HomeMy WebLinkAboutAGENDA REPORT 1992 0520 CC REG ITEM 09Cq'0 C 'I
MOORPARK
799 Moorpark Avenue Moorpark, California 93021 (805) 529 -6864
MEMORANDUM
TO: The Honorable Mayor and Members of City Counc'1
FROM: Ken Gilbert, Director of Public Works
DATE: May 18, 1992 (Meeting of 5- 20 -92) M- c-A,.;If�_�;;,3
of 199-..
SUBJECT: Consider a Resolution Revising the Fees for f:CTI N: Public Works and City Engineering Services
overview
This presents for adoption a resolution
and Engineering fees in order to make
compatible with comparable fees charge
adequately provide for cost recovery
provided.
Background
to update the Public Works
them more consistent and
d by other agencies and to
for the services being
The present Public Works and City Engineering fees were adopted by
Resolution No. 84 -119 in July 31, 1984. There have been no
adjustments to these fees since that date. Since that date normal
inflationary factors have increased the cost of most services,
including those discussed herein. Since 1984 the Consumer Price
Index has increased approximately 370. In addition, during that
period, there have been a number of changes in terms of government
mandates, the methods and means used in the industry, technology,
etc. which have resulted in requirements for a higher level of
effort and skill in providing plan checking, inspection, and
related services to the building community and the general public.
Discussion
A. Proposed Fee Schedule
Attached is a draft Resolution which, if adopted, would repeal
the existing fee resolution and adopt a new fee structure.
Exhibit "A" of the resolution sets forth the proposed new
Encroachment Permit Fees and Exhibit "B" sets forth subdivision
map and improvement plan checking and inspection fees. Except
for a few minor differences, the proposed fees are identical to
the fees adopted by the County of Ventura in September of 1991.
PAUL W. LAWRASON JR. JOHN E. WOZNIAK SCOTT MONTGOMERY BERNARDO M. PEREZ ROY E. TALLEY JR.
.._..__.._.....ti,,. Cnuncilmember Councilmember
0
C.
RN
2
Comparison
Attachment #1 is a comparison of fees from a number of
agencies. This comparison includes the present Moorpark fee,
the proposed new Moorpark fee, the County of Ventura fees and
those charged by a number of other agencies. The comparison
demonstrates the fact that the City's fees have fallen sub-
stantially behind those used by other jurisdictions.
Proposed Fee__ Adjustment
Depending on the particular item, the proposed new fee
structure generally represents an increase of from thirty to
fifty per cent (30% - 50 %) over the existing City fee
structure. As in the past, the City Engineer would continue to
receive seventy per cent (70 %) of the fees collected.
Consistent with past City policy regarding all of the fees for
property development services (planning / engineering), the
City would receive the remaining thirty (30 %) to off -set the
City's overhead and administrative costs.
Changes
The new fee structure is different from the existing fee
structure, and in some case the County of Ventura fee
structure, in a number of ways including those noted below.
1. Park Land Dedication Fee -- It is recommended that this
fee be deleted from the list of Engineering fees. It is the
intent of staff to add this fee to the City's Miscellaneous
Fee Resolution to cover costs incurred by the Community
Services Department in the administration of this program.
2. Geology and Soils Review -- The City has recently adopted
a new Building & Safety Fee Schedule which refers to the
Engineering fee schedule for the collection of fees for
Geological and Geotechnical engineering review. Said fees
are set forth in Section 4 of Exhibit "B."
3. Other -- In addition a number of other changes address such
matters as appeals, a warrantee period guarantee deposit,
oversize trucks, etc.
E. Regular Review
Fees should be reviewed on a regular basis. The attached
resolution proposes that staff submit an annual report to the
City Council on the adequacy of the subject fee structure.
3
F. Geological and Geotech' cal Standards
The City has recently been faced with two significant problems
associated with geology and soil failures. In an effort to
address these types of problems, it is recommended that the
City establish geology and soil review procedures to assure
that geology and soil engineering reports are reviewed by
qualified geologists and soil engineers who are specialists in
this area. Such consultants are also best qualified to advise
grading inspectors and building inspectors on matters relating
to grading compaction and control and foundation design when
problems are discovered during construction.
