HomeMy WebLinkAboutAGENDA REPORT 2012 0718 CC REG ITEM 10U ITEM 10.U.
Council WieetinQ
MOORPARK CITY COUNCIL
AGENDA REPORT
TO: Honorable City Council
FROM: David A. Bobardt Communi ty Development Director
Dave Klotzle, City Engineer/Public Works
Dire or
Prepared by: Joseph Fiss, Principal Planner
DATE: July 11, 2012 (CC Meeting of 7/18/2012)
SUBJECT: Consider Amendment No. 4 to Agreement for Professional Services
with Parsons Transportation Group for Preliminary Engineering,
Environmental Analysis, Design, and Right-of-Way Activities for the
Installation of Soundwalls on SR-23
BACKGROUND/DISCUSSION
On March 18, 2009, the City Council awarded an agreement to provide professional
services with Parsons Transportation Group for preliminary engineering, environmental
analysis, design, and right-of-way activities for the installation of the soundwalls along
the west side of State Route 23, north of Tierra Rejada Road. The $257,932.94
agreement was finalized and executed on May 28, 2009. The term of the agreement
(one year) and the scope of work were based on early discussions with Caltrans on
what was needed for encroachment permits for the construction of the soundwalls.
On September 1, 2010, the City Council approved a budget amendment for a new total
amount not to exceed $294,416.56 to address aerially deposited lead (ADL) testing
required by Caltrans to address the handling and disposition of dirt that will be hauled
off the site when the footings for the soundwall are excavated, and for design of a
soundwall overlap that was required by Caltrans for the soundwalls to be 224 feet
longer than originally presented in the City's request for proposals and the associated
noise study.
On March 20, 2011, the City Council approved another budget amendment for a new
total amount not to exceed $320,402.08 to address a procedural difference where
450
Honorable City Council
July 18, 2012
Page 2
Parsons assumed that a Permit Evaluation Engineering Report (PEER)-Noise Barrier
Scope Summary Report (NBSSR) would be prepared for the project, and submitted with
the full Plans, Specifications, and Estimates (PS&E) and environmental document to the
Caltrans Encroachment Permit office as a single submittal. The additional work
required by Caltrans for a drainage analysis resulting in the number of plan sheets
increasing from 26 to 36 sheets.
On July 20, 2011, the City Council approved another budget amendment for a new total
amount not to exceed $336.056.40 to revise the PS&E Storm Water Data Report;
Update Plans for a Bioswale and New Storm Drain Designs; and Update Cost Estimate
and Caltrans Specifications. Just prior to permit approval, Caltrans added an
additional requirement not anticipated in the original contract. Caltrans required
additional stormwater Best Management Practices (BMPs) including a bioswale/storm
drain to address an existing deficiency in the area not related to the soundwall project.
This consists of design and construction of a bioswale on the west side of the
southbound off-ramp at the bottom of the 2:1 slope. The device would require
retrofitting the existing storm drain and would treat 3.6 acres of the northbound and
southbound SR-23 travelled way. This requirement added $15,654.32 to the
engineering design and permitting costs, and is expected to add an additional $80,000
to the construction costs. Mayor Parvin and staff appealed this new requirement to the
Caltrans District 7 Director, however, on June 24, 2011; the District Director denied this
appeal.
During the finalization of this work, Caltrans requested that Parsons update certain
reports, as a result of changes due to previous additional work that Caltrans required.
These were a "Biology Study Revalidation Report" and additional "Source Inspection
Quality Management Plans" research and coordination. There were sufficient funds in
the agreement budget to fund these additional requirements, however, that took away
funds from Design Support during Bidding and Construction, which had been approved
under the original agreement. Parsons has continued to work on Design Support within
the original approved budget; however there currently remains only $1,817.83.
Staff is now requesting an amendment of the agreement to cover the cost of several
tasks during the bidding and construction phase of the project. Attached is Parson's
Proposal for Additional Services for an additional agreement amount of $40,902.32, for
a new total amount of$376,958.72.
FISCAL IMPACT
The FY 2012-2013 budget includes $1,764,046 for this project, of which $64,046 is
available for Design and Engineering, $1,600,000 is for construction and $100,000.00 is
for construction management. The increased compensation to Parson will be absorbed
by the available appropriation in Design and Engineering. No budget amendment is
requested at this time. On May 16, 2012, the City Council approved authorization of a
consultant agreement for construction management with Filippin Engineering, Inc. in the
S:\Community Development\DEV PMTS\S P\SP 92-1 Carlsberg Specific Plan\Soundwall\Parsons SR 23 Soundwall Contract\Parsons Contract
Amendment 120701\cc agenda report 120718.docx
451
Honorable City Council
July 18, 2012
Page 3
amount of $228,500. This was funded through a line item transfer from the construction
budget for the project. The Design Support costs needed at this time can also be
funded from the existing City budget with a line item transfer from one of these funds. A
budget amendment would, however, likely be needed in the future for the construction
contract at the time it is awarded.
The funding source for this project has been the Carlsberg portion of the Citywide
Traffic Mitigation Fund, which currently has a balance of $1,906,920.47 of which
$1,766,733.84 is encumbered and appropriated, leaving a balance of $140,186.63.
