Loading...
HomeMy WebLinkAboutAGENDA REPORT 1993 0407 CC REG ITEM 11BITEM U• 15• AGENDA REPORT "DORPARK, CALIFORNIA City Council Meeting of 1993 To: The Honorable City Council ACTION: From: Ken Gilbert, Director of Public Works Date: March 30, 1993 (Meeting 4 -7 -93) Subject: Consider Bids for the Realignment and Widening of Tierra Rejada Road East of Spring Road At the meeting on February 24, 1993, the City Council approved the plans for the subject project and authorized staff to advertise for receipt of bids. DISCUSSION A. Project Design The project design includes the following: • A full four lane divided highway. • Bike lanes on both sides of the roadway. • The relocation of all utilities by each utility company per the contractor's construction schedule. [Note: the Camrosa Water line is to be relocated by the City's contractor as described in Section G.] • Full median improvements, less landscaping and irrigation, with concrete curbs and gutters from the end of the existing median located approximately 400 feet west of Spring Road to Moorpark Road. • Spring Road street improvements sufficient for adequate transitions to full signalization improvements at the intersection of Spring Road and Tierra Rejada Road. • Temporary Asphalt curbs in the median at the future intersection of Science Drive. • Curb and gutter on the north side of Tierra Rejada Road west of Spring Road along the Embassy frontage. • Drainage improvements on the south side of Tierra Rejada Road along the frontage of the Watt property. • Conduits for the installation of street lights in the median. The plans call for the installation of street lights along the Embassy frontage. Installation of street lights east of Spring Road is optional. trvld7 Tierra Rejada Widening Project April 7, 1993 Page 2 The contract calls for a construction time of ninety -six (96) working days. The project will be constructed in three phases. At the end of Phase 1 and Phase 2, project construction and contract time will be suspended for a period of time to allow for the relocation of utilities. B. Bid Schedules and Alternates 1. Schedule I: Schedule I of the bidding documents includes all of the items of work required to construct the project, except matters relating to traffic control. Bid items related to traffic control were set forth in two Alternate Bids defined as follows: a. Alternate 'A': Bid Alternate 'A' sets forth the items and bid amounts required to maintain two lanes of traffic throughout the duration of the project. This alternate calls for a contract time of ninety -six (96) working days. b. Alternate 'B': Bid Alternate 'B' sets forth the items and bid amounts required to construct the project in a manner which allows for the complete closure of the road during construction. This alternate calls for a contract time of only sixty - five (65) working days. 2. Schedule II: Schedule II of the bidding documents includes all of the items of work required to relocate a water main owned by the Camrosa Water District. C. Bid Results Bids for the subject project were received and opened on March 18, 1993. A tabulation of the bid results is attached as Exhibit 1. The apparent low bidder for the project based on Traffic Control Alternate 'A' is R & H Paving. The apparent low bidder for the project based on Traffic Control Alternate 'B' is SP Milling. A summary of these bids are as follows: Traffic Control Plan Bidder Alt. 'A': Road Open R & 8 Paving Alt. 'B': Road Closed S P Billing trvid7 Bid Amunt Scb. I & Alt SO. II I + Alt + II 1,275,367.00 78,950.00 1,354,317.00 1,224,400.50 98,460.00 1,322,860.50 Tierra Rejada Widening Project April 7, 1993 Page 3 E. Recommended Alternate During the development of the project design, it was anticipated that the closure of the road during construction could result in significant cost savings. The bid results do not reflect the degree of cost savings anticipated. It is the opinion of staff that the cost difference between the two traffic control plans is not great enough to warrant the disruption of traffic which would result from the closure of the road. For this reason staff recommends the selection of Traffic Control Alternate 'A', keeping the road open during construction. F. Qualifications The apparent low bidder for both Alternates have verified that their bids are valid and that they are prepared to proceed with the project. The City Engineer for the project (Willdan Associates) has determined that both firms are qualified to perform the required work. G. Camrosa Water Line Schedule II provides for the relocation of a water main owned by the Camrosa Water District. The