The City of Moorpark has six conditions that suggest the value
of establishing a geology and soil review mechanism. These
factors are listed as follows:
1. The City is in a hillside environment with more development
occurring in steeper areas;
2. Settlement problems have recently been identified that are
causing significant hardship to property owners in the City;
3. Typical development in the City involves extensive grading
operations with many hundreds of homes being built on
compacted fill;
4. The City contains an area of high water table and granular
soil that makes structures located within it more
susceptible to severe damage in earthquakes due to
liquefaction;
5. Known geologic faults traverse the City;
6. The City has a wide range of soil conditions from granular
to highly expansive clays.
It is the intent of staff to develop an ordinance for future
City Council consideration, which would provide more detailed
provisions pertaining to geologic hazards and soil conditions.
Recommendation
Staff recommends that the City Council adopt the attached
Resolution (Attachment 2) rescinding Resolution No. 84 -119 and
adopting a new fee structure for Public Works and Engineering
Services.
wp5ljrptjengfe9k
*$3,471= $32 + $1,624 + ($30.25 X 60 lots)
Eng & PW fee comparison
Page 1
Ir"
ENG & PW FEE COMPARISON
May -92
PROPOSED
EAsTING
VENTURA
THOUSAND
MOORPARK
MOORPARK
OXNARD
SIMI
CAMARILLO
COUNTY
OAKS
FOR MAP CHECK OF A 60
LOT FINAL MAP
'$3471
$2,690
$3,510
$3,580
$4,196
$3,471
$4,094
COMMERCIAL DRIVEWAY
PERMIT
$185
$35
$123
$90
$167
$185
$25+
$45/H R
PERMIT FOR 500 L.F.
OF CURB AND GUTTER
$310
$35
$214
$315
$67
$310
$25+
$45 /HR
REVIEW OF SOILS REPORT
$1,600
NA
NA
$300
$300+
NA
NA
(CONSULTANT)
CONSUL. COST
PERMIT TO DEPOSIT
MATERIAL INSTREET(POOL)
$110
$35
$123
$45
$117
$110
$50
GRADING INSPECTION FOR
150,000 CUBIC YARDS
$2,529
$1,275
$935
$2,198
$700
$2,529
$1,975
PLAN CHECK $500,000
SUBDIVISION IMPROVEMENTS
$16,270
$16,150
$16,250
$10,000
$6,500
$16,270
$16,250
*$3,471= $32 + $1,624 + ($30.25 X 60 lots)
Eng & PW fee comparison
Page 1
Ir"
RESOLUTION NO. 92-
A RESOLUTION OF THE CITY COUNCIL OF
THE CITY OF MOORPARK, CALIFORNIA
ADOPTING A REVISED FEE SCHEDULE FOR
SERVICES RENDERED PURSUANT TO THE
MOORPARK CITY CODE RELATING TO PUBLIC
WORKS AND CITY ENGINEERING AND
RESCINDING RESOLUTION NO. 84 -119
PERTAINING THERETO
WHEREAS, State law and the Moorpark City Code require the
performance of certain plan review, inspection and other services
by the Public Works Director and City Engineer for the purpose of
safeguarding the public health, safety and welfare; and
WHEREAS, the City Council of the City of Moorpark adopted
Resolution No. 84 -119 providing for the collection of certain fees
to allow the cost of such services to be borne by the users and
beneficiaries of same; and,
WHEREAS, the fee schedules for these services must be revised
from time to time to assure adequate recovery of all costs
associated with rendering such services; and,
WHEREAS, the City Council received and considered written
evidence and oral testimony pertaining a possible increase in said
fees at a public hearing scheduled in accordance with the
provisions of Section 66016 of the Government Code and convened on
May 6, 1992, and May 20, 1992.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK,
CALIFORNIA DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. That fees for encroachment permits shall be as set
forth in Exhibit "A" attached hereto.
SECTION 2. That fees for processing of land division ap-
plications and related improvement plans shall be as set forth in
Exhibit "B" attached hereto.
RESOLUTION 92-
PAGE 2
SECTION 3. That resolution num
land use and development services
effective date of this Resolution
determined that the rates, fees an(
wholly or partially invalid by
constitutional provisions, then the
and adoption of this resolution as 1
is void.
)er 84 -119 relating to fees for
is hereby rescinded upon the
provided, however, if it is
charges set forth herein are
virtue of any statutory or
repeal of resolution 84 -119
.o any such rate, fee or charge
SECTION 4. That the fees established in this resolution do not
exceed the estimated reasonable cost of providing the service for
which the fee is imposed.
