City Council Meeting
MOORPARK CITY COUNCIL -�
AGENDA REPORT
TO: Honorable City Council
FROM: David Klotzle, City Engineer/Public Works Director
Prepared by: Linda Williams, Administrative Assistanw
DATE: June 6, 2012 (CC Meeting of 06/20/12)
SUBJECT: Consider Seven-Year Capital Improvement Program (CIP) for the
Department of Public Works for FY 2011/12— FY 2017/18
BACKGROUND
The City's seven-year Capital Improvement Program (CIP) for the Department of Public
Works is typically updated annually, however, the CIP was not updated for FY 2010/11.
Staff has prepared the final draft of the updated CIP for FY 2011/12 — FY 2017/18 and
has distributed that document to the City Council under separate cover. This staff
report summarizes the recommended changes from the previous CIP.
DISCUSSION
A. General Description / Purpose
The CIP sets forth a list of planned municipal improvement projects for the City's
Department of Public Works. Proposed improvements for parks, buildings and
facilities are not included. Also, costs for general public works maintenance
programs (i.e. pavement marking, striping, regulatory signs, tree trimming, etc.) are
not included in this program as this type of Public Works Operations and
Maintenance expense is set forth in the annual Departmental Operating Budget.
The purpose and focus of the CIP is to provide the City Council with a tool for
planning and programming major public works capital improvement projects
related to streets and roads, over the next several years.
SAPublic Works\Everyone\Reports\Staff Reports\2012\June\06-20-2012(7 Year CIP).doc 148
Honorable City Council
June 20, 2012
Page 2
B. Changes from Last Report
1. The updated CIP includes a new list of Potential Objectives as identified in
Appendix `D'.
2. New Projects added are as follows: 122 (Alderbrook Street Asphalt Overlay
[8091]); 129 (Asphalt Overlay on Spring Road, Princeton Avenue, and
Poindexter Avenue [TBD]); and 207 (Civic Center Pedestrian Access and Bus
Stop Improvements [TBD]). Section 'O' of this report lists the completed
projects which have been added to Appendix `I' of the CIP.
C. Committee Review and Input
On January 23, 2012, the Transportation and Public Works Committee (TPWC),
(Councilmembers Millhouse and Van Dam), reviewed a draft copy of the subject
document. It was recommended that the final draft be forwarded to the Planning
Commission for review and comment.
D. Planning Commission Review
Section 65401 of the Government Code of the State of California requires the
Planning Commission to review the City's Capital Improvement Program each
year, for the purpose of reporting to the City Council on the conformity of said
document with the City's General Plan. On May 22, 2012, the final draft of the
subject document was presented to the Moorpark Planning Commission for such
action. The Planning Commission found the subject CIP to be in conformance
with the Circulation Element of the Moorpark General Plan.
E. Seven Year Program / Congestion Management Program
The subject CIP provides for the planning and programming of projects over a
seven year period. In this way the CIP is compatible with the Ventura County
Transportation Commission's (VCTC) Congestion Management Program (CMP).
The CMP requires a seven-year projection of projects which might enhance the
traffic capacity on any street on the CMP Roadway Network. A map of the CMP
network and a chart listing the projects on that network, are listed in Section 'D' of
the CIP.
F. Priorities and Planninq
The funding year shown for each project listed in the CIP is an indication of its
relative priority. Should the Council wish to recommend project priorities different
from those set forth in the draft document prepared by staff, it may do so.
SAPublic Works\Everyone\Reports\Staff Reports\2012\June\06-20-2012(7 Year CIP).doc 149
Honorable City Council .
June 20, 2012
Page 3
G. Fiscal Year 2011/12: Budget Consistency
The first year of the subject CIP is Fiscal Year 2011/12. The funding amounts and
sources cited in the CIP for FY 2011/12 are consistent with the current adopted FY
2011/12 Budget.
