HomeMy WebLinkAboutAGENDA REPORT 2022 0420 CCSA JNT DC ITEM 09ACITY OF MOORPARK, 
CALIFORNIA City Council Meeting of April 20, 2022 ACTION RECEIVED PRESENTATION. BY A. Hurtado. A. Receive Presentation on the City of Moorpark Capital Improvement Plan Project Status Report. Staff Recommendation: Receive presentation on the Capital Improvement Plan Project Status Report. (Staff: Shaun Kroes, Public Works Manager) Item: 9.A. MOORPARK CITY COUNCIL AGENDA REPORT TO: Honorable City Council FROM: Shaun Kroes, Public Works Manager DATE: 04/20/2022 Regular Meeting SUBJECT: Receive Presentation on the City of Moorpark Capital Improvement Plan Project Status Report BACKGROUND AND DISCUSSION The City of Moorpark’s Capital Improvement Plan (CIP) identifies projects that are intended to meet the City’s Mission Statement of “Striving to preserve and improve the quality of life in Moorpark.” On November 17, 2021, staff provided the first CIP Project Status Report to City Council. The CIP Project Status Report is a biannual report and was developed to help stay on top of the CIP and ensure that projects move forward. The CIP Project Status Report (attached) provides a snapshot of the progression of projects included in the City’s CIP. Many of the projects identified span more than two-years and in some instances can be several years depending on the complexity of the project and the various agencies/stakeholders that are involved. The Project Status Report identifies key elements of each respective project and is intended to keep City Council and the general public updated on the current status of projects. During each presentation to City Council, staff will provide updates on active projects as well as any challenges or obstacles that may have been encountered and/or overcome. It should be noted that the Status Report is not intended to identify new projects. Updates to the CIP itself, such as adding or removing projects will continue to be performed during the City’s fiscal year budget development, which usually begins in February of each year. FISCAL IMPACT None. Item: 9.A. 1 Honorable City Council 04/20/2022 Regular Meeting Page 2 COUNCIL GOAL COMPLIANCE This action does not support a specific strategic directive; however, the CIP Status Report is intended to keep projects moving forward, many of which are included in the current strategic directives. STAFF RECOMMENDATION Receive presentation on the Capital Improvement Plan Project Status Report. Attachment: Capital Improvement Plan Project Status Report. 2 ATTACHMENT City of Moorpark Capital Improvement Plan Project Status Report April 20, 2022 The City of Moorpark’s Capital Improvement Plan (CIP) identifies projects that are intended to meet the City’s Mission Statement of “Striving to preserve and improve the quality of life in Moorpark.” The CIP Project Status Report provides a snapshot of the progression of projects included in the City’s CIP. Many of the projects identified span more than two-years and in some instances can be several years or even decades-long depending on the complexity of the project and the various agencies/stakeholders that are involved. The Project Status Report identifies key elements of each respective project and is intended to keep City Council and the general public updated on the current status of projects identified in the Fiscal Year (FY) 2021/2022 CIP. Each project includes key areas of description that include: - Project Number: Established through the Finance Department (for cost accounting). - Project Description: Provides purpose of the project/areas of improvement. - City Council Goal/Objective: This identifies whether a project is connected to one of the City Council’s Strategic Priorities. The current two-year cycle of the Strategic Priorities includes fiscal year (FY) 2021/22 and FY 2022/23. - Objective Estimated Completion Year: If applicable. Comes from City Council objectives identified in the Strategic Priorities. - Project Type: Identifies which category a project falls within the CIP; A. Facility, B. Parks, C. Streets, D. Trails, or E. Transportation. - Responsible Department: Identifies which City department has primary responsibility. It should be noted that many CIP projects include the support/input from multiple departments. - Project Manager: Identifies primary City staff person responsible for the project. - Project Consultants/Contractors: Identifies the primary consultants/contractors that the City has an agreement with for work related to the project. This primarily includes the design engineer/architect during the design phase of a project and the construction contractor once the project is under construction. - Current Stage: Identifies whether the project has yet to begin; is in preliminary/final design; out to bid; in pre-construction; under construction; or completed. - Items of Note: Provides a brief synopsis of activities that may have occurred in between reporting periods or explanations for any delays or new details about the project that impact the progress of the project. - Six Month Look-ahead: Provides key next steps/activities that are expected to occur during the next six months of the project. 