SECTION 5. The Public Works Director shall report to the City
Council on the cost of development services and the adequacy of the
fee schedule to recover these costs and shall make such report
during the second quarter of each calendar year.
SECTION 6. This Resolution shall take effect sixty (60) days
from the date of adoption in accordance with the provisions of
Section 66017 of the Government Code of the State of California.
SECTION 7. The City Clerk shall certify to the adoption of
this resolution and shall cause this resolution and its certifi-
cation to be filed in the Office of the City Clerk of the City of
Moorpark.
APPROVED AND ADOPTED this
ATTEST:
City Clerk
day of
Mayor
1992.
EXHIBIT "A"
CITY OF MOORPARK
ENCROACHMENT FEE SCHEDULE
PRESENT PROPOSED
FEE FEE
I. GENERAL ENCROACHMENT PERMITS
1. Aunlication /Issuance Fee
Without Engineering Review 10.00 35.00
With Engineering Review 25.00 75.00
2. Permit /Inspection Fees: Permit fees shall be collected in addition to the issuance fee as
follows:
a.
Construction of curb, gutter
and /or sidewalk.
• Less than 100 linear feet
25.00
75.00
• More than 100 linear feet
25.00
75.00
* Plus $0.50 per linear foot over 100.
b.
Construction of residential
driveway (each opening).
25.00
75.00
c.
Construction of Commercial
driveway (each opening).
25.00
150.00
d.
Use of City right -of -way for
access to private property
(swimming pools, equipment
access, etc.)
25.00
75.00
e.
Major tree trimming, tree
removal, stump removal.
25.00
75.00
f.
Approved landscaping
25.00
75.00
g.
Surveying and traffic
counting (per year)
50.00
125.00
h.
Miscellaneous construction
and /or use of City road
right -of -way.
25.00
75.00
Annual blanket permit
100.00
200.00
ENCROACHMENT FEE SCHEDULE
PAGE 2
PRESENT PROPOSED
FEE FEE
i. Placing and /or relocation
of power or telephone poles
(blanket permit per year) 100.00 200.00
Each permit for pole placement
and /or relocation 15.00 35.00
�:-- Hand } }ng - and- }ead }ng- €rni�
eemtaincrs- en- shen }dcrs -e€
the- read- 4per -year3 100.00 Deleted
II. EXCAVATION PERMITS
1. Application /Issuance Fee:
Without engineering review
10.00
35.00
With engineering review
25.00
75.00
2. Permit /Inspection Fees for excavations shall be
collected in addition to the
issuance
fee as follows:
100 linear feet or less
50.00
150.00
101 to 1,000 linear feet
75.00
200.00
1,001 to 3,000 linear feet
100.00
250.00
3,001 to 5,000 linear feet
150.00
350.00
Excavations exceeding 5,000 linear feet
150.00
350.00
plus 0.05
plus 0.10
over 5,000. In
ft.
any additional costs related to the review of
soils reports and /or shoring
plans required for
trench depths in excess of five feet shall be subject to additional charges
sufficient to cover
actual costs plus City overhead.
3. Annual blanket permit for utility trenches
not exceeding two feet in width and sixty
feet in length, dug at a right angle to the
centerline of the road, or an excavation not
exceeding thirty square feet in area
100.00
200.00
Each excavation permitted
under blanket permit
15.00
36.00
ENCROACHMENT FEE SCHEDULE
PAGE 3
PRESENT PROPOSED
FEE FEE
III. TRANSPORTATION PERMITS
Permit Fee:
�: � ieatien- f�sseanee -gee-
Witbetrt- Errgtreer }mg- Rer3err
10.00
Deleted
With- Btfg3neer3mg-Rev ;err
25.00
Deleted
1. Permit Fee: Truck or tractor and load exceeding
legal width, legal length, legal height and/
or legal weight as per State of California
Vehicle Code (per vehicle per trip)
10.00
15.00
2. Annual Blanket Permit: Truck or tractor and load,
maximum width 12 feet, maximum height (loaded)
16 feet, maximum total length 75 feet, weight not
to exceed purple loading (per vehicle per year)
50.00
200.00
3. Additional Charges: Special services necessitated
by unusually large or heavy loads requiring
engineering investigations, or other services.
