HomeMy WebLinkAboutAGENDA REPORT 2024 0918 CCSA REG ITEM 09ACITY OF MOORPARK, CALIFORNIA
City Council Meeting
of September 18, 2024
ACTION RECEIVED PRESENTATION.
BY A. Hurtado.
A. Consider Presentation by Joon Kang, Assistant Division Chief, Caltrans District 7
Division of Program/Project Management Providing Update on the Arroyo Simi
Bridge (State Route 118/23 Overpass) Suicide Prevention Project. Staff
Recommendation: Receive presentation. (Staff: Troy Brown, City Manager)
Item: 9.A.
Caltrans Update on Arroyo Simi Bridge
Suicide Prevention Project -Task Force
Quarterly Meeting
of
July 22, 2024
Item: 9.A.
9
Arroyo Simi Safety Barrier
Project
10
Project Timeline Targets
Project Initiation
•Start: July 22
•Finish: Mid Nov 22
1
Environmental/
Prelim Design
•Start: Jan 2023
•Finish: Oct 2023
2
Final Design
•Start: Sept 2023
•Finish: August 2024
3
Construction
Procurement
•Start: November 2024
•Finish: March 2025
4
Construction
•Start: May 2025
•Finish: November 2025
5
11
Project Timeline Targets
100% PS&E:07/03/2024 (A)
RW Certificate:06/21/2024 (A)
Ready to List (RTL):08/02/2024 (T)
Construction Funds Allocation by CTC:10/18/2024 (T)
Advertise the Project:11/19/2024 (T)
Bid Open:01/08/2025 (T)
Award:02/05/2025 (T)
Approve Contract:03/05/2025 (T)
This project construction duration is 95 Working Days, approximately 5 months. With the
additional time needed for the Contractor to obtain approval for construction material and
their procurements, the construction activities will complete within 2025 Calendar year.
12
Proposal:
Install a safety barrier system
13
Chain link railing Type 7
14
Chain link railing Type 7
15
Planning Study
16
Planning Study
17