HomeMy WebLinkAboutAGENDA REPORT 2012 1107 CCSA REG ITEM 10D ITEM 10.D.
City Council Meeting
01 R - -
MOORPARK CITY COUNCILC ION: --�
AGENDA REPORT - -cam
TO: Honorable City Council
FROM: Hugh R. Riley, Assistant City Manager
BY: Ky Spangler, Special Projects Consultant
DATE: October 23, 2012 (CC Meeting of 11/07/12)
SUBJECT: Consider Additional Funding for Cabinetry and Casework
Revisions and Amendment No. 3 to the Agreement with K&Z
Cabinet Company for the Ruben Castro Human Services Center
BACKGROUND & DISCUSSION
The Ruben Castro Human Services Center (RCHSC) is being constructed as a multiple-
prime contract project with construction management provided by Barnhart Balfour-
Beatty Construction (Balfour-Beatty). Bids were solicited from trades in September,
2010, opened on October 21, 2010 and bids were awarded by the Moorpark City
Council on January 19, 2011. K&Z Cabinet Company, Inc., (K&Z) was selected as the
lowest responsive and responsible bidder for the Finish Carpentry and Casework bid
package and a construction agreement was executed on May 2, 2011.
During the course of construction of the project, the County of Ventura Health Care
Agency requested a variety of casework and cabinetry additions and changes, and the
City of Moorpark requested modifications to suites within Building B. These requests
resulted in Amendments that exceeded the amount of the original contract contingency
and which were previously brought forward for approval by the City Council.
As part of the final review and punch list process conducted by the architect of record
and County of Ventura to reach project completion, minor changes were requested.
The architect made adjustments to cabinetry in the break rooms and clarified the
Building B lobby desk base kick-plate finish, and the County of Ventura requested
changes to their break room locker keying schedule. The total cost for the changes
requested by the architect and County of Ventura is $1,656.00.
102
Honorable City Council
November 7, 2012
Page 2
A recap of the K&Z agreement and amendments to date is shown below:
Original Agreement $ 153,700.00
Amendment No. 1 $ 13,351.00
Amendment No. 2 $ 36,935.00
Current Agreement Amount $ 211,636.00
Amendment No. 3
Relocation of upper cabinets in breakrooms (Building B) $ 456.00
Lobby desk base finish (Building B) $ 450.00
Correction of breakroom locker keying (Building A) $ 750.00
Total Amendment No. 3 Amount $ 1,656.00
Revised Agreement Amount $ 213,292.00
Currently there is no contingency available under K&Z's contract. The cost for the
electrical additions and revisions is $1,656.00 which exceeds the available contingency.
Therefore staff is seeking the approval of this additional amount.
FISCAL IMPACT
The Capital Improvement budget for the Ruben Castro Human Services Center (Fund
5020) is $13,770,119. To date $12,017,801 has been expended with $1,488,816 left in
encumbrances and $263,501 available project balance. Therefore, no additional funds
need to be budgeted for the work at this time. Sufficient funds exist in the budget to
cover this work.
STAFF RECOMMENDATION (ROLL CALL VOTE)
Approve additional funding in the amount of $1,656.00 for cabinet and casework
revisions for the Ventura County Health Care Agency medical clinic and the City of
Moorpark for the Ruben Castro Human Services Center and authorize the City Manager
to execute Amendment No. 3 in the amount of $1,656.00 to K&Z Cabinet Company,
Inc., subject to final language approval of the City Manager and City Attorney.
Attachment 1: Amendment No. 3 to K&Z Cabinet Company, Inc.
103
ATTACHMENT 1
THIRD AMENDMENT TO AGREEMENT 2011-121
FOR BID PACKAGE #8 — FINISH CARPENTRY AND CASEWORK
AT THE RUBEN CASTRO HUMAN SERVICES CENTER
THIS THIRD AMENDMENT TO THE AGREEMENT FOR BID PACKAGE #8 — FINISH
CARPENTRY AND CASEWORK ("Third Amendment"), is made and entered into this
day of , 2012, ("the Effective Date") between the City of
Moorpark, a municipal corporation, hereinafter referred to as "CITY", and K & Z Cabinet
Company, Inc., a California corporation, hereinafter referred to as "CONTRACTOR".
