Loading...
HomeMy WebLinkAboutAGENDA REPORT 1992 0520 CC REG ITEM 08FITEM �' F MOORPARK 799 Moorpark Avenue Moorpark, California 93021 TO: HONORABLE CITY COUNCIL \ ✓ N FROM: RICHARD HARE, DEPUTY CITY MANAGE DATE: May 20, 1992 SUBJECT: Consider Authorizing Final Payment and Filing of Notice of Completion for Park Shelter and Restroom Project Constructed by Jevon Construction Inc. Background (805) 529 -6864 '•'COR ?ASK. CAUFC 7111:,1 Ci4'COUn,, of / 199x2. ACTION: J i The City Council on August 7, 1992 budgeted $256,913.78 for the construction the of three restrooms and four picnic shelters in several parks. The construction project was awarded to Jevon Construction Co. Inc. for $245,713.82 with an additional $17,199.96 for contingencies and inspection. The final contract with Jevon was amended to $241,793.82. The City Manager approved six change orders during the project for a total of $817. Jevon has completed all of the work specified in the contract and change orders, and has requested $200 for extra work for a total of $242,610.82. Staff is requesting direction to file the notice of completion on this project and to make final payment upon receipt of all unconditional releases from the sub - contractors and suppliers for this project. Work Performed The work performed included the construction of picnic shelters at Campus, Glenwood, Griffin and North Meadows parks. Restrooms were constructed at Campus Canyon, Griffin and North Meadows parks. The final inspection and request for final payment was prepared on April 24th by PICON, the project manager. Change Orders There were six change orders on this project. First, $575 was allowed to run sewer connections under asphalt at North Meadows park instead of grass. Second, $400 was allowed to take the same sewer to a depth of four feet. Third, $3,860 was allowed at the same park for additional water, electric, and sewer line after the restroom location was changed. Fourth, $4,000 was deducted from the project costs by omitting partitions which were subject to vandalism and replacing them with 4" slumpstone painted with PAUL W. LAWRASON JR. JOHN E. WOZNIAK SCOTT MONTGOMERY BERNARDO M. PEREZ ROY E. TALLEY JR. Mayor Mayor Pro Tern Councilmember Councilmember Councilmember Printed On Ren 1a 1 an.,a. graffiti resistant paint. Fifth, $818 was deducted due to the elimination of in -wall faucets and vents. The sixth and final change order was for $800 which was for painting all shelters with graffiti resistant paint. To date, Jevon has received $215,958.19 in progress payments. The amount remaining to be paid is $26,673.25. Staff is requesting that a retention of 5% of the total contract for a total of $12,131 be deducted from the final payment, to be released by the City Manager after satisfactory clearance of the 35 day lien and /or receipt of unconditional releases from all sub - contractors and suppliers. Extra Work Performed As part of the project, structures graffiti resistant paint. Jevon's instructions and also painted the with the graffiti resistant paint. the cost of the paint which is $20 this be authorized. Funding were painted with special personnel misunderstood their shelter at Campus Canyon Park Jevon is asking to recover D. Staff is recommending that The entire project was funded from the Park Improvement Fund (05). Each zone is being charged for the work which took place in that zone. The Mountain Meadows zone however did not have adequate funds and Council authorized on 8/7/91 the loan of $3,947.17 from the Campus Park zone to the Mt. Meadows zone to be repaid as funds become available. The actual deficit in the Mountain Meadows zone was $2,377 due to the project being completed for less than the original estimate. The total cost of this contract including the extra work performed is $242,810.82. This is $2,903 less than the original award granted by Council on 8/7/92. Inducement to Make Final Payment As an inducement to make final payment, Jevon has made a contractual guarantee to the city from the date of completion and acceptance of all work under this contract to perform all emergency repairs within 24 hours of notification and normal repairs within 72 hours of notification. This is pursuant to the Standard Conditions of the contract. Recommendation Staff recommends that the City Council take the following actions: 1. Accept the above described work as completed. 