3 2 The Project Status Report is divided into two main sections: I. Active Projects: This section covers projects that are active in one format or another. They could be under design, construction, land acquisition, etc. They could also include projects that may have become active in between reporting periods. Projects are listed in alphabetical order. Not all projects are in the current Goals and Objectives. II. Five-Year CIP: This section contains the remaining projects included in the City’s Five-Year CIP. Projects are categorized as Facility, Parks, Streets, Trails or Transportation. Projects are listed in alphabetical order. It should be noted that as the CIP covers five years of projects, many of the projects in this section will not show activity as they are not ready to begin; or, in some instances, had activity from years prior but have not progressed for a number of reasons, such as right-of-way/land acquisition concerns, funding availability, or other priority projects/areas of responsibility. 4 3 I. Active Projects Arroyo Drive Overlay & Arroyo Drive Bike/Ped Project Project Number: C0035 & C0037 Project Description: Pavement rehabilitation on Arroyo Drive, from Collins Drive to entrance of Villa Del Arroyo Mobile Home Park (C0035). Pedestrian improvements along Arroyo Drive, between Collins Drive and Simi Valley city limit line. TDA Article 3 grant for FY 2015/16 and FY 2016/17 provides $200,000 for a sidewalk starting at west end of Villa Del Arroyo Mobile Home Park, eastward to the Simi Valley city limit line. $200,000 grant requires a 50% local match. Fiscal year 2018/19 includes new grant ($531,180) and a local match of $68,820. City Council Goal/Objective: 2.15: Improve Arroyo Drive, including complete design and construction of sidewalk on south side of Arroyo Drive east of the train tracks to Simi Valley city limit line; and complete conceptual design of pedestrian improvements between Collins Drive and train tracks. Objective Estimated Completion Year: 2023 Project Type: Streets Responsible Department: Public Works Project Manager: Shaun Kroes, Public Works Manager Project Consultants/Contractors: Stantec Consulting Services, Inc. Current Stage: Preliminary design. Items of Note: Conceptual layout from Collins Drive to City limit line is near completion. Project is also exploring storm drain improvements that eliminates utilizing infrastructure that runs underneath Villa Del Arroyo Mobile Home Park and instead discharges directly into the Arroyo Simi. Six Month Look-ahead: Work on receiving conceptual approval from Ventura County Watershed Protection District for alternative stormwater discharge points. Finalize schematic design. Agency coordination with California Department of Transportation (Caltrans) and Southern California Regional Rail Authority (SCRRA/Metrolink) and Union Pacific for potential input/concerns. Begin work on preliminary design and environmental clearance. Potentially begin plans, specifications and estimates for construction of sidewalk and street improvements on Arroyo Drive from west-end of Villa Del Arroyo Mobile Home Park to Simi Valley city limit line. Arroyo Simi Trail Plan Project Number: C0061 Project Description: Conduct an Arroyo Simi Trail feasibility study and develop a phasing plan for trail improvements along the Arroyo Simi from the west City limits to east City limits at Arroyo Drive. Estimated future improvement costs to cover construction of the initial phase between the Arroyo Vista Recreation Center pedestrian bridge and Spring Road, including an undercrossing under the Spring Road bridge. City Council Goal/Objective: 4.5: Develop an RFP and hire consultant to develop an Arroyo Simi Trail Master Plan and phasing plan, from the west City limits to east City limits at Arroyo Drive. Objective Estimated Completion Year: 2023 Project Type: Trails Responsible Department: Parks, Recreation & Community Services 5 4 Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: RFP for Consultant to draft master plan expected to be released in April 2022. Items of Note: Six Month Look-ahead: Release RFP and get consultant under contract, begin project design kick off. Arroyo Vista Recreation Center HVAC Replacement Project Number: M0024 Project Description: Remove and replace the four HVAC units at Arroyo Vista Recreation Center, 10 ton unit ($15,000), 12.5 ton unit ($20,000), 15 ton unit ($30,000), and 25 ton unit ($35,000); total $100,000. $40,000 for design of the system and replacing gas line to Arroyo Vista Recreation Center gym and $95,000 for gas line construction. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: Bon Air, Incorporated. Current Stage: Project awarded in November. Items of Note Six Month Look-ahead: Gas line replacement to occur in November, HVAC replacement likely in Spring due to long lead times on equipment. City Entry Monument Signage Project Number: C0065 Project Description: Install four City welcome monument signs, including solar-powered LED illumination, at locations on Tierra Rejada Road, Grimes Canyon Road, and Princeton Avenue. