SUBJECT: Consider Change Order #1 for Removal of Underground Storage Tanks
(UST) and Demolition of Structures at 412/450 High Street (Project 5084)
and Resolution Amending the Budget for FY 2013/14
BACKGROUND
The Redevelopment Agency of the City of Moorpark purchased the property at 412/450
High Street, formerly the JE Clark Fueling Station, in November 2010. The Successor
Agency Board authorized the advertisement for bids on October 3, 2012 for demolition of
the structure and underground storage tanks. Five bids were received by the due date of
November 5, 2012, and the Agency awarded the bid to NCM Demolition and Remediation,
L.P. (NCM) on December 19, 2012. The Notice to Proceed (NTP) was issued on March 21,
2013 and the original contract end date was April 17, 2013.
DISCUSSION
NCM immediately began work on the project pursuant to the NTP. They submitted
permanent tank closure paperwork to the County of Ventura Environmental Health
Department (EHD) who indicated that the permanent closure permit would be ready within
one to two weeks. For reasons unknown EHD took 30-days to issue the permit. Additionally,
it took Southern California Edison 30-days to schedule the removal of the live electrical
service line. NCM was finally able to begin work on the project at the end of May. While
exposing the tanks scheduled for removal under the original scope of work, NCM exposed
one of the two older tanks on site that had been previously abandoned in place. Since NCM
is on site and has already exposed one of the older tanks, staff requested a change order to
remove this tank and search for the second tank and remove that one if found pursuant to a
revised permanent tank closure permit issued by EHD.
NCM is requesting a change order to the contract completion date of 90-days and additional
funds to remove the third and fourth tank.
375
Honorable Successor Agency Board
July 17, 2013
Page 2
FISCAL IMPACT
The project bid was $107,700.00, with a 10% project contingency of $10,770.00 for a total
approved project cost of $118,470.00. Since the requested amount for the change order
work is more than the project contingency, staff is requesting a budget amendment of
$24,800.00 for the change order work in order to keep the original project contingency intact
for other unforeseen circumstances. This makes the total authorized contract amount,
including contingency funds, $143,270.00 and is less than the approved Recognized
Obligation Payment Schedule (ROPS) 13-14A amount of $200,000.00, which was approved
by the Successor Agency and Oversight Board February 19, 2013 . A budget amendment
from the RDA-SA Econ Devt Fund (9101) in the amount of $24,800.00 is needed to fund the
requested change order.
STAFF RECOMMENDATION (ROLL CALL VOTE)
1) Approve Change Order #1 for NCM Demolition and Remediation, L.P., amending the
Agreement in the amount of $24,800.00 and authorize the Executive Director to execute the
Change Order, subject to final language approval by the Executive Director and Agency
Counsel.
2) Approve Resolution No. SA-2013-
Attachment 1: Change Order#1
Attachment 2: Resolution No. SA- 2013-
376
ATTACHMENT HMENT I
SUCCESSOR AGENCY OF THE
REDEVELOPMENT AGENCY
OF THE CITY OF MOORPARK
CHANGE ORDER
Change Order No. 1
Job Title: DEMOLITION AND REMOVAL OF UNDERGROUND STORAGE TANKS
Project No: SARA-12-01
This Change Order Provides for:
ITEM #1 —Time Extension
1. Reason for Change: Numerous delays outside of the Contractor's control
relevant to permit processing with the Environmental Health Department (EHD) and
discovery of additional tanks and revision to current EHD permit.
2. Description of Change:
Adding time to contract (non-monetary)
3. ADDED WORK—AGREED PRICE ADD: $0
4. Change in Contract Time: Ninety (90) days are added to contract time. New
completion date is August 27, 2013.
ITEM #2 —Removal of additional tanks
1. Reason for Change: Contractor found one of the two suspected additional tanks
that had been previously closed in place. City is requesting removal of this tank and
discovery and removal of the second tank, if found.
2. Description of Change:
Removal of third and fourth tanks per EHD revised permanent closure permit.
