HomeMy WebLinkAboutAGENDA REPORT 1993 0106 CC REG ITEM 08ITO:
FROM:
DATE:
MOORPARK ITEM
799 Moorpark Avenue Moorpark, California 93021 (805) 529.6864
c,-.,y Coundl pl,�c;:, ;3
AGENDA REPORT cf 199
THE HONORABLE CITY COUNCIL <,CTION:�
DIRK LOVETT, ASSISTANT CITY ENGINEER Co
�y
JANUARY 6, 1992
SUBJECT: HIGH STREET REHABILITATION PROJECT
BACKGROUND:
The City Council awarded the High Street Rehabilitation and Storm
Drain Project to Miki Construction Co. on March 25, 1992. The
project involved the retrofit of large amounts of curb, gutter and
sidewalk on High Street between Moorpark Ave. and Spring Rd. A new
storm drain system was also installed.
Construction began on May 18, 1992 and, excepting punch list items,
was completed on schedule by the August 11, 1992 deadline. Several
change orders were authorized for the contract and a discussion has
been attached for your review. (Exhibit 1)
All work specified as part of the contract plans and specifications
has been completed and accepted by the City Engineer and Public
Works Director. A Notice of Completion has been prepared for
recordation (Exhibit 2).
Stop payments have been received from several of the subcontractors
and the State Labor Commission. Miki Construction is presently
working to have them released. An analysis of the claims has been
prepared by the finance department and is attached for your
reference. (Exhibit 3)
FISCAL IMPACT•
1. Construction Contract:
Bid Amount
Quantity Adjustment
Subtotal
Change
Change
Change
Change
Change
PAUL W. LAWRASON JR BERNAR00 M PEREZ
Mayor Mayor Pro Tem
order #1
order #2
order #3
order #4
order #5
Total
SCOTT MONTGOMERY
Covnc—emoer
$215,317.85
a
$216,517.65
$ 0.00
$ 1,089.00
$ 5,400.00
$ 1.596.00
8 607.20
$225,263.85
ROY E TALLEY JR JOHN E. WOZNIAK
Cwnciimem0er CouncilmemDer
A copy of the final payment authorization is attached (Exhibit 4).
2. Total Project:
A recap of total project costs are summarized in the
attached Exhibit No. 5
Contract change orders and additional work at contract costs have
amounted to $9,946 (4.6%) of the approved loo contingency, to be
used.
RECOMMENDATION:
1. Accept the described work as complete.
2. Instruct the City Clerk to file the Notice Of Completion.
3. Authorize the final progress payment and release the
retention upon satisfactory clearance of the existing Stop
Payment claims and 35 day lien period.
co: CC Accept High St.
Attachments (5)
MOORPARK
799 Moorpark Avenue Moorpark, California 93021 (805) 529-6864
TO: KEN GILBERT, DIRECTOR OF PUBLIC WORKS
FROM: CHRIS OBERENDER, ASSISTANT ENGINEER Co
DATE: SEPTEMBER 11, 1992
SUBJECT: HIGH STREET CHANGE ORDERS
Attached are the change orders that were the subject of our
meeting in your office on Sept. 10th. Provided is a discussion on
the history behind each item so they can be fully evaluated.
Change Order #1-
Was submitted as a result of the storm drain realignment two feet
to the north and a transition to meet the existing centerline.
This was necessary to avoid existing utilities. Miki agreed that
he would notify the surveyor and make the adjustments at no charge
to the City
Total expense to the City-
Change Order #2-
4�
This Change Order was originally signed by Miki at no cost to the
City on May 29, 1992. Since then Miki has resubmitted the Change
Order reflecting charges that he feels were due him for the work.
Evidently it was his initial understanding when he signed the
change order that he would receive the difference from the
modified location in additional unit costs. Since the bid for
conduit construction was lump sum it left no option for these
items to be included.
The cost reflects the field modification necessitated by the
additional crossing and extra pull box locations. The extra
crossing was the result of restrictive field conditions on the
northeast corner of Magnolia and High St.
Originally the intent was to cross High St. on the east side of
Magnolia and then lay the lighting conduit under the sidewalk in
front of "Sweet Cinns ". In discussions with you it was decided
that the concrete sidewalk on Lhat corner was in excellent shape
EXHIBIT 1
PAUL W. LAWRASON JR. BERNARDO M PEREZ SCOTT MONTGOMERY ROY E. TALLEY JR JOHN E. WOZNIAK
Mayor Mayor Pro Tern Councllmember CounclImember Covncllmember
and to avoid disruption to the businesses on that corner, we
should not remove the sidewalk. This decision resulted in the need
for a different course for the conduit. To save the sidewalk,
avoid conflicts, and provide lighting conduit to the trees along
the north side of High St., on both sides of Magnolia, it was
necessary to make the second crossing.