2. Instruct the City Clerk to file the Notice of Completion for the project. 3. Authorize payment for work performed by Jevon Construction Co. Inc., including $200 of extra work, of $26,873.25 as a final payment and the retention of $12,131 from that payment ($14,742.25 net payment this warrant register). 4. Authorize the release of the retention upon satisfactory clearance of the thirty five (35) day lien period and /or receipt of uncondition releases from all sub - contractors or suppliers. attachment: Minutes 8/7/91 Staff Rpt. 8/7/92 Contract pg. Chg. Orders 1 -6 Extra Work Request Inducement for Final Payment Payments per Recommendation Minutes of the City Council Moorpark, California Page 10 &17 „%,I C/ August 7, 1991 D. Consider Award of Bid for Picnic Shelters and Restrooms. Staff Recommendation: Award bid to Jevon Construction. (Continued Item 8.J. from 9/4/91) (ROLL CALL VOTE) The staff report was waived. MOTION: Councilmember Perez moved and Councilmember Montgomery seconded a motion to approve the staff recommendation to award the bid for picnic shelters and restrooms to Jevon Construction in the amount of $245,713.82, to be constructed as follows: 1) four picnic shelters, one each at Campus, Glenwood, Griffin and North Meadows Parks, a 7% contingency / inspection fund of $6,35?.96 to be appropriated for a total project cost of $97,186 from the neighborhood portion of the Park Improvement Fund; and 2) construction of three slumpstone restroom buildings, one each at Campus Canyon, Grif fin and North Meadows Parks at a of $154,885.78, with a contingency/ inspection fund of $10,842.00 for a total project cost of $165,727.78; staff directed to reimburse Jevon Construction with the first progress payment for the approximate $12,000 cost Jevon Construction paid to secure a labor and performance bond, this reimbursement payment to be in exchange for a credit of $12,737.50 for electrical construction work necessary to provide electrical service to the picnic shelters; staff directed that capital improvements approved in the FY 91/92 budget for North Meadows Park are to be deferred and a loan made to the neighborhood portion of the Mountain Meadows Zone of $3,947.17 from the Campus Park Zone with the understanding that the loan shall be repaid when funds are received. The motion carried by unanimous roll call vote. E. Consider Community Services Department Logo. Staff Recommendation: Approve Parks and Recreation Commission recommendation. This item was continued to September 25, 1991. F. Consider Award of Temporary Commercial Refuse Permits. Staff Recommendation: Award permits to E. J. Harrison and Sons, G. I. Rubbish, and Moorpark Disposal. The staff report was waived. MOTION: Councilmember Montgomery moved and Councilmember Perez seconded a motion to approve the staff recommendation to award temporary commercial refuse permits to E.J. Harrison and Sons Rubbish Service, G.I. Rubbish Company and Moorpark Disposal Service. The motion carried by unanimous voice vote. G. Consider Rescheduling Meeting Date for Second Meeting in ITEM a -G1 MOORPAjaxx TZ ^/ 799 Moorpark Avenue Moorpark, California 93021 ;8 ? 