WITNESSETH:
WHEREAS, on May 2, 2011, the CITY and the CONTRACTOR entered into an
Agreement for finish carpentry and casework for the Ruben Castro Human Services
Center; and
WHEREAS, on May 22, 2012, the CITY and the CONTRACTOR executed a First
Amendment in an amount not-to-exceed thirteen thousand three hundred fifty-one
dollars ($13,351.00) for additional finish carpentry and casework for the Ruben Castro
Human Services Center increasing the total not-to-exceed amount to one hundred sixty-
seven thousand fifty-one dollars (167,051.00); and
WHEREAS, on June 28, 2012, the CITY and the CONTRACTOR executed a
Second Amendment in an amount not-to-exceed forty-four thousand five hundred
eighty-five dollars ($44,585.00) for additional finish carpentry and casework for the
Ruben Castro Human Services Center increasing the total not-to-exceed amount to two
hundred eleven thousand six hundred thirty-six dollars ($211,636.00); and
WHEREAS, the CITY wishes to further amend the Agreement to include
revisions to cabinetry locations in break rooms in Building B per the direction of the
architect of record at a cost not-to-exceed four hundred fifty-six dollars ($456.00) as
described in CONTRACTOR'S Change Order Request 08 dated August 7, 2012 and
incorporated herein as Exhibit K to the Agreement by this Third Amendment; and
WHEREAS, the CITY wishes to amend the Agreement to include installation of a
kick-plate finish for the lobby counter in Building B at a cost not-to-exceed four hundred
fifty dollars ($450.00) as described in CONTRACTOR'S Change Order Request 09
dated August 27, 2012 and incorporated herein as Exhibit L to the Agreement by this
Third Amendment; and
Construction Agreement Page 1 of 3
Third Amendment Between City of Moorpark and K&Z Cabinet Company, Inc. 104
WHEREAS, the CITY wishes to amend the Agreement to include the
modification to the break room locker keying schedule in the Building A at a cost not-to-
exceed seven hundred fifty dollars ($750.00) as described in CONTRACTOR'S Change
Order Request 10 dated October 22, 2012 and incorporated herein as Exhibit M to the
Agreement by this Third Amendment; and
WHEREAS, this total dollar amount of $1,656.00 exceeds the ten percent (10%)
contingency amount approved with the original Agreement; and
WHEREAS, on November 7, 2012 the City Council of the City of Moorpark
approved additional funding for these cabinetry and casework additions, revisions and
changes.
NOW, THEREFORE, in consideration of the mutual covenants, benefits, and
premises herein stated, the parties hereto AMEND the aforesaid Agreement follows:
I. Section 2 of the Agreement is amended to include:
Contractor's Scope of Services is amended to include the materials and labor
required to:
• revise cabinetry above refrigerator locations in break rooms in Building B
according to the direction of the architect of record and per Change Order
Request 08 (8.08); and
• provide and install lobby counter base kick-plate finish in Building'B according to
the response of the architect of record to RFI #328 and per Change Order
Request 09 (8.09); and
• revise the keying schedule for lockers located in break room 544 of Building A
according to the response of the architect of record to RFI #270 and per
specification section 10 51 23, and Change Order Request 10 (8.10).
The Scope of Services for the additional cabinetry and casework services is
described in the Change Order Requests dated August 7, August 27, October 22, 2012
respectively, attached hereto and incorporated herein as Exhibits K, L, and M to the
Agreement by this Second Amendment.
II. Section 7 of the Agreement is amended to include:
CITY hereby increases the not-to-exceed amount of $211,636.00 under this
Agreement by $1,656.00 to $213,292.00.