3. ADDED WORK— AGREED PRICE ADD: $24,800
4. Change in Contract Time: Incorporated in Item #1.
The Total Amount of this change is......................................................... $24,800
Original Contract Amount: $107,700.00
Sum of Prior Change Orders: $0.00
This Change Order(#1) amount total $24,800.00
New Contract Amount with all change orders: $132,500.00
Change Order No. 1
Page 1 of 2 377
Changes in Project Duration:
Original Project Duration: 30 Days
Prior Approved Additional Project Days 0 Days
This Change Order(#1) adds: 90 Day
Revised Project Duration: 120 Days
Original Completion Date: April 17, 2013
New Completion Date: August 27, 2013"
*new completion date has adjustments based on City Holidays during the extended time period.
The undersigned hereby propose and agrees to furnish any and all labor, material, equipment,
etc, in strict accordance with the requirements of the original contract documents except as
specifically above noted or otherwise required in connection with the above proposed change.
The original contract documents remain in full force ad effect except as specifically modified
herein.
The Agency and Contractor hereby agree that the compensation set forth in this change order
shall comprise the total direct and indirect costs due to the Contractor for the work or changes
defined in the Change Order.
This Change Order constitutes full and mutual accord and satisfaction for all time and all cost
related to this change. By acceptance of this Change Order the Contractor aggress that the
Change Order represents an equitable adjustment to the contract.
APPROVED:
Subhas Kara, President, NCM Demolition and Remediation DATE
APPROVED
Steven Kueny, Executive Director DATE
Successor Agency of the Redevelopment Agency of the City of Moorpark
Attachment:
Contractor's Request for Change Order's#1 and#2
Change Order No. 1
Page 2 of 2 378
NCM Derncihhon and Remediation, LP
404 North Berry Street
Brea: CA 92821-3104
T 714.673-3500
"714.672.3501
NCM .:wva ncrn>rou��con,
CA License#914688
REQUEST FOR CHANGE ORDER
June 26, 2013 REQUEST NO. it
TO: Jessica Sandifer Via Email:jsandifer(i�ci.moorpark.ca.us
City of Moorpark
Community Development
799 Moorpark Avenue
Moorpark,CA 93021
Project Name: Demolition and Removal of Underground Storage Tanks 412/45o High Street
This request covers proposed changes to the contract as described herein.
Description of Changes:
Due to numerous delays caused by the Ventura County of Environmental Health Department,NCM
Demolition and Remediation and the City of Moorpark have been unable to obtain the required permits to
start the removal of the underground storage tanks.Additionally a 3rd and possibly 4th tank have been
discovered on site.As a result we are requesting a non-monetary change order,in the form of a 90-day
time extension,to allow for the permitting process to be completed,at which time the removal of the tanks
will commence.
TOTAL ADD TO CONTRACT: ....................................................................................... $ 0.00
Contract Time shall be extended by: qo calendar days.
Work described above is: (X)required Q optional
Submitted by:
By: James Vallejos—NCM Demolition and Remediation, LP 6/26/2012
The described changes have been reviewed and authorized to proceed at the above dollar
amount.
Approved by:
By: Jessica Sandifer—City of Moorpark 4122/2012
JV:js
412/45o High Street Change Order#1
379
NCM Demolition and Rernediati0;9_-P
404 North Perry Stre.tt
Brea,CA 92821-3104
T 714,672.3500
F 714,6 7 gt0U
wr w.ncmgroup com
GA License 4914688
REQUEST FOR CHANGE ORDER
June 18, 2013 REQUEST NO. 2
TO: Jessica Sandifer Via Email:jsandifer(?,ci.moorpark.ea.us
City of Moorpark
Community Development
799 Moorpark Avenue
Moorpark,CA 93021
Project Name:
Demolition and Removal of Underground Storage Tanks 412/45o High Street
This request covers proposed changes to the contract as described herein.
Description of Changes:
Expose,two approximately 8,000 gallon abandoned underground storage tanks,filled with concrete
slurry.Concrete will have to be broken out from each tank to allow for proper cleaning of residual solids
and liquids. Price includes permits,testing,backfill and compaction.
