HomeMy WebLinkAboutAGENDA REPORT 1995 0920 CC REG ITEM 08MAGENDA REPORT
City of Moorpark
To: The Honorable City Council
From: Ken Gilbert, Director of Public Works
Date: September 12, 1995 (Meeting 9- 20 -95)
//,.� - /c�-(6 7
ITEM O. A
Subject: Consider Bids for the 1995 Slurry Seal Project
BACKGROUND
1. On August 2, 1995, the City Council authorized staff to
advertise for receipt of bids for the application of slurry seal
to certain designated streets throughout the City.
2. Plans and specifications were placed on sale and notices were
published advising that bids were due by 2:00 p.m. September 5,
1995.
3. On Monday August 28, 1995, staff received a call from a supplier
of latex material required to be added to the slurry seal. He
was concerned that the City's specifications did not appear to
allow the use of his product. After discussing the matter with
the City Engineer's Office, it was decided to issue an Addendum
to the specifications which would permit the use of this
product. This change provided the bidders with more options in
selecting the type of latex material to be used, which could
have the effect of lowering bid costs.
4. Addendum #1 was sent to all of the plan holders by Certified
Mail, Return Receipt Requested, on Wednesday, August 30, 1995.
DISCUSSION
A. Bid Results
Bids for the subject project were received and opened on
September 5, 1995. A tabulation of the bid results is attached
as Exhibit 1. A summary is as follows:
Vendor
1. Asphalt Maintenance
2. California Pavement Maint.
3. Roy Allan Slurry Seal
slry95b.avd
Amount
238,492.50
244,456.20
267,575.10
Addendum #1
Acknowledaed
No
Yes
No
( )OUSS
1995 Slurry Seal Project
September 20, 1995
Page 2
B. Qualifications
All of the bidders are qualified to perform the work required.
C. Addendum Acknowledgement
The bid received from Vendor #2 includes the required
acknowledgment of the receipt of Addendum #1. The bids received
from Vendors #1 and #3 did not include this acknowledgement.
D. Bid Withdrawal
In addition to the bids described in Exhibit 1, on the morning
of September 5, 1995, the staff received a request (by telephone
and fax) from another firm, that the bid they had sent by
courier be withdrawn and returned unopened. Staff complied with
that request. The reason cited for this request was that
Addendum #1 was received subsequent to the transmittal of their
bid.
E. Impact of Addendum #1
As briefly discussed in the Background of this report, Addendum
#1 expands the specification pertaining to the latex material to
be used, by providing more options to the bidders. The net
effect, if any, would be to reduce costs by allowing the bidders
more options and encouraging competition. A bidder's awareness
of this change could allow a bidder to present a lower bid.
The following is a discussion of the impact of Addendum #1, if
any, on each of the bids received.
1. Vendor #1 presented the lowest bid. Vendor #1 has advised
the City that, even though they were unaware of Addendum #1
and therefore did not acknowledge it in their bid, the oil
supplier they intend to use was aware of the Addendum and was
only able to participate in the process and provide a lower
price for asphalt emulsion than other suppliers because of
the issuance of this Addendum. Therefore, had this bidder
been aware of and had acknowledged the Addendum, their bid
amount would have been unchanged.
2. The bid presented by Vendor #2 is $5,963.70 higher than the
bid of Vendor #1, even though they were aware of and
acknowledged the Addendum.
slry95b.awd
000Lsy
1995 Slurry Seal Project
September 20, 1995
Page 3
3. The bid presented by Vendor #3 is $29,082.60 higher than the
bid of Vendor #1. For the purpose of this analysis, it is
assumed that this bid amount was based on higher material
costs resulting from an unawareness of the Addendum. After
discussing the various material costs with the bidders, it
has been determined that the potential cost reduction which
could result from the awareness of the Addendum, is far less
than $29,082.60. This bidder's awareness of the Addendum
would not have changed the ranking of his bid.
For these reasons it is the determination of staff that the
acknowledgement of the Addendum, or the lack thereof, had no
impact on the bid results.
F. Waiver of Irregularities
As stipulated in the bidding documents, the City has the right
to waive any irregularities in a bid. Accordingly, the City may
waive the failure of Vendor #1 to acknowledge the Addendum and
declare that bidder to be the lowest responsive bidder.
G. Protest
Staff has received letter from Vendor #2 (Exhibit 2), in which
they state that they would protest the award of a contract to
another firm.
H. Fiscal Impact
Should the City Council decide to
bidders, a project costs (based
Vendor #2) is as follows:
1. Total Project Cost Estimate
award a contract to one of the
on the bid amount submitted by
Est.
Element Cost ($)
• Design 200
• Construction 244,456
• Construction Contingency (10 %) 24,544
• Admin & Insp 26,000
Total 295,200
2. Budget: The budget for this project (03 -142- 903 -0210) is
$400,000.
slry95b.ewd
V0V0()
1995 Slurry Seal Project
September 20, 1995
Page 4
I. Schedule
If a contract is awarded, construction should begin in October
and be completed within sixty (60) days.
