HomeMy WebLinkAboutRES 1993 281 0907jr-
RESOLUTION NO. PC 93 -281
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF
MOORPARK, CALIFORNIA, APPROVING THE NEGATIVE DECLARATION AND
MITIGATION MONITORING PROGRAM; AND APPROVING CONDITIONAL USE
PERMIT NUMBER 92 -4 RELATED TO ASSESSOR'S PARCEL NUMBERS 512 -0-
111 -270, 512 -0- 111 -160 AND 512 -0- 111 -170, FOR MOORPARK UNITED
METHODIST CHURCH
WHEREAS, at a duly noticed hearing on August 16, 1993, the
Planning Commission considered the application filed by Moorpark
United Methodist Church for the proposed church expansion and
Conditional Use Permit for parcels 512 -0- 111 -270, 512 -0- 111 -160 and
512 -0- 111 -170; and
WHEREAS, at its meeting of August 16, 1993, the Planning
Commission opened the public hearing, received public testimony,
and closed the public hearing; and
WHEREAS, the Planning Commission after review and
consideration of the information obtained within the Staff Report
dated August 16, 1993 as well as the Mitigated Negative
Declaration, Initial Study and Mitigation Monitoring Program for
the proposed development, have reached a decision on this matter.
NOW, THEREFORE, THE PLANNING COMMISSION OF THE CITY OF
MOORPARK CALIFORNIA, DOES RESOLVE AS FOLLOWS:
SECTION 1. Pursuant to the provision of the California
Environmental Quality Act (CEQA) (Division 13 of the Public
Resource Code of the State of California {beginning at Section
2100)) and the requirements under Section 21081.6, the Planning
Commission of the City of Moorpark approves the Mitigated Negative
Declaration and Mitigation Monitoring Program.
SECTION 2. The Planning Commission hereby adopts the
findings as outlined below:
a. The proposed expansion is consistent with the intent and
provisions of the City's General Plan and the Moorpark
zoning ordinance;
b. Is compatible with the character of the surrounding
development;
C. Would not be detrimental to the public interest, health,
safety, convenience or welfare;
d. Would not be obnoxious or harmful, or impair the utility
of neighboring properties or uses; and
e. Is compatible with existing and planned land uses in the
general area where the development is to be located.
N
SECTION 3. The Planning Commission hereby conditionally
approves CUP 92 -4 subject to compliance with all of the conditions
of approval attached hereto as Exhibit 1.
The action with the foregoing direction was approved by the
following role call vote:
AYES: Chairman Wenner and Commissioner's Brodsky, Kay,
Miller and Torres;
NOES:
ABSTAIN:
ABSENT:
Chairman presiding:
ael Wenner, Jr
ATTEST:
— C/ �' , Z—�
Celia LaFleur, Secretary
to the Planning Commission
Attachment: Conditions of Approval
%N -2- Ilwolutlan No. ►C-93 -2a1
EXHIBIT 1
CONDITIONS OF APPROVAL
CONDITIONAL USE PERMIT NUMBER 92 -4
MOORPARK UNITED METHODIST CHURCH
261 FLORY AVENUE, MOORPARK
GENERAL REQUIREMENTS:
1. The permit is granted for the land and project as shown on the
submitted plot plan and elevation of the existing structure
and the building expansion and other exhibits displayed at the
Planning Commission hearing of August 16, 1993.
The development in subject to all applicable regulations of
the R -2 Zone (unless otherwise as approved by the Planning
Commission), and all agencies of the State, Ventura County,
the City of Moorpark and any other governmental entities.
3. That unless the expansion to the existing building is
inaugurated (building foundation slab in place and substantial
work in progress) not later than two (2) years after this CUP
is granted, the expansion part of this CUP shall automatically
expire on that date. The Director of Community Development
r may, at his discretion, grant up to one (1) additional year
extension for expansion inauguration if there has been no
changes in the adjacent areas and if applicant can document
that he has diligently worked towards inauguration of the
project during the initial one year period. No additional
extension will be granted without approval of a minor
modification to this permit.
r-
4. All facilities and uses other than those specifically
requested in the application or allowed herein are prohibited
unless a modification application has been approved by the
City of Moorpark.