N/A
Actual Cost Plus
City Overhead
IV. MOVIE AND TELEVISION FILMING
1. Application /Issuance Fee:
Without Engineering Review 10.00 35.00
With Engineering review 10.00 75.00
2. Permit Fee: A filming fee shall be charged for
each day 24 hours) or partial day 100.00 Actual Cost Plus
City Overhead
3. Inspection Fee: The City may require that
an inspector be present during filming on
City public roads. The permittee shall pay
to the City the actual costs of providing
the inspector. Actual Cost Plus Actual Cost Plus
City Overhead City Overhead
V. EXTRAORDINARY INSPECTION COSTS AND CHARGES FOR CITY LABOR
AND MATERIALS.
Extraordinary costs and charges for inspection labor and materials due City shall be charged on the
basis of actual cost plus City overhead. Extraordinary costs and charges for City inspection labor and
materials shall be defined for purposes of this resolution as any costs or charges incurred by City
resulting from permittee's failure to comply with all applicable permit conditions, ordinances and
statutes.
ENCROACHMENT FEE SCHEDULE
PAGE 4
VI. EMERGENCY "CALL OUTS"
Charges for emergency "call outs" shall be paid at the overtime rate, plus City overhead, for the
positions responding for the time of the "call out" (Saturday, Sunday, Holiday, etc.). The charge for
any emergency "call out" shall be based upon a minimum time of four hours per employee used, regardless
of the actual length of time of the "call out," for up to the first four hours used, and then at said
applicable hourly overtime rate, plus City overhead, for the actual number of hours worked. Emergency
"call outs" for the purposes of this resolution shall be defined as providing men and equipment called
to work at times when normal Public Works operations are secured.
VII. FEE EXEMPTION
As required, any Federal, State or local agency shall be exempt from the fees set forth herein, in
accordance with applicable State and /or Federal law.
VIII. TIME EXTENSION FEE
PRESENT PRESENT
FEE FEE
For extension of each permit beyond the
expiration date. One (1) extension is allowed. 15.00 35.00
IX. GEOLOGY AND GFOTECHNICAL REPORT REVIEW DEPOSIT
When the policies, guidelines and procedures of the City require geological or geotechnical
submissions, investigations, reports, or reviews, the applicant shall be required to pay an additional
fee based on the actual or anticipated actual cost of review services including City overhead.
X. OTHER
The fee for records search and other services for which no specific fee is otherwise specified shall
be the total cost to the City including City overhead as determined by the Director of Public Works.
EXHIBIT "B"
CITY OF MOORPARK
SUBDIVISION FINAL PROCESSING FEE SCHEDULE
NOTE: IN EACH ITEM BELOW THE CURRENT FEE IS IN PARENTHESES BEFORE
THE PROPOSED FEE.
1. MAPS
a. Tract or Parcel Hap Issuance Fee: (25.00) 32.00
b. Final Hap. Parcel Hap Check Fee: A Fixed Quality Control fee of ($1,220.00) $1,624.00 per map
plus ($24.50) $30.25 per lot for the first three map checks and quality control only.
C. Additional Checks: Actual Costs including City overhead. A refundable deposit of ($340.00)
$497.00 per map plus ($7.00) $11.50 per lot shall be required for the fourth and each
subsequent map check.
d. General Provisions:
• Any alterations to the exterior boundary or redesign of any interior lots after the
initial map check will be considered as a new submittal.
• All fees shall be paid at the time of submitted.
• If the Actual Cost (including the City overhead) of map checking exceeds the total
deposits, the developer shall pay the Actual Cost (including City overhead) to the
City.
• Actual Cost shall include: staff labor costs (plus City overhead) and /or contract
labor costs (plus City overhead), plus reimbursable expenses (i. e. blueprinting
reproduction, etc.).
2. PLAN CHECKS
a. Subdivision and Other Major Improvements, A fixed fee based upon the Fee Schedule set forth
in Section 5 of this Exhibit.
b. Subdivision and other Hajor Improvement Plan Changes: An Improvement Plan Change Fee of 3%
of the estimate of costs of additional improvements including work for which a Grading Permit
must be obtained.