[CONTINUED ON NEXT PAGE]
Construction Agreement Page 2 of 3
Third Amendment Between City of Moorpark and K&Z Cabinet Company, Inc. 105
III. Remaining Provisions
All other terms and conditions of the original Agreement shall remain in full force
and effect.
CITY OF MOORPARK K & Z CABINET COMPANY, INC.
By: By:
Steven Kueny Dennis Chan
City Manager President
ATTEST:
Maureen Benson, City Clerk
Exhibit K— Change Order Request 01-R1 dated August 7, 2012 (8.08)
Exhibit L — Change Order Request 02-revised dated August 27, 2012 (8.09)
Exhibit M — Change Order Request 03 dated October 22, 2012 (8.10)
Construction Agreement Page 3 of 3
Third Amendment Between City of Moorpark and K&Z Cabinet Company, Inc. 106
35q
• EXHIBIT K AE.
(8.08)
K & Z Cabinet Co., Inc.
1450 South Grove Avenue, Ontario California 91761 • (909) 947-3567 • Fax (909) 947-3264 • State Lie. 319196
CHANGE ORDER REQUEST
Date: August 7,2012 Job No: 5549
Contractor: Barnhart Balfour Beatty Attn: John Squillace Jr.
7_99 Moorpark Avenue Change Order
Request No.: 08
Moorpark,CA 93021
Project: Ruben Castro Human Resource Center
We Are Proposing The Following Changes:
Bldg B
Re-locate upper cabinets at building B 6 Man hours $76,00 .... $456.00
TOTAL. . 456.00
�j We are proceeding with this work based on your Company's verbal instructions on
A written billable change order is required before we deliver this work per our agreement.
❑ We have proceeded with this work per your Company's instructions. Please issue us a written change
order as soon as possible.
❑ We are NOT proceeding with this extra until we have received a written change order from your company.
The above quoted price is guaranteed for 30 days from the date of this quote.
K&Z CABINET CO.,INC. Accepted
By:
General Contractor/Construction Manager
\\ Date:
Hugo Cervera
Project Manager By:
Owners Authorized Representative
Date:
1
107
EXHIBIT L (8.09)
K & Z Cabinet Co., Inc. cl
1450 South Grove Avenue,Ontario California 91761 •(909)947-3567• Fax(909)947-3264 • State Lie.3.19196
CHANGE ORDER REQUEST
Date: August 27,2012 Job No: 5549
Contractor Barnhart Balfour Beatty Attn: John Souillace Jr.
799 Moorpark Avenue Change Order
Request No.: 09
Moorpark,CA 93021
Project: Ruben Castro Human Resource Center
We Are Proposing The Following Changes:
Bldg B
Installing Plastic laminated base to the reception counter at Building B
Labor 4 Man hours$76,00 each $304.00
Material Y<" Plastic laminated material $146,00
TOTAL.. 450.00
❑ We are proceeding with this work based on your Company's verbal instructions on
A written billable change order is required before we deliver this work per our agreement.
❑ We have proceeded with this work per your Company's Instructions. Please issue us a written change
order as soon as possible.
® We are NOT proceeding with this extra until we have received a written change order from your company.
The above quoted price is guaranteed for 30 days from the date of this quote.
K&Z CABINET CO.,INC. Accepted
By:
General Contractor/Construction Manager
Date:
Hugo Cervera
Project Manager By:
Owners Authorized Representative
1
108
Squillace, John Jr
From: Emily Kay[Emily.Kay @hmcarchitects.com]
Sent: Friday,August 24, 2012 10:05 AM
To: Squillace, John Jr
Cc: Hammond, Jeff
Subject: RE: RCHSC:Tile Finish At Lobby Casework
Laminate the toe kick with the same facing as the rest of the casework and then install the standard height the base to
that.
Emily Kay CCCA, LEEDS'AP/Associate
HMC Architects/633 W.Fifth Street,Third Floor/Los Angeles.CA 900711 T 213 542 8300
From: Squillace,John Jr[mailto:jrsquillace @ balfourbeamus.com]
Sent:Thursday, August 23, 2012 10:28 AM
To: Emily Kay
Cc: Hammond,Jeff
Subject: RCHSC:Tile Finish At Lobby Casework
Emily,
Would like you opinion on the transition and closure of the casework to the the at the main lobby reception desk in Bldg
B. I have included a few photo's showing the condition.
The tile base their using isn't tall enough to cover all of the cabinet.We could possible cut down the full size tile to fit
however when we wrap the small corner and return back into the wall&base as seen in the first photo,it will be taller
than the base tile.
Thank You,
John Squillace Jr I Project Engineer,LEED Green Assoc.,CMIT,CISEC,QSP
office:805.523.00151 mobile:805-607-3637 1 email:irsguillace @balfourbeattvus.com
Balfour Beatty Construction 1 612 Spring Rd.,Moorpark Ca 930211 www.balfourbeattyus.com
Connect with us:Facebook I Twitter I YouTube I Linkedln
Proud to be one of FORTUNE magazine's 100 Best Companies to Work For—three years in a row!
1
109
EXHIBIT M (8.10)
K & Z Cabinet Co., Inc.
1450 South Grove Avenue,Ontario California 91761 • (909) 947-3567 •Fax(909)947-3264 •State Lic.319196
CHANGE ORDER REQUEST
Date: October 22,2012 Job No: 5549
Contractor: Barnhart Balfour Beatty Attn: John Sauillace Jr.
799 Moorpark Avenue Change Order
Request No.: 10
Moorpark,CA 93021
Project: Ruben Castro Human Resource Center
We Are Proposing The Following Changes:
Bldg"A"Room 544
Replace lockers cabinet's locks @ Bldg A $750.00
TOTAL. . 750.00
❑ We are proceeding with this work based on your Company's verbal instructions on
A written billable change order is required before we deliver this work per our agreement.
❑ We have proceeded with this work per your Company's instructions. Please issue us a written change
order as soon as possible.
We are NOT proceeding with this extra until we have received a written change order from your company.
The above quoted price is guaranteed for 30 days from the date of this quote.
K&Z CABINET CO.,INC. Accepted
By:
General Contractor/Construction Manager
Date:
Hugo Cervera
Project Manager By:
Owner's Authorized Representative
1
110
Squillace, John Jr
From: Squillace, John Jr
Sent: Wednesday, September 12, 2012 10:19 AM
To: 'hcervera @kzcabt.com'
Cc: Hammond, Jeff; Kuykendall, Dennis
Subject: RE: K&Z Cabinets-Break room 544 cabinets Key's
Attachments: RFI 270-Answer.pdf
Hugo,
Please see the attached copy of RFI 270 which included details and specifications for the lockers in break room 544.
Within specification 10 5123, it states to"Provide one key-controlled combination cam lock for each locker. Master key
all key locks. Provide six(6) master keys."
All lockers were to be keyed separately with(6)master keys to be provided.
Please move forward with providing individual locks for each of the lockers in break room 544.Confirm with Balfour
Beatty when these locks will be provided so we may schedule an appropriate time to swap out the cores.
Thank You,
John Squillace Jr I Project Engineer,LEED Green Assoc.,CMIT,CISEC,QSP
office:805.523.00151 mobile:805-607-3637 1 email:jrsciuillace!ebalfourbeattvus.com
Balfour Beatty Construction 1 612 Spring Rd.,Moorpark Ca 930211 www.balfourbeattyus.com
Connect with us:Facebook I Twitter I YouTube I Linkedln
Proud to be one of FORTUNE magazine's 100 Best Companies to Work For—three years in a row!
From: hggrveoftzcabt.com [maIb:hcerveraQkzcabt.com]
Sent:Tuesday, September 1f, 2012 6:04 PM
To: Squillace,John Jr