It should be noted that had this additional crossing not been done
on High Street the City would have incurred approximately $1,800
for removals and replacement per the unit prices.
Remove and Replacement Credit $1,800
Change Order Expense (51,089)
Net Savings to the City $ 711
Change Order #3
This change order was submitted as the result of a different
existing street cross section than was shown on the plans. An
additional 5 inches of concrete was found below the existing AC on
High Street.
Initially I calculated the cost for the removals based on the
county's estimate list and the City Manager signed the Change
order for $4,900. After a review of the bid items I noticed that
the cost should have been calculated from the agreed upon bid
prices instead of the counties estimate sheet. The error was my
own and should be reflected in a modification to the change order
allowing the contractor $5,400 instead of $4,900.
Change Order #4
Change Order #4 is the result of Ventura County Flood Control
requirements that additional measures be used in the connection to
a Flood control structure.
Miki submitted this Change Order as a result of additional work
done to make the connection to the existing RC box structure under
High Street. we were not informed at the design stage that a
Flood Control structure would be involved in the project and hence
different standards were employed in the connection design and
construction. It was not until the project began that we were
required by Flood Control to get. a permit and implement a modified
storm drain connection requiring this additional work.
The contractor has documented the additional costs to our
satisfaction and shown them on the Change Order.
EXHIBIT 1
Change Order #5
During construction of the curb and gutter on the northwest corner
of High St. and Magnolia Ave. it was noted that the proposed curb
and flowline elevations would present problems with the pavement
and drainage configuration on that corner. The inspector caught
the problem prior to the curb and gutter being poured and the
corrective measures were brought to your attention.
co: High St. C. 0.
cc: Steve Kueny
Dirk Lovett
Correspondence
Project File
Attachments
EXHIBIT 1
City of Moorpark
Analyis of Contractor Retention &
Stop Notices Served
Miki Construction
As of December 11,1992
MIK1 CONSTRUCTION
Total Contract Amount
Total Contract Earned to Date
Total Paid To Date
Retention field
Stop Notices Served
Contractors Coldplating & Sweeping Service
Loera Paving Co. Inc
Labor Comission, State of California re: wages Owed
Labor Comission, State of California :Penalities
Total Stop Notices
Excess ( Deficiency ) Of Retention Held over
Stop Notices Served
Amount
$225,263.05
225,263.55
$202,576.25
$22,526.39
4,015.00
16,W0.Uu
1,340.14
4,250.UU
$26,113.14
(;93,586.75)
EXHIBIT 3
PROGRESS PAYMENT AUTHORIZATION #5
High Street Rehabilitation
Final payment
CONTRACTOR:
Date:
Miki Construction I
6016 Fenwood Ave.
Woodland Hills, CA
11/9/92
PAYMENT REQUEST ITEMS
TOTAL COMPLETED TO DATE
BID
EST.
UNIT
TOTAL
QTY. or %
ITEM
DESCRIPTION
QTY.
UNITS
BID PRICE
CONTRACT
COMPLETED
AMOUNT
1
Traffic Control
1
LS
$3,600.00
$3,600.00
100%
$3,600.00
2
4" P.C.C. Sidewalk
7000
SF
$2.25
$15,750.00
7,040
$15,840.00
3
Driveway
1916
SF
$2.50
$4,790.00
1,908
$4,770.00
4
6 " P.C.C. Curb & Gutter
680
LF
$11.00
$7,480.00
768
$8,448.00
5
Saw Cutting
1120
LF
$0.75
$840.00
3829
$2,871.75
6
Handicapped Ramps
252
SF
$3.75
$945.00
266
$997.50
7
Remove Existing AC
53
CY
$20.00
$1,060.00
76
$1,520.00
8
Remove Curb & Gutter
637
LF
$3.25
$2,070.25
768
$2,496.00
9
Catch Basin #2
3
EA
$2,500.00
$7,500.00
3
$7,500.00
10
Saddle connection
2
EA
$650.00
$1,300.00
1
$650.00
1 1
Local Depression
5
EA
$475.00
$2,375.00
5
$2,375.00
12
Install 18" RCP
83
LF
$47.30
$3,925.90
75
$3,547.50
13
Install 24" RCP
538
LF
$50.25
$27,034.50
565
$28,391.25
14
Install 33" RCP
492
LF
$60.80
$29,913.60
458
$27,846.40
15
Tree Root Barrier
500
LF
$10.00
$5,000.00
280
$2,800.00
16
Catch Basin #3
2
EA
$3,800.00
$7,600.00
2
$7,600.00
17
Junction Structure
2
EA
$750.00
$1,500.00
3
$2,250.00
18
Manholes
4
EA
$1,725.00
$6,900.00
4
$6,900.00
19
A.C.
