HomeMy WebLinkAboutAGENDA REPORT 2012 0418 CC REG ITEM 10H ITEM 10.H.
tJiy council Mee in
MOORPARK CITY COUNCIL�'�'°""
AGENDA REPORT %. _vim
TO: Honorable City Council
FROM: Hugh R. Riley, Assistant City Man
Dave Klotzle, City Engineer/Public Works irector
BY: Ky Spangler, Special Projects Consultantr�
DATE: April 5, 2012 (CC Meeting of 4/18/12)
SUBJECT: Consider Additional Funding to Construct an Asphalt Overlay of
the Northbound Lanes of Spring Road from Flinn Avenue to
South of the Union Pacific Railroad Tracks and Amendment No. 5
to the Agreement with John S. Bascom, Inc., dba Precision
Plumbing-Mechanical for the Ruben Castro Human Services
Center
BACKGROUND & DISCUSSION
Construction of the Ruben Castro Human Services Center (RCHSC) began in February,
2011. During the course of construction it was determined that an offsite storm drain
connection within Spring Road was necessary to adequately drain the RCHSC site due
to drainage coming from the adjacent railroad right of way. At their meeting on
November 2, 2011, the City Council approved two amendments with John S. Bascom,
Inc., dba Precision Plumbing-Mechanical (Precision Plumbing). The first amendment, in
an amount not-to-exceed $35,000, covered utility potholing operations necessary for
engineering design purposes to confirm the feasibility of a storm drain connection
proposed to cross Spring Road.
The second amendment authorized by the City Council included: funds to construct a
storm drain connection based on the feasibility of a preliminary alignment proposal;
provide for an asphalt overlay of the northbound lanes of Spring Road from Flinn
Avenue to south of the Union Pacific Railroad tracks; and inclusion of a design
contingency to be applied to cost changes commonly experienced with a final design
process. The cost of the two amendments is summarized below:
148
Honorable City Council
April 18, 2012
Page 2
City Council approvals granted November 2, 2011
Amendment No. 2
Task#1 — Potholing existing utilities for Alternative #2 $35,000
Amendment No. 3
Task #2 — Preliminary construction cost of Storm Drain $143,946
Alternative #2
Task#3 —Asphalt Overlay, northbound Spring Road $50,000
20% Contingency for final design $39,000
Total Amendment No. 3 Amount $232,946
Following preparation of the formal engineering design and an updated construction
cost estimate, the final cost for the Spring Road storm drain construction was revised to
$190,357. A portion of the increase was absorbed through use of $20,000 of the
approved contingency. On April 4, 2012 the City Council approved an additional
appropriation of $26,411 and authorized approval of Amendment No. 4 for the Spring
Road offsite storm drain connection to Precision Plumbing in an amount not-to-exceed
$190,357. Construction of the storm drain connection began April 9, 2012.
The cost for the asphalt overlay was initially estimated at $50,000 based upon general
assumptions of roadway square footage, asphalt tonnage required, and the condition of
the existing road surface, with some design contingency accounted for. The revised
cost estimate prepared based on the final design plans, specifications and schedule of
work is $102,063 which is $52,063 over the original estimate. The final design and
estimate includes hot mix crack sealing and weed spraying and removal and
replacement of additional areas of asphalt which were not anticipated in the initial cost
for the overlay. Additionally, the relatively small tonnage of rubberized asphalt required
resulted in a higher unit price than anticipated and rising petroleum prices have also had
an impact on asphalt materials costs.
Based on the precise conditions in the field following construction of the storm drain
connection, some of the line items in the asphalt overlay schedule of work may be
deleted. The cost for the work is priced on a unit cost not-to-exceed basis, and only
those items of work necessary will be performed.
149
Honorable City Council
April 18, 2012
Page 3
Presently there is $69,000 remaining from within the Council approval granted in
November, 2011 for the project, leaving a shortfall of $33,063 to complete the asphalt
overlay of Spring Road from Flinn Avenue to south of the Union Pacific Railroad tracks.
In order to move forward with project, staff is requesting approval of this additional
amount. Completion of the overlay, in conjunction with the recently approved Spring
Road storm drain connection, will alleviate existing drainage problems and ponding of
water experienced in this location during rain events, and improve the deteriorated
condition of Spring Road.
FISCAL IMPACT
The Capital Improvement budget for the Ruben Castro Human Services Center (Fund
5020) is $11,038,064. To date $5,363,356 has been encumbered with an available
balance of $1,105,213. Therefore, no additional funds need to be budgeted for the
proposed work at this time. Sufficient funds exist in the budget to cover this work.
STAFF RECOMMENDATION (ROLL CALL VOTE)
Approve additional funding in the amount of $33,063 for an asphalt overlay of the
northbound lanes of Spring Road associated with the construction of the Ruben Castro
Human Services Center and authorize the City Manager to execute Amendment No. 5
in the amount of $102,063 to John S. Bascom, Inc., dba Precision Plumbing-
Mechanical, subject to final language approval of the City Manager and City Attorney.
