Loading...
HomeMy WebLinkAboutAGENDA REPORT 2012 0516 CC REG ITEM 10F ITEM Gity Council Meeting MOORPARK CITY COUNCIL AGENDA REPORT ACTION: TO: Honorable City Council WXFROM: Dave Klotzle, City Engineer/Public Works Director DATE: May 4, 2012 (CC Meeting of 05116/12) SUBJECT: Consider Plans and Specifications, Authorization to Advertise for Construction Bids, and Authorization of a Consultant Agreement for Construction Management and Inspection Services for State Route 23 Soundwall at Tierra Rejada Road (Project 8079) BACKGROUND On May 21, 2008, the City Council authorized staff to initiate the permitting process for soundwalls along the west side of State Route 23, north of Tierra Rejada Road. On March 18, 2009, the City Council awarded a contract to provide professional services with Parsons Transportation Group (Parsons) for preliminary engineering, environmental analysis, design, and right-of-way activities for the installation of the soundwalls. The contract was finalized and executed on May 28, 2009. On February 17, 2010, the City Council selected the soundwall design which includes decorative patterns of light brown, dark brown, and grey masonry blocks. The design also includes vines to be planted which will eventually cover most of the wall, providing a graffiti deterrent. On September 1, 2010, March 2, 2011 and July 20, 2011, City Council approved amendments to Parsons' design agreement for additional testing, reports, and design of a bioswale drainage system required by Caltrans. The soundwall project has been designed in accordance with Caltrans requirements and will require the issuance of an encroachment permit by Caltrans for final project approval prior to the City advertising for construction bids. The final requirement to be met before Caltrans will issue the encroachment permit is the preparation of a Quality Management Plan (QMP) for the inspection of certain construction materials. The QMP must be prepared by the consulting firm hired by the City to provide construction management and inspection services. S:\Public Works\Everyone\Reports\Staff Reports\2012\May\05-16-12(23 Soundwall Authority to Bid&CM Agreement).doc 237 Honorable City Council May 16, 2012 Page 2 DISCUSSION A. Scope of Work The subject project will construct two fourteen foot high masonry block soundwalls on the west side of State Route 23 (SR-23) at the southbound off-ramp to Tierra Rejada Road. The first wall will begin north of the off-ramp and extend south along the off- ramp for a total length of approximately 1,000 feet. A second wall will begin just past the off-ramp and extend south for approximately 700 feet, ending just before the bridge over Tierra Rejada Road. The project also includes drainage, lighting, landscaping and irrigation improvements. Other than intermittent closures of short duration, the off-ramp will remain open at all times during construction. Working hours will typically be 7:00 a.m. to 3:30 p.m. however extended hours of work may be necessary for certain portions of the work. The project plans and specifications have been completed and a copy has been placed on top of the file cabinet in the City Council Conference Room. B. Construction Management and Inspection Construction management, inspection and materials testing services will be provided by a consultant. The consultant will prepare the QMP which is required for Caltrans to issue the encroachment permit. Staff solicited proposals for these services from several qualified consultants and received the following proposals: Consultant Amount Filippin Engineering, Inc. $ 228,500 MINIS Engineers. Inc. $ 283,960 Parsons Corporation $ 450,000 Staff is recommending that the City Council authorize the City Manager to execute a consultant agreement with Filippin Engineering Inc. in an amount not to exceed $228,500.00. C. Environmental A CEQA Categorical Exemption was prepared for the project and has been approved by Caltrans. S:\Public Works\Everyone\Reports\Staff Reports\2012\May\05-16-12(23 Soundwall Authority to Bid&CM Agreement).doc 238 Honorable City Council May 16, 2012 Page 3 D. Project Schedule The anticipated project schedule is as follows: Execute Agreement for Construction Management May 21, 2012 Preparation and Caltrans Approval of QMP June 1, 2012 Obtain Caltrans Encroachment Permit June 8, 2012 Advertise for Bids June 11, 2012 Bid Opening July 10, 2012 Award of Construction Contract July 18, 2012 Notice to Proceed August 13, 2012 Project Completion April 13, 2013 FISCAL IMPACT The project is funded by the Carlsberg portion of the Citywide Traffic Mitigation Fund (Fund 2002) which had an estimated beginning balance of $2,276,003.63 available for the soundwall project. To date, $367,143.94 has been spent on the project. The table below provides an overview of current estimated project costs, the FY 2011/12 Budget, and total expenditures to date. Task Estimated FY 2011/12 Total Expenditures Cost Budget (to date) Design $ 380,000.00 $ 89,045.59 $ 331,326.94 Construction $ 1,750,000000 $ 1,600,000.00 $ - Construction 10% Contingenc $ 175,000.00 $ - $ - Construction Management, Inspection & Testing $ 228,500000 $ 100,000.00 $ - Staff Costs $ 100,000.00 $ - $ 35,817.00 Totall $ 2,633,500.00 1 $ 1,789,045.59 $ 367,143.94 As can be seen from the table above, if Estimated Costs are accurate, the Carlsberg portion of Fund 2002 will have a deficit of $357,496.37. The actual deficit may vary depending on the actual bids and final cost of construction. An additional $780,157.75 in Carlsberg revenue is expected from future development; such as UST Patriot Commerce Center ($265,577.95), Home Depot ($414,402.50), and Peach Hill Medical Center ($100,177.30); however, these funds are not expected for several years. To fully fund the project in the coming months the City will most likely need to use non-Carlsberg funds from Fund 2002, or fund the difference with another funding source. S:\Public Works\Everyone\Reports\Staff Reports\2012\May\05-16-12(23 Soundwall Authority to Bid&CM Agreement).doc 239 Honorable City Council May 16, 2012 Page 4 The FY 2011/12 budget for the project includes $1,789,045.59 of which $1,600,000.00 is for construction and $100,000 is for construction management and inspection. An additional $128,500.00 is required for the proposed construction management and inspection services which can be funded by a line item transfer from the construction budget. A future budget amendment to appropriate additional funds for construction will likely be needed at the time that City Council awards the construction contract. The amount of the future budget amendment will depend on the actual construction bid amount. STAFF RECOMMENDATION Approve the plans and specifications for the subject project and authorize staff to advertise for construction bids. Authorize the City Manager to award a consultant agreement for construction management and inspection services to Filippin Engineering, Inc. in an amount not to exceed $228,500.00, subject to final language approval by the City Manager and City Attorney. S:\Public Works\Everyone\Reports\Staff Reports\2012\May\05-16-12(23 Soundwall Authority to Bid&CM Agreement).doc 240