bid price submitted by R &H Paving for this work is $78,950. The bid price submitted by SP Milling for this work is $98,460. The District has tentatively requested that in the event the contract is awarded to R &H Paving, that the work be done under the City's contract. H. Street Lights The construction contract calls for the placement of street lighting conduits throughout the project. Southern California Edison Company (SCE) is to install the street lights in the median west of Spring Road at an additional City cost of approximately $2,500. As now defined, the project does not include the installation of street lights east of Spring Road. If the City Council wishes these additional lights to be installed at this time, it would require an additional expenditure of approximately $12,143. trvld7 Tierra Rejada Widening Project April 7, 1993 Page 4 I. Fiscal Impact 1. Construction Cost Estimate: The bids for the construction of the project are summarized in Section 'D' above. The actual cost will be determined on the basis of actual quantities of the bid items required to construct the project. 2. Utility Relocations: Pursuant to the terms of Settlement Agreements with the utility companies / districts affected by the project, the City made advance payments to those utilities as follows: • Southern California Edison 116,284 • Pacific Bell 388,600 • Shell Oil Company 182,500 Total $687,384 The Settlement Agreements provide for final payment based on actual cost. It is anticipated that additional payments, based on actual cost, will be required. The amounts of those payments have not yet been determined. 3. Reimbursement from UWC: Pursuant to the terms of a Settlement Agreement between the City and Urban West Communities (UWC), UWC shall pay the City for one -half of the cost of this project, said payment to be reimbursed to UWC as a credit to future AOC fees or repaid as AOC fees are collected from others. 4. Total Project Cost Estimate: The following is the estimated cost of the total project exclusive of right - of -way and legal costs: tmid7 Prior Year FY Eleitent Egmes _ 1992193 Total Design UWC ** CAA (Embassy) 4,000 Willdan 52,000 Sub -Total 56,000 86,000 142,000 Construction 1,354,317 1,354,317 Street Lights 2,500 2,500 tmid7 Tierra Rejada Widening Project April 7, 1993 Page 5 Plus Street Lights Prior Year FY 12,143 Element Expgnses 1992193 Total Construction Eng. * ** 28,000 1,406,072 1,434,072 Contr. Admin. (Est.) 40,000 Inspection (Est.) 110,000 Surveying (Est.) 50,000 Soils Test (Est.) 70.000 Sub -total 270,000 270,000 contingency (10 %) 187,183 187 183 Sub -total 56,000 1,900,000 1,956,000 Utility Relocation (Est.) 900,000 900,000 TOTAL 56,000 2,800,000 2,856,000 UWC Share (50 %) 28,000 1,400,000 428,000 City Share (50 %) 28,000 1,400,000 1,428,000 Plus Street Lights 0 12,143 12,143 Adj. UWC Share 28,000 1,406,072 1,434,072 Adj City Share 28,000 1,406,072 1,434,072 Notes: ** Cost of prior design effort subject to reibbursement to be determined. * ** Construction Engineering costs are estimates only. These services are to be provided by contract services, the full scope of cost of saHe are yet to be determined. 5. Budget: The following is a re —cap of the funds budgeted for this project for Fiscal Year 1992/93: Fund Total 03 -- Gas Tax Funds 1,445,000 15 -- SB 821 (Bicycle Facilities Grant) Inspection 55,000 TOTAL 1,500,000 crwsa7 Tierra Rejada Widening Project April 7, 1993 Page 6 6. Grants: Project funding includes funds from two grants sources summarized as follows: a) SB -821: [$55,000] The City has received approval of a State grant for additional pavement surface to provide for Bike Lanes. b) State -Local Transportation Partnership Program: This project is funded under Cycle III of the program. In Cycle III the grant amount is Approximately 21% of the actual construction cost plus ten per cent (10 %) for construction engineering. The Estimated grant amount based on the bid (including the water line relocation) is $321,338.86. The actual amount of the grant will be determined on the basis of final actual cost, not to exceed $415,525. 7. Budget Amendment: It is recommended that the funds be reappropriated and the budget amended as follows: * Advance frog Urban West Conunities 8. Budget Carryover: It is anticipated that only a portion of the project costs will be expended this Fiscal Year and that those expenses expected to be incurred next fiscal year will be included in next years budget. 