6FIlr02,NIA �; y Council Meettng OO'rE `. j•1 ; / 19 MEMORANDUM TO: The Honorable City Council FROM: Philip E. Newhouse, Director of Community Services DATE: September 13, 1991 SUBJECT: Consider Award of Bid for Picnic Shelters and Restrooms T. ^_is -:em is presented for Council's consideration_ award a bid to J_- :oa Construction Co., Inc., for the constrct -on of three restrooms and four picnic shelters as follow=: FACILITY: ?ARK: picnic Shelter Restroom �ampus _. X :ampus Canyon - _enwood X -ffin X ':o-th Meadows X -' BACKGROUND: B-ds for the construction of three restrooms and four picnic s el ers were received and opened on July 30, 199 -, at 2:00 p.m. at Ci`y ,Hall . Please refer to Exhibit "A" for bid details. r _eceipt of the bids, staff was made away= Of addi Tonal a =ion related to the work to be done at Nor-: _-.endows Park. -af T ::as informed about stub outs for sewer and installed a_ _-.e park by Urban West Communities not show-_ on the park's as -built plans. �_a == contacted the apparent low bidder, Jevcn onstruction o inform then of _::e s-ub ou�s to discu --s -_'-e bid for the work to ce perfor::ed. Staff also _ _ _ed - :c-.e adinc tie block wall conS:ruct on bid Lro�. -sic -. �icc _ mss_ one __ock mach _.he _cni.c s:-�e_= _n = ~e restrcc_.. p ., �t_on t'-e Jr.-: ric_ and ;_:r_ericr c _AU_ Jn 6ERNARDO M PEREZ -,SO TT YONTGOMFti� ROY E TA--7-1 JOHN E W) NIAK V-,: Mayor Pro Tem CoL.,icilmember Gouncli - cr' Coc i r • r . .,r T:ne Honorab -e City Council Page 2 9/13/91 restroom facility with "ultra shie -y" graffiti paint; and eliminate sit soap dispensers. evor_'s prices for the items requested were as follows: 1. Upgrade block restroom buildings fr:;:n precision block to slu- :pstone S 8,000 2. Credit for six soap dispensers $ ( 300) 3. Credit for sewer lateral (stub) and eliminate 20' of pipe and street excavation (No. Meadow's Park) $(1,475) 4. Credit for 300' of water line to connect to stub (No. r'_eadows Park) $( 700) 5. Exchange metal toilet partitions fo- high density polyethylene S 1,495 6. Application of Ultra Shield to both sides of restroom block walls $ 1,945 Subtotal of extra charges: $ 8,965 Staff recommends elimination of the Ultra Shield (staff can apply) $ O TOTAL EXTRA CHARGES: $ 7,020 As modified, the extra charges requested by staff adjust Jevon's initial bid to $248,498.26. PROJECT FUNDS: The total funds appropriated in the FY 91/92 budget to construct the restrooms and picnic shelters are $165,000.00. The low bid for`each picnic shelter.. came in. at $7,707.01 above -the budget appropriation. The low bid for the restroom buildings at Campus Canyon and North Meadows Parks came in $2,923.44 under the budget appropriation. The low bi:i for the restroom at Griffin Park came in $5,456.70 above the buziget appropriation. This is because a storage room is being added to the Griffin Park restroom. Additionally, utility costs to conne--t electricity, water and sewer to the restrooms were appropriate in the FY 91/92 budget as the costs were unknown -t that time. Utility costs for the restrooms total $32,514.r'0 A summary of the project funds compared to to low bid ar_ as foll--ws: -'ne Honorable :ity Page 3 9/13/91 BID COMPFRISONS LOW BID FUNDS E=-C'- RICAL PARK APPROP. STRU TL:r S RV =::E SUBTOTAL BALANCE Campus $15,300 $22,7C-.01 $ 2,1:0.00 22, -;7.01 ($ 7,707.01) Glenwood *$ -0- $22,70 ".J1 $ 3,577.50 S 22, 7:7.01 ($22,707.01) Griffin $15,C00 $22,70 ".01 $ 4,0:0.00 5 22,-:7.01 ($ 7,707.01) N Meadows $15,000 $22,70-.01 $ 3,0:0.00 3 22, 7:7.01 ($ 7,707.01) Total: $45,000 $90,82:.04 * *$12,737.50 S 90,:28.04 ($45,828.04) * Funds in the amloun= of $15,C00 were appr opriated in the FY 90/91 City budget for a Picnic Shelter a= Glenwood Park. Through an oversight in prepa rin= and adop =ing the FY 91/92 City budget, the funds were not = e- a -ppropriated. S =aff will be recommending the Council appropriate funds in the amor-=t of $22,707.01 from the neighborhood portion of the Northwest ;ark improvement Fund to construct a picnic shelte= at Glenwood Park. ** Jevon Construction has agreed =o eliminate this cost if the City will pay Jevon the full cos-: of =he labor and performance bond with the first prcgress paynent a =d schedule award of the picnic shelters and restrooms at September 18, 1991, Council meeting. The Contractor will insta =l and stub out :lectr__a' co- uit and lights at each picnic shelter at no add- =ic-sl cost. Ti7= City y :u -d r_ responsible to extend the electrical service from the shelters to 7:--e po » -ar source to make the security lights and recep =ac -as opera= io - =_l. RESTR RESTROOM W/O STORAGE ROOM BID j - Park / 1 Frame/ Appropr', Stucco Campus Canyon: $40,000 $33,076.56 Griffin: $40,000 $33,076.56 *T . meadows: 540,1100 533,:76.59- C- oncfete Hlock $35,- -6.56 -.56 56 -..56 UTILITY E3OKUP ELEC. /SETti_R WATER SUBTOTAL BALANCE $38,544.06 $ 1,455.94 ;,46-7.51- 540,544.06 ($ 544.06) S1= ,9C2.0: S45,y78.56 ($ 5,987.56) ..