated above)(calculated above)
2913.0
per Cost Proposal
2913.0
2913.0
Completed Each Year
2185
728
0
0
0
Total Direct Labor Cost with Escalation
Direct Labor Subtotal before Escalation
Estimated total of Direct Labor Salary Increase
176
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract
are actual, reasonable, allowable, and allocable to the contract in accordance with the contract terms and the following requirements:
1. Generally Accepted Accounting Principles (GAAP)
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Proceedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management and Administration of Engineering and
Design Related Service
6. 48 Ccode of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable)
All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files
and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements
are not eligible for reimbursement.
Local governments are responsible for applying only cognizant agency or Caltrans accepted Indirect Cost Rate(s).
List services the consultant is providing under the proposed contract:
Page 3 of 3
Certification of Direct Costs:
Prime Consultant or Subconsultant Certifying:
* An individual executive or financial officer of the consultant's or subconsultant's organization at a level no lower than a Vice
President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish
the cost proposal for the contract.
Name: Maha Alfakhouri
Signature: _________________________________________________
Email: maha.fakhouri@fcgconsultants.com
Title *: President / CEO
Date of Certification: 2/16/2022
Phone number: 714.312.0317
Address: 22885 Savi Ranch Pkwy, Suite G, Yorba Linda, CA 92887
Construction Management & Inspection
177
Local Assistance Procedures Manual EXHIBIT 10-H1
Cost Proposal 2021
X Prime Consultant Subconsultant 2nd Tier Subconsultant
Consultant:
Project No. Contract No.Date 2/16/2022
Hours Actual Hourly Rate Total
830.00 95.95$ 79,638.50$
1500.00 60.60$ 90,900.00$
176.00 60.60$ 10,665.60$
415.00 40.40$ 16,766.00$
LABOR COSTS
197,970.10$
-$
c) TOTAL DIRECT LABOR COSTS [(a) + (b)]197,970.10$
INDIRECT COSTS
40.76%)e) Total Fringe Benefits [(c) x (d)]80,692.61$
15.15%) included g) Overhead [(c) x (f)]29,992.47$
65.79%)i) Gen & Admin [(c) x (h)]130,244.53$
121.70%
j) TOTAL INDIRECT COSTS [(e) + (g) + (i)]240,929.61$
FIXED FEE 10.00%k)TOTAL FIXED FEE [(c) + (j)] x fixed fee:43,889.97$
l) CONSULTANT'S OTHER DIRECT COSTS (ODC) - ITEMIZE (Add additional pages if necessary)
Quantity Unit Unit Cost Total
-$
-$
-$
l) TOTAL OTHER DIRECT COSTS -$
m) SUBCONSULTANTS' COSTS (Add additional pages if necessary)
-$
-$
-$
-$
m) TOTAL SUBCONSULTANTS' COSTS -$
n) TOTAL OTHER DIRECT COSTS INCLUDING SUBCONSULTANTS [(l) + (m)]-$
TOTAL COST [(c) + (j) + (k) + (n)]482,789.68$
NOTES:
1.
2.
3.
Page 1 of 3
Subconsultant 2:Material Testing - Twining
Subconsultant 3:Wagner Engineering (DBE) - Surveying
Subconsultant 4:Biological Monitoring - HES
Key personnel must be marked with an asterisk (*) and employees that are subject to prevailing wage requirements must be marked with two
asterisks (**). All costs must comply with the Federal cost principles. Subconsultants will provide their own cost proposals.
The cost proposal format shall not be amended. Indirect cost rates shall be updated on an annual basis in accordance with the consultant's
annual accounting period and established by a cognizant agency or accepted by Caltrans.
Anticipated salary increases calculation (page 2) must accompany.
Subconsultant 1:Structures Rep. & Scheduler - WSP
Office Engineer Jasmine Fakhouri
a) Subtotal Direct Labor Costs
b) Anticipated Salary Increases (see page 2 for calculation)
d) Fringe Benefits (Rate:
f) Overhead & G&A (Rate:
h) General & Admin (Rate:
Description of Item
Field Office
Project Manager / RE A.B. Fakhouri, PE
Construction Inspector - 1 Don Lewis
Construction Inspector - 2 Leon Fuentes
Classification/Title Name
Note: Mark-ups are Not Allowed
FCG Consultants, Inc.