9. Available TDA Funds (Fund 11): The projected year end fund balance for Fund 11 is $1,234,000. An additional $500,000± in TDA revenues is anticipated next fiscal year. tr.ia7 Current Increase / Fund Budget (Decrease) Total 03 -- Gas Tax Funds 1,445,000 - 1,445,000 0 26 -- T R AOC 0 1,400,000 * 1,400,000 11 -- TDA Funds 0 1,008,660 1,023,660 State Local Partnership 0 321,340 321,340 15 -- SB 821 (Bicycle Facilities 55,000 0 55,000 Grant) TOTAL 1,500,000 1,300,000 2,800,000 * Advance frog Urban West Conunities 8. Budget Carryover: It is anticipated that only a portion of the project costs will be expended this Fiscal Year and that those expenses expected to be incurred next fiscal year will be included in next years budget. 9. Available TDA Funds (Fund 11): The projected year end fund balance for Fund 11 is $1,234,000. An additional $500,000± in TDA revenues is anticipated next fiscal year. tr.ia7 Tierra Rejada Widening Project April 7, 1993 Page 7 10. Tierra Rejada AOC Funds (Fund 26): The project costs to be paid by UWC are shown as advance revenues to Fund 26. J. Schedule It is anticipated that construction will begin in May and be completed by February 1994. RECOMMKDATION (Roll Cal Vote) Staff recommends that the City Council take the following actions: 1) Approve the revised appropriations and budget amendment as set forth in Section I -7 of this report. 2 ) Direct staff whether or not to add street lighting east of Spring Road. Note: If this work is added, costs for same will be funded from the contingency. 3) Determine the Scope of Work to include Traffic Control Alternate 'A' (two traffic lanes open at all times) and Schedule II (water line relocation); 4) Award a contract for said project to R &H Paving, Inc. for the bid amount of $1,354,317.00; 5) approve a ten per cent contingency for the project; and, 6) Authorize the Mayor to sign necessary contract documents. trwia7 City of Moorpark Bid opening Tierra Rejada Road Widening 1e -MAR43 Bid Tabulation Spreadsheet BtaTrs W ENGINEER'S ESTIMATE R & H PAVING, INC. S.P.MILLING CO. Item Approx. Unit Total Unit Total Unit Total No. Item Description Oty Units Price Price Price Price Price Price 1 MOBILIZATION 1 LS $15,000.00 $15,000.00 $24,000.00 $24,000.00 $10,000.00 $10,000.00 2 CLEARING AND GRUBBING 1 LS $50,000.00 $50,000.00 $14,000.00 $14,000.00 $6,000.00 $6,000.00 3 LOCATING EXISTING FACILITIES 1 LS ' $10,000.00 $10,000.00 $6,500.00 $6,500.00 $17,000.00 $17,000.00 4 EARTHWORK 67000 CY $3.00 $201,000.00 $2.30 $154,100.00 $2.29 $153,430.00 4a TEMPORARY EARTHWORK MOORPARK RD 1 LS $5,000.00 $5,000.00 $15,000.00 $15,000.00: $1,250.00 $1,250.00 5 ALLUVIUM & UNCERTIFIED MATERIAL REMOVAL 60000 CY $2.00 $120,000.00 $1.15 $69,000.00: $1.25 $75,000.00 6 TOPSOIL STOCKPILING 32000 SF $0.10 $3,200.00 $0.10 $3,200.00 $0.15 $4,800.00 7 42' R.C.P. CLASS 111 25 LF $110.00 $2,750.00 $142.00 $3,550.00 $100.00 $2,500.00 8 36' R.C.P. CLASS IV 123 LF $74.00 $9,102.00 $65.00 $7,995.00: $82.00 $10,086.00 9 30' R.C.P. CLASS IV 141 LF $72.00 $10,152.00 $110.00 $15,510.00: $70.00 $9,870.00 10 27' R.C.P. CLASS IV 286 LF $70.00 $20,020.00 $72.00 320,592.00. $70.00 $20,020.00 11 18' R.C.P. CLASS III 153 LF $50.00 $7,650.00 $46.00 $7,038.00 $47.00 $7,191.00 12 5'X T CSP ARCH 70 LF $120.00 $8,400.00: $110.00 $7,700.00 $129.00 $9,030.00 13 VCFCD STD NO. 2 TYPE II JUNCTION STRUCTURE 3 EA $2,500.00 $7,500.00 $2,500.00 $7,500.00 $1,600.00 $4,800.00 14 C.S.P. 48' D93 INLET RISER 1 EA $750.00 $750.00 $3,000.00 $3,000.00 $2,200.00 $2,200.00 15 MOD. DOUBLE CONC. HDWALL 2 EA $5,000.00 $10,000.00 $7,000.00 $14,000.00 $4,900.00 $9,800.00 16 SINGLE CONCRETE HEADWALL 5 EA $2,500.00 $12,500.00 $3,500.00 $17,500.00 $2,600.00 $13,000.00 17 3' THICK CONCRETE BENCH DRAIN 505 LF $10.00 $5,050.00 $12.00 $6,060.00 $10.50 $5,302.50 18 3' THICK CONC. DRAIN. SWALE 310 LF - $17.00 $5,270.00 $16.00 $4,960.00 $16.50 $5,115.00 19 CONC. TERRACE DOWNDRAIN JUNCT. 2 EA $1,500.00 $3,000.00 $250.00 $500.00 $640.00 $1,280.00 20 10' WIDE CONCRETE INTERCEPTOR DRAIN 3160 LF $16.00 $50,560.00 $14.00 $44,240.00 $17.00 $53,720.00 21 FLARED CONC. DRAIN TERMINUS 1 EA $1,500.00 $1,500.00 $850.00 $850.00 $1,700.00 $1,700.00 22 CURB OPEN. CATCH BASIN W/LOCAL DEPRES.W -14' 2 EA $4,500.00 $9,000.00 $4,000.00 $8,000.00 $4,600.00 $9,200.00 23 CURB OPEN. CATCH BASIN W/LOCAL DEPRES.W -3.5' 1 EA $2,000.00 $2,000.00 $1,800.00 $1,800.00 $1,900.00 $1,900.00 24 D87B A.C. OVERSIDE DRAIN W/TAPERED INLET 75 LF $30.00 $2,250.00 $22.00 $1,650.00 $28.00 $2,100.00 25 D87A C.M.P. OVERSIDE DRAIN WlrAPERED INLET 25 LF $50.00 $1,250.00 $48.00 $1,200.00 $50.00 $1,250.00 26 1/4 TON CONCRETED RIP RAP 537 CY $100.00 $53,700.00 $73.00 $39,201.00 $100.00 $53,700.00 27 METAL BEAM GUARD RAILING 826 LF $20.00 $16,520.00 $13.00 $10,738.00 $13.50 $11,151.00 28 SAWCUTTING A.C. PAVEMENT 