Attachment 1: John S. Bascom, Inc. dba Precision Plumbing-Mechanical Proposal
dated March 27, 2012
150
ATTACHMENT 1 License lt 533836
#10363
o a �y y^y
r P 4 AYR ..rs t(L c' r'K ;7i� #L' `j- �` 4� 3 $
..� !- :bei" ...'tY<.r ,U' r-i .. l- 599-4 718 . `-!v TQ •.' 5,2 ^3
Page No. of Pages
PROPOSAL SUBMITTED TO 1 PHONE DATE
Balfour Beatty Construction - Dennis Ku kendall l 805 523-0015 '03-27-2012
TREET T1(}8 NAM
300 E. Esplanade Dr. #350 IAs halt Overlay Spring Rd.
— --- ._�._. _. ------ __ .._...____.. - -_P.... _ Y p b
CITY, SiA;E AND ZIP CODE JOB 10CATI0k
Oxnard, CA 93036 1612 Spring Rd. Moorpark,CA 93021 I
ARCHITECT DATE Of P ANA JO8 PHONE I
RJR Engineers N/A dkuy ken dall @balfourbeattyus (SOS) 523-0015
We hereby propose to furnish in accordance with specifications below,or on attached pages,all labor and materials necessary to complete the following: _
We propose to provide the labor and materials needed to install items 412-15 & 19 on the, "Proposed Schedule of
Work and Prices" for the, "Spring Road Storm Drain and Asphalt Overlay". Installation will be per plan sheets #
1-6 of plans drawn by RJR Engineering of plans distributed on March 05, 2012 labeled preliminary only, not for
construction.
PLEASE SEE ATTACYMENT"A"FOR ITE]'✓IS INCL UDED AND EXCL UDED
PPM FOREMAN.•
Provide foreman at all times on site while work is being performed $ 755.00 per day. Total cost included in price
below.
`?C=OST:hereby to furnish material and labor—complete in accordance with above specifications,for the sum of:
One Hundred Two Thousand Sixty Three Dollars & NO 1100 _dohar5 is 102,063.00
Payment to be made as follows:
All material is guaranteed to be as specified. All work to be completed in a sub-
stantial workmanlike manner according to specifications submitted, Per standard Authorized ./ ` �J, Daniel'Bascom
practices. Any alteration or deviation from above specifications involving extra Signature
costs will be executed only upon written orders,and will become an extra charge -` --`--' — -
over and above the estimate.All agreements contingent upon strikes,accidents or Rote:This proposal may be 30
delays beyond our control. Owner to carry fire, tornado and other necessary in- xiihdra�n by us it not accepted within da S.
surance,Our workers are fully covered by Workmen's Compensation Insurance, N
ACCE?;C>fti�E O PROPOSAL Tne above prices, specifications and condi-
tions are satisfactory and are hereby accepted. you are authorized to do the work
as specified.Payment will be made as outline above- Signature
Date of Acceptance. Signature
� -- —-— --- - -- � 151
Attachment"A"
PROPOSAL #10363
The following items are included in this proposal:
• Provide and install items # 12-15 & 19 of attached cost breakdown per plans and specifications.
• Performance and payment bond.
• Traffic control. Price included in items #12-15 & 19.
• Prices are based on one mobilization charge for each division of work.
• Asphalt Rubber has to be scheduled when Vulcan materials has the rubber plant set up for a larger project,
Precision Plumbing Mechanical will need at least 1 month notice to order asphalt.
• Pricing for asphalt overlay is good for work completed through September 30, 2012
• All work will be performed during the normal business hours of 8:30 AM to 4:30 PM Monday through Friday.
The following items are excluded from this proposal:
• Off hours work.
• Permits or fees, related to project including required NPDES permit.
• Removal of excess dirt. (Balfour Beatty has approved dumping and spreading of any excess dirt on Ruben
Castro Human Service Center site)
• Line items 42-11, 16-18.
• Furnish and install water for project at contractors own expense including metering.
152
Page 2 of 2
SPRING ROAD STORM DRAIN AND ASPHALT OVERLAY
PROPOSED SCHEDULE OF WORK AND PRICES
Item Unit
No. Description Qty Unit Price Total
1 Traffic Control 1 LS
2 Stormwater Pollution Control Plan 1 L S
f
Furnish and install 18" RCP per the plans and
3 specifications including excavation, backfill and 53 LF r
pavement repair.
Furnish and install 4 ft. x 1 ft. RCB per the plans
4 and specifications including excavation, backfill 10 LF
and pavement repair. {
Furnish and install 10" HDPE pipe per the plans t
5 and specifications including excavation, backfill 202 LF
and pavement repair.
Join 18" RCP to existing RCB per the plans and
6 specifications including excavation, backfill and 1 LS
pavement repair. r 1
RCP to RCB transition structure per the plans and )
7 specifications including excavation, backfill and 1 LS
pavement repair.
8 Furnish and install manhole, frame and cover. 1 LS F
r
9 Curb opening catch basin and local depression 1 LS
including excavation, backfill and pavement repair. f�
Lower existing 2"AT&T cable and place 2—4"
10 Sch. 80 conduits, each 20 ft. long with all ends 1 LSl ,
capped.
11 Relocate existing 6"ACP water main per VCWWD 1 LS
Standards including excavation and backfill
12 Crack sealing and weed spraying 1 LS �-
13 Pavement Milling 8,300 SF � � i CC,
14 Furnish and Install Asphalt Rubber Hot Mix 205 TON
(ARHM-GG-C) 't v `ice
15 Remove and replace 6° asphalt concrete 2,500 SF
Remove and replace existing median J
16 improvements including median curb, stamped 1 LS
concrete, landscaping and irrigation tt
17 Remove and replace PCC sidewalk 200 SF , M-
18 Remove and replace PCC spandrel 1 LS i(1;;;— �` E
19 Install striping per the plans and specifications 1
TOTAL