HSIPL-5436(018)TBD
DIRECT LABOR - 2023
178
Consultant
Project No. Contract No.Date 2/16/2022
1. Calculate Average Hourly Rate for 1st year of the contract (Direct Labor Subtotal divided by total hours)
Avg Hourly 5 Year Contract
Rate Duration
$ 197,970.10 =67.77476891 Year 1 Avg Hourly Rate
Avg Hourly Rate
Year 1 $- += $- Year 2 Avg Hourly Rate
Year 2 $- += $- Year 3 Avg Hourly Rate
Year 3 $- += $- Year 4 Avg Hourly Rate
Year 4 $- += $- Year 5 Avg Hourly Rate
Total Hours
per Year
Year 1 0.00%*=0.0 Estimated Hours Year 1
Year 2 0.00%*=0.0 Estimated Hours Year 2
Year 3 0.00%*=0.0 Estimated Hours Year 3
Year 4 0.00%*=0.0 Estimated Hours Year 4
Year 5 0.00%*=0.0 Estimated Hours Year 5
Total 0%=0.0
Year 1 $- *=0 Estimated Hours Year 1
Year 2 $- *= $- Estimated Hours Year 2
Year 3 $- *= $- Estimated Hours Year 3
Year 4 $- *= $- Estimated Hours Year 4
Year 5 *= $- Estimated Hours Year 5
= $-
= $-
= $- Transfer to Page 1
NOTES:
1.
2.
3.
4.
Page 2 of 3
Calculations for anticipated salary escalation must be provided.
0
0
0
0
0
Total Direct Labor Cost with Escalation
Direct Labor Subtotal before Escalation
Estimated total of Direct Labor Salary Increase
This is not the only way to estimate salary increases. Other methods will be accepted if they clearly indicate the % increase, the # of years of the contract, and a breakdown of
the labor to be performed each year.
An estimation that is based on direct labor multiplied by salary increase % multiplied by the # of years is not acceptable. (i.e. $250,000 x 2% x 5 yrs = $25,000 is not an
acceptable methodology).
This assumes that one year will be worked at the rate on the cost proposal before salary increases are granted.
0.0
Total
4. Calculate Total Costs including Escalation (Multiply Average Hourly Rate by the number of hours)
Avg Hourly Rate Estimated hours Cost per Year(calculated above)(calculated above)
0.0
1%
1%
3. Calculate estimated hours per year (Multiply estimate % each year by total hours)
Estimated % Total Hours
Completed Each Year per Cost Proposal
0.0
0.0
0.0
1%
Direct Labor Subtotal Total Hours
per Cost Proposal per Cost Proposal
2921
2. Calculate hourly rate for all years (Increase the Average Hourly Rate for a year by proposed escalation %)
Proposed Escalation
0%
HSIPL-5436(018)TBD
CALCUATIONS FOR ANTICIPATED SALARY INCREASES
FCG Consultants, Inc.
179
I, the undersigned, certify to the best of my knowledge and belief that all direct costs identified on the cost proposal(s) in this contract
are actual, reasonable, allowable, and allocable to the contract in accordance with the contract terms and the following requirements:
1. Generally Accepted Accounting Principles (GAAP)
2. Terms and conditions of the contract
3. Title 23 United States Code Section 112 - Letting of Contracts
4. 48 Code of Federal Regulations Part 31 - Contract Cost Principles and Proceedures
5. 23 Code of Federal Regulations Part 172 - Procurement, Management and Administration of Engineering and
Design Related Service
6. 48 Ccode of Federal Regulations Part 9904 - Cost Accounting Standards Board (when applicable)
All costs must be applied consistently and fairly to all contracts. All documentation of compliance must be retained in the project files
and be in compliance with applicable federal and state requirements. Costs that are noncompliant with the federal and state requirements
are not eligible for reimbursement.
Local governments are responsible for applying only cognizant agency or Caltrans accepted Indirect Cost Rate(s).
List services the consultant is providing under the proposed contract:
Page 3 of 3
Certification of Direct Costs:
Prime Consultant or Subconsultant Certifying:
Name: Maha Alfakhouri Title *: President / CEO
Signature: _________________________________________________Date of Certification: 2/16/2022
Email: maha.fakhouri@fcgconsultants.com Phone number: 714.312.0317
Address: 22885 Savi Ranch Pkwy, Suite G, Yorba Linda, CA 92887
* An individual executive or financial officer of the consultant's or subconsultant's organization at a level no lower than a Vice
President or a Chief Financial Officer, or equivalent, who has authority to represent the financial information utilized to establish
the cost proposal for the contract.