1420 LF $1.00 $1,420.00 $0.50 $710.00 $0.60 $852.00 29 COLD PLANING EXISTING A.C. PAVEMENT 950 SF $2.50 $2,375.00 $2.00 $1,900.00 $2.00 $1,900.00 30 3' THICK TEMPORARY A.C. PAVEMENT 600 TON $35.00 $21,000.00 $30.00 $18,000.00 $30.00 $18,000.00 31 18' THICK CLASS 2 AGGREGATE BASE 25000 TON $15.00 $375,000.00 $10.58 $264,500.00 $8.80 $220,000.00 32 2' THICK FINAL A.C. CAP 3000 TON $30.00 $90,000.00 $28.00 $84,000.00 $28.00 $84,000.00 33 3' THICK A.C. BASE COURSE 4500 TON $30.00 $135,000.00 $28.00 $126,000.00 $26.00 $117,000.00 34 1 -1/2' A.C. OVERLAY 200 TON $30.00 $6,000.00 $28.00 $5,600.00 $28.00 $5,600.00 35 ADJUSTING EXISTING UTILITIES 1 LS $3,000.00 $3,000.00 $3,000.00 $3,000.00 $3,200.00 $3,200.00 36 RELOCATE EXISTING FENCE 6500 LF $3.00 $19,500.00 $3.50 $22,750.00: $2.50 $16,250.00 37 6' WIDE CONCRETE SWALE (DETAIL -A -) 1400 LF $15.00 $21,000.00 $13.00 $18,200.00: $12.30 $17,220.00 38 6' A.C. BERM (V.C. STANDARD 5 -3, TYPE D -1) 690 LF $6.00 $4,140.00 ': $1.20 $828.00 $3.00 $2,070.00 39 6' CONCRETE CURB (APWA STD Al -6) 3600 LF $6.00 $21,600.00 $5.00 $18,000.00 $8.30 $29,880.00 40 6' A.C. MOUNTABLE A87 TYPE 'D' DIKE 2470 LF $5.00 $12,350.00 $1.20 $2,964.00 $2.80 $6,916.00 41 6' P.C.C. CURB AND 18' GUTTER (APWA STD A2 -6) 460 LF $12.00 $5,520.00 $6.50 $2,990.00 $10.00 $4,600.00 42 6' P.C.C. CURB AND 12' GUTTER (APWA STD A2 -6) 2920 LF $10.00 $29,200.00 $6.00 $17,520.00 $9.75 $28,470.00 City of Moorpark BW op.nin0 ENGINEER'S R & H PAVING, INC. S.P.MILLING CO. Tierra Rejada Road Widening 18-MAR -93 ESTIMATE $21.00 $70,875.00 Bid Tabulation Spreadsheet sto- �iw�c, $87,750.00 55 12" TAPPING SLEEVE & GATE VALUE ON 12 0AC PIPE Item EA Approx. $3,500.00 Unit Total Unit Total Unit Total No. Item Description Qty Units Price Price Price Price Price Price 43 STAMPED MEDIAN CONCRETE 1320 SF >:' $6.00 $7,920.00 $3.50 $4,620.00 $5.80 $7,656.00 44 HYDROSEEDING i LS $30,000.00 $30,000.00 $15,000.00 $15,000.00 $19,000.00 $19,000.00 45 MEDIAN IRRIGATION CROSSOVERS (SCH 40 PVC) 300 LF $18.00 $5,400.00: $19.00 $5,700.00 $20.00 $6,000.00 46 MEDIAN IRRIGATION CROSSOVER RISERS 9 EA $500.00 $4,500.00 $300.00 $2,700.00 $310.00 $2,790.00 47 FINAL PAVEMENT DELINEATION 1 LS $20,000.00 $20,000.00 $18,000.00 $18,000.00 ' $24,000.00 $24,000.00 48 STREET LIGHTING CONDUITS 1 LS $26,000.00 $26,000.00 $15,000.00 $15,000.00 $15,400.00 $15,400.00 49 FINAL TRAFFIC SIGNALS 1 LS $80,000.00 $80,000.00 $60,000.00 $60,000.00 $62,000.00 $62,000.00 50 WATER POLLUTION CONTROL AND SWPPP 1 LS :; $10,000.00 $10,000.00: $1,000.00 $1,000.00 $4,200.00 $4,200.00 51 ITERMINATION OF LIABILITY 1 LS $1.001 $1.00 ' $1.001 $1.00 1 $1.001 $1.00 TOTAL SCHEDULE I, BID BASE $1,574,050.00 1 $1,218,367.00 $1,199,400.50 :: TRAFFIC CONTROL ALTERNATE A 52 ITWO TRAFFIC LANES OPEN AT ALL TIMES 1 LS $120,000.00 $57,000.00 $158,000.00 TRAFFIC CONTROL ALTERNATE B 53 ICOMPLETE ROAD CLOSURE 1 LS $25,000.00 $30,000.00 $25,000.00 IWATERLINE RELOCATION 54 12" PVC PIPE, CLASS 200 3375 LF $27.00 $91,125.00 $21.00 $70,875.00 $26.00 $87,750.00 55 12" TAPPING SLEEVE & GATE VALUE ON 12 0AC PIPE 1 EA $3,500.00 $3,500.00 $2,800.00 $2,800.00 $3,700.00 $3,700.00 56 2" BLOW -OFF ON 12" PIPE 2 EA $2,000.00 $4,000.00 $1,000.00 $2,000.00 $1,180.00 $2,360.00 57 1" COMB. VALVE & AIR REL. VALVE ASSEM. 2 EA $2,250.00 $4,500.00 $1,100.00 $2,200.00 $1,100.00 $2,200.00 58 12" GATE VALVE 1 EA $1,500.00 $1,500.00 $760.00 $760.00 $1,000.00 $1,000.00 59 1 INST. 12" CAP -CONC. THRUST BILK ON EXIST. PIPE 1 EA $2,500.00 $2,500.00 $315.00 $315.00: $1,450.001 $1,450.00 TOTAL SCHEDULE II $107,125.00 $78,950.00 $98,460.00 SCHEDULE I + ALTERNATE A (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,863,455.00 $1,275,367.00: $1,357,400.50 SCHEDULE I + ALTERNATE B (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,758,955.00 $1,248,367.00: $1,224,400.50 SCHEDULE I + ALTERNATE A + SCHEDULE II (ENGR'S EST. INCL. 10% CONT.) $1,981,292.50 :: $1,354,317.00 $1,455,860.50 SCHEDULE I + ALTERNATE B + SCHEDULE II (ENGR'S EST. INCL 10% CONT.) $1,876,792.50 $1,327,317.00: $1,322,860.50 City of Moorpark Bid Opening Tierra Rejada Road Widening 1e- MAP-03 Bid Tabulation Spreadsheet BID- TRNMCI RANDOM CONSTRUCTION NYE & NELSON, INC. BERRY GENERAL ENGINEERING CONTRACTORS, INC. Item Approx. Unit Total Unit Total Unit Total No. Item Description Oty Units Price Price Price Price Price Price 1 MOBILIZATION 1 LS :: $101,000.00 8101,000.00 $51,951.00 851,951.00 $39,000.00 $39,000.00 2 CLEARING AND GRUBBING 1 LS $40,000.00 840,000.00 872,276.00 $72,276.00 $24,740.00 $24,740.00 3 LOCATING EXISTING FACILITIES 1 LS 89,500.00 89,500.00 $18,000.00 $18,000.00 $21,200.00 821,200.00 4 EARTHWORK 67000 CY $1.70 $113,900.00 $3.00 8201,000.00 82.93 $196,310.00 4a TEMPORARY EARTHWORK MOORPARK RD 1 LS 89,500.00 $9,500.00 $12,000.00 812,000.00 818,300.00 $18,300.00 5 ALLUVIUM & UNCERTIFIED MATERIAL REMOVAL 60000 CY 81.00 $60,000.00 $1.30 $78,000.00 $1.63 897,800.00 6 TOPSOIL STOCKPILING 32000 SF $0.13 84,160.00 $0.05 $1,600.00 $0.03 $960.00 7 42" R.C.P. CLASS III 25 LF $105.00 $2,625.00 $105.00 82,625.00 $104.00 82,600.00 8 36" R.C.P. CLASS IV 123 LF - $70.00 $8,610.00 $85.00 810,455.00 882.50 $10,147.50 9 30" R.C.P. CLASS IV 141 LF $48.00 86,768.00 $70.00 $9,870.00 869.70 $9,827.70 10 27" R.C.P. CLASS IV 286 LF $51.00 814,586.00. 