MEMORANDUM
TO: The Honorable City Council BY
FROM: Patrick J. Richards, Director of Community Development
DATE: May 5, 1992 (for May 6, 1992 City Council Meeting)
SUBJECT: Termination of PBR's contract for Updating of the General
Plan Land Use and Circulation Elements, Sphere of
Influence Study and Related Environmental Impact Report.
Staff is suggesting that the Council consider termination of the
General Plan Consultant's contract. The following information has
been provided to assist the Council in their decisions regarding
this matter.
GENERAL PLAN UPDATE - BACKGROUND
HISTORY
Original Contract Amounts
In June of 1989, the original PBR contract amount was $143,500.00.
In September of 1990, this contract amount was revised and the
contract amount was increased by $24,230.00; subsequently in
September of 1990 the original contract was revised from
$143,500.00 to $167,730.00.
The additional costs incurred was due to: the need for additional
property ownership identification and mapping, additional
Environmental Impact Report alternative analysis, and expansion of
the Environmental Impact Report to include areas within the
proposed Sphere of Influence Expansion study area.
In March of 1991, PBR's contract was increased by $2,250.00 for
preparation of: a Horizon Line Exhibit, Valley Floor Exhibit, and
a comparison table of land use alternatives within the
Environmental Impact Report.
In September of 1991, the City and PBR (in cooperation with AFA)
agreed to "close out" the first contract with an outstanding
balance. By September of 1991, PBR's contract had been "revised"
PAUL W. LAWRASON JR. JOHN E. WOZNIAK SCOTT MONTGOMERY BERNARDO M. PEREZ ROY E. TALLEY JR.
Mayor Mayor Pro Tem Councilmember Councilmember Councilmember
The Honorable City Council
May 5, 1992
Page 2
three times and AFA' s contract had been revised twice. By September
of 1991, PBR's contract, due to the subsequent contract revisions,
had totalled $169,980.00.
CONTRACTS
Settlement and Agreement Contracts
On September 9, 1991, the City and PBR signed a Compromise,
Settlement and Mutual Release Agreement and an Agreement for
Completion of the General Plan Update.
The Compromise, Settlement and Mutual Release Agreement closed the
first contract. However, a caveat was put in the Settlement
(Section 1A, page 2) which stated that the City shall pay to PBR
$14,729.49 remaining of the first contract. The Settlement Contract
also stated that the City would pay, in two installments,
$44,000.00 to PBR. In total, the Settlement specified that the City
would pay to PBR a total of $58,729.49, after closure of the first
contract.
The Agreement Contract stated that the City would pay to PBR
$38,959.00 for completion of the General Plan Update.
Settlement and Agreement Summa.ry
The remaining balance to PBR is as follows:
First Contract: $14,729.49 (Contract closed -
with balance due to
PBR, money due
w i t h i n t h e
Settlement Contract)
Settlement Contract: $44,000.00 (Settlement)
Completion Agreement: $38,959,00
The Honorable City Council
May 5, 1992
Page 3
Contract Summary, Including all Contract Revisions
PBR: Contract Amounts: Cumulative Budget:
Original
Revised
Revised
Settlement
Agreement
Total PBR Amount:
PAYMENTS
$143,500.00
$ 24,230.00
$ 2,250.00
$ 58,729.49
$ 38,959.00
$167,730.00
$169,980.00
$228,709.49
$267,668.49
$267,668.49
Payments Remaining to be Paid to PBR Under the Settlement:
The City has paid the entire Settlement amount of $58,729.49, no
balance remains.
Payments Remaining to be Paid to PBR Under the Agreement:
As of March 1, 1992, under the Agreement Contract, PBR has
indicated that $12,730.00 remains to be paid (1). Per work task
PBR Is invoices show the following remaining balances for completion
of the following work tasks:
1 The balance amount includes money due to AFA.
The Honorable City Council
May 5, 1992
Page 4
Task Budget Invoiced (2) Remaining
Phase I $16,000.00
Task A (DEIR(3) $ 2,000.00 $ 2,000.00 $ 0
Task B (FEIR( °) $14,000.00 $14,000.00 $ 0
Phase II $14,959.00
Task A (DLU +C(5)
$
2,150.00
$
2,150.00
$
0
Task B (FLU +C(6)
$
6,900.00
$
79.00
$
6,821.00
Task C (LUMaps)
$
4,900.00
$
0
$
4,900.00
$
1,009.00
$
0
$
1,009.00
Phase III
$
8,000.00
$8,000.00
$
0
Public Hearings
Total Remaining:
$12,730.00
ADDITIONAL COSTS
Special Meeting Attendance Costs outside of Contract Budgets:
PBR's contract identifies that PBR will attend two Planning
Commission meetings and two City Council meetings. Any meeting
attendance in addition to these two meetings, would require payment
of funds above and beyond the contract amount to the consultant.
On two occasions, PBR attended additional meetings (November 21,
1991 at a cost of $653.80 and December 20, 1992 at a cost of
$823.80). Total special meeting costs above and beyond any contract
cost has totaled $1,477.60.
2 As of March 9, 1992
3 Draft Environmental Impact Report
4 Final Environmental Impact Report
5 Draft Land Use and Circulation Element
6 Final Land Use and Circulation Element
The Honorable City Council
May 5, 1992
Page 5
SPHERE OF INFLUENCE STUDY - BACKGROUND
HISTORY
Original Contract Amounts
The City entered into a contract with PBR for a Sphere of Influence
Expansion Study. The original contract amount was $38,550.00. Of
this contract amount, PBR has identified that $12,610.40 is
remaining to be paid to PBR.
Based upon the Sphere of Influence contract, the remaining Sphere
of Influence Contract balance is allocated for the following work
tasks: Consultant attendance at City Council meetings, Local Agency
Formation Commission ( LAFCO) application submittal, LAFCO meetings,
revisions as requested by LAFCO, and project coordination.
Recommendation:
1) Concur with staff's recommendation to terminate the General
Plan Consultant's contract for updating of the General Plan
Land Use and Circulation Elements and Sphere of Influence
Contract.