HomeMy WebLinkAboutAGENDA REPORT 2016 0420 CCSA REG ITEM 10N ITEM 10.N.
CATV OF i.1OORPARK.CALIFORNIA
City Council Meting
of __toga
Actiorl:__ e
AOS *MOORPARK CITY COUNCILBY: 91-7. .b
AGENDA REPORT
TO: The Honorable City Council
FROM: Jeremy Laurentowski, Parks and R .�eation Directo
BY: Jessica Sandifer, Program Manag 4
DATE: April 12, 2016 (CC Meeting of April 20, 2016)
SUBJECT: Consider Rejection of Bids for the Recreational Trail Project at
Arroyo Vista Community Park (AVCP) (CIP Projects 7852)
BACKGROUND
On October 2, 2013 the City Council approved a conceptual plan for a proposed
recreational trail system at Arroyo Vista Community Park (AVCP) and on November 20,
2013, Penfield and Smith was hired to prepare the plans and specifications for the
Recreational Trail Improvements at AVRC.
On February 5, 2014, the City Council approved the project plans and specifications in
order for staff to apply for the Land and Water Conservation Fund Grant.
On January 20, 2016, the City Council approved the revised plans and authorized staff
to go to bid on the project.
The City Council will recall that the Recreational Trail Project incorporates a safe route
of travel for both pedestrians and bicyclists from the existing pedestrian bridge at the
east end of the park, to the Arroyo Vista Recreation Center. Approximately 17 new
parking spaces will be added to the park. The design was able to accommodate a
separated bicycle path and pedestrian walkway along the entire length of the portion of
the trail system that parallels the access road, from the east end of the park to the west,
separated by lodge pole fencing on both sides of the bicycle path. Internally, the
proposed trail system will incorporate an approximate one mile fitness loop around the
perimeter of AVCP, with exercise stations set along the route.
The design proposes the use of permeable concrete in the new parking areas,
permeable asphalt for the bicycle trail, concrete for the sidewalks and decomposed
granite paving for the surface material of the loop trail. The use of permeable pavement
386
Honorable City Council
April 20, 2016
Page 2
minimizes the storm water retention requirements of this project and increases the
amount of storm water that will infiltrate back into the groundwater supply. The design
proposes the creation of a detention basin at Parking Lot B to capture the portion of
runoff from the non-permeable surfaces, such as the proposed concrete sidewalks, as
well as existing surfaces, such as the asphalt parking lots and access road. In addition,
the design provides for ADA compliant walkways to the softball fields and other open
turf areas throughout the park. The project was also revised to include additional
parking adjacent to Parking Lot D; modifications to the Countrywood Drive corner to
create a safer entry and exit out of the park for vehicles, pedestrians and cyclists; the
addition of lighting along the trail, access road and Parking Lots C and D; as well as
landscaping for the various areas of improvements.
Due to the estimated project costs for the bid exceeding one million dollars
($1,000,000), a contractor pre-qualification process was started in February 2016.
Notices of the request for contractor pre-qualification were sent out to various trade
magazines, contractor organizations, and posted on the City's website. Staff was able to
pre-qualify seven of the eight contractors that submitted pre-qualification paperwork.
DISCUSSION
Once the pre-qualification process was completed, a request for bids for the project was
posted in the paper on March 4, 2016, and March 7, 2016. The original bid due date
was April 5, 2016 but was extended to April 11, 2016, due to some questions that arose
during the bidding process. Three bids were received from pre-qualified contractors by
the extended bid due date of April 11, 2016. The results are:
Berry General Engineering, Inc. $3,938,275.00
R.C. Becker and Sons, Inc. $3,729,238.00
Lee Construction Company $3,675,507.00
During the proposal evaluation, it was noted that the low bidder, Lee Construction
Company did not meet the self-performance requirement. Self-performance requires
that no less than 50% of the work be completed by the contractor's own forces. Lee
Construction Company's sub-contractor performance was 52.5% of the bid. The City
Attorney has opined that the City cannot waive the self-performance requirement
because it may have given the low bidder an advantage in the bidding process. Lee
Construction Company has indicated that there was a mistake on their sub-contractor
listing that led to the higher percentage listing. However, there is no way to substantiate
that the error was a true error.
In addition to the error with the bids, the project costs came in almost $400,000 higher
than staffs estimate. Given the two problems with this bid, staff is recommending
rejecting all the bids and re-authorizing the project to go out to bid.
387
Honorable City Council
April 20, 2016
Page 3
The original project completion date was August 2016. Staff estimates that re-bidding
the project will cause an additional six to eight week delay. This will still allow the project
to be completed by the end of calendar year 2016.
FISCAL IMPACT
There will be minimal fiscal impact related to re-bidding the project. Costs of
approximately $1,000.00 will be incurred as a result of re-advertising for the bid in the
newspaper.
STAFF RECOMMENDATION
Reject all bids and authorize staff to re-advertise for bids for the Recreational Trail
Project at Arroyo Vista Recreation Center.
388