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: Frank & Sons, Inc. DBA Express Sign & Neon Current Stage: Contractor preparing submittals. Items of Note: Sign manufacturing delays extending anticipated project timeline. Six Month Look-ahead: Sign fabrication winter 2021, installation spring 2022. 6 5 City Hall at 323 Science Drive Project Number: C0070 Project Description: Establish a temporary City Hall at 323 Science Drive. City Council Goal/Objective: 3.12: Identify and transition to temporary City Hall location. Objective Estimated Completion Year: 2022 Project Type: Facility Responsible Department: City Manager Project Manager: Troy Brown, City Manager Project Consultants/Contractors: SVA Architects Current Stage: Preliminary Design Items of Note: On February 16, 2022, City Council approved establishing a new CIP (C0070) to separate expenses associated with 323 Science Drive (temporary City Hall) from CIP (C0012) “New City Hall and Civic Center Complex”. At the same date, City Council also approved an Agreement with SVA Architects, Inc. for architectural design services for tenant improvements. Six Month Look-ahead: Finalize design layout for tenant improvements at 323 Science Drive. High Street Arts Center Roofing Replacement Project Number: C0068 Project Description: Demo, repair, and replace roofing material at the High Street Arts Center including roof drains and galvanized flashing. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: Commercial Waterproofing Systems dba ERC Roofing and Waterproofing (ERC). Current Stage: Construction. Items of Note: City released Notice Inviting Bid on January 24, 2022 and City Council awarded agreement to ERC on March 16, 2022 in the amount of $251,275. Six Month Look-ahead: Replacement of High Streets Arts Center roof. 7 6 High Street Improvements Project Number: C0009 Project Description: Improve sidewalks on High Street to include traffic calming devices and street parking improvements. Install new site furnishings. City Council Goal/Objective: 3.15: Complete the approved street improvements and streetscape enhancements along the frontage of the proposed High Street Depot development project. Objective Estimated Completion Year: 2023 Project Type: Streets Responsible Department: Public Works Project Manager: Shaun Kroes, Public Works Manager Project Consultants/Contractors: None on contract at this time. Current Stage: Yet to begin. Items of Note: No change since last report. City has received preliminary concepts for right-of-way improvements as part of the High Street development project. Design elements incorporated in the streetscape improvements included in the Metrolink North Parking Lot Expansion (CIP C0032) project. With final approval of the Metrolink North Parking Lot Expansion design City staff can begin work on establishing an agreement for design services for the High Street Improvements project. Six Month Look-ahead: Establish agreement with engineering design services for development of improvements along High Street. Inclusive Playground at Tierra Rejada Park Project Number: C0063 Project Description: Design and install inclusive playground at Tierra Rejada Park. City will receive Land and Water Conservation Fund (LWCF) grant funds and Per Capita Grant Funds to offset 50% of the improvement costs. Grants are reimbursement grants so full project costs need to be appropriated. Staff anticipates project starting in Summer 2021. City Council Goal/Objective: 2.12: Upon receipt of grant funding, construct an inclusive playground at Tierra Rejada Park. Objective Estimated Completion Year: 2023 Project Type: Parks Responsible Department: Parks, Recreation & Community Services Project Manager: Jessica Sandifer, Community Services Manager Project Consultants/Contractors: Architerra, Inc., RecWest, Inc., Phoenix Civil Engineering, Inc. Current Stage: Construction. Items of Note: Authorization to spend grant funds from California State Parks received end of March 2022. Six Month Look-ahead: Construction will start within the next six months. 8 7 Los Angeles Avenue Widening – Spring Road to Moorpark Avenue Project Number: C0021 Project Description: Street widening and improvements for additional vehicle travel lanes, an emergency lane, curb and gutter, and sidewalk along the south side of Los Angeles Avenue, from Moorpark Avenue to Spring Road. Project scope of work will also include storm drainage infrastructure improvements along the south side of Los Angeles Avenue and installation of a traffic signal at the intersection of Millard Street/Los Angeles Avenue. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: AECOM Technical Services Inc. for design Current Stage: Right-of-way acquisition. Items of Note: Purchase of 240 Los Angeles Avenue completed (includes two-year rent-back to current occupant of the house). Staff has met with AECOM to review the project design and requested a proposal to update the previous draft design. Six Month Look-ahead: Expected to return to City Council in May 2022 with a proposed amendment to AECOM’s Agreement. Upon execution proceed with updating the draft design. Metrolink North Parking Lot Expansion Project Number: C0032 Project Description: Convert vacant lot (approximately 150-feet wide x 120-feet long west of Metrolink North Parking Lot into a formal parking lot, adding an estimated 35- 40 parking stalls. The project also includes reconstruction the existing North Parking Lot (owned by the Ventura County Transportation Commission [VCTC]). City Council Goal/Objective: 3.14: Complete renovation of the existing north Metrolink parking lot and expand the parking lot to the west for a net increase in downtown public parking spaces. Objective Estimated Completion Year: 2023 Project Type: Transportation Responsible Department: Public Works Project Manager: Shaun Kroes, Public Works Manager Project Consultants/Contractors: Phoenix Civil Engineering, Inc. (engineering design services/construction management services). F.S. Contractors, Inc. (construction). Current Stage: Under Construction. Items of Note: City Council awarded construction agreement to F.S. Contractors, Inc. on October 21, 2021, in the amount of $1,784,971 (includes 10% contingency). Construction began March 7, 2022. Estimated completion is July 2022. Six Month Look-ahead: Complete construction. 9 8 New City Hall and Civic Center Complex Project Number: C0012 Project Description: Acquisition of property and design and construction of a city hall and civic center complex on the northwest corner of Moorpark Avenue and High Street. Request is for design expenses. Balance of funds to be used in future years for engineering, construction, and associated administrative expenses. City Council Goal/Objective: Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: Current Stage: Yet to begin Items of Note: Six Month Look-ahead: Pending. New Moorpark City Library Project Number: C0056 Project Description: Design and construction of a new City Library. City Council Goal/Objective: 3.11: Complete construction plans for the City’s new Library. Objective Estimated Completion Year: 2023 Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Preliminary Design. Items of Note: City awarded a Agreement to LPA, Inc. for architectural design services for the library on December 15, 2021, and the Agreement was executed on December 22, 2021. Six Month Look-ahead: Work with LPA on design concepts. 10 9 North Train Station Public Art Project Number: C0052 Project Description: Public art project to be constructed at the north Metrolink Train Station. City Council Goal/Objective: 3.13: Develop an RFP and contract with an artist to construct artwork at the Metrolink north parking lot. Objective Estimated Completion Year: 2022 Project Type: Transportation Responsible Department: Parks, Recreation & Community Services Project Manager: Chris Ball, Senior Management Analyst Project Consultants/Contractors: TBD Current Stage: RFQ/P in process. Items of Note: Informal RFQ released January 11, 2022. City received 9 applications. An artist review panel was created consisting of two Arts Commissioners, two stakeholders from the current site renovation project, and a representative from the High Street business community. The review panel evaluated the applications on March 22 and selected three semi-finalists to develop preliminary proposals. The proposals will be considered by the review panel on April 25, 2022. Six Month Look-ahead: Select artist and execute Agreement. Artist to conduct design development and approval, and artwork fabrication. Princeton Avenue Improvement Project Number: C0020 Project Description: Road widening, realignment, and reconstruction of Princeton Avenue, from a point east of Spring Road to South Condor Drive. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: Stantec Consulting Services, Inc. for design and Administration Services, FCG Consultants, Inc. for Construction Management and Inspection Services, and Security Paving Company for Construction Current Stage: Construction Items of Note: Request for Bid released December 1, 2021 and closed January 14, 2022. City Council awarded construction contract to Security Paving Company on February 16, 2022. Utility relocation efforts have begun. Six Month Look-ahead: Utility work currently being performed by the Gas Company and Southern California Edison prior to construction. Security Paving’s mobilization and pre-construction activities are expected to occur through May and June 2022 and construction is expected to start in June 2022, pending completion of utility relocation. Project completion is expected to be completed in December 2023. 11 10 Downtown Sidewalk Rehabilitation Project Number: M0050 Project Description: Sidewalk rehabilitation within the boundaries of the Redevelopment Area. The scope of work and improvements include sidewalk repair, sidewalk replacement, curb cuts, access ramps, and street transitions. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Ariane Quizon, Assistant Engineer Project Consultants/Contractors: F.S. Contractors, Inc. Current Stage: Completed. Items of Note: Project completed and City Council approved the Notice of Completion on April 6, 2022. The project replaced 19,863 square feet of sidewalk within the former Redevelopment Agency Project Area, including approximately 4,000 square feet along High Street. Six Month Look-ahead: None. Project will be removed from next report. 12 11 II. Five-Year CIP A. Facility ADA Improvements Project Number: M0002 Project Description: Bus Stop improvements ($85,000); Facilities and Parks improvements ($5,225,000); Intersections ($1,378,000); and Curbs and sidewalks ($17,212,000). City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Some improvements to occur during other CIPs, such as Metrolink North Parking Lot. Arroyo Vista Community Park Storage Facility Project Number: C0047 Project Description: Design and construction of a storage facility at Arroyo Vista Community Park. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jessica Sandifer, Community Services Manager Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending. 13 12 Arroyo Vista Recreation Center Facility Expansion Project Number: C0042 Project Description: Develop design plan for Arroyo Vista Recreation Center for improvements to the facility which include office expansion. City Council Goal/Objective: 4.4: Prepare a feasibility study to expand the Arroyo Vista Recreation Center, including office spaces and gym, with emphasis on expanded opportunities for both City programs and private events. Objective Estimated Completion Year: 2023 Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jessica Sandifer, Community Services Manager Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Project pending completion of a feasibility study as noted in City Council Objective 4.4. Feasibility study to take place in late 2022, early 2023. Arroyo Vista Recreation Center Gym Expansion Project Project Number: C0048 Project Description: Professional Services to review existing building plans and facility to update facility to current building codes. Construction costs estimated at $2.3 million. City Council Goal/Objective: 4.4: Prepare a feasibility study to expand the Arroyo Vista Recreation Center, including office spaces and gym, with emphasis on expanded opportunities for both City programs and private events. Objective Estimated Completion Year: 2023 Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jessica Sandifer, Community Services Manager Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Project pending completion of a feasibility study as noted in City Council Objective 4.4. Feasibility study to take place in late 2022, early 2023. 14 13 Arroyo Vista Recreation Center Remodel Project Number: M0025 Project Description: Kitchen: Upgrade cabinets, replace new sink to comply with Health and Safety Code, replace appliances and interior painting. Building: Exterior masonry waterproofing; replace windows. Rooms: Replace flooring, add drop down ceiling, paint. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Back-up Generator for Community Center and AVRC Project Number: M0023 Project Description: Replace back-up generator for Community Center. Portable generator for AVRC Sewer Lift Station. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 15 14 Central Irrigation System Project Number: C0019 Project Description: Phase 2: Installation of controllers, flow sensors and master valves at Arroyo Vista Community and Miller Parks ($74,362). Previously completed Phase 1: Installation at Peach Hill Park, Mammoth Highlands Park, Lighting & Maintenance Assessment Districts: Zone 2 (Steeple Hill), Zone 5 (Pheasant Run), Zone 10 (Mountain Meadows), Zone 12 (Carlsberg), Zone 15 (Toll Brothers), and Zone 22 (Pardee Homes) accounted for under Capital Outlay Account 55000 ($293,519). City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Phase II completed at the end of FY 2021/22; not previously accounted for in the Fall 2021 report. Items of Note: Six Month Look-ahead: Project will be removed from next report. Community Center Fire Sprinkler System Installation Project Number: M0035 Project Description: Fire sprinkler system for the Community Center. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 16 15 Moorpark Public Service Facility Asphalt Repair and Slurry Project Number: C0069 Project Description: Crack repair and slurry coat the asphalt driveway and yard at Public Service Facility, including parking stall and curb painting. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Pedestrian Access Improvements at the Civic Center Project Number: C0014 Project Description: Create ADA accessible pedestrian access from Moorpark Avenue through the Civic Center including an improved bus turnout. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Facility Responsible Department: Public Works Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending. 17 16 B. Parks Campus Park Playground Upgrades Project Number: C0066 Project Description: Replace children’s play structures and equipment at Campus Park and replace sand with engineered wood fiber. Install separate sand play area. Replace restroom with prefabricated restroom facility. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Parks Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Park and Facility Pavement Rehabilitation Project Number: M0044 Project Description: Parking lot rehabilitation at Mountain Meadows Park and Tierra Rejada Park, Peach Hill Park, Community Center parking lot, and Library parking lot. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Parks Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 18 17 Replace Play Equipment at Community Center Park Project Number: C0064 Project Description: Replace children’s play structures and equipment at Community Center Park. Replace sand with engineered wood fiber and construct ADA parking lot improvements. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Parks Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Replace Play Equipment at Glenwood Park Project Number: C0067 Project Description: Replace children’s play structures and equipment for ages 5-12 at Glenwood Park and replace sand with engineered wood fiber. ADA sidewalk improvements. Install sand play area. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Parks Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 19 18 C. Streets Los Angeles Avenue Traffic Signals/Fiber Optic Upgrade Project Number: M0040 Project Description: Replace copper lines with fiber optic technology. New timing/coordination improvements for traffic signals along Los Angeles Avenue. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Los Angeles Avenue Undergrounding Project Number: C0033 Project Description: Undergrounding the overhead utilities along the north side of Los Angeles Avenue, east and west of the Arroyo Simi bridge. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 20 19 Millard Drain Project Number: C0003 Project Description: Construction of storm drainage infrastructure improvements to serve the residential area north of the intersection of Los Angeles Avenue and Millard Street. No funding source has been identified for this project. The full scope and cost of this project has not been determined. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: TBD Current Stage: City Council approved $250,000 of Tax Allocation Bonds to be applied to this project at a Special City Council Meeting (4/29/2021; Item 9.A). Items of Note: Six Month Look-ahead: Pending Moorpark Widening Project Project Number: C0004 Project Description: Widening of Moorpark Avenue to add a southbound lane along the west side from Casey Road to Third Street. Includes street realignment at First Street and Poindexter Avenue (Prior Project 8057) and rail crossing improvements (Prior Project 8038). Prior year appropriations for those projects have been returned to funding sources. Prior to commencing work on this project, the General Plan and Circulation Element must be updated to identify the second southbound lane. Therefore, funding has been moved to Future Years. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Department Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 21 20 North Hills Parkway Project Number: C0031 Project Description: Construction of an east- west arterial street north of the railroad corridor, to be generally located within the right-of-way reserved for the Previous Route 118 bypass project. Initial costs are for the development of a conceptual design. 50% of design and engineering costs will be funded through Route 23 North Alignment Project (C0025). Project includes 1449 and 1493 Walnut Canyon Road properties. In 2008, a feasibility study prepared by Parsons estimated the total construction cost to be $85 million. This includes costs for actual construction, engineering support and R/W. The buildout of North Hills Parkway will be dependent on several proposed development projects, including Hitch Ranch, Tract 5906, Tract 5130, Tract 5847, and the Moorpark Movie Studios. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Route 23 North Alignment Project Number: C0025 Project Description: Design and construction of a roadway north of Princeton Avenue to connect to Broadway Road. Initial costs are for the development of conceptual design plans. Note, 50% of the design and engineering costs will be funded through the North Hills Parkway Project (C0031). The projected cost estimate is $85 million. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: On Hold Sidewalk Reconstruction Project 22 21 Project Number: M0029 Project Description: Replacement of sidewalks, curbs, and gutters at various locations. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Ariane Quizon, Assistant Engineer Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Spring Road Widening Project Number: C0022 Project Description: Widening of east side of Spring Road, from Los Angeles Avenue to Flinn Avenue. Widening improvements will also require relocation of the traffic signal pole at the NE corner of Los Angeles Avenue and Spring Road City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Traffic Signal Cabinet Upgrades Project Number: M0033 Project Description: 1) Replace signal controller and battery backup units on Tierra Rejada Road ($140,875), Spring Road ($40,250), and Miller Parkway ($40,250). 