__.:32.0: 547,$78.56 ($ 7,987.56) 4- ._21.5c (° 21.56) .'he Honorable City Co- ;ncil Page 5 9/13/91 ., ANTIC. (1) ANTIC. REVENUE EXPEND. 6/30/91 EXCEPT EXCLUDING ZONE INTEREST SHELTERS TRIAL INCOME RESTROOMS EkL. BALANCE FY 91/92 SUBTOTAL FY 91/92 £.'30/92 Campus Zone: Campus /Campus Cyn. Griffin Parks $586,318 -0- $586,31_8 *5254,380 Mtn. Meadows Zone: N. Meadows Park $ 62,775 $ 13,430 $ 76,205 * *$ 12,000 S (Fedelety) Northwest Zone: Glenwood Park $ 74,185 $ 8,954 $ 83,139 * * *$ 52,125 $ =:,014 (Boething) (1) Summary of Anticipated Park Zone Expenditures FY 91/92 *Campus Park Zone Camp,zs Park 1. Capital Improvements awarded to J & H Engineering $128,900 2. Restroom sky lights - $ 5,000 3. Upgrade irrigation system $ 20,000 !' Campus Canyon Park 1. Light for picnic pavilion $ 750 --2. Additional play equipment for tot lot $ 1,000 Griffin Park 1. Capital improvements awarded to J & H Engineering $ 72,879 2. Horseshoe pits (2) $ 500 3. Two picnic tables $ 1,800 4. Trash receptacles $ 800 * *Mountaiin Meadows Zone North Meadows Park 1. Play equipment $ 7,500 2. Security lighting $ 4,500 ** *Northwest Zone Glenwood Park 1. Capital improvements awarded to J & H Engineering $ 30,625 2. Irrigation upgrade $ 20,000 5. Relocate volleyball courts w /sand S 1,50 o-. ._able =- _ Cc:ac�l acam 6 9 13/9_ FUNDING SUMMARY SHELTE-cS : BY ZONE FOR CONSTRUCTION OF PICNIC COST PICNIC SHELTER () $45,414.02 $22,707.01 $22,707.01 7% CON /INSP..SUBTOTAL $3,178.98 $48,593.00 $1,589.49 $24,296.50 $1,589.49 $24,296.50 BALANCE $283,345.00 $ 39,908.50 $ 6,717.50 FUNDING SUMMARY BY ZONE FOR CONSTRUCTION OF SLUMPSTONE BLOCK RESTROOMS: t ==31 funds available $283,345.00 TRUCTUR• 7 40N11INSP. Cam---.)us :anyon =ark S 43,524.06 $3,046.68 Park N storage S 59. 160.16 $4,141-2-1 Total 5102,684.22 $7,187.89 $109,872.11 Zo -e Ealance $173,422.89 Me =�ows Zane total funds available $ 39,908.50 ?-e -lows ?ark 5 52, 201.56 $3,654.11 $ 55, 855.66 Zone Ealance ($ 15,947.17) cu_ -ently budgeted capital improvement projects at North ve a :ow_ Park =f security lights of $7,500 and play equipment of :,OC cl-ss t:e restrocm building and picnic structures are built, _his z_ne wit- have a deficit of $16,605.00. - Tf = °.omme-ds dele =ion- of the North Meadows capital project .o=a1_ng $12, ,'00 and proceed with construction of the picnic eIte_ and - es_room which would result in a zone deficit of 53,94 7. 7 is you k-now, City Council terminated the Fedelety _ease _o rev_nue profections for the Mountain Meadows Zone are :�n =_2 _- -c-sgh = 1/31/91. oa=f -_ -1 b= =ecomme-:dir.c the undeveloped balance of the Arroyo s.a _o -mu r. Park oon__nue co be leased. If this is done, ad;i='onal revenue of $9,000 annually to the c rountain Meadows Park Imorovement EST. V)NE Sir.. :/30/92 Ca:n7:-,as --ne S =31, 938 Meadows one 5 64,205 - D - =hwe= _ Zone 5 31,014 BY ZONE FOR CONSTRUCTION OF PICNIC COST PICNIC SHELTER () $45,414.02 $22,707.01 $22,707.01 7% CON /INSP..SUBTOTAL $3,178.98 $48,593.00 $1,589.49 $24,296.50 $1,589.49 $24,296.50 BALANCE $283,345.00 $ 39,908.50 $ 6,717.50 FUNDING SUMMARY BY ZONE FOR CONSTRUCTION OF SLUMPSTONE BLOCK RESTROOMS: t ==31 funds available $283,345.00 TRUCTUR• 7 40N11INSP. Cam---.)us :anyon =ark S 43,524.06 $3,046.68 Park N storage S 59. 160.16 $4,141-2-1 Total 5102,684.22 $7,187.89 $109,872.11 Zo -e Ealance $173,422.89 Me =�ows Zane total funds available $ 39,908.50 ?