872.00 $20,592.00 $71.30 $20,391.80 11 18" R.C.P. CLASS 111 153 LF $35.00 $5,355.00 848.00 $7,344.00 $47.70 $7,298.10 12 5'X 3' CSP ARCH 70 LF $38.00 $2,660.00 $130.00 89,100.00 8130.00 $9,100.00 13 VCFCD STD NO.2 TYPE II JUNCTION STRUCTURE 3 EA $3,700.00 $11,100.00 $1,650.00 84,950.00 $1,608.00 84,824.00 14 C.S.P. 48" D93 INLET RISER 1 EA $3,500.00 $3,500.00 82,250.00 $2,250.00 $2,235.00 $2,235.00 15 MOD. DOUBLE CONC. HDWALL 2 EA 87,400.00 $14,800.00 85,000.00 $10,000.00 $4,905.00 $9,810.00 16 SINGLE CONCRETE HEADWALL 5 EA $4,200.00 $21,000.00 $2,700.00 $13,500.00 $2,680.00 $13,400.00 17 3" THICK CONCRETE BENCH DRAIN 505 LF $12.50 86,312.50 $13.00 $6,565.00 $10.40 $5,252.00 18 3" THICK CONC. DRAIN. SWALE 310 LF $14.00 $4,340.00 817.00 $5,270.00 $22.65 $7,021.50 19 CONC. TERRACE DOWNDRAIN JUNCT. 2 EA $750.00 $1,500.00 $1,300.00 $2,600.00 $275.00 $550.00 20 10' WIDE CONCRETE INTERCEPTOR DRAIN 3160 LF 817.00 $53,720.00 $20.00 $63,200.00 $14.05 $44,398.00 21 FLARED CONC. DRAIN TERMINUS 1 EA $1,600.00 $1,600.00 8800.00 $800.00 $1,450.00 $1,450.00 22 CURB OPEN. CATCH BASIN W /LOCAL DEPRES.W -14' 2 EA $5,000.00 $10,000.00 84,500.00 $9,000.00 $4,610.00 $9,220.00 23 CURB OPEN. CATCH BASIN W/LOCAL DEPRES.W -3.5' 1 EA $3,100.00 83,100.00 $1,950.00 81,950.00 $1,930.00 $1,930.00 24 D87B A.C. OVERSIDE DRAIN W/TAPERED INLET 75 LF $21.00 $1,575.00 $17.00 81,275.00 $19.60 81,470.00 25 D87A C.M.P. OVERSIDE DRAIN WITAPERED INLET 25 LF $36.00 8900.00 $50.00 $1,250.00 $72.40 $1,810.00 26 1/4 TON CONCRETED RIP RAP 537 CY $72.00 $38,664.00 $103.00 $55,311.00 $106.75 857,324.75 27 METAL BEAM GUARD RAILING 826 LF $17.00 $14,042.00 $13.50 $11,151.00 813.60 $11,233.60 28 SAWCUTTING A.C. PAVEMENT 1420 LF $1.50 $2,130.00 $0.60 $852.00 $0.55 $781.00 29 COLD PLANING EXISTING A.C. PAVEMENT 950 SF $2.80 $2,660.00 $1.20 $1,140.00 $3.40 $3,230.00 30 3" THICK TEMPORARY A.C. PAVEMENT 600 TON $33.50 $20,100.00 830.00 $18,000.00 $31.10 818,660.00 31 18" THICK CLASS 2 AGGREGATE BASE 25000 TON $10.00 $250,000.00 $9.80 $245,000.00 $10.40 $260,000.00 32 2" THICK FINAL A.C. CAP 3000 TON $30.00 $90,000.00 $29.00 $87,000.00 833.75 $101,250.00 33 3" THICK A.C. BASE COURSE 4500 TON $32.00 $144,000.00 $29.00 8130,500.00 831.15 $140,175.00 34 1 -1/2" A.C. OVERLAY 200 TON $30.00 $6,000.00 $29.00 $5,800.00 834.15 $6,830.00 35 ADJUSTING EXISTING UTILITIES 1 LS $2,500.00 82,500.00 84,000.00 $4,000.00 83,360.00 $3,360.00 36 RELOCATE EXISTING FENCE 6500 LF $3.00 819,500.00 $3.50 $22,750.00 $3.40 $22,100.00 37 6' WIDE CONCRETE SWALE (DETAIL "A ") 1400 LF $13.00 818,200.00 $12.50 $17,500.00 812.45 817,430.00 38 6- A.C. BERM (V.C. STANDARD 5 -3, TYPE D -1) 690 LF 84.00 $2,760.00 82.00 $1,380.00 $1.70 $1,173.00 39 6" CONCRETE CURB (APWA STD Al -6) 3600 LF 83.75 $13,500.00 $5.75 $20,700.00 85.50 819,800.00 40 6" A.C. MOUNTABLE A87 TYPED" DIKE 2470 LF $2.50 $6,175.00 82.30 $5,681.00 $2.25 $5,557.50 41 6' P.C.C. CURB AND 18" GUTTER (APWA STD A2 -6) 460 LF 85.75 $2,645.00 $7.00 $3,220.00 $6.20 $2,852.00 42 6" P.C.C. CURB AND 12" GUTTER (APWA STD A2 -6) 2920 LF 85.50 $16,060.00 $6.50 $18,980.00 $7.40 821,608.00 City of Moorpark Ba opening RANDOM NYE & NELSON, INC. BERRY GENERAL Tierra Rejada Road Widening ,e -MAa -W CONSTRUCTION $21.00 ENGINEERING Bid Tabulation Spreadsheet BID -TRwa1 $83,700.00 > 55 CONTRACTORS, INC. Item EA Approx. $2,700.00 Unit Total Unit Total Unit Total No. Item Description Oty Units Price Price Price Price Price Price 43 STAMPED MEDIAN CONCRETE 1320 SF ' : $5.75 $7,590.00 $5.20 $6,864.00 - $5.40 $7,128.00 44 HYDROSEEDING 1 LS $25,000.00 $25,000.00 $23,300.00 $23,300.00 59 $0.00 45 MEDIAN IRRIGATION CROSSOVERS (SCH 40 PVC) 300 LF $14.00 $4,200.00 $20.00 $6,000.00: $19.30 $5,790.00 46 MEDIAN IRRIGATION CROSSOVER RISERS 9 EA $300.00 $2,700.00 $320.00 $2,880.00 ' $315.00 $2,835.00 47 FINAL PAVEMENT DELINEATION 1 LS ' $18,500.00 $18,500.00 $10,700.00 $10,700.00 $18,445.00 $18,445.00 `. 