HomeMy WebLinkAboutAGENDA REPORT 2022 0420 CCSA JNT DC ITEM 09A POWERPOINTCity of Moorpark
Capital Improvement Plan
Project Status Report
Moorpark City Council
April 20, 2022
Project Status
Report
Purpose
Biannual report presented to City
Council (October and April).
Provides a snapshot of the
progression of projects included
in the City’s Capital
Improvement Plan.
Opportunity to provide updates
on projects and identify any
challenges or obstacles that
have been encountered and/or
overcome.
Keeps projects in the forefront.
Project Status Report
Active Projects (contains projects
that are active in one form or
another).
Five Year CIP (contains remaining
projects included in the City’s
Five-Year CIP).
Project Status Report –Updates Since November 2021
Added Project C0070 (City Hall at 323 Science Drive)
Moved 3 Projects to “Active”:
-Project M0024 (AVRC HVAC Replacement)
-Project C0068 (High Street Arts Center Roof Replacement)
-Project C0065 (City Entry Monument Signage)
Removed 2 Projects:
-Project C0050 (Streetlight LED Conversion)
-Project C0026 (Los Angeles Avenue Medians)
Active Projects
16 Active Projects (out of 47).
1 completed project (Downtown Sidewalk Rehabilitation).
5 active construction:
-AVRC HVAC Replacement
-City Entry Monument Signage
-High Street Arts Center Roofing Replacement (pending contract execution)
-Metrolink North Parking Lot Expansion
-Princeton Avenue Improvement
Remaining 10 projects are in some phase of design, or preparing to go out to bid for design/construction, etc.
Princeton Avenue Improvement (C0020)
Construction contract awarded
to Security Paving on February 16,
2022.
Utility relocation is currently in
progress.
Construction expected to begin
June 2022, with completion
estimated for December 2023.
Metrolink North Parking Lot Expansion (C0032)
Construction contract awarded
to F.S. Contractros, Inc. on
October 21, 2021.
Construction began March 7,
2022.
Completion expected in July
2022.
Fiscal Year 2021/22 Expenditure Info:
Active Projects
$7,967,990.45;
21%
$5,518,888.60;
15%$23,986,410.7
6; 64%
FY 2021/22 Capital Improvement Program
Active Projects: Budget & Expenditures
FY 2021/22 Expenditures
Year-to-Date
FY 2021/22
Encumbrances
FY 2021/22
Unencumbered Balance
$7,967,990.45;
59%
$5,518,888.60;
41%
FY 2021/22 Capital Improvement Program
Active Projects: Year-to-Date Expenditures
FY 2021/22 Expenditures
Year-to-Date
FY 2021/22
Encumbrances
Fiscal Year 2021/22
Expenditure Info: Active
Project Funding Sources
$37.5 Million
2.87% (or $1.07 million) is General Fund (nearly 42% will be reimbursed from outside source).
Nearly $8 million in Year-to-Date Expenditures.
(1000) General Fund;
$1,074,862.80; 3%
(2002) City-wide
Traffic Mitigation;
$2,350,000.09; 6%
(2014) LA AOC;
$9,199,316.56; 25%
(2409) Federal/State
Grant; $1,744,220.00;
5%
(2800) ARPA;
$5,688,798.00; 15%
(3001) City Hall
Improvement;
$9,127,283.57; 24%
(3005) Remaining
Bond Proceeds;
$1,773,324.00; 5%
(1000) General Fund (2001) Traffic System Management
(2002) City-wide Traffic Mitigation (2007) Art In Public Places
(2010) Community Wide Park Development (2014) LA AOC
(2018) Endowment (2401) ISTEA (Federal)
(2409) Federal/State Grant (2412) TDA 8a
(2413) State Transit Assistance (2414) TDA 8c
(2416) Road Maint & Rehab (2417) State of Good Repair
(2434) Prop 1B (2800) ARPA
(3001) City Hall Improvement (3003) Equipment Replacement
(3005) Remaining Bond Proceeds
Fiscal Year 2021/22 CIP
Active Projects: Year-to-
Date Expenditures
$Nearly $8 million in expenditures
$6.6 million (or 83%) is from the City Hall Improvement Fund for purchase of 323 Science Drive (C0070).
Nearly $1 million (or 12%) is from Los Angeles AOC Fund, with $802k spent on 240 Los Angeles Avenue (SR-118) for Los Angeles Avenue Widening (C0021).
(2001) Traffic
System
Management
1%(2014) LA AOC
12%
(3001) City Hall
Improvement;
83%
(3005)
Remaining
Bond Proceeds
3%
(1000) General Fund
(2001) Traffic System Management
(2010) Community Wide Park Development
(2014) LA AOC
(2412) TDA 8a
(2434) Prop 1B
(3001) City Hall Improvement
Highlights for
the Next Six
Months
Completion of the Metrolink
North Parking Lot Project.
Construction of Princeton
Avenue Improvement.
Finalize design of tenant
improvements for 323 Science
Drive.
Complete the AVRC HVAC
Replacement; High Street Arts
Center Roof Replacement; and
City Entry Monument Signage
projects.