-e -lows ?ark 5 52, 201.56 $3,654.11 $ 55, 855.66 Zone Ealance ($ 15,947.17) cu_ -ently budgeted capital improvement projects at North ve a :ow_ Park =f security lights of $7,500 and play equipment of :,OC cl-ss t:e restrocm building and picnic structures are built, _his z_ne wit- have a deficit of $16,605.00. - Tf = °.omme-ds dele =ion- of the North Meadows capital project .o=a1_ng $12, ,'00 and proceed with construction of the picnic eIte_ and - es_room which would result in a zone deficit of 53,94 7. 7 is you k-now, City Council terminated the Fedelety _ease _o rev_nue profections for the Mountain Meadows Zone are :�n =_2 _- -c-sgh = 1/31/91. oa=f -_ -1 b= =ecomme-:dir.c the undeveloped balance of the Arroyo s.a _o -mu r. Park oon__nue co be leased. If this is done, ad;i='onal revenue of $9,000 annually to the c rountain Meadows Park Imorovement 1- The Honorable City Council Page 7 9/13/91 If Council approves staff's recommendations, the estimated 6/1/92 park zone balances would be as follows: ZONE EST, BALANCE Campus $188,892.00 Mountain Meadows $ 520.00 Northwest $ 18,671.00 STAFF RECOMMENDATION: 1. Award bid to Jevon Construction in the amount of $245,713.82 to: A. Construct four picnic shelters, one each at Campus, Glenwood, Griffin and North Meadows Parks. Appropriate a 7% contingency/ inspection fund of $6,357.96 for a total project cost of $97,166.00 funded from the Neighborhood portion of the Park Improvement Fund as - .follows: Campus Zone $48,593.0()* *2 shelters (Campus & Griffin Parks) Mountain Meadows Zone $24,296.50 Northwest Zone $24,296.50 $97,186.00 B. Construct three slumpstone restroom buildings, one each at Campus Canyon, Griffin and North Meadows Parks at a cost not to exceed $154,885.78. Griffin Park w /storage room $59,160.16 Campus Canyon Park $43,524.06 North Meadows Park $52,201.56 Appropriate a 7% contingency /inspection fund of $10,842.00 for a total project cost of $165,727.78. 4 2. Au s thorize payment of labor and performance bond (approximately $12,OOG) with first progress payment with credit of $12,737.50 for electrical service to picnic shelters. 3. Defer capital improvements approved in the FY 91/92 budget for North Meadows Park and authorize a loan to the neighborhood portion of =he Mountain Meadows Zone of $3,947.17 from the Carpus Park Zone with understanding it shall be repaid when funds are received. PEI:: db Attachment BID OPENING for EXHIBIT "A" PICNIC SHELTERS AND RESTROOM CONSTRUCTION JULY 30, 1991, 2:00 PM Jevon Restroom Carignan N.S. Pellico Construction Facilities, Construction Co. & LeMar, Co., Inc. Ltd. Company Ltd. Inc. Lump Sum: $196,226.26 $249,997 $273,096 $218,058 $314,389 1. Each restroom facility w/o Utility Fees storage room: Not included Frame /Stucco $ 33,076.56 $ 39,205 ** $ 39,651 $ 35,565 $ 57,362 Concrete Block $ 35,076.56 $ 43,000 $ 45,839 $ 44,560 $ 50,200 (3 each) ALT.; add for storage room: Frame /Stucco $ 6,168.54 $ 9,982 ** $ 46,876 $ 6,246 $ 8,767 Concrete Block $ 7,713.48 $ 11,259 $ 56,622 $ 10,722 $ 9,249 (1 each) 2. Each picnic shelter $ 22,707.01 $ 30,600 ** $ 32,599 $ 23,781 $ 32,271 (4 each) UL ;ry Hookup A. Campus Park: Electric to picnic shelter $ 2,160.00 No Bid $ 1,600 1 $ 1,507 $ 7,715 B. Campus Canyon Park: i Water, sewer & electric $ 5,467.50 No Bid S 11,200 $ 10,140 $ 21,584 to restroom C. Griffin Park: Water, sewer & electric $ 12,902.00 No Bid $ 9,171 $ 2,510 $ 11,674 to restroom Electric to picnic shelter $ 4,000.00 No Bid $ 2,500 $ 300 $ 3,388 D. r,1r,,nwood Park: 1- :I(:cLric Lo picnic shelter $ 3,57-1.50 No 13id $ 2,100 $ 910 G, V)8 E. North Meadows Park: wr jt-er, sewer & electric $ 14,145.00 No Bid $ 11,000 $ 10,304 $ 20,404 to restroom Electric to picnic shelter $ 3,000.00 No Bid $ 1.990 $ 300 $ 3,751 TOTALS: $241,478.26 $249,997 $312, 657 $249, 029 $388,963 ** our offer to sell is restricted to 75 days from Notice to Proceed and receipt of approved shop drawings for construction. (This note on Restroom Facilities Ltd bid.) Attachment to Request #3 CITY OF MOORPARK CHANGE ORDER #1 PROJECT TITLE: Restrooms and Picnic Shelters All work involved in this Change Order shall conform with the Standard Specifications, Plans, General Provisions and Special Provisions. The following