HomeMy WebLinkAboutAGENDA REPORT 1991 0918 CC REG ITEM 08G /W71/ 7 F 7.T , CMS
•
oPa ITEM 8- G
®®RPAI�I{
-41
latiNpNe0 799 Moorpark Avenue Moorpark, California 93021 (805) 5296864
oqT
E� J
MEMORANDUM
TO: The Honorable City Council ()f
FROM: Kenneth C. Gilbert, Director of Public Works
DATE: September 11, 1991 (Council Meeting 9-18-91)
Council Meol ng
SUBJECT: Consider Approval of the Construction of a G/�s?' 199L
Sidewalk on the West Side of Spring Road / �
from Roberts Street to the Southern Pacific ACTION:
Railroad Right-of-Way
ByYX1tfitt
OVERVIEW
This requests authorization to proceed with the construction of the
subject project as Change Order to an existing contract for similar
work now underway in the general vicinity.
DISCUSSION
A. Background
Recently the City Council awarded a contract to Padilla & Sons.
Inc. for the construction of a sidewalk on the north side of Los
Angeles Avenue between Spring Road and Millard Street. The
construction of this project is now underway.
B. Spring Road Sidewalk [West Side]
The list of capital improvement projects shown in this year's
budget includes a project to construct a sidewalk on the west
side of Spring Road from Roberts Street to the Railroad right-
of-way. The amount budgeted for this project is $50,000. It is
funded by the L. A. AOC Fund.
PAUL W. LAWRASON JR. BERNARDO M. PEREZ SCOTT MONTGOMERY ROY E. TALLEY JR. JOHN E. WOZNIAK
Mayor Mayor Pro Tern Councilmember Councilmember Councilmember
Spring Road Sidewalk
September 18, 1991
Page 2
C. Project Desiarl
The design proposed for this project is comparable to and
compatible with the sidewalk recently constructed on the west
side of Spring Road south of Roberts Street. That design called
for the construction of a five feet wide sidewalk adjacent to
the curb with a variable width unpaved area adjacent to the
block wall fences, suitable for the future planting of
landscaping.
D. Change Order
Padilla & Sons, Inc. was asked to submit a proposal to construct
the subject sidewalk as a change order to our existing contract.
A proposal has been prepared and submitted to the City. The
prices quoted in that proposal are compatible with the bid
prices submitted in their original bid.
E. Project Cost Estimate
Based on the figures being considered in the price negotiations
mentioned above, staff anticipates the total cost of this
project -- including Engineering costs for design, inspection
and contract administration -- will not exceed $25,000.
F. Caltrans Permit
In order to expedite this project, an application for an
Encroachment Permit has already been submitted to Caltrans. It
is expected that the a Permit could be issued the week ending
September 20. The issuance of that permit does not obligate the
City to proceed with the construction of the project in the
manner recommended herein.
G. Conclusions
. In that the dollar amount of this additional work will be
less than twenty-five per cent (25%) of the total contract
amount for the existing (L. A. Ave. ) sidewalk construction
contract, this additional work may be added to the existing
contract through the execution of a contract Change Order.
. It is the opinion of staff that the total cost of the project
via a negotiated Change Order, will be less than the total
cost of the project if it were to be accomplished via a
separate contract.
. It is, therefore, recommended that the City Council approve
the subject project and authorize staff to negotiate a Change
Order with Padilla & Sons. Inc. for its construction.
Spring Road Sidewalk
September 18, 1991
Page 3
RECOMMENDATION
Staff recommends that the City Council take the following actions:
1. Approve a project to construct a sidewalk on the west side of
Spring Road from Roberts Street to the paved driveway just south
of the Southern Pacific Railraod right-of-way.
2. Authorize the City Manager to negotiate a Change Order to the
existing contract with Padilla & Sons, Inc. for the construction
of said work -- said Change Order Not to Exceed $20,000.
3. Approve a ten per cent (10%) contingency for this project and
authorize the City Manager to approve additional work, if
required, for an amount not to exceed ten per cent (10%) of the
contract price.