SUMMARY
The City Council could declare Vendor #1 unresponsive and award the
contract to Vendor #2 at a slightly higher contract price. The
City Council could also waive the irregularity in the bid presented
by Vendor #1 and award that firm the contract. It appears likely,
however, that the latter action would give rise to a protest from
Vendor #2. Such a protest could cost the City considerable time
and money to resolve. On the other hand, the delay which would
result from the rejection of bids and the readvertisement of the
project will cost little. It is even possible that lower bids
would be received.
CONCLUSION
For the reasons stated above, staff recommends that the bids be
rejected and the project readvertised.
RECOMMENDATION
Staff recommends that the City Council reject all bids and direct
staff to readvertise the project for receipt of bids.
SlryM.awd
( MWAL
September 5, 1995
---------------------------------------
- -------- - - - - --
City of Moorpark
Bid Results: 9 -5 -95
1995 Slurry Seal Project
--------------------------------------
ITEM DESCRIPTION Qty Units
1 Traffic Control 1 IS
2 Public Notice 1 LS
3 A/C R &R Areas 200 SF
4 Crack Sealing 1 LS
5 A/C Leveling Course 5 Tons
6 Type I Slurry Seal 1700 ELT
7 Type II Slurry Seal 140 ELT
8.1 18 Limit Bar (121) 2900 LF
8.2 19 Crswlk White- 12" 250 LF
8.3 #11 Yel Cntr Line 160 LF
8.4 #14 Dluble Yellow 3100 LF
8.5 #16 Yel Cross Walk 750 LS
8.6 #23 Arrows 3 EA
8.7 #23 Words & Sym 652 EA
9 Release 1 LS
----------------------
----------------------
Engineer's Est.
--------------- - - - - --
Unit $ TOTAL BID
4950.00 4,950.00
550.00 550.00
9.46 1,892.00
6600.00 6,600.00
363.00 1,815.00
81.40 138,380.00
83.60 11,704.00
0.52 1,508.00
0.07 17.50
0.29 46.40
0.29 899.00
0.55 412.50
12.10 36.30
6.66 4,342.32
1.00 1.00
--------------------
--------------------
VENDOR 1 * **
Asphalt Maintenance
1641 Tulare Ave
Visalia, CA 93292
Gregg Glick
(209) 627 -5373
Unit $ TOTAL BID
7000.00 7,000.00
7500.00 7,500.00
15.45 3,090.00
44000.00 44,000.00
1108.00 5,540.00
88.00 149,600.00
99.00 13,860.00
0.50 1,450.00
0.55 137.50
0.30 48.00
0.40 1,240.00
0.55 412.50
16.50 49.50
7.00 4,564.00
1.00 1.00
* ** Addendum #1 not
included
VENDOR 2
Calif. Pavement Maint
9390 Elder Creek Rd
Sacramento, CA 95829
Robert Blakey
(916) 381 -8033
Unit $ TOTAL BID
7000.00 7,000.00
3000.00 3,000.00
16.00 3,200.00
44000.00 44,000.00
440.00 2,200.00
95.70 162,690.00
96.31 13,483.40
0.55 1,595.00
0.60 150.00
0.33 52.80
0.44 1,364.00
0.60 450.00
18.00 54.00
8.00 5,216.00
1.00 1.00
Page 1
VENDOR 3 * **
Roy Allan Slurry Seal
11922 Bloomfield
Sante Fe Springs
Roy Allan
(310) 864 -3363
Unit $ TOTAL BID
5000.00 5,000.00
3500.00 3,500.00
10.00 2,000.00
69460.00 69,460.00
240.00 1,200.00
97.00 164,900.00
97.00 13,580.00
0.50 1,450.00
0.55 137.50
0.28 44.80
0.38 1,178.00
0.55 412.50
16.50 49.50
7.15 4,661.80
1.00 1.00
* ** Addendum #1 not
included
Total 173,154.02 238,492.50 244,456.20 267,575.10
()z
LtK�, [,> J. z
THE PAVEMENT
MAINTENANCE
COMPANY
September 7, 1995
City of Moorpark
Mr. Ken Gilbert
799 Moorpark Ave.
Moorpark, CA 93021
Subject: 1995 Slurry Seal Project
Dear Mr. Gilbert,
As the lowest responsible bidder on the subject project we
should be awarded the project. Of the contractors who
acknowledged Addenda number one we had the lowest bid, making
us the lowest responsible bidder. According to our attorney
the law says projects are to be awarded to the lowest
responsible bidder.
To award a contract to a contractor who did not comply with
the bid requirements at bid time is unfair to the other
contractors. This is especially true when there is only 2.5%
difference between the bidders.
While re- bidding the project is another alternative to award,
we feel by complying with the bidding requirements we should
be awarded the project.
Sincerely,
Robert A. Blakey
Vice President
California Pavement Maintenance Company, Inc. • 4891 Ronson Court, Ste. J • San Diego, CA 92111
(619) 268 -9884 • Fax (619) 268 -1529 • California License # 374514
000;