change(s) is (are) hereby made to the Contract Documents: SEE REQUEST #3 ATTACHED. CHANGE TO CONTRACT PRICE The original Contract Price prior to this Change Order: $241,793.82 The Cost of prior Change Orders: $ -0- The Cost of this Change Order: $ 575.00 The new Contract Price is: $242,638.82 REASON FOR CHANGE: Bid documents considered sewer connection under turf. It is under asphalt. CHANGE TO CONTRACT TIME The Contract time will be increased -0- working days by this Change Order. All other terms of the contract remain the same. REMARKS: APPROVALS REOUIRED Recommended by: 1 5 Dire for of Community Services Date Accepted by: Contractor Date Approved by: City Manager ate-' CITY OF MOORPARK CHANGE ORDER 2 PROJECT TITLE: Restrooms and Picnic Shelters CONTRACTOR: Jevon Construction All work involved in this Change Order shall conform with the Standard Specifications, Plans, General Provisions and Special Provisions. The following change is hereby made to the Contract Documents: 1. Add 4' to sewer depth at North Meadows per Change Order #1. Cost is $400.00. 2. 3. CHANGE TO CONTRACT PRICE The original Contract Price prior to this Change Order: The Cost of prior Change Orders: The Cost of this Change Order: The new Contract Price is: REASON FOR CHANGE: Sewer was 10' dew. . . $241,793.82 $ 575.00 $ 400.00 $242,768.82 The Contract time will be increased 0 working days by this Change Order. All other terms of the contract remain the same. REMARKS: APPROVALS REQUIRED Recommended by: Dir ctor of Comm nity Services —Date Accepted by: 12-15 9/ Contract Date Approved by: /` % ✓' �- "City Manager ate CITY OF MOORPARK CHANGE ORDER 3 PROJECT TITLE: Restrooms and Picnic Shelters CONTRACTOR: Jevon Construction All work involved in this Change Order shall conform with the Standard Specifications, Plans, General Provisions and Special Provisions. The following changes are hereby made to the Contract Documents: 1. At North Meadows Park, extend sewer line 7' to behind sidewalk. Cost = $ 1,450.00 2. Campus Canyon Park: A. 75' additional water line @ $3 /ft. _ $ 225.00 B. 75' additional electric line @ $7 /ft. _ $ 525.00 C. 100' additional sewer line @ $15 /ft. _ $ 1,500.00 D. Move fence $ 160.00 TOTAL: $ 3,860.00 CHANGE TO CONTRACT PRICE The original Contract Price prior to this Change Order: The Cost of prior Change Orders: The Cost of this Change Order: The new Contract Price is: REASON FOR CHANGE: 1. Sewer was not stubbed behind sidewalk 2. City relocated restroom after fence was up. CHANGE TO CONTRACT TIME $241,793.82 $ 975.00 $ 3,860.00 $246,628.82 The Contract time will be increased 5 working days by this Change Order (Campus Canyon). All other terms of the contract remain the same. REMARKS: APPROVALS REQUIRED Recommended by: Dire or of Community Services Date Accepted by: Contract -r- Date Approved by: City Manager Date CITY OF MOORPARK CHANGE ORDER _4_ PROJECT TITLE: Restrooms and Picnic Shelters CONTRACTOR: Jevon Construction All work involved in this Change Order shall conform with the Standard Specifications, Plans, General Provisions and Special Provisions. The following changes are hereby made to the Contract Documents: 1. Omit toilet partitions as specified and use 4" slumpstone reinforced to code vertical and horizontal. Height to be as shown. 2. Paint all structures in and out with graffiti proof clear paint CHANGE TO CONTRACT PRICE The original Contract Price prior to this Change Order: The Cost of prior Change Orders: The Cost of this Change Order: The new Contract Price is: REASON FOR CHANGE: $ (4,000.00) $ N/C $241,793.82 $ 4,835.00 $ (4,000.00) $242,628.82 1. Partitions specified subject to vandalism more than block. CHANGE TO CONTRACT TIME The Contract time will be increased 5 working days by this Change Order and 2 days because of weather. Total time extension is 7 working days. All other terms of the contract remain the same. REMARKS: APPROVALS REQUIRED Recommended by: �- Dir for of Commun' Services to % Accepted by: �' - i" f /3 /9 7 Contractor Date Approved