48 STREET LIGHTING CONDUITS 1 LS $27,000.00 $27,000.00 $15,500.00 $15,500.00 $15,568.00 $15,568.00 49 FINAL TRAFFIC SIGNALS 1 LS $71,000.00 $71,000.00 $66,000.00 $66,000.00 $70,700.00 $70,700.00 50 WATER POLLUTION CONTROL AND SWPPP 1 LS '' $3,200.00 $3,200.00 $10,000.00 $10,000.00 $3,327.00 $3,327.00 51 TERMINATION OF LIABILITY 1 LS $1.00 $1.00 $1.00 $1.00 $1.00 1 $1.00 TOTAL SCHEDULE I, BID BASE 1 $1,320,238.50 1 $1,407,633.00 1 $1,378,204.45 : TRAFFIC CONTROL ALTERNATE A 52 ITWO TRAFFIC LANES OPEN AT ALL TIMES 1 LS $115,000.00 $61,000.00 $68,429.00 ALTERNATE B $38,000.00 IWATERLINE RELOCATION 54 12' PVC PIPE, CLASS 200 3375 LF $21.00 $70,875.00 $21.00 $70,875.00 $24.80 $83,700.00 > 55 12' TAPPING SLEEVE & GATE VALUE ON 12'AC PIPE 1 EA $2,700.00 $2,700.00 $3,000.00 $3,000.00 $3,785.00 $3,785.00 56 2' BLOW -OFF ON 12' PIPE 2 EA $1,100.00 $2,200.00 $1,100.00 $2,200.00 $1,196.00 $2,392.00 57 1' COMB. VALVE & AIR REL. VALVE ASSEM. 2 EA $1,300.00 $2,600.00 $1,200.00 $2,400.00 $1,115.00 $2,230.00 58 12' GATE VALVE 1 EA $1,500.00 $1,500.00 $800.00 $800.00 $1,008.00 $1,008.00 59 1 INST. 12' CAP -CONC. THRUST BLK ON EXIST. PIPE 1 EA $750.00 $750.00 $350.00 $350.00 $1,770.00 $1,770.00 TOTAL SCHEDULE II $80,625.00 $79,625.00 $94,885.00 SCHEDULE I + ALTERNATE A (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,435,238.50 - $1,468,633.00 $1,446,633.45 SCHEDULE I + ALTERNATE B (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,358,238.50 $1,427,733.00 $1,423,406.45 SCHEDULE I + ALTERNATE A + SCHEDULE II (ENGR'S EST. INCL. 10% CONT.) $1,515,863.50 $1,548,258.00 $1,541,518.45 SCHEDULE I + ALTERNATE B + SCHEDULE II (ENGR'S EST. INCL 10% CONT.) $1,438,863.50 $1,507,358.00 $1,518,291.45 City of Moorpark Bid opening Tierra Rejada Road Widening 18-MAP-0 Bid Tabulation Spreadsheet BID -TRwKI C.A. RASMUSSEN, INC. SUMMITIKELLER A JOINT VENTURE PREMIER ENGINEERS, INC. Item Approx. Unit Total Unit Total Unit Total No. Item Description Oty Units Price Price Price Price Price Price 1 MOBILIZATION 1 LS $41,600.00 $41,600.00 $4,070.00 $4,070.00 $80,331.04 $80,331.04 2 CLEARING AND GRUBBING 1 LS $27,000.00 $27,000.00 $5,470.00 $5,470.00 $61,480.00 $61,480.00 3 LOCATING EXISTING FACILITIES 1 LS ' $6,000.00 $6,000.00 $5,450.00 $5,450.00 $17,145.50 $17,145.50 4 EARTHWORK 67000 CY $5.97 $399,990.00 $3.86 $258,620.00 $2.36 $158,120.00 4a TEMPORARY EARTHWORK MOORPARK RD 1 LS $9,800.00 $9,800.00 $8,870.00 $8,870.00 $5,830.00 $5,830.00 5 ALLUVIUM & UNCERTIFIED MATERIAL REMOVAL 60000 CY $0.75 $45,000.00 $1.65 $99,000.00 $2.39 $143,400.00 6 TOPSOIL STOCKPILING 32000 SF $0.04 $1,280.00 $0.03 $960.00. $0.11 $3,520.00 7 421 R.C.P. CLASS III 25 LF $93.00 $2,325.00 $115.00 $2,875.00 $102.82 $2,570.50 8 36e R.C.P. CLASS IV 123 LF $80.00 $9,840.00 $58.00 $7,134.00 $81.62 $10,039.26 ' 9 3011 R.C.P. CLASS IV 141 LF $70.00 $9,870.00 $58.00 $8,178.00 $68.90 $9,714.90 10 2711 R.C.P. CLASS IV 286 LF $68.00 $19,448.00 $51.00 $14,586.00 $70.68 $20,214.48 11 1811 R.C.P. CLASS III 153 LF $45.00 $6,885.00 $44.00 $6,732.00 $47.17 $7,217.01 12 5'X 3' CSP ARCH 70 LF $115.00 $8,050.00 $106.00 $7,420.00 $128.53 $8,997.10 13 VCFCD STD NO. 2 TYPE 11 JUNCTION STRUCTURE 3 EA $1,600.00 $4,800.00 $2,392.00 $7,176.00 $1,590.00 $4,770.00 14 C.S.P. 4811 D93 INLET RISER 1 EA $2,100.00 $2,100.00 $3,220.00 $3,220.00: $2,211.16 $2,211.16 15 MOD. DOUBLE CONC. HDWALL 2 EA $8,700.00 $17,400.00 $8,090.00 $16,180.00 $4,849.50 $9,699.00 16 SINGLE CONCRETE HEADWALL 5 EA $3,100.00 $15,500.00 $3,950.00 $19,750.00 $2,650.00 $13,250.00 17 311 THICK CONCRETE BENCH DRAIN 505 LF $11.00 $5,555.00 $11.72 $5,918.60 $11.34 $5,726.70 ` 18 311 THICK CONC. DRAIN. SWALE 310 LF $14.50 $4,495.00 $17.80 $5,518.00 $16.16 $5,009.60 19 CONC. TERRACE DOWNDRAIN JUNCT. 2 EA $700.00 $1,400.00 $720.00 $1,440.00 $1,247.62 $2,495.24 20 10' WIDE CONCRETE INTERCEPTOR DRAIN 3160 LF $15.50 $48,980.00 $19.43 $61,398.80 $18.82 $59,471.20 ' 21 FLARED CONC. DRAIN TERMINUS 1 EA $800.00 $800.00 $960.00 $960.00 $848.00 $848.00 22 CURB OPEN. CATCH BASIN W/LOCAL DEPRES.W -14' 2 EA $4,300.00 $8,600.00 $4,450.00 $8,900.00 $4,558.00 $9,116.00 23 CURB OPEN. CATCH BASIN W /LOCAL DEPRES.W -3.5' 1 EA $1,850.00 $1,850.00 $2,030.00 $2,030.00 $1,908.00 $1,908.00 24 D87B A.C. OVERSIDE DRAIN W/TAPERED INLET 75 LF $17.00 $1,275.00 $18.94 $1,420.50 $58.30 $4,372.50 25 D87A C.M.P. OVERSIDE DRAIN W/TAPERED INLET 25 LF $58.00 $1,450.00 $18.00 $450.00 $49.18 $1,229.50 26 1/4 TON CONCRETED RIP RAP 537 CY $73.00 $39,201.00 $57.91 $31,097.67 $79.50 $42,691.50 27 METAL BEAM GUARD RAILING 826 LF $17.00 $14,042.00 $18.80 $15,528.80 $17.49 $14,446.74 28 SAWCUTTING A.C. PAVEMENT 1420 LF $1.00 $1,420.00 $1.28 $1,817.60 $2.65 $3,763.00 29 COLD PLANING EXISTING A.C. PAVEMENT 950 SF $2.00 $1,900.00 $2.20 $2,090.00 $1.06 $1,007.00 " 30 311 THICK TEMPORARY A.C. PAVEMENT 600 TON $28.00 $16,800.00 $31.70 $19,020.00 $27.83 $16,698.00 31 1811 THICK CLASS 2 AGGREGATE BASE 25000 TON $10.43 $260,750.00 $11.56 $289,000.00 $12.22 $305,500.00 32 211 THICK FINAL A.C. CAP 3000 TON $28.50 $85,500.00 = $31.69 $95,070.00 $27.83 $83,490.00 33 311 THICK A.C. BASE COURSE 4500 TON $27.20 $122,400.00 $31.69 $142,605.00 $27.83 $125,235.00 34 1 -1/211 A.C. OVERLAY 200 TON $27.00 $5,400.00 $31.69 $6,338.00 $27.83 $5,566.00 35 ADJUSTING EXISTING UTILITIES 1 LS $3,100.00 $3,100.00 $7,774.00 $7,774.00 $2,470.50 $2,470.50 36 RELOCATE EXISTING FENCE 6500 LF $3.00 $19,500.00 $3.47 $22,555.00: $3.71 $24,115.00 37 6' WIDE CONCRETE SWALE (DETAIL -Ae) 1400 LF $12.75 $17,850.00: $13.85 $19,390.00 $13.95 $19,530.00 38 611 A.C. BERM (V.C. STANDARD 5 -3, TYPE D -1) 690 LF - $3.50 $2,415.00 $2.75 $1,897.50 $6.89 $4,754.10 ' 39 611 CONCRETE CURB (APWA STD Al -6) 3600 LF $5.20 $18,720.00 $10.76 $38,736.00 $8.41 $30,276.00 40 611 A.C. MOUNTABLE A87 TYPE eD11 DIKE 2470 LF $3.50 $8,645.00 $2.10 $5,187.00 $8.48 $20,945.60 41 611 P.C.C. CURB AND 1811 GUTTER (APWA STD A2 -6) 460 LF $6.50 $2,990.00 $15.55 $7,153.00 $11.08 $5,096.80 42 611 P.C.C. CURB AND 1211 GUTTER (APWA STD A2 -6) 2920 LF $6.00 $17,520.00 $13.15 $38,398.00 $9.97 $29,112.40 ' City of Moorpark Sid 0p.n1nq C.A. RASMUSSEN, INC. SUMMIT/KELLER PREMIER Tierra Rejada Road Widening 1e- MAF143 $70,368.75 A JOINT VENTURE ENGINEERS, INC. Bid Tabulation Spreadsheet eIaTawx, $82,653.75 55 12" TAPPING SLEEVE & GATE VALUE ON 12'AC PIPE Item EA Approx. $3,100.00 Unit Total Unit Total Unit Total No. Item Description Oty Units Price Price Price Price Price Price 43 STAMPED MEDIAN CONCRETE 1320 SF <' $3.80 $5,016.00 $4.20 $5,544.00: $5.58 $7,365.60 44 HYDROSEEDING 1 LS $11,000.00 $11,000.00 $11,720.00 $11,720.00: $29,447.33 $29,447.33 45 MEDIAN IRRIGATION CROSSOVERS (SCH 40 PVC) 300 LF $13.30 $3,990.00 $15.25 $4,575.00 ' $13.52 $4,056.00 46 MEDIAN IRRIGATION CROSSOVER RISERS 9 EA $350.00 $3,150.00 $130.00 $1,170.00 $114.48 $1,030.32 47 FINAL PAVEMENT DELINEATION 1 LS : $19,600.00 $19,600.00: $20,590.00 $20,590.00 $18,250.02 $18,250.02 48 STREET LIGHTING CONDUITS 1 LS $15,400.00 $15,400.00 $21,528.00 $21,528.00 $15,046.70 $15,046.70 49 FINAL TRAFFIC SIGNALS 1 LS .' $64,000.00 $64,000.00 $74,152.00 $74,152.00 $60,812.20 $60,812.20 50 WATER POLLUTION CONTROL AND SWPPP 1 LS $500.00 $500.00 $3,575.00 $3,575.00 $10,600.00 $10,600.00 51 ITERMINATION OF LIABILITY 1 1 LS ;; $1.001 $1.001.1 $1.001 $1.0011 $1.00 $1.00 TOTAL SCHEDULE 1, BID BASE 1 $1,462,103.00: 1 1 $1,450,239.47 $1,529,993.50 TRAFFIC CONTROL ALTERNATE B 53 1 COMPLETE ROAD CLOSURE 1 LS $7,500.00 $33,600.00 $55,032.59 WATERLINE RELOCATION 54 12' PVC PIPE, CLASS 200 3375 LF -' $20.85 $70,368.75 $30.00 $101,250.00 $24.49 $82,653.75 55 12" TAPPING SLEEVE & GATE VALUE ON 12'AC PIPE 1 EA $3,100.00 $3,100.00 $3,750.00 $3,750.00 $3,741.80 $3,741.80 56 2" BLOW -OFF ON 12' PIPE 2 EA $1,200.00 $2,400.00 $1,400.00 $2,800.00 $1,18296 $2,365.92 57 1' COMB. VALVE & AIR REL. VALVE ASSEM. 2 EA $1,200.00 $2,400.00 $1,460.00 $2,920.00 $1,10240 $2,204.80 58 12" GATE VALVE 1 EA $800.00 $800.00 $990.00 $990.00 $996.40 $996.40 59 INST. 12" CAP -CONC. THRUST BLK ON EXIST. PIPE 1 EA $350.00 $350.00 $410.00 $410.00 $1,749.00 $1,749.00 TOTAL SCHEDULE II $79,418.75 $112,120.00 $93,711.67 SCHEDULE I + ALTERNATE A (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,512,103.00 $1,521,039.47 $1,622,514.96 SCHEDULE I + ALTERNATE B (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,469,603.00 $1,483,839.47 $1,585,026.09 SCHEDULE I + ALTERNATE A + SCHEDULE II (ENGR'S EST. INCL. 10% CONT.) $1,591,521.75 $1,633,159.47 $1,716,226.63 SCHEDULE I + ALTERNATE B + SCHEDULE II (ENGR'S EST. INCL 10% CONT.) $1,549,021.75 $1,595,959.47 $1,678,737.76 City of Moorpark Tierra Rejada Road Widening Bid Tabulation Spreadsheet Ba opening SECURITY PAVING BURNS PACIFIC 1"A R-93 I I COMPANY, INC. I I CONSTRUCTION, INC. Item No. Item Description Approx. Oty Units Unit Price Total Price Unit Price Total Price 1 MOBILIZATION 1 LS - $231,600.00 $231,600.00 $50,000.00 $50,000.00 2 CLEARING AND GRUBBING 1 LS >? $18,900.00 $18,900.00 $50,000.00 $50,000.00 3 LOCATING EXISTING FACILITIES 1 LS $15,800.00 $15,800.00 $17,000.00 $17,000.00 4 EARTHWORK 67000 CY $3.80 $254,600.00 $5.00 $335,000.00 4a TEMPORARY EARTHWORK MOORPARK RD 1 LS $23,000.00 $23,000.00 $21,000.00 $21,000.00 5 ALLUVIUM & UNCERTIFIED MATERIAL REMOVAL 60000 CY $1.00 $60,000.00 $5.00 $300,000.00 6 TOPSOIL STOCKPILING 32000 SF : $0.25 $8,000.00 $0.03 $960.00 7 42" R.C.P. CLASS 111 25 LF $85.00 $2,125.00 $102.00 $2,550.00 8 36" R.C.P. CLASS IV 123 LF $75.00 $9,225.00 $81.00 $9,963.00 9 30" R.C.P. CLASS IV 141 LF - $62.00 $8,742.00 $68.00 $9,588.00 10 27" R.C.P. CLASS IV 286 LF $62.00 $17,732.00 $70.00 $20,020.00 11 18" R.C.P. CLASS III 153 LF $43.00 $6,579.00 $47.00 $7,191.00 12 5' X 3' CSP ARCH 70 LF $125.00 $8,750.00 $130.00 59000.00 '. 