D. Consider the Notice of Completion for the 2021 Sidewalk Rehabilitation Project
(CIP Project No. M0050) Specification No. MPK 21-01 and Authorization for
Release of Project Bonds in Accordance with the Contract Provisions. Staff
Recommendation: 1) Accept completion of the 2021 Sidewalk Rehabilitation
Project, (CIP Project No. M0050) Specification No. MPK 21-01, and authorize the
City Clerk to file the Notice of Completion with the Ventura County Recorder’s
Office; and 2) Authorize the City Clerk to release the Faithful Performance and
Material Suppliers and Laborers Bond, Bond No. RCB0031252, one year after the
date of recordation of the Notice of Completion. (Staff: Daniel Kim, City
Engineer/Public Works Director)
Item: 10.D.
MOORPARK CITY COUNCIL
AGENDA REPORT
TO: Honorable City Council
FROM: Daniel Kim, City Engineer/Public Works Director
Ariane Quizon, Assistant Engineer
DATE: 04/06/2022 Regular Meeting
SUBJECT: Consider the Notice of Completion for the 2021 Sidewalk
Rehabilitation Project (CIP Project No. M0050) Specification No. MPK
21-01 and Authorization for Release of Project Bonds in Accordance
with the Contract Provisions
BACKGROUND
On April 29, 2020, the City Council authorized staff to allocate remaining funds
associated with the Tax Allocation Bond issued in 2006 to undertake Capital
Improvement Projects that benefit the former Redevelopment Agency Project Area.
One of the approved and appropriated project allocations was in the amount of
$273,324 for sidewalk rehabilitation within the RDA Project Area. On September 1,
2021, the City Council awarded a construction contract to F.S. Contractors, Inc. in the
amount of $220,001.00, plus a 10% project contingency amount of $22,000.10, for a
total contract amount of $242,001.10.
The Plans and Specifications for the 2021 Sidewalk Rehabilitation Project originally
proposed 14,000 square feet of sidewalk replacement. Because the total contract
award amount, including the 10% contingency amount, is less than the appropriated
project allocations, staff determined that additional sidewalk replacement can be
performed. On November 1, 2021, the City Council approved Amendment No. 1 to the
construction contract for a total amount of $272,270.90 to increase the total quantity of
sidewalk replacement.
Staff issued a Notice to Proceed with an effective start date of November 1, 2021. The
project was originally scheduled to be completed on January 3, 2022. However, the
project encountered several weather-related delays, and the completion date was
pushed to February 28, 2022.
Item: 10.D.
269
Honorable City Council
04/06/2022 Regular Meeting
Page 2
DISCUSSION
Final inspection for the project is complete and the work performed by F.S. Contractors
Inc. is satisfactory. It is staff’s determination that F.S. Contractors, Inc. has executed
100% of the construction contract and that it is now appropriate for the City Council to
accept the 2021 Sidewalk Rehabilitation Project as complete. In summary, the project
replaced 19,863 square feet of sidewalk within the former Redevelopment Agency
Project Area, including approximately 4,000 square feet along High Street.
As part of this project completion and acceptance, the City Clerk will file a Notice of
Completion with the County Recorder’s Office. If no Stop Work Notices are received
from the sub-contractor(s) and/or materials supplier(s), the retainage will be released
thirty-five (35) days after the date of recordation of the Notice of Completion.
Additionally, in accordance with the contract documents, the Faithful Performance and
Material Suppliers and Laborers Bond, Bond No. RCB0031252 in the amount of
$242,001.10, will be released by the City Clerk’s Office one year after the date of
recordation of the Notice of Completion.
The actual construction cost, based on final quantities and field measurements, is
$262,851.91. The following is a summary of project expenditures.
Account No. 3005-311-M0050-55200 $273,324.00
Legal Advertisement $1,053.10
Final Construction Cost $262,851.91
Total $263,905.01
FISCAL IMPACT
None.
COUNCIL GOAL COMPLIANCE
This action does not support a current strategic directive.
STAFF RECOMMENDATION
1. Accept completion of the 2021 Sidewalk Rehabilitation Project, (CIP Project No.
M0050) Specification No. MPK 21-01, and authorize the City Clerk to file the
Notice of Completion with the Ventura County Recorder’s Office; and
2. Authorize the City Clerk to release the Faithful Performance and Material
Suppliers and Laborers Bond, Bond No. RCB0031252, one year after the date of
recordation of the Notice of Completion.
Attachment: Notice of Completion (Specification No. MPK 21-01)
270
Form Issued: February 15, 2013
RECORDING REQUESTED BY
AND WHEN RECORDED MAIL TO:
CITY OF MOORPARK
799 Moorpark Avenue
Moorpark, California 93021
Attn: City Clerk
NO FEE REQUIRED PURSUANT TO:
Government Code Sections 6103 and 27383
Space above this line for Recorder's use
NOTICE OF COMPLETION
Notice pursuant to Civil Code Section 9204 must be filed on or within 15 days after the date of completion of a work of
improvement. Civil Code Section 9200 provides that completion of a work of improvement occurs at the earliest of
(a)acceptance of the work of improvement by the public entity or (b) cessation of labor on the work of improvement for a
continuous period of 60 days.
Notice is hereby given that:
1.The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the
property hereinafter described:
2.The full name of the owner is: City of Moorpark
3.The full address of the owner is: 799 Moorpark Avenue, Moorpark, California 93021
4.The nature of the interest or estate of the owner is: public right-of-way
5.The owner retained a contractor to perform a work of improvement as follows:
Repair and replacement of sidewalks on city streets.
The name and address of the contractor, if any, for such work of improvement was:
F.S. Contractors, Inc., 14838 Bledsoe Street, Sylmar, California 91342
The date of the contract was: September 28, 2021
6.The name and address of the surety, if any, was:
RLI Insurance Company, 9025 N. Lindbergh Drive, Peoria, Illinois 61615
7.The name and address of the construction lender, if any, for such work of improvement was:
None
8.The property on which the work of improvement was constructed is in the City of Moorpark, County of
Ventura, State of California, and is described as follows: former Redevelopment Agency Project Area
9.The street address of said property is: None
10.Date labor ceased on the work of improvement: February 18, 2022
11.The work of improvement was completed on: February 28, 2022
Dated: Signed:
Troy Brown, City Manager, City of Moorpark, 799 Moorpark Ave., Moorpark, California
VERIFICATION
I, the undersigned, say: I am the City Manager of the City of Moorpark. I am authorized to make this
verification for and on behalf of the City of Moorpark and I make this verification for that reason. I have read this
Notice of Completion and the matters stated in this Notice of Completion are true of my own knowledge. I
declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct.
Executed on , 2022, at Moorpark, California.
Signed:__________________________________________________________________________________
Troy Brown, City Manager, City of Moorpark, 799 Moorpark Avenue, Moorpark, California 93021