This change order includes 400 gallons of manifested material with excess gallons being additionally
billed at$1.85 per gallon.Solids and/or sludge will be billed at$300.00 per drum.
This proposal assumes that tanks are not larger than 8'in diameter.If tanks are larger than 8'in diameter,
there will be an additional charge for drop decks and permits.
This change order assumes that there will be a water source within 150 feet of the tank hole.It no water
will be available,a water tank can be provided at an additional cost of$300.00 Fiberglass tank disposal is
an additional charge that is not included in this change order.
TOTAL ADD TO CONTRACT: ..............................................................................$24,800.00
Contract Time shall be extended by: _5_ calendar days.
Work described above is: (X)required Q optional
Submitted by:
By: James Vallejos—NCM Demolition and Remediation,LP 6/18/2013
380
ATTACHMENT 2
RESOLUTION NO. SA-2013-
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE
SUCCESSOR AGENCY OF THE REDEVELOPMENT AGENCY
OF THE CITY OF MOORPARK, CALIFORNIA, AMENDING THE
FISCAL YEAR 2013/2014 BUDGET BY APPROPRIATING
$24,800.00 FROM THE RDA-SA ECONOMIC DEVELOPMENT
FUND (9101) FOR CHANGE ORDER #1 FOR DEMOLITION OF
STRUCTURES AND UNDERGROUND STORAGE TANKS AT
412/450 HIGH STREET
WHEREAS, on December 19, 2012 the Successor Agency approved staff
recommendation to award the demolition of structures and underground storage tanks
at 412/450 High Street contract to NCM Demolition and Remediation, LP; and adopted
Resolution No. SA-2012-2 to appropriate $118,470.00 from RDA-SA Economic
Development Fund (9101); and
WHEREAS, on June 19, 2013, the City of Moorpark adopted the Operating and
Capital Improvement budget for Fiscal Year 2013/14; and
WHEREAS, a staff report has been presented to the Successor Agency Board
requesting additional appropriation to fund Change Order #1 for the demolition of
structures and underground storage tanks at 412/450 High Street; and
WHEREAS, a budget adjustment in the aggregate amount of $24,800.00 is
requested for this work; and
WHEREAS, Exhibit "A", attached hereto and made a part hereof, describes said
budget amendment and the resultant impact to the budget line item.
NOW, THEREFORE, THE BOARD OF DIRECTORS OF THE SUCCESSOR
AGENCY OF THE REDEVELOPMENT AGENCY OF THE CITY OF MOORPARK
DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. A budget amendment in the amount of $24,800.00 from the RDA-
SA Economic Development Fund (9101) as more particularly described in Exhibit "A",
attached hereto, is hereby approved.
SECTION 2. The City Clerk shall certify to the adoption of this resolution and
shall cause a certified resolution to be filed in the book of original resolutions.
381
Resolution No. 2013 — SA-
Page 2
PASSED AND ADOPTED this 17th day of July, 2013.
Janice S. Parvin, Chair
ATTEST:
Maureen Benson, Agency Secretary
Exhibit A — Budget Amendment
382
EXHIBIT A
BUDGET AMENDMENT FOR
RDA-SA Economic Development Fund for Change Order#1 for the Demolition of
Structures and Underground Storage Tanks
412-450 High Street
2013/14
FUND ALLOCATION FROM:
Fund Account Number Amount
RDA-SA Economic Development Fund 9101-5500 $ 24,800.00
Total $ 24,800.00
DISTRIBUTION OF APPROPRIATION TO EXPENSE ACCOUNTS:
Account Number Current Budget Revision Amended Budget
1000.2411.5084.9611 $ 24,393.00 $ - $ 24,393.00
9101.2411.5084.9611 $ - $ 24,800.00 $ 24,800.00
9103.2411.5084.9611 $ 200,000.00 $ - $ 200,000.00
Total $ 224,393.00 1 $ 24,800.00 $ 249,193.00
*current budget in 9101 fund does not reflect pending Capital Improvement Project rollovers from FY 12/13
Approved as to Form: (2,,AUK
383