C. Revisions to Approved Tentative Subdivision MR: Any substantial revisions (i. e. street
alignments, pad sizes, pad elevation changes in excess of two feet) to approved tentative
subdivision maps shall require City Council approval. A fee of $500.00, not including any
required planning fees, shall be required for any request for any such application of map
revision.
d. General Provisions:
• The number of plan checks covered by the above described fees shall be limited to
three. The third plan submittal shall be checked to confirm that said plan submittal
is correct and complete. Any additional plan checking efforts required to approve
said plans shall be subject to additional fees based upon Actual Cost plus City
overhead.
• All fees shall be paid at the time of submitted.
SUBDIVISION FEES
PAGE 2
If the Actual Cost (including the City overhead) of map checking exceeds the total
deposits, the developer shall pay the Actual Cost (including City overhead) to the
City.
Actual Cost shall include: staff labor costs (plus City overhead) and /or contract
labor costs (plus City overhead), plus reimbursable expenses (i. e. blueprinting
reproduction, etc.).
3. INSPECTION
a. Subdivision and Other Major Inn- ovement Construction Inspection: Actual Cost, including City
overhead. A refundable fee deposit shall be paid based upon the Fee Schedule set forth in
Section 5 of this Exhibit.
b. Subdivision Time Extension of Improvement A egr event: A ($300.00) $315.00 processing fee,
plus a refundable deposit of 10% of the fee deposit made under 3a above. The Time Extension
deposit shall be collected for the purpose of off setting all costs associated with the
requested time extension. Any costs associated with a time extension shall not be charged to
the remaining portion of the inspection deposit. Upon completion and acceptance of the
improvements, any balance remaining after deducting the Actual Costs of inspection (including
City Overhead) shall be refunded to developer. In the event Actual Cost exceeds available
deposit funds, the developer shall pay balance due upon receipt of invoice therefor.
C. Deferred Construction Agreement: ($300.00) $315.00 fixed fee for processing this agreement.
d. Guarantee Period Inspection: Actual Cost, including City overhead. Prior to initial
acceptance of improvements, the developer shall pay a fee deposit of $1,000.00. Upon final
acceptance of improvements after the guarantee period, any balance remaining after deducting
Actual Cost of inspection (including City overhead) shall be refunded to the developer. In
the event Actual Costs exceed the $1,000.00 deposit, developer shall pay the balance due upon
receipt of invoice therefor.
4. GEOLOGY AND SOIL ENGINEERING REVIEW
The fees set forth below shall be required for the review and processing of geology and soil
engineering reports by outside geotechnical consultants, when and if such review is required by the
City Engineer as determined by City or State guidelines:
Geotechnical
Single lot $1600.00
2 -6 lot subdivision $2100.00
7 -50 lot subdivision $3000.00
Subdivision over 50 lots $3000.00
- for each lot over 50 $ 200.00
Geology
$1600.00
$2100.00
$3000.00
$3000.00
$ 200.00
Special submittal, investigations, reports, or reviews will require deposits based on the actual or
anticipated actual cost including City overhead. The above fees will cover one review and one follow -
up review. Fees for additional reviews are to paid on a actual time basis plus City overhead.
SUBDIVISION FEES
PAGE 3
0
M
FEE SCHEDULE
The following schedule
Inspection Fee Deposit
costs.