13 VCFCD STD NO. 2 TYPE II JUNCTION STRUCTURE 3 EA $1,730.00 $5,190.00 $1,600.00 $4,800.00 14 C.S.P. 48" D93 INLET RISER 1 EA $2,150.00 $2,150.00 $2,200.00 $2,200.00 15 MOD. DOUBLE CONC. HDWALL 2 EA $5,000.00 $10,000.00 $4,800.00 $9,600.00 16 SINGLE CONCRETE HEADWALL 5 EA $3,240.00 $16,200.00: $2,625.00 $13,125.00 17 3" THICK CONCRETE BENCH DRAIN 505 LF $12.65 $6,388.25: $10.40 $5,252.00 18 3" THICK CONC. DRAIN. SWALE 310 LF $14.00 $4,340.00: $16.00 $4,960.00 19 CONC. TERRACE DOWNDRAIN JUNCT. 2 EA $2,100.00 $4,200.00 $630.00 $1,260.00 20 10' WIDE CONCRETE INTERCEPTOR DRAIN 3160 LF $16.00 $50,560.00: $17.00 $53,720.00 :> 21 FLARED CONC. DRAIN TERMINUS 1 EA $2,200.00 $2,200.00 $750.00 $750.00 22 CURB OPEN. CATCH BASIN W/LOCAL DEPRES.W =14' 2 EA $4,915.00 $9,830.00 $4,500.00 $9,000.00 23 CURB OPEN. CATCH BASIN W/LOCAL DEPRES.W =3.5' 1 EA $3,025.00 $3,025.00 $1,900.00 $1,900.00 24 D87B A.C. OVERSIDE DRAIN WITAPERED INLET 75 LF $55.00 $4,125.00 $20.00 $1,500.00 25 D87A C.M.P. OVERSIDE DRAIN W/TAPERED INLET 25 LF `: $60.00 $1,500.00 $50.00 $1,250.00 !. 26 114 TON CONCRETED RIP RAP 537 CY $83.00 $44,571.00 $70.00 $37,590.00 27 METAL BEAM GUARD RAILING 826 LF $17.00 $14,042.00 $16.50 $13,629.00 <' 28 SAWCUTTING A.C. PAVEMENT 1420 LF $1.50 $2,130.00 $1.00 $1,420.00 29 COLD PLANING EXISTING A.C. PAVEMENT 950 SF $3.00 $2,850.00 $1.00 $950.00 30 3" THICK TEMPORARY A.C. PAVEMENT 600 TON $37.00 $22,200.00 $34.00 $20,400.00 31 18" THICK CLASS 2 AGGREGATE BASE 25000 TON $10.25 $256,250.00 $10.00 $250,000.00 32 2" THICK FINAL A.C. CAP 3000 TON $30.50 $91,500.00 $32.50 $97,500.00 33 3" THICK A.C. BASE COURSE 4500 TON $28.85 $129,825.00 $30.00 $135,000.00 34 1 -1/2" A.C. OVERLAY 200 TON $30.50 $6,100.00 $37.00 $7,400.00 35 ADJUSTING EXISTING UTILITIES 1 LS $5,500.00 $5,500.00 - $2,600.00 $2,600.00 36 RELOCATE EXISTING FENCE 6500 LF $3.15 $20,475.00 $3.15 $20,475.00 37 6' WIDE CONCRETE SWALE (DETAIL "A ") 1400 LF $14.60 $20,440.00 $12.20 $17,080.00 38 6" A.C. BERM (V.C. STANDARD 5 -3, TYPE D -1) 690 LF $2.60 $1,794.00 $2.80 $1,932.00 39 6" CONCRETE CURB (APWA STD Al -6) 3600 LF $5.40 $19,440.00 $5.80 $20,880.00 40 6" A.C. MOUNTABLE A87 TYPE "D" DIKE 2470 LF ':. $2.60 $6,422.00 $3.50 $8,645.00 41 6" P.C.C. CURB AND 18" GUTTER (APWA STD A2 -6) 460 LF :: $11.45 $5,267.00 $6.20 $2,852.00 42 6" P.C.C. CURB AND 12" GUTTER (APWA STD A2 -6) 2920 LF $7.00 $20,440.00 $5.80 $16,936.00 '' City of Moorpark ew Opening Tierra Rejada Road Widening 1e- MAR-93 Bid Tabulation Spreadsheet &D -TRWKI SECURITY PAVING COMPANY, INC. BURNS PACIFIC CONSTRUCTION, INC. Item Approx. Unit Total Unit Total No. Item Description Oty Units Price Price Price Price 43 STAMPED MEDIAN CONCRETE 1320 SF $4.50 $5,940.00 $6.50 $8,580.00 44 HYDROSEEDING 1 LS ! $12,000.00 $12,000.00 $36,000.00 $36,000.00 45 MEDIAN IRRIGATION CROSSOVERS (SCH 40 PVC) 300 LF $26.00 $7,800.00 $21.00 $6,300.00 46 MEDIAN IRRIGATION CROSSOVER RISERS 9 EA $245.00 $2,205.00 $315.00 $2,835.00 47 FINAL PAVEMENT DELINEATION 1 LS $19,240.00 $19,240.00 $20,000.00 $20,000.00 48 STREET LIGHTING CONDUITS 1 LS $19,200.00 $19,200.00 :: $21,000.00 $21,000.00 49 FINAL TRAFFIC SIGNALS 1 LS $60,115.00 $60,115.00 $81,300.00 $81,300.00 50 WATER POLLUTION CONTROL AND SWPPP 1 LS $15,000.00 $15,000.00 $3,000.00 $3,000.00 51 TERMINATION OF LIABILITY 1 1 LS $1.001 $1.00 $1.00 $1.00 TOTAL SCHEDULE I, BID BASE $1,595,508.25 $1,775,994.00 WATERLINE RELOCATION 54 12" PVC PIPE, CLASS 200 3375 LF $23.25 $78,468.75 $24.40 $82,350.00 55 12" TAPPING SLEEVE & GATE VALUE ON 12 "AC PIPE 1 EA $2,700.00 $2,700.00 $3,700.00 $3,700.00 56 2" BLOW -OFF ON 12" PIPE 2 EA $1,620.00 $3,240.00 $1,170.00 $2,340.00 57 1" COMB. VALVE & AIR REL. VALVE ASSEM. 2 EA $1,296.00 $2,592.00 $1,100.00 $2,200.00 58 12" GATE VALVE 1 EA $918.00 $918.00 $1,000.00 $1,000.00 59 1 INST. 12" CAP -CONC. THRUST BLK ON EXIST. PIPE 1 EA $594.00 $594.00 $1,730.00 $1,730.00 TOTAL SCHEDULE II $88,512.75 $93,320.00 SCHEDULE I + ALTERNATE A (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,704,808.25 $1,810,994.00 SCHEDULE I + ALTERNATE B (ENGR'S EST. INCLUDES 10% CONTINGENCY) $1,611,008.25 $1,808,994.00 SCHEDULE I + ALTERNATE A + SCHEDULE II (ENGR'S EST. INCL. 10% CONT.) $1,793,321.00 $1,904,314.00 SCHEDULE I + ALTERNATE B + SCHEDULE II (ENGR'S EST. INCL 10% CONT.) $1,699,521.00 $1,902,314.00