413
TON
$43.00
$17,759.00
470
$20,210.00
20
6" Base
300
CY
$18.00
$5,400.00
250
$4,500.00
21
Grinding
722
SY
$3.30
$2,382.60
1236
$4,078.80
22
Cross gutter & Spandral
1140
SF
$3.75
$4,275.00
927
$3,476.25
23
Yellow Centerline
2000
LF
$0.77
$1,540.00
2000
$1,540.00
24
White Parking Markings
1160
LF
$0.40
$464.00
348
$139.20
25
Remove Catch Basin
2
EA
$730.00
$1,460.00
2
$1,460.00
26
Relocate gas meter
1
EA
$560.00
$560.00
1
$560.00
27
Remove Striping
2000
LF
$1.86
$3,720.00
0
$0.00
28
Earthwork
1
LS
$13,750.00
$13,750.00
100%
$13,750.00
EXHIBIT 4
Page 1
BID
EST.
UNIT
TOTAL
QTY. or %
ITEM
DESCRIPTION
QTY.
UNITS
BID PRICE
CONTRACT
COMPLETED
AMOUNT
29
Survey
1
LS
$4,000.00
$4,000.00
100%
$4,000.00
30
Clearing & Grubbing
1
LS
$2,000.00
$2,000.00
100%
$2,000.00
31
Adjust meter box to grad(
11
EA
$75.00
$825.00
11
$825.00
32
Adjust manhole elevation
6
EA
$275.00
$1,650.00
4
$1,100.00
33
Adjust valve Cvr. El.
8
EA
$170.00
$1,360.00
8
$1,360.00
34
Remove Exist Pole
7
EA
$50.00
$350.00
7
$350.00
35
Install Yard Drains
2
EA
$200.00
$400.00
4
$800.00
36
Relocate Telephone Line
1
LS
$2,300.00
$2,300.00
100%
$2,300.00
37
Temp AC Curb
50
LF
$10.00
$500.00
92
$920.00
38
8" Curb & Gutter
254
LF
$13.00
$3,302.00
256
$3,328.00
39
A/C rolled curb
61
LF
$15.00
$915.00
0
$0.00
40
2" PVC conduit/pull box
1
LS
$2,350.00
$2,350.00
100%
$2,350.00
41
18" X 18" catch basin
1
LS
$500.00
$500.00
100%
$500.00
42
Install 12" RCP
60
LF
$37.00
$2,220.00
55
$2,035.00
43
Remove Concrete
15
CY
$90.00
$1,350.00
46.5
$4,185.00
45
Contract Release
1
LS
$1.00
$1.00
1
$1.00
48
Remove Boardwalk
1
LS
$2,200.00
$2,200.00
100%
$2,200.00
49
Install Boardwalk
1
LS
$8,200.00
$8,200.00
100%
$8,200.00
SUBTOTAL
$215,317.85
$216,571.65
C01
S.D. Centerline Relocation
1
LS
$0.00
$0.00
100%
$0.00
CO2
2" PVC Conduit Relocatior
1
LS
$1,089.00
$1,089.00
100%
$1,089.00
CO3
Conc. Removal (C.041)
1
LS
$5,400.00
$5,400.00
100%
$5,400.00
C04
VCFCD Junction Structure
1
LS
$1,596.00
$1,596.00
100%
$1,596.00
C05
Resurvey /Reset Forms
1
LS
$607.20
$607.20
100%
$607.20
TOTAL
$225,263.85
Progre ent nz . n
TOTAL
$225,263.85
- -- - -- - -- -
t
- - - - -- --
LESS
10% Retention
$22,526.39
Reviewed By:
Date
SUB TOTAL
$202,737.47
LESS PRIOR
------------- - - - - --
---- - - - - --
PAYMENTS
$202,576.05
TOTAL DUE
$161.42
Approved By: Date
EXHIBIT 4
Page 2
Exhibit 5
Total Project Expenses
A re -cap of project
expenses is as
follows:
283,633
Description
Prior Years
FY 92193
Total
Sidewalks, Curb &
Design
29,000
110,548
29,000
Geotechnical Review
4,000
4,000
Biding (92 -002)
250,000
ITotal Budget
Consider Decorative
4,140
360,548
4,140
poles (91 -30)
Construction
183,418
41,846
225,264
Pepper Trees
140
140
Contract
Administration /
25,225
25,225
Inspection
(92 -06)
Total
216,422
671215
283,633
Budget Recap
Less Actual Cost
Fund 03
Fund 15
283,633
Project
Gas Tax
SB -821
Total
Sidewalks, Curb &
81,096
291452
110,548
Gutter
Storm Drain
250,000
250,000
ITotal Budget
331,096
29,452
360,548
Less Actual Cost
254,181
29,452
283,633
Budget Surplus
76,915
0
76,915
wp \rpt \highs E H I B I T 5