Staff estimates that there will be additional revenue to this fund of approximately
$780,000.00 as a result of the build-out of the Patriot Commerce Center, the Home
Depot site, and the former Peach Hill Medical site. This additional money would not be
collected until building permits are issued for these properties. There would likely be a
deficit in the current funding source if the soundwall is built before the buildings
identified above, but the final amount will be unknown until the soundwall construction
bids are received. If the deficit remains, the Council would either need to defer the
project, or authorize a loan from other available funds.
The following table shows the current and previously estimated total project costs for
the soundwall. This differs from the current budgeted amount in that it includes the
proposed increases, and the most recent Engineer's construction cost estimate.
Previous New Estimate
Estimate
Engineering/Design (Current Agreement, including $310,817.24
Amendment No. 1 and No. 2, Completed/Paid)
Engineering/Design (Current Agreement, including $ 9,584.84
Amendment No. 1 and No. 2, Remaining/Unpaid)
Subtotal (Current Agreement) $320,402.08 $320,402.08
Proposed Amendment No. 3 $15,654.32
Subtotal (Including Amendment No. 3) $336,056.40 $336,056.40
Proposed Amendment No. 4 $40,902.32 $40,902.32
Subtotal (Including Amendment No.4) $376,958.72
Construction Costs(Engineer's construction cost $1,633,000.00 $1,633,000.00
estimate based on future costs and contingencies)
Construction Management/Resident Engineer $100,000.00 $228.500
Inspections
Additional City Staff Time $40,000.00 $40,000.00
Stormwater Best Management Practices (BMPs) $80,000.00 $80,000.00 $80,000.00
Total Estimated Project Cost $ 2,189,056.40 $ 2,358,458.72
S:\Community Development\DEV PMTS\S P\SP 92-1 Carlsberg Specific Plan\Soundwall\Parsons SR 23 Soundwall Contract\Parsons Contract
Amendment 120701\cc agenda report 120718.docx
452
Honorable City Council
July 18, 2012
Page 4
STAFF RECOMMENDATION
1. Authorize the City Manager to amend the agreement with Parsons
Transportation Group for preliminary engineering, environmental analysis,
design, and right-of-way activities for the soundwalls on SR-23, extending the
agreement to May 30, 2013, and increasing the total amount by $40,902.32 so
as not to exceed $376,958.72, subject to final language approval by the City
Manager and City Attorney.
ATTACHMENTS:
1. Proposal for Additional Services
2. Draft Amendment to Agreement for Professional Services
S:\Community Development\DEV PMTS\S P\SP 92-1 Carlsberg Specific Plan\Soundwall\Parsons SR 23 Soundwall Contract\Parsons Contract
Amendment 120701\cc agenda report 120718.docx
453
PARSONS
2201 Dupont Drive, Suite 200• Irvine, California 92612•(949)333-4500•Fax: (949)263-1225•www.parsons.com
April 30, 2012
Mr.Joseph Fiss
Principal Planner
City of Moorpark
799 Moorpark Avenue
Moorpark, CA 93021
Subject: SR-23 Soundwall Project - Amendment Request#4: to provide Design Support
during Bidding & Construction
Dear Mr. Fiss,
Parsons has now completed our contract scope of work in relation to obtaining Caltrans approval of the
SR-23 Soundwall Project PS&E. Parsons was requested by Caltrans to perform a couple final tasks
during the design stage that used up any budget that was remaining in the contract to perform Design
Support during Bidding and Construction. These final tasks requested by Caltrans that Parsons
performed included:
• Biology Study Revalidation Report
• Source Inspection Quality Management Plans research and coordination
The City instructed Parsons to proceed with the above work at that time, and that budget for
construction support could be revisited at a later date. Please see the attached backup email.
Parsons proposes to perform the following tasks during the bidding and construction phase of the
project:
• Answer Requests for Information(RFIs) from bidders during the Bidding Phase
• Attend the Pre-Construction Meeting
• Review Design-Related Contractor Submittals, Shop Drawings,and RFIs
• Attend 4 meetings at the City or the Site during Construction
• Prepare As-Built Plans after Construction is complete
Please see the attached fee proposal. Parsons is requesting and$40,902.32 for this effort. Our effort
has been and will continue to be as efficient as possible. Feel free to call me at(949) 333-4527 if you
have any questions. Thank you very much.
Sincerely,
Eric Spangler,P. .,T.E.
Project Manager
454
CC ATTACHMENT 1
CITY OF MOORPARK -SR 23 Soundwalls at Tierra Rejada Road -Amendment 4: Design Support During Bidding & Construction
PARSONS Fee Proposal - May 2012
SUBdONSULTANT
Project Manager Highway Engineer Lynn Capouya,Inc. TASK TOTAL
Eric Spangler Dion Osmond HOURS BY PARSONS TOTAL
ACTIVITY LABOR
$158.52 $107.72 Landscape Architecture
DESIGN SUPPORT DURING BIDDING 8 CONSTRUCTION
1 Answer Bidder RFIs 16 $2,536.32 $2,536.32
Other Meetings 30 30 $4,755.60 $4,755.60
2 Attend Pre-Construction Meeting$4
------------
3 Review Design-Related Submittals,Shop Drawings,and RFls 120 40 160 $23,331.20 $1,300.00 $24,631.20
4 Prepare As-Built Plans 20 40 60 $7,479.20 $1,500.00 $8,979.20
HOURS: 186 80 1=266
LABOR: $29,484.72 $8,617.60 $38,102.32 $2,800.00 $40,902.32
rA
CJl
L71