HomeMy WebLinkAboutAGENDA REPORT 1993 0106 CC REG ITEM 11EITEM � /•�•
MOORPARK
799 Moorpark Avenue Moorpark, California 93021 (805) 52g ARK, CALI�""�
ouncll NOC ,-
AGENDA REPORT
TO: The Honorable City Council
FROM: Kenneth C. Gilbert, Director of Public Works
DATE: December 29, 1992 (Council Meeting 1 -6 -93)
Ct
ACTION:
SUBJECT: Consider Bids for the Construction of the Community
Building and Gymnasium at Arroyo Vista Community Park.
OVERVIEW
This presents the bid results for the subject project and
recommends award of a contract for proposed construction.
DISCUSSION
A. Background
On November 30, 1992, the City received and opened bids for the
subject project. On December 2, 1992, the City Council reject
all bids and directed staff to re- advertise the project with
certain changes.
B. Revised Scope of Work
As recommended by the Public Works, Facilities and Solid Waste
Committee (Mayor Pro tem Montgomery and Councilmember Wozniak),
it is anticipated that the City Council will direct staff to
make certain changes to the project scope prior to re-
advertising. Those changes are summarized as follows:
1. Add Deduct Alternates -- All of the Add / Deduct Alternates
previously included in the bid documents were eliminated.
2. Deleted Items -- Most of the Add /Deduct Alternates remain as
a part of the Scope of Work. The items deleted from the
Scope of Work are as follows:
Ref.
Item Alt. i Description Remarks
MOORPARK, CAUFORN§k 1 Delete courtyard fountain in its entirety as shown To be considered for
City C Meetlno on 1 /A2, 11 /A17 and 1 /A9. Provide plumbing and construction at a later
of i 19q,� electrical stub for future fountain. date.
ACTIO : 4#�/O�
BY
PAUL W. LAWRASON JR. JOHN E. WOZNIAK SCOTT MONTGOMERY BERNARDO M. PEREZ ROY E. TALLEY JR.
Mayor Mayor Pro Tem Councilmember Councilmember Councilmember
Printed On Recycled Paper
Consider Bids Arroyo Vista Park
January 6, 1993
Page 2
3. Added Items -- The following items were added to the Contract
documents:
Ref .
Item Alt. I Description Remarks
I -- Provide sleeves in Gymnasium floor for the
placement of volleyball net poles.
J 21 Change contract time from 240 to 210 days.
K -- Add provisions for a $15,000 incentive payment for
the completion of construction sufficient for
occupancy by June 28, 1993.
L -- Clarify language regarding timely inspections to
be provided by City.
M -- Delete requirements for continuous inspections to
be paid be Contractor.
vp \rpt \avpt-ad2
Specific language to be
approved by City Attorney
and City Manager.
Allows Contractor to save
contract time.
Allows for more flexibility
and cost control by City.
Ref .
Item
Alt. I
Description
Remarks
B
2
Delete pavers at courtyard per Detail 5/A16 and
provide concrete walkway with heavy salt finish.
C
4
Delete all cabinetry as shown in Rooms No. 106,
To be provided under
110, 112, 114 and 115 in their entirety as shown
separate contract.
on Sheet A3 and interior elevations.
D
6
Delete ceramic tile in Kitchen Room No. 101.
Provide "Marlite" panels and sheet vinyl flooring
with integral cove base in lieu of finish
indicated.
E
7
Delete operable wall at Room No. 112 in its
entirety as shown on Floor Plan A -3 Grids A -3.
Provide soffit and framing as shown.
F
14
Delete flagpole indicated on site plan and
To be provided by City.
detailed per 5/A22.
G
18
Delete curved seat wall at courtyard as shown on
Addition of seating to be
Sheets Al, A2 and detailed on 1 and 8/A16.
considered in future
fountain design.
H
20
Delete pre- fabricated fireplace as shown on Sheet
A3 and detailed on 13, 17, 18 and 19/A18 (Sheet A
18).
3. Added Items -- The following items were added to the Contract
documents:
Ref .
Item Alt. I Description Remarks
I -- Provide sleeves in Gymnasium floor for the
placement of volleyball net poles.
J 21 Change contract time from 240 to 210 days.
K -- Add provisions for a $15,000 incentive payment for
the completion of construction sufficient for
occupancy by June 28, 1993.
L -- Clarify language regarding timely inspections to
be provided by City.
