FROM: Donald P. Reynolds Jr., Administrative Services Managefr.�
DATE: September 9, 1994
SUBJECT: Consider Budget Amendment for the Installation of an
Emergency Generator for City Hall
Staff has concluded the bid process for the installation of an
emergency generator. As a result of identifying the cost for
construction, is requesting that the Council appropriate an
additional $4,920 to complete the project. The proposed costs are
identified in Attachment "A."
11.12 %Z�Lelk
.�
On January 25, 1994, Council approved the procurement of electrical
engineering services for a needs analysis and design of a standby
generator system. The engineer was to assist staff in identifying
the options for the type of equipment and the building to be
powered in case of an emergency, based on a budget of $23,000.
During budget deliberations, the allocation of Gann monies for
fiscal year 1994/95 was approved by the Council increasing the
generator budget to $33,000. After completing the design of the
project and receiving the engineer's cost estimate of $29,000, it
was determined that the budget would be very close. Staff
concluded the bid process on August 19, 1994, which resulted in a
a cost of $30,489 to build the system, and was able to finalize the
projected costs, (as set forth in the attachment).
Staff has added a cost for fencing around the generator equipment
and a 10% contingency for construction, totalling $37,920; $4,920
above budget. Less the contingency and the fencing, the project
would be $1,371 over budget.
Staff has met with the successful bidder and the electrical
engineer to discuss the different perceptions of the bid proposal,
in order to identify the need for change orders prior to the City's
execution of the contract. The contractor is comfortable with the
engineer's design, and felt that perhaps there could be a small
savings. Therefore, it was agreed that there are very few
unidentifiable factors related to this project that would cause a
need for changes. For this reason, staff is optimistic that very
little or none of the contingency will be needed.
Fencing was not originally perceived as part of this project. It
is recommended however, that this feature be included to preserve
the dependability of the generator by protecting it from vandalism.
The project will begin ten days after City execution of the
contract, (approximately within the first week of October, 1994).
It is estimated that work will be completed by the end of December,
1994. Eight to ten weeks are required to receive the generator
equipment from the manufacturer.
Recommendation
That the City Council authorize the appropriation of $4,920 to the
Emergency Generator budget in 01.4.117.903, from the General Fund
Reserve, to be added to the existing budget of $33,000, for a cost
not to exceed $37,920.
Attachments: A) Summary of Proposed Generator Costs
ATTACHMENT "A"
EMERGENCY GENERATOR PROJECTED COSTS
ITEM
COST Sub-Total Total
-----
-----------
ELECTRICAL ENGINEER
Initial Study of City Facilities/Needs 800
Design Documents 2000
Construction Administration/Inspection 600 3400
BUILDING PERMIT 483 483
CONSTRUCTION
Proposed Contract Amount
30489
Contingency (10%) 3049 33538
FENCING 500 500
------- - - - - --