by: 'i''�," ---�i 3 �. City Manager Date CITY OF MOORPARK CHANGE ORDER 5_ PROJECT TITLE: Restrooms and Picnic Shelters CONTRACTOR: Jevon Construction All work involved in this Change Order shall conform with the Standard Specifications, Plans, General Provisions and Special Provisions. The following changes are hereby made to the Contract Documents: 1. Credit for six (Win-wall faucets 2. Credit for six (6) vents 3. Extra for six (6) outside wall faucets TOTAL CREDIT: CHANGE TO CONTRACT PRICE The original Contract Price prior to this Change Order: The Cost of prior Change Orders: The Cost of this Change Order: The new Contract Price is: REASON FOR CHANGE: $( 900.00) ${ 20.00) $ 102.00 $( 818.00) $241,793.82 $ 835.00 $( 818.00) $241,810.82 1. In wall faucets would not work Vents were not necessary because skylights are self- ventilating. CHANGE TO CONTRACT TIME The Contract time will be increased 0 working days by this Change Order; however, completion time(s) are extended five (5) working days due to inclement weather. All other terms of the contract remain the same. REMARKS: APPROVALS REQUIRED Recommended by: 1/10/92 "Dbi�rec' 4of,,communit Services Date Accepted by: —W �� �� Contrra Date Approved by : /.1 ,y1,1 : c± �— y rCity Manager 6ate CITY OF MOORPARK CHANGE ORDER 6_ PROJECT TITLE: Restrooms and Picnic Shelters CONTRACTOR: Jevon Construction All work involved in this Change Order shall conform with the Standard Specifications, Plans, General Provisions and Special Provisions. The following changes are hereby made to the Contract Documents: 1. Paint all shelters (block) with graffiti -proof pigmented paint. $ 800.00 2. Change paint on previous Change Order from clear to pigmented per sample in Griffin Park store room. NBC CHANGE TO CONTRACT PRICE The original Contract Price prior to this $241,793.82 t`- Change Order: The Cost of prior Change orders: $ 8-3-5—G-9- �� y� The Cost of this Change Order: $ 800.00 The new Contract Price is: $243,428.82 REASON FOR CHANGE: 1. Makes block on all structures uniform and crraffiti resistant. CHANGE TO CONTRACT TIME The Contract time will be increased three (3) working days by this Change Order. All other terms of the contract remain the same. REMARKS: APPROVALS REQUIRED Richard T. Hare Deputy City Manager Recommended by : Directo o Comm 'ty Services Date Accepted by: Zvi'' -3 Contractor Date Approved by: City Manager Date AEVON CONSTRUCTION CO. INC. April 20,1992 Mr. Phil Newhouse Director of Community Services 799 Moorpark Ave. Moorpark Ca. 93201 8383 WILSKRE BLVD., SUITE 1000 BEVERLY HILLS, CA 9C211 • (213) 842 -8530 LICE'-:5E 1597964 - BONDED & INSURED Re: Picnic Shelters & Restrooms Const./ Griffity paint at Campus Canyon Park Gentlemen; This is to inform you that the Picnic Sheltter at Campus Canyon Park was painted with -graffity paintin error. Now it is requested that a total amount of Two Hundred Dollars ( $200.00) be paid in order to compensate for material which was used. -­"ease do not hesit� ?T-e to contact this oFf icv should you any questions. Sinc rely, Mehrdad Tabar TO: City of Moorpark 799 Moorpark Avenue Moorpark, CA 93021 FROM: Contractor: :3-e,var ('o fi s�yvc4,,on 6- ) -T�nc -• Address: ts�k4Y3 Wl000 Beverl 1)s 90211 Phone: 21 x%653- 3560 v Trade: evh�4 c,A2.--- Person to Contact: a75 as C, J- ba Contract: P iChi c- Skel4res #s{p4yoo.-- Date: 4 -1(a INDUCEMENT TO MAKE FINAL PAYMENT AND CONTRACTUAL GUARANTEE Gentlemen: We submit that our work under the above contract has been completed and inspected. In order to induce your to make final payment, and pursuant to the terms of the above contract and the Standard Conditions, we do hereby submit this document as a written guarantee for material and /or labor performed under our contract. This letter does not change or amend any other terms or conditions of the contract. We are aware that our guarantee is from the date of completion and acceptance of all work under this contract. The date of this document is not the start of the guarantee period. We will perform emergency repairs within 24 hours of notification and normal service calls for repairs within 72 hours of notification. For Emergency Calls - Phone No.: Z-60-0 - -773( f a 9e>-- For Normal Repair Service Calls: 2131,015-3- 35 9'0 °)V%�e Signed: Company: .Se-ALQl,- Con J 'aeL,62,. ?