M E M O R A N D U M
TO: The Honorable Mayor and City Council
FROM: Community Services Department
DATE: March 10, 1987
STEVEN KUENY
City Manager
CHERYL J. KANE
City Attorney
PATRICK RICHARDS, A.I.C.P.
Director of
Community Development
R. DENNIS DELYEIT
City Engineer
JOHN V. GILLESPIE
Chief of Police
THOMAS P. GENOVESE
City Treasurer
SUBJECT: GRIFFIN SENIOR PARK IMPROVEMENT PROJECT - AWARD OF CONTRACT
ITEM
Based upon City Council direction on March 4, 1987, staff has
reviewed the scope of the above project with the Parks &
Recreation Commissioner's on March 9, 1987.
Attached for City Council review is an Overview of the Project
and Costs as recommended by the Commissioners along with revisions
and corrections to February 25th's report noted.
Regarding the gazebo and drinking fountain, recommendation #2 in
the February 25th report, the Commission voted not to pursue this
item due to financial considerations relative to the costs of
$43,500 associated with the recommendation below.
RECOMMENDED ACTION
City Council award the contract for the Griffin Senior Park
Improvement project, as it was bid and approved to BLM
Constructors as the lowest responsible bidder in the amount of
$28,200. Projects cost to include the play equipment, swing
set, backstop, minor landscape and irrigation in,the amount
of $15,284, total project not to exceed $43 , 500 M00VA�:.:, CAL:M^T),N1A
`tcii�l vCL''1r;�
The Commission vote was 3 -2. Motion carried.
of _. 7�.1. -� L...
AC-10-
799 Moorpark Avenue Moorpark, California 93021 (805) 529 -6864
BLM
Benches(3) & slab, BarBQ(3) &
slab, trash(3) & slab, picnic
tables & slab(5), 240+ lineal
feet plus walkway, curbs &
sand.
City
OVERVIEW GRIFFIN SENIOR PARK IMPROVEMENT PROJECT
2/19/86 Price Increases
Original and Total of
Estimate Additions * **
$12,537.00 + $9,944.00
Play Equipment $11,296.00
Swing Set
Backstop $ 1,477.00
Minor Landscape & Irrigation $ 1,000.00
Bid
Amount
$28,200.00
$28,200.00
$10,557.00 **
750.00 750.00*
$ 1,477.00*
$1,500.00 $ 2,500.00 **
* The original report dated February 25, 1987
did not break these costs out.
** These amounts were corrected from the $2,300, 12,000
& 42,500 shown in the February 25, 1987 report.
* ** Additions approved by Parks & Recreation Commission:
Concrete curb & walkway 5,360 This reflects straight price increase
2 Picnic tables & slabs 1,820
2 Bar BQ & slabs 500
2 trash & slabs 1,014 Combination additions & price increase
Swing Set 750/
Sump 500
$9,944.00
$15,284.00
$28,200.00 BLM
$15,284.00 City
$43,484.00 **
- 30,000.00 Griffin
$13,484.00 Out of
City's
30,000
Balance of $60,000= $16,500