5. The design, maintenance, and operation of the permit area and
facilities thereon shall comply with all applicable
requirements and enactments of Federal, State, County, and
City authorities, and all such requirements and enactments
shall, by reference, become conditions of this permit.
6. No conditions of this entitlement shall be interpreted as
permitting or requiring any violation of law or any unlawful
rules or regulations or orders of an authorized governmental
agency. In instances where more than one set of rules apply,
the stricter ones shall take precedence.
Pop -3- Rwolutlon No. K -93-281
Applicant: Moorpark United Methodist Church
Date: August 19, 1993
7. If any of the conditions or limitations of this Conditional
Use Permit are held to be invalid, that holding shall not
invalidate any of the remaining conditions or limitations set
forth.
S. The permittee agrees as a condition of issuance and use of
this permit to defend, at his sole expense, any action brought
against the City because of issuance (or renewal) of this
permit or in the alternative to relinquish this permit.
Permittee will reimburse the City for any court costs and /or
attorney's fees which the City may be required by the court to
pay as a result of any such action. The City may, at its sole
discretion, participate in the defense of any such action, but
such participation shall not relieve permittee of his
obligation under this condition.
9. A sign permit is required for all on -site signs to be approved
by the Director of Community Development.
10. Prior to the submission of any construction plan for plan
check or initiation of any construction activity, a zoning
clearance shall be obtained from the Community Development
Department.
11. Prior to initial occupancy and any subsequent change in
occupancy, the owner of the subject building, or the owner's
representative shall apply for a Zone Clearance from the
Community Development Department.
12. If in the future, any use or uses are contemplated on the site
differing from that specified in the Conditional Use Permit
and the zoning clearance approved for the occupancy, either
the permittee, owner, or each prospective tenant shall file a
project description prior to the initiation of the use. A
review by the Director of Community Development will be
conducted to determine if the proposed use is compatible with
the R -2 Zone and the terms and conditions of this permit.
Said review will be conducted at no charge and an approval
letter sent, unless another entitlement permit is required, in
which case all applicable fees and procedures shall apply.
13. The permittee's acceptance of this permit and /or commencement
of construction and/ or operations under this permit shall be
deemed to be acceptance of all conditions of this permit.
14. This permit shall expire if the use for which it is granted is
discontinued for a period of 180 consecutive days or more.
Pw -4- - RMOolutlon No. K- 93-751
Applicant:
Date:
Moorpark United Methodist Church
August 19, 1993
15. That the CUP is granted for a period of time of ten (10) years
ending August 16, 2003. That at the and of this ten year
period, the Director of Community Development may have the
ability to continue this use for an additional ten year period
of time ending August 16, 2013, providing full compliance with
all conditions have been accomplished and that the use
authorized by this permit will remain compatible with the
properties in the general area for the duration of the
additional period authorized by this permit and that the
applicant files an application for an extension at least six
months prior to the termination of the ten year period. The
Director of Community Development will look at issues such as
congregation expansion, increase in traffic, complaints from
surrounding property owners, etc. when making a determination
as to whether an extension to the permit shall be granted.
The applicant will be required to pay the full cost of staff
time associated with the review and consideration of the
extension of the CUP.
At least six months prior to the termination of any extension
to this Conditional Use Permit granted by the Director of
Community Development, the applicant shall file an application
for a new Conditional Use Permit.
16. That all activities on the premises shall begin no earlier
than 7:00 a.m. to 11:00 p.m., Monday through Saturday and 7:00
a.m. to 10:00 p.m. on Sunday. For Easter Sunrise, Christmas
Eve Communion and Candlelight, the church may operate from
6:00 a.m. to 1:00 a.m. The Director of Community may
authorize the adjustment of hours to accommodate other
traditional religious events through the issuance of a
Temporary Use or Conditional Use Permit, as determined by the
Director of Community Development after payment of the
application fees.