-C- Name: u c- =T bar' Dated:_ - 16 - �? 2-_ PAY ESTIMATE Schedule of Expenditures Restroom and Picnic Shelter Project DATE WARRANT ----- - - - - -- ----- - - - - -- SUBTOTAL Retention PAID 20- Nov -91 14278 * * 47,013.87 4,675.81 (5,356.64) 41,657.23 4,675.81 20- Nov -91 20- Nov -91 14279 14280 * * 11169.25 2 486.10 1,169.25 2,486.10 20- Nov -91 20- Nov -91 14281 14282 * 1 11 377.96 1,377.96 2,200.00 20- Nov -91 18- Dec -91 14283 16437 * * 21200.00 3,800.00 3,800.00 750.00 18- Dec -91 18- Dec -91 16438 16439 * * 750.00 2,216.53 2,216.53 3,138.66 18- Dec -91 18- Dec -91 16440 16441 * * 3, 38.66 1,100.00 1,100.00 10,407.22 18- Dec -91 18- Dec -91 16442 16443 * * 10 407.22 10,182 10 (3,159.46) 7,022.64 3,138.66 15- Jan -92 15- Jan -92 14376 14377 * * 3,138..66 553.42 553.42 1,600.00 15- Jan -92 15- Jan -92 16533 16534 * * 1,600.00 1,000.00 1,000.00 1,309.86 15- Jan -92 15- Jan -92 16535 16537 * * 1,309.86 1,980.00 1,980.00 81043.08 15- Jan -92 15- Jan -92 16538 16539 * * 8,043.08 50,644.91 (6,206.35) 44,438.56 10,000.00 05- Feb -92 05- Feb -92 16667 16668 * * 10,000.00 7,131.00 7,131.00 11560.73 05- Feb -92 05- Feb -92 16669 16670 * * 1,560.73 23 490.27 (4,218.20) 19,272.07 22 427.41 01 -A r -92 O1 -A r -92 17154 17155 * 24,992.68 660.00 (2,565.27) 660.00 13- May -92 MANUAL 12,023.75 (1,202.37) 10,821.38 20- May -92 20- May -92 TBD TBD 3,964.96 200.00 10,577.29 14,742.25 Subtotals 242,810.82 (12,131.00) 230,679.82 NOTICE OF COMPLETION Notice pursuant to Civil Code Section 3093, must be filed within 10 days after completion. (See reverse side for Complete requirements.) iPersonal s,gnalwe of The mpndual .ho is seearmg Ihat ere contents cf I" no1Qe of comple Lon are tl„ e I NOTICE OF COMPLETION WOLCCTTS FORM II III —Rl1 6 Ta 'X"Ci11131 .. '•ce :r a•I. Notice is hereby given that: 1. The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described: 2. The full name of the owner is rixy of Moorpark 3. The full address of the owner is 79,21 Moorpark Rd Moorpark, f.A 931177 4. The nature of the Interest or estate of the owner is; In fee. fit other than lee. strike "In fee" and Insert. for eramDle. curchaser under Contract of Cu,cnasi or "lessee") S. The full names and full addresses of all persons, if any, who hold title with the undersigned as joint tenants or as tenants in common are: NAMES ADDRESSES 6. A work of Improvement on the property hereinafter described was completed on 5 -202 The work done was: 7. The name of the contractor, if any, for such work of Improvement was - Aevon -Cons tcu- tion-La Inc. 10- 4 -91 A nn centractor lot 6(1 cf 'mpruremenl as a *hole. Insert 'none' 1 (Date of Ccntiact) d. The property on which said work of Improvement was completed Is In the city of Moorpark County of Ventura____ State of Callfornla. and Is described as follows LonstruLti on of 4 picnic shelters and 3 restrooms in various parks, 9. The street address of sad property is 799 - Moorpark -Ave III no street address has been officiany assigned, insert "none".) Dated. verification for In d-dual Owner << Signature Of cwntr or corporate officer of erner named m paragraph 2 or his agent VERIFICATION I, the undersigned. say: I am the _ the declarant of the foregoing I "Prevdenf of Manager of "A partner of" "Owner of etc.) I I notice of completion: I have read said notice of completion and know the contents thereof; the same is true of my own knowledge. di �t III I declare under penalty of perjury that the foregoing is true and correct. Executed on _ 19_. at . California. Dale of slgnaWre.) (City ehere signed 1 iPersonal s,gnalwe of The mpndual .ho is seearmg Ihat ere contents cf I" no1Qe of comple Lon are tl„ e I NOTICE OF COMPLETION WOLCCTTS FORM II III —Rl1 6 Ta 'X"Ci11131 .. '•ce :r a•I.