Improvement
Costs M
0 -
999
1,000 -
9,999
10,000 -
49,999
50,000 -
99,999
100,000 -
999,999
1,000,000 and over
shall be used to calculate the Plan Checking Fee (Paragraph 2a) and the
(Paragraphs 3a). Said fee schedule is based upon the estimate of improvement
Deposit (5)
(300) 420.00
(300) 420.00 + 15% of cost over 1,000
(1,650) 1,770.00 + 101 of cost over 10,000
(5,650) 5,770.00 + 51 of cost over 50,000
(8,150) 8,270.00 + 21 of cost over 100,000
(26,150) 26,270.00 + It of cost over 1,000,000
GRADING PERMIT AND PLAN CHECKING FEE SCHEDULE
QUANTITY
CUBIC
YARDS-
50 or
less
51 -
100
101 -
200
201 -
300
301 -
400
401 -
500
501 -
600
601 -
700
701 -
800
801 -
900
901 -
1,000
1,001 -
2,000
2,001 -
3,000
3,001 -
4,000
4,001 -
5,000
5,001 -
6,000
6,001 -
7,000
7,001 -
8,000
8,001 -
9,000
9,001 -
10,000
10,001 -
20,000
20,001 -
30,000
30,001 -
40,000
40,001 -
50,000
50,001 -
60,000
60,001 -
70,000
70,001 -
80,000
80,001 -
90,000
90,001 -
100,000
100,001
OR ABOVE
PLAN CHECK
FEES (S)
(28.00) 44.00
(43.00) 67.00
(63.00) 99.00
(82.00) 130.00
(102.00) 161.00
(122.00) 191.00
(141.00) 221.00
(161.00) 253.00
(182.00) 287.00
(202.00) 318.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(213.00) 334.00
(228.00) 357.00
(243.00) 380.00
(258.00) 403.00
(273.00) 426.00
(288.00) 449.00
(303.00) 472.00
(318.00) 495.00
(333.00) 518.00
(348.00) 541.00
Note A
INSPECTION
(30.00) 59.00
(45.00) 88.00
(65.00) 128.00
(85.00) 168.00
(105.00) 208.00
(125.00) 248.00
(145.00) 288.00
(165.00) 328.00
(185.00) 368.00
(205.00) 408.00
(225.00) 448.00
(242.00) 481.00
(259.00) 514.00
(276.00) 547.00
(293.00) 580.00
(310.00) 613.00
(327.00) 646.00
(344.00) 679.00
(361.00) 712.00
(378.00) 745.00
(445.00) 896.00
(530.00) 1,047.00
(606.00) 1,198.00
(682.00) 1,349.00
(758.00) 1,500.00
(834.00) 1,651.00
(910.00) 1,802.00
(986.00) 1,953.00
(1,062.00) 2,104.00
Note B
TOTAL
103.00
155.00
227.00
298.00
369.00
439.00
509.00
581.00
655.00
726.00
782.00
815.00
848.00
881.00
914.00
947.00
988.00
1,013.00
1,046.00
1,079.00
1,253.00
1,427.00
1,601.00
1,775.00
1,949.00
2,123.00
2,297.00
2,471.00
2,645.00
Notes: A = $541.00 for the first 100,000 cubic yards, plus $14.00 for each additional
10,000 cubic yards or fraction thereof.
B = $2,104.00 for the first 100,000 cubic yards, plus $85.00 for each additional
10,000 cubic yards or fraction thereof.
SUBDIVISION FEES
PAGE 4
7. ADDITIONAL GRADING PLAN CHECKING / INSPECTION FEES
a. Time Extension Fee; ($75.00) 135.00 time extension fee will be required for each time
extension of up to six months.
b. Change Order Fee: ($75.00)
1) Minor (Staff Review Only): An additional plan checking and /or inspection fee, as
required, based upon the amount of earth subject to the proposed change, calculated
per the fee schedules set forth in Section 6 of this Exhibit.
2) Major (City Council Action Required): An additional submittal fee of $500.00, plus
an additional grading plan checking and inspection fee, based upon the amount of earth
subject to the proposed change, calculated per the fee schedules set forth in Section
6 of this Exhibit.
C. Exception for Subdivisions and Other Major Improvements.
Grading Permit and Plan Check fees do not apply to subdivisions and other major improvements,
inasmuch as the actual costs of plan checking and inspection have been included in the final
plan checking and construction inspection fees.
e. Illegal Grading Fees
2002 of the applicable Grading Permit fee, plus City overhead, will be charged for any grading
project undertaken without a grading permit that is in violation of the Grading Ordinance.
a- PARKyBANB- BEBieATIeN
Eeatriaearred- in- preeess4nq -fie- perk - }and - Bed }eat }en- requ3reme�s
($150.00)
8. CERTIFICATES
Issuance of Certificate of Compliance
($250.00)
9. OTHER
Deleted
$420.00 per parcel (fixed fee)
The fee for records search and other services for which no specific fee is otherwise specified shall
be the total cost to the City including City overhead of any time spent retrieving said records as
determined by the Director of Public Works. Time shall be in 1/4 hour increments at the then
applicable hourly rate(s).
10. APPEAL FEE
Any appeal of a decision of the City Engineer regarding the interpretation or application of the City's
Engineering Standards or this fee schedule shall be accompanied by a deposit of $500.00. The amount
of the Appeal Fee shall be actual cost plus City overhead.