17. within two days after approval of this CUP, the applicant
shall deposit with the City a Condition Compliance review fee
in the amount of the original filing fee for the Conditional
Use Permit and applicant must submit written verification from
the County of Ventura that the State required Notice of
determination filing fee of $1,250 plus a $25.00 recordation
fee has been paid in accordance with Assembly Bill 3158.
PON -5- R000Wttan No. PC -93 -781
Applicant: Moorpark United Methodist Church
Date: August 19, 1993
18. If at any time the lease for the parking spaces with the
Moorpark Unified School District is not renewed, the church
shall reduce the number of participants at the prescribed rate
of four (4) fixed seats per parking space. Failure of the
applicant to comply shall be cause for revocation of the
Conditional Use Permit (CUP).
19. The Fellowship Hall and the Sanctuary (Worship area) shall be
not used concurrently. Occupancy of both the Fellowship Hall
and the Sanctuary (Worship area) shall not exceed the parking
capacity for the existing 302 fixed seats, unless additional
parking spaces are provided for the project, at which time the
occupancy may be increased proportionally not to exceed 350
fixed seats.
PRIOR TO ISSUANCE OF A ZONE CLEARANCE FOR CONSTRUCTION, THE
FOLLOWING CONDITIONS SHALL BE SATISFIED:
20. Prior to the issuance of a Zone Clearance, the pormittss shall
sign a statement indicating awareness and understanding of all
permit conditions, and shall agree to abide by these
Conditions.
21. All roof mounted equipment (vents, stacks, blowers, air
conditioning equipment, etc.) that may extend above any
parapet wall shall be enclosed on all four sides by view
obscuring material, the height of which shall not be less than
the equipment. Prior to the issuance of a zoning clearance,
the final design and materials for the roof screen and
location of any roof mounted equipment must be approved by the
Director of Community Development.
22. All trash disposal areas shall be provided in a location which
will not interfere with circulation, parking or access to the
building, and shall be screened with a six foot high wall
enclosure with metal gates.
The final design of the trash enclosure shall be subject to
the issuance of a zoning clearance. Trash areas and recycling
bins shall be depicted on the construction plans, the size of
which shall be approved by the Director of Community
Development and the City Employee responsible for
recycling /solid waste management programs.
23. Pullover parking (overhangs) shall be limited to 24 inch
maximum. No vehicles shall be allowed to encroach onto
walkways or into the required landscaped setbacks along
roadways.
Vte -6- RMetutlon Ilo. VC -93-281
le-
Applicant: Moorpark United Methodist Church
Date: August 19, 1993
24. No exterior access ladder of any kind shall be permitted.
25. No downspouts shall be permitted on the exterior of the
building unless otherwise approved by the Director of
Community Development.
26. All exterior building materials and paint colors shall be
approved by the Director of Community Development to ensure
compatibility with adjacent development.
27. No asbestos pipe or construction materials shall be used.
28. All utilities are required to be underground to the nearest
off -site utility pole except through transmission lines.
Prior to the issuance of a zoning clearance, the applicant
shall submit a plan for review and approval to the Director of
Community Development which identifies how compliance with the
undergrounding requirement will be met.
29. If skylights are proposed, the specific type and model must be
approved by the Director of Community Development to ensure
that they shall be of an opaque type to minimize evening
illumination as viewed from the exterior.
30. All roof mounted equipment and other noise generation sources
on -site shall be attenuated to 55 dBA at the property line, or
to the ambient noise level at the property line measured at
the time of the occupant request, excluding the church chimes.
31. The applicant shall deposit with the City a Condition
Compliance review fee with the Department of Community
Development, to cover costs incurred by the City for Condition
Compliance review.
32. For all exterior lighting, a lighting plan shall be prepared
by an electrical engineer registered in the State of
California and submitted to the Director of Community
Development and the City Police Department for review and
approval. The lighting plan shall achieve the following
objectives: Avoid interference with reasonable use of
adjoining properties; minimize on -site and off -site glare;
provide adequate on -site lighting; limit electroliers height
in order to avoid excessive illumination and provide
structures which are compatible with the total design of the
facilities.
