HomeMy WebLinkAboutAGENDA REPORT 1994 0518 CC REG ITEM 08EITEM S .
CITY MANAGER APPROVED CONTRACTS
Contractor: Picon, Inc.
Prior Approval: $ 63,369.00
Date of Contract: February 28, 1992 Present Approval: $ 4,722.00
Total Contract: $ 68,091.00
Year to Date
for this Contractor:
Purpose (s) Additional time due to contract delay as described in
letter dated May 2, 1994.
Location(s): Arroyo Vista Community F-ark
11JN:
Date(s) of Performance:
Other Information:
City Council Agenda:
Please note the City Managers limit of authority to increase contract is
$6337.00. City Council approval date is JuLy 7, 1992.
These additional project management :osts are the result of the fact
that the contractor has exceeded the original contract time. The City
is considering recovery of all or a portion of these cost from the
contractor.
PW /KCG94001 /RPT /05/09/94