MEMORANDUM
The Honorable City Council
John F. Knipe, City EngineeK
September 13, 1990
AWARD OF CONTRACT
LOS ANGELES AVENUE WIDENING (WEST)
BACKGROUND INFORMATION
STEVEN KUENY
City Manager
CHERYL J. KANE
City Attorney
PATRICK RICHARDS, A.I.C.P.
Director of
Community Development
R. DENNIS DELZEIT
City Engineer
JOHN V. GILLESPIE
Chief of Police
RICHARD T. HARE
City Treasurer
On September 4, 1989, sealed bids from six (6) contractors were received and
opened for the Los Angeles Avenue Widening (West) Project. This project will
provide for the widening of Los Angeles Avenue between Park Lane and Maureen Lane
to two travel lanes in each direction. This work will provide for the paveout
of Los Angeles Avenue along the northside with all necessary grading, drainage
and signing and striping. The project will also construct specific improvements
along certain properties per right -of -way acquisition agreements.
The bids received were as follows:
The Engineer's estimate for this pro,jec° was $586,051.00
799 Moorpark Avenue Moorpark, California 93021 (805) 529 -6864
CONTRACTOR
PRICE BID
1.
D.W. Burhoe Construction
$420,772.90
2.
S. P. Milling
$465,754.00
3.
Nye & Nelson
$478,813.00
4.
Berry General
$487,606.00
5.
C.A. Rasmussen
$499,948.00
6•
Granite Construction
$526,363.00
The Engineer's estimate for this pro,jec° was $586,051.00
799 Moorpark Avenue Moorpark, California 93021 (805) 529 -6864
Page -2-
The anticipated construction schedule is as follows:
ITEM
1. Award of Contract
2. Preconstruction Meeting
3. Notice to Proceed
4. Construction Period
RECOMMENDED ACTION
DATE
September 19, 1990
October 3, 1990
October 8, 1990
October 9, 1990 to
December 17, 1990
It is recommended that the contract be awarded to D. W. Burhoe Construction, Inc.
in the amount of $420,772.90 for the Los Angeles Avenue Widening (West) Project.
Copy: Steve Kueny, City Manager
Mark G. Wittgraf, Project Engineer
Ron Wilson, Construction Observer