PON .7. NMOlutlan No. vC -43 -281
r-
Applicant: Moorpark United Methodist Church
Date: August 19, 1993
The lighting plan shall include the following:
a. A photometric plan showing a point -by -point foot
candle layout to extend a minimum of twenty feet
(201) outside of the property lines. Layout plan to
be based on a ten foot (101) grid center;
b. Maximum overall height of fixtures shall be twenty
feet (201);
C. Fixtures must possess sharp cut -off qualities with
a maximum of one foot candle illumination at the
property lines;
d. There shall be no more than seven -to -one (7:1)
ratio of level of illumination shown (maximum -to-
minimum ratio between.lighting standards);
s. Energy efficient lighting fixtures shall be
provided which are compatible with adjacent
properties;
f. No light shall be emitted above the 90 degree or
horizontal plane;
g. in order to prevent light "spillage" and glare all
parking lights shall be fully hooded and
backshielded. All lighting fixtures shall be
equipped with a minimum of a 45 degree shield;
additional shielding may be required at the
discretion of the Director of Community
Development.
PRIOR TO THE ISSUANCE OF A BUILDING PERMIT, THE FOLLOWING
CONDITIONS SHALL BE SATISFIED:
33. An "Unconditional Will Serve Letter" for water and sewer
service will be obtained from the Ventura County Waterworks
District No. 1.
34. If any archaeological or historical finds are uncovered during
excavation operations, the permittee shall assure the
preservation of the site; shall obtain the services of a
qualified archaeologist to recommend disposition of the site;
and shall obtain the Director of Community Development's
written concurrence of the recommended disposition before
resuming development.
PON -a- Resolution W. vC- 93 -251
Applicant:
%^ Date:
Moorpark United Methodist Church
August 19, 1993
PRIOR TO OCCUPANCY THE FOLLOWING CONDITIONS SHALL BE SATISFIED:
35. All parking areas shall be surfaced with asphalt or concrete
and shall include adequate provisions for drainage, striping
and appropriate wheel blocks, curbs, or posts in parking areas
adjacent to landscaped areas. The on -site parking lot shall
be re- stripped indicating 9' x 20' parking stalls; no parking
stalls shall be located within ten (10) feet of the driveway
entrance of on Flory Avenue; a total of 16 on -site parking
spaces shall be provided.
36. Prior to the issuance of a zoning clearance to tenant
occupancy, the proposed use shall be reviewed and approved by
the Ventura County Environmental Health Division to ensure
that the proposal will comply with all applicable State and
local regulations related to storage, handling, and disposal
of potentially hazardous materials, and that any required
permits have been obtained. 'If required by the County
Environmental Health Division, the applicant shall prepare a
hazardous waste minimization plan.
37. All landscaping and planting shall be installed and inspected
prior to issuance of a Zone Clearance for occupancy.
38. A complete landscape plan (2 sets), together with
specifications and a maintenance program shall be prepared by
a State Licensed landscape Architect, generally in accordance
with the Ventura County Guide to Landscape Plans, and in
compliance with the City of Moorpark Zoning Code and shall be
submitted to the Director of Community Development. The
applicant shall bear the total cost of the landscape plan
review and final installation inspection. The landscaping and
planting plan submitted for review and approval shall be
accompanied by a deposit to cover all landscape plan check and
inspection fees. The final landscape plans shall be approved
by the Director of Community Development prior to issuance of
a Zone Clearance for occupancy. The landscape plan shall
indicate the total value of the installed landscaping and
indicate where the $3,468.00 (the cost of the removal of three
tress in order to expand the church) for additional
landscaping has been accomplished; the value of the tree
replacement shall be over and above the normal landscaping
required. If the applicant does not want to install
additional landscaping at a value of $3,468.00, the applicant
shall be the landscaping mitigation fee of $3,468.00 to the
Department of Community Development. Further, the trees
provided to meet the requirements of the tree removal
sanctions shall be over and above the landscaping normally
required.
r�
Pqo -9- Noaolutlan No. K- 45-281
Applicant:
Date:
Moorpark United Methodist Church
August 19, 1993
39. No use for which this permit is granted shall be commenced
until a Certificate of Occupancy has been issued by the
Building and Safety Division.