2) Replace signal cabinets and battery backup units on Campus Park ($25,875), Princeton ($25,875). 3) Replace safety lights from halogen to LED ($95,318). Total project cost estimate of $368,443 is proposed to be spent over the course several fiscal years City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets 23 22 Responsible Department: Public Works Project Manager: Ariane Quizon, Assistant Engineer Project Consultants/Contractors: Siemens Mobility, Inc. Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Traffic Signal Improvements at Spring Road (Charles & Second) Project Number: C0060 Project Description: The Spring Road railroad crossing improvements completed thus far have reduced congestion and delays; however, the work is not completely coordinated with Spring Road signals at Charles Street and Second Street. The road segment between Charles Street and Second Street will be evaluated for future improvements, including signal coordination, timing/phasing adjustments, and signal/striping/signage changes. Once the engineering analysis and design is complete, improvement work will be completed and evaluated. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Staff determining if any improvements are needed and if the project is to move forward. Underground Utility District No. 2 Project Number: C0027 Project Description: Establishment and implementation of an underground utility district along Los Angeles Avenue, between Shasta Avenue and Millard Street, to underground high voltage overhead transmission lines and remove all poles and overhead wires. SCE Rule 20A monies in the approximately amount of $400,000 are not included in the CIP budget. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Streets Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Director 24 23 Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 25 24 D. Trails Championship Drive Sidewalk and Trail Improvements Project Number: C0053 Project Description: Championship Drive trail and drainage improvements. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Trails Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 80 Acre Parcel Trail Project Project Number: C0062 Project Description: In conjunction with the Moorpark Watershed Parks, Recreation and Conservation Authority (MWPRCA), develop a multi-use recreational trail in the 80-acre parcel. Costs represent City contributed match funding. MWPRCA is seeking grant funding for the remainder of the project cost of $501,600. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Trails Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: Phoenix Civil Engineering Current Stage: Stakeholder meetings and review of potential trail alignments. Items of Note: Six Month Look-ahead: Finalizing stake holder meetings to gather input on project, and identification of preferred trail alignment to be completed in early Spring and presented to the MWPRCA Board for review. 26 25 E. Transportation Bus Shelters and Other Bus Stop Amenities Project Number: P0011 Project Description: Bus stop adjustments, refurbishments, additions, and amenities. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Transportation Responsible Department: Public Works Project Manager: Shaun Kroes, Public Works Manager Project Consultants/Contractors: TBD Current Stage: Moorpark Station North Parking Lot bus shelter replacement will be part of Project C0032 (Metrolink North Parking Lot Expansion). Items of Note: Six Month Look-ahead: Replace Moorpark Station North Parking Lot bus shelter. Princeton Avenue/Campus Park Drive Landscape Renovation Project Number: M0045 Project Description: Design and renovation of medians and parkways on Princeton Avenue from Condor Drive along Campus Park Drive to Marquette Street. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Transportation Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending 27 26 Los Angeles Avenue Landscape Renovation Project Number: M0046 Project Description: Renovate the landscaped parkways and enhance the wall treatments on the north side of Los Angeles Avenue from Spring Road to Millard Street. Wall enhancements will include removal and replacement of the existing vine, stone pilasters, and stucco finish. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Transportation Responsible Department: Parks, Recreation & Community Services Project Manager: Jeremy Laurentowski, Parks and Recreation Director Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending Spring Road Bus Turn Out Project Number: C0007 Project Description: Design and construction of a bus turnout on Spring Road, at Charles Street. City Council Goal/Objective: n/a Objective Estimated Completion Year: n/a Project Type: Transportation Responsible Department: Public Works Project Manager: Dan Kim, City Engineer/Public Works Department Project Consultants/Contractors: TBD Current Stage: Yet to begin. Items of Note: Six Month Look-ahead: Pending. 28