H. GASB-34
City staff monitors and maintains an Infrastructure Valuation Program consistent
with the requirements of the Government Accounting Standards Board Statement
No. 34 (GASB-34). The initial analysis which established the valuation of the
City's infrastructure, inventoried, quantified, categorized and valued (replacement
cost estimate) all of the City's capital assets. The valuation amount for the City's
infrastructure assets is over $225 million, with "street-related" improvements
valued at over$70 million.
I. Program Content
In addition to known projects planned to be constructed by either the City or
private developers, a number of projects have been included in the CIP in order to
fully address the needs described in certain infrastructure planning documents,
noted as follows:
1. Circulation Element All of the "future" arterial and collector streets identified
in the Circulation Element of the Moorpark General Plan, have been included
in the program.
2. Master Drainage Study. All of the "future" drains identified in the 1995 Master
drainage Study, have also been included in the program.
J. Program Format
The projects listed in the CIP are.organized into five categories listed as follows:
• Streets (including underground utility projects);
• Trails and Walkways;
• Traffic Signals;
• Medians and Parkways; and
• Storm Drains.
SAPublic Works\Everyone\Reports\Staff Reports\2012\June\06-20-2012(7 Year CIP).doc 150
Honorable City Council
June 20, 2012
Page 4
K. Program Cost Estimate
Section 'A' of the CIP provides a general introduction to the program and includes
a listing of the total program cost estimate (exceeding $49 million), summarized as
follows:
Estimated
Section Program Cost($)
100 Streets 31,785,215
200 Trails/Walkways 712,000
300 Traffic Signals 550,000
400 Medians & Parkways 1,309,599
500 Storm Drains 16,400,000
Total 50,756,814
L. Project Descriptions
Section '13' of the CIP sets forth a "Project Description" page for each project. The
information provided on each Project Description page includes estimated project
costs, recommended funding year and recommended funding sources.
It should be noted that no detailed preliminary engineering was proposed for the
projects listed. The cost estimates are, therefore, very preliminary and will be
subject to change as the full scope and requirements of each project are
developed.
M. Program Expenditure Summary
Section 'C' of the CIP sets forth a table listing all projects in the CIP along with
total estimated project costs for each fiscal year of the program.
N. Past Proiects
In order to document past projects, Appendix 'I' of the CIP lists all known major
Capital Improvement projects (for the Public Works Department) constructed since
the City's incorporation in 1983. The following projects were added to Appendix 'I':
2010
Streets & Trails
• Mountain Tail Street/Spring Road Pavement Rehabilitation
• Julliard Avenue/Reedley Street Overlay
Parkways & Medians
• City Entry Signs
• Mountain Tail Street/Spring Road Pavement Rehabilitation
S'.\Public Works\Everyone\Reports\Staff Reports\2012\June\06-20-2012(7 Year CIP).doc 151
Honorable City Council
June 20, 2012
Page 5
2011
Streets & Trails
• Metrolink Security Wall & Camera System
Traffic Signal
• Collins Drive & University Drive
• Los Angeles Avenue & Tierra Rejada Road
O. Funding Sources: Definitions
Attached as Appendix 'll' is a listing of the major funding sources for the program,
along with a description for each.
P Conclusion
The subject CIP is designed to serve many purposes.
• It is a budget planning document.
• It is a funding source reference.
• It is a plan for future improvements.
• It is a list of infrastructure needs.
• It sets forth the scope and estimated cost of specific projects.
• It is a tool for prioritizing and scheduling capital improvement projects.
• It provides a list of projects already completed.
• It provides a list of potential projects.
• It documents compliance with requirements of the Congestion Management
Program.
• Additionally, it is a "hands-on" working reference document to identify, define
and describe future planned capital improvement projects.
FISCAL IMPACT
None.
STAFF RECOMMENDATION
Approve the updated CIP for FY 2011/12 — FY 2017/18.
SAPublic Works\Everyone\Reports\Staff Reports\2012\June\06-20-2012(7 Year CIP).doc 152