M -- Delete requirements for continuous inspections to
be paid be Contractor.
vp \rpt \avpt-ad2
Specific language to be
approved by City Attorney
and City Manager.
Allows Contractor to save
contract time.
Allows for more flexibility
and cost control by City.
Consider Bids Arroyo Vista Park
January 6, 1993
Page 3
4. Cost Estimate -- It is estimated that the value of the items
which have been deleted from the Scope of Work ( approximately
$70,000) will be off -set by the estimated value of the items
added. In addition, based on the bids previously submitted,
the architect has revised his construction cost estimate to
$1,750,000.
C. Fire Sprinklers
It was recently brought
City's architect that
requires the buildings t
#24 was added to the Bid
construction of a fire
Contractor.
D. Bid Results
to the attention of the City and the
the Ventura County Fire Department
o have Fire Sprinklers. Add Alternate
Documents providing for the design and
suppression sprinkler system by the
Attached as Exhibit 1 is a listing of the bid results.
Wesley Thomas Enterprises, Inc. submitted the lowest bid. This
firm also submitted a bid for the November 23 bid opening. They
then requested that they be allowed to withdraw their bid due to
a clerical error. Section 5105 of the Public Contracts Code
states that "A bidder who claims a mistake ... shall be
prohibited from participating in further bidding on the project
which the mistake was claimed ...." In the opinion of staff,
this statue requires the City to disqualify Wesley Thomas
Enterprises, Inc.
Jevon Construction Company submitted the next lowest bid. The
bidding documents require all bonds to be executed by an
admitted surety insurer. The bid bond submitted by this firm
did not comply with this requirement. In the opinion of staff,
the bid submitted by Jevon Construction Company should be
declared unresponsive.
Presuming the City Council agrees with the above findings, the
apparent low bidder is Allee Construction Company, Inc. with a
bid amount of $1,921,000.00
`rp \rpt \avph -&d2
Consider Bids Arroyo Vista Park
January 6, 1993
Page 4
E. Qualifications
The bid documents included information to assist the City in
evaluating the bidders' qualification to undertake and complete
the project in a satisfactory manner. Staff has reviewed the
information included in the proposal, made inquiries into the
reference provided and has determined that AIIee Construction
Company, Inc. is qualified to construct the project.
F. Committee Review
On Monday, December 28, 1992, the Public Works, Facilities and
Solid Waste Committee met to review the bids. It was the
opinion of the Committee that the amount bid by the apparent low
bidder, Allee Construction Company, Inc., exceeds the funds
available for the project. The Committee further recommends
that the bids be rejected and the project be abandoned.
Staff and the Committee recommend that the City Council reject all
bids and abandon the project as now designed.
vp \rpt \avpb -ad3
Exhibit 1
Bid Results: Bid Opening 12 -22 -92
Arroyo Vista Community Park Building and Gymnasium
vp \rpt \avpb -ads
Base Bid
Add Alt.
No.
Bidder
Amount (t
No.24 ($)
Total 0 )
Architect's Estimate
1,750,000.00
30,000.00
1,780,000.00
1
Wesley- Thomas Enterprises
Nancy Wesley
1,747,000.00
45,000.00
1,792,000.00
Westlake Village, CA
(805 379 -2365
2
Jevon Construction Co.
Albert Sharaf
1,744,226.00
69,000.00
1,813,226.00
Los Angeles, CA
(213) 892 -8136
3
Allee Construction Co.
Oscar Brocamonte
1,876,000.00
45,000.00
1,921,000.00
Los Angeles, CA
(213 261 -9262
4
Construction Group, Inc.
Sarah Herthel
1,886,000.00
42,000.00
1,928,000.00
Chatsworth, CA
(818) 998 -6905
5
GRD Construction
Gary Oswald
1,900,000.00
34,200.00
1,934,200.00
Ventura, CA
(805) 644 -2404
6
Viola, Inc.
Virginia Viola
1,905,000.00
33,000.00
1,938,000.00
Oxnard, CA
(805) 487 -3871
7
Southwest Engineering
Joseph Sagati
1,955,000.00
40,000.00
1,995,000.00
Santa Monica, CA
(310) 394 -9494
8
McCarthy Construction
Patrick McCarthy
1,973,349.00
41,250.00
2,014,599.00
Oxnard, CA
(805) 485 -4646
vp \rpt \avpb -ads