In addition, no Certificate of Occupancy may be issued until
all on -site improvements specified in this permit have been
completed or the applicant has provided a Faithful Performance
Bond in an amount to be determined by the Director of
Community Development.
Said on -site improvements shall be completed within 120 days
of issuance of the Certificate of Occupancy. In case of
failure to comply with any term or provision of this
agreement, the City Council may by resolution declare the
surety forfeited.
Upon completion of the required improvements to the
satisfaction of the Director of Community Development, the
surety may be exonerated by action of the Director of
Community Development.
40. At the time water service connection is made for the future
expansion, cross connection control devices shall be installed
for the water system in accordance with the requirements of
the Ventura County Environmental Health Department.
41. The applicant is required to replace existing wood light poles
with marbelite lighting poles .along the frontage of the
subject site on Flory Avenue. The applicant will be required
to underground the electrical service to each pole. It may be
possible to remove existing lighting and utilize the existing
poles along the school frontage, in order to meet this
criteria. The applicant is encouraged to negotiate with staff
and the School District on this issue.
42. The applicant agrees to participate in and be a part of any
landscape maintenance district which the City may form related
to efforts to beautify the downtown.
43. A 6' wrought iron gate shall enclose the entire length of the
west side of the property. A 6' self - closing wrought iron
gate shall also enclose the parking lot on the east side of
the property facing Flory Street. A 6' self- closing wrought
iron gate shall be installed 25 feet from the property line on
Third Street in the walkway area. All gates shall be closed
outside of the normal hours of operation.
PW -10- Rrolutlan No. K -93-231
Applicant: Moorpark United Methodist Church
Date: August 19, 1993
AFTER ISSUANCE OF A CERTIFICATE OF OCCUPANCY, THE FOLLOWING
CONDITIONS SHALL BE APPLICABLE:
44. The striping for parking spaces shall be maintained so that it
remains clearly visible.
45. No later than ten (10) days after any change of property
ownership or change of lessee(s) or operator(s) of the subject
building, there shall be filed with the Director of Community
Development the name(s) and address(es) of the new owner(s),
lessee(s) or operator(s) together with a letter from any such
person(s) acknowledging and agreeing with all conditions of
this permit.
46. Prior to initial occupancy or any subsequent change of tenant
occupancy, the owner of the subject building, or the owners
representative shall apply for a zoning clearance from the
Community Development Department.
The purpose of the zoning clearance shall be to determine if
the proposed uses(s) are compatible with the zoning and terms
and conditions of the permit.
47. The continued maintenance of the permit area and facilities
shall be subject to periodic inspection by the City. The
permittee shall be required to remedy any defects in ground
maintenance, as indicated by the Code Enforcement Officer
within five (5) days after notification.
48. All uses and activities shall be conducted inside the
buildings, except as authorized by the Director of Community
Development as seen in Exhibit 2, attached. All temporary
activities not listed on Exhibit 2 or within these conditions
of approval, including wedding receptions, which are conducted
inside, outside or outside the normal hours of operation,
requires a Temporary Use Permit or a CUP, as determined by the
Director of Community Development. If any of the Annual
Repeating Activities (see Exhibit 2) are to occur more than
once a year, a Temporary Use Permit or a CUP, as determined by
the Director of Community Development, will be required.
CITY ENGINEER CONDITIONS
PRIOR TO ISSUANCE OF ZONE CLEARANCE, FOR OCCUPANCY:
49. The applicant shall improve the alley adjacent to the project.
This improvement shall include repairing all damaged /failed
pavement and overlaying the alley along the property frontage
with Type II slurry.
PW -11- l000lution No. PC -93-281
Applicant:
!1 Date:
Moorpark United Methodist Church
August 19, 1993
PRIOR TO ISSUANCE OF A ZONE CLEARANCE FOR OCCUPANCY
50. The applicant shall comply with the Ventura County Waterworks
District No. A, "Rules and Regulations ", including all
provisions of or relating to the existing Industrial Waster
Discharge Requirements and subsequent additions or revisions
thereto. Ultra low plumbing fixtures are required in all new
construction.