Construction Management & Inspection
180
Local Assistance Procedures Manual EXHIBIT 10-H2
Cost Proposal
EXHIBIT 10-H2 COST PROPOSAL Page 1 of 3
SPECIFIC RATE OF COMPENSATION (USE FOR ON-CALL OR AS-NEEDED CONTRACTS)
(CONSTRUCTION ENGINEERING AND INSPECTION CONTRACTS)
Note: Mark-ups are Not Allowed
Consultant - FCG Consultants, Inc.
RE: Princeton Avenue Improvement Project X PRIME Consultant ☐Subconsultant ☐2nd Tier Subconsultant
Project No. HSIPL-5436(018)Contract No. TBD Participation Amount Date 2/16/2022
Fringe Benefits %Overhead %G & A %ICR%
For Combined Rate 40.76%+15.15%+65.79%=121.70%
For Home Office Rate 40.76%+15.15%+65.79%=121.70%
For Field Office Rate 40.76%+15.15%+65.79%=121.70%
Fee %=10.000%
BILLING INFORMATION CALCULATION INFORMATION
*Actual/% or $
average Increase
Straight OT OT From To hourly rate
(1.5 X)(2.0 X)
A.B. Fakhouri* **231.68$ 231.68$ 231.68$ 1/13/22 12/31/22 95.00$ 0.0%
Role 233.99$ 233.99$ 233.99$ 1/1/23 12/31/23 95.95$ 1.0%
236.33$ 236.33$ 236.33$ 1/1/24 12/31/24 96.91$ 1.0%
Non-Exempt If extension granted Year 4 238.70$ 238.70$ 238.70$ 1/1/25 12/31/25 97.88$ 1.0%
If extension granted Year 5 238.70$ 238.70$ 238.70$ 1/1/26 12/31/26 98.86$ 1.0%
Don Lewis* **146.32$ 146.32$ 146.32$ 1/13/22 12/31/22 60.00$ 0.0%
147.79$ 147.79$ 147.79$ 1/1/23 12/31/23 60.60$ 1.0%
149.26$ 149.26$ 149.26$ 1/1/24 12/31/24 61.21$ 1.0%
Non-Exempt If extension granted Year 4 150.76$ 150.76$ 150.76$ 1/1/25 12/31/25 61.82$ 1.0%
If extension granted Year 5 152.26$ 150.76$ 150.76$ 1/1/26 12/31/26 62.44$ 1.0%
Leon Fuentes* **146.32$ 60.00$ 60.00$ 1/13/22 12/31/22 60.00$ 0.0%
147.79$ 60.60$ 60.60$ 1/1/23 12/31/23 60.60$ 1.0%
149.26$ 61.21$ 61.21$ 1/1/24 12/31/24 61.21$ 1.0%
Non-Exempt If extension granted Year 4 150.76$ 61.82$ 61.82$ 1/1/25 12/31/25 61.82$ 1.0%
If extension granted Year 5 152.26$ 61.82$ 61.82$ 1/1/26 12/31/26 62.44$ 1.0%
Jasmine Fakhouri * **97.55$ 146.32$ 195.10$ 1/13/22 12/31/22 40.00$ 0.0%
98.52$ 147.79$ 197.05$ 1/1/23 12/31/23 40.40$ 1.0%
99.51$ 149.26$ 199.02$ 1/1/24 12/31/24 40.80$ 1.0%
Non-Exempt If extension granted Year 4 100.50$ 150.76$ 201.01$ 1/1/25 12/31/25 41.21$ 1.0%
If extension granted Year 5 100.50$ 152.26$ 201.01$ 1/1/26 12/31/26 41.62$ 1.0%
Page 1 of 3
January 2020
Not Applicable
Not Applicable
Not Applicable
Name/Job Title/Classification
Hourly Billing Rate Effective Date of Hourly Rate
Hourly range for class
Not Applicable
NOTES:
1.Key personnel must be marked with an asterisk (*) and employees that are subject to prevailing wage requirements must be marked with two asterisks (**).All costs must comply with the Federal cost principles.
Subconsultants will provide their own cost proposals.
2.The cost proposal format shall not be amended.
3.Billing rate = actual hourly rate * (1+ ICR) * (1+ Fee). Indirect cost rates shall be updated on an annual basis in accordance with the consultant‘s annual accounting period and established by a cognizant agency
or accepted by Caltrans. All costs must comply with the Federal cost principles for reimbursement.
4.For named employees and key personnel enter the actual hourly rate. For classifications only, enter the Average Hourly Rate for that classification.
181