HomeMy WebLinkAboutAGENDA REPORT 2013 0619 CCSA REG ITEM 10D ITEM 10.D. :�Zy Council Mee4inq ? N: MOORPARK CITY COUNCIL - AGENDA REPORT _. m TO: Honorable City Council FROM: Dave Klotzle, City Engineer/Public Works Director DATE: June 7, 2013 (CC Meeting of 06/19/13) SUBJECT: Consider Amendment No.2 to Agreement for Engineering Services with RJR Engineering Group DISCUSSION On April 9, 2009, the City entered into an Agreement with RJR Engineering Group (RJR) for engineering services. The scope of work included Development Engineering, Plan Checks and Land Development Review. On November 4, 2009, the City executed Amendment No. 1 to the Agreement to add Public Works Encroachment Permits and Land Development Inspection to RJR's scope of work. The Agreement allows for RJR's hourly rates to be adjusted annually, effective July 1, upon a request submitted by RJR and approved by the City. The adjustment in rates is based on the Consumer Price Index (CPI), using the U.S. City Average for All Urban Consumers All Items Indexes for the previous April to April 12-month period, or seven percent (7%), whichever is less. The City approved a 2.3 percent increase in RJR's hourly rates, effective July 1, 2012, based on the CPI described above. This was the first increase in RJR's hourly rates since the Agreement was executed on April 9, 2009. On May 16, 2013, RJR submitted a request for a 1.1 percent increase in their hourly rate to be applied only to the classification of Construction Inspector. The requested increase is based on the CPI described above. The proposed Amendment No. 2 includes a new hourly rate schedule to replace the hourly rate schedule currently in the Agreement. The new hourly rate schedule includes the increased rate for Construction Inspector and current rates for all other classifications. If approved, the new hourly rate schedule will become effective July 1, 2013. FISCAL IMPACT The majority of engineering services performed by RJR are paid for by developer plan check and inspection fees and deposits. Occasionally, RJR performs engineering services for City projects, and such services are funded by the adopted project budget. 85 Honorable City Council June 19, 2013 Page 2 STAFF RECOMMENDATION Authorize the City Manager to sign Amendment No. 2 subject to final language approval by the City Manager and City Attorney. Attachment: Amendment No. 2 86 AMENDMENT NO. 2 TO AGREEMENT BETWEEN THE CITY OF MOORPARK AND RJR ENGINEERING GROUP FOR ENGINEERING SERVICES This Amendment, made and entered into this day of , 2013, between the City of Moorpark, a California municipal corporation, hereinafter referred to as "City" and RJR Engineering Group, a corporation, hereinafter referred to as "Consultant." Whereas, on April 9, 2009, the City and Consultant entered into an Agreement for engineering services; and Whereas, on November 4, 2009, the City executed Amendment No. 1 to the Agreement to add Public Works Encroachment Permits and Land Development Inspection to Consultant's scope of work; and Whereas, the Agreement allows for Consultant's hourly rates to be adjusted annually, effective July 1, based on the Consumer Price Index (CPI), using the U.S. City Average for All Urban Consumers All Items Indexes for the previous April to April 12- month period, or seven percent (7%), whichever is less, upon a request submitted by Consultant and approved by the City; and Whereas, the City approved a 2.3 percent increase in Consultant's hourly rates, effective July 1, 2012; and Whereas, on May 16, 2013, Consultant submitted a request for a 1.1 percent increase in their hourly rate to be applied only to the classification of Construction Inspector; and Whereas, the City now desires to increase Consultant's hourly rate for Construction Inspector by 1.1 percent and replace the hourly rate schedule in Exhibit B with the revised hourly rate schedule in Revised Exhibit B. Now, therefore, in consideration of the mutual covenants, benefits, and premises herein stated, the parties hereto agree to amend the aforesaid Agreement as follows: I. Hourly Rate Schedule Exhibit B of the Agreement is hereby replaced with Revised Exhibit B, Hourly Rate Schedule. The rates in Revised Exhibit B shall be effective as of July 1, 2013. II. Remaining Provisions All other provisions of the aforesaid Agreement shall remain in full force and effect. 87 In witness whereof, the parties hereto have executed this Amendment on the date and year first above written. CITY OF MOORPARK RJR ENGINEERING GROUP Steven Kueny, City Manager Robert Anderson, Principal Engineer Attest: Maureen Benson, City Clerk RJR Engineering Group 28 Revised Exhibit B Land Development&Planning 1�01 Storm Water Management&Engineering Hydrology/Flood Control Soil BioEngineering&Stream Restoration Airport Engineering Design&Support Public Agency/Municipality Consultant June 13,2013 PN 1503 CITY OF MOORPARK 799 Moorpark Avenue, Moorpark, California 93021 Attention: Mr. Dave Klotzle, City Engineer/Public Works Director Subject: 2013 CONSULTING PEES Dear Mr. Klotzle: RJR Engineering Group (RJR) has prepared the following sulmnary of the current and proposed consulting fees: Current Year Upcoming Year Classification 7/2012-612013 7/2013-6/2014 Change Principal Professional $ 172.17 $ 172.17 - Senior Professional $ 149.21 $ 149.21 - Project Professional $ 114.78 $ 114.78 - Staff Professional $ 104.38 $ 104.38 - Senior Draftsman $ 95.42 $ 95.42 - Draf-snian $ 78.08 $ 78.08 - Construction Inspector . $ 72.00 $ 72.79 1.1% Permit Technician $ 61.56 $ 61.56 - Admin.Assistant $ 46.96 $ 46.96 - If you have any questions,please do not hesitate to contact us at(805)485-3935. i Sincerely, i 89 3500 Carnino Avenue,Suite 200 1 Oxnard,CA 93030 1 p:805.485.3935 1 f:805.485.6496 Malibu p;310.456.9085 I San Luis Obispo 1):805-596.0216 1 Lake Tahoe/Sacramento p:530.888.7356 I www.rjreng.com i i HEM i RJR ENGINEERING GROUP Robert W.Anderson, N.S.P.E., R.C.E., G.C.,Juris Doctorate Principal Civil Engineer-RCE 58383 (CA) Arizona: RCE 51923 Washington PE 47559 South Dakota PE11546 Colorado PE 44734 Hawaii RCE 14230 Oregon RCE 84690 North Dakota PE 8252 New York PE Certified CPESC#6840 Certified CISEC#113 7 California Certified QSP/QSD#21902& Certified CESSWI#3270 Trainer of Record(ToR) Certified CPSWQ#0920 Certified CPSWPPP/CCIS#3367 Certified CMS4S#0223 June 11,2013 Page:2 Project No.6000.10 Copyright 2013 RJR Engineering Group—All Rights Reserved 90