PRIOR TO THE ISSUANCE OF A OCCUPANCY PERMIT, THE FOLLOWING
CONDITIONS SHALL BE MET:
51. Lighting devices shall be a minimum of 8 feet in height and a
maximum height of 20 feet and shall eliminate anyone on the
ground from tampering with them.
52. Landscaping shall not cover any exterior door or window.
53. Landscaping at entrances /exits or at any intersection within
the parking lot shall not block or screen the view of a seated
driver from another moving vehicle or pedestrian.
54. Landscaping (trees) shall not be placed directly under any
overhead lighting which could cause a loss of light at ground
level.
55. All entrance /exit driveways shall be a minimum of 18 feet in
width with radius curb returns or 22 feet in width without
radius curb returns.
56. All exterior doors shall be constructed of solid wood core, a
minimum of 1 and three quarters inches thick, or of metal
construction. Front glass doors commonly used for entry are
acceptable but should be visible to the street.
57. Doors utilizing a cylinder lock shall have a minimum five (5)
pintumbler operation with the locking bar or bolt extending
into the receiving guide a minimum of 3/4 inch.
58. There shall not be any easy exterior access to the roof area,
i.e. ladders, trees, high walls, etc.
59. If an alarm system is used, it shall be wired to all exterior
doors and windows and to any roof vents or other roof openings
where access may be made.
Ppe -12- Rwolutlan Ro. PC- 93-281
Applicant:
Date:
Moorpark United Methodist Church
August 19, 1993
60. Address shall be clearly visible to approaching emergency
vehicles and mounted against a contrasting color. Address
numbers shall be a minimum of 6 inches in height and
illuminated during the hours of darkness.
61. Front door entrances shall be visible from the street.
DURING CONSTRUCTION THE FOLLOWING CONDITIONS SHALL APPLY:
62. A licensed security guard is recommended during the
construction phase, or a 6 -foot high chain link fence shall be
erected around the construction site.
63. Construction equipment, tools, etc., shall be properly secured
during non - working hours (for future expansion).
64. All appliances (microwave ovens, dishwashers, trash
compactors, etc.) shall be properly secured prior to
installation during non - working hours. Al serial numbers
shall be recorded for identification purposes.
65. If an alarm system is used, it should be wired to all exterior
doors and windows and to any roof vents or other roof openings
where access may be made.
66. A "Police Facilities Fee ", shall be assessed. This fee is due
when the buildings permits are pulled for construction of the
project.VENTURA COUNTY FIRE DEPARTMENT CONDITIONS
PRIOR TO CONSTRUCTION, THE FOLLOWING CONDITIONS SHALL BE SATISFIED:
67. A "Fire Facilities Fee", shall be assessed. This fee is due
when the building permits are pulled for construction of the
project.
68. That prior to construction, the applicant shall submit two
site plans to the Ventura County1Bureau of Fire Prevention for
approval of the location of fire lanes. The fire lanes shall
be posted in accordance with California Vehicle Code, Section
22500.1 and Article 10 of the Uniform Fire Code prior to
occupancy.
Pam -13- RMolutlon Ro. PC- 43 -207
Applicant: Moorpark United Methodist Church
Date: August 19, 1993
69. That address numbers, a minimum of 6 inches high, shall be
installed prior to occupancy, shall be of contrasting color to
the background. Where structures are setback more than 250
feet from the street, larger numbers will be required so that
they are distinguishable from the street. in the event a
structure(s) is not visible from the street, the address
number(s) shall be posted adjacent to the driveway entrance.
70. Prior to construction, the applicant shall submit plans to the
Fire District for approval of the location of hydrants. On
plans, show existing hydrants within 300 feet of the
development.
71. That fire hydrants shall be installed and in service prior to
combustible construction and shall conform to the minimum
standards of the Moorpark Water Works Manual:
a. Each hydrant shall be 6 inch wet barrel design and
shall have one 4 inch and two 2 1/2 inch outlet(s).
b. The required fire flow shall be achieved at no less
than 20 psi residual pressure.
C. Fire hydrants shall be spaced 300 feet on center,
and so located that no structure will be farther
than 150 feet from any one hydrant.
d. Fire hydrants shall be recessed in from curb face
24 inches at center.
72. That the minimum fire flow required is determined by the type
of building construction, proximity to other structures, fire
walls, and fire protection devices provided, as specified by
the I.S.O. for determining Required Fire Flow. Given the
present plans and information, the required fire flow is
approximately 2,250 gallons per minute. The applicant shall
verify that the water purveyor can provide the required volume
at the project.
73. Building(s) shall be protected by an automatic sprinkler
system; plans shall be submitted, with payment for plan check,
to the Ventura County Bureau of Fire Prevention for review.
74. Any structure greater than 5,000 square feet in area and /or 5
miles from a fire station shall be provided with an automatic
fire sprinkler system in accordance with Ventura County
Ordinance Number 14.
P"W -14- Resolution No. K -93 -281
Applicant:
Date:
Moorpark United Methodist Church
August 19, 1993
75. That building plans of all A, E and i occupancies shall be
submitted to the Ventura County Bureau of Fire Prevention for
plan check.
76. Plans for any fire alarm system shall be submitted to the Fire
District for plan check.
77. That fire extinguisher shall be installed in accordance with
National Fire Protection Association, Pamphlet 110. The
placement of extinguisher shall be reviewed by the Fire
Prevention Bureau.
78. Plans for the installation of an automatic fire extinguishing
system (such as halon or dry chemical) shall be submitted tot
the Fire District for plan check.
79. That all grass or brush exposing any structures shall be
cleared for a distance of 100 feet prior to framing, according
to the Ventura County Weed Abatement Ordinance.
80. Commercial trash dumpsters and containers with an individual
capacity of 1.5 cubic yards or greater, shall not be stored
within 5 feet of openings, combustible walls, combustible roof
save lines, unless protected by approved automatic fire
sprinklers. (Uniform Fire Code, Article 11).
81. All structures on -site will require retrofitting of a
sprinkler system in existing occupancy per County Ordinance
Number 14.
82. An alarm system shall be required per Uniform Building and
Fire Codes for educational and gssembly occupancies.
83. Water systems may be required to be upgraded.
Attached: Exhibit 2
Vpa -15- RMOluttan No. K- 93-291
N
r
Applicant: Moorpark United Methodist Church
Date: August 19, 1993
EXHIBIT 2
MOORPARK UNITED METHODIST CHURCH (CUP 92 -4)
STANDARD AND TYPICAL OUTSIDE BUILDING USAGE
A. DAILY OR WEEKLY REPEATING ACTIVITIES
1. Rainbow Children play (weekdays).
2. Church Children play (weekend mornings).
3. Worship Service fellowship (weekend mornings).
4. Apostolic Church fellowship (weekend afternoons).
5. Youth Group recreation (weekend evenings).
6. Cub Scout recreation (weekday evening).
7. Boy Scout recreation (weekday evenings).
S. Girl Scout recreation (weekday afternoon and evenings).
B. ANNUAL REPEATING ACTIVITIES
1. Cub Scout Pancake Breakfast with outside play (front lawn
- February, Saturday morning).
2. CROP Walk Finishing Line reception (front lawn - March,
Sunday afternoon).
3. Cub Scout race (front lawn - March, Saturday morning).
4. Boy Scout Pancake Breakfast with outside play (front lawn
- April, Saturday morning).
5. Summer Church BBQ Picnic (front lawn - June, Sunday
morning and afternoon) .
6. Vacation Bible School with outside children play (front
lawn and playground - two weeks in August of mornings and
evenings).
7. Rally Day Picnic (front lawn - September Saturday).
8. Annual Church Rummage Sale (front lawn - September,
Saturday).
9. Country Days' Ice Cream Social (front lawn - October,
Saturday).
10. Turkey Dinner with outside play (front lawn and
playground - November, Saturday).
11. Alternative Christmas Market with outside play (front
lawn - December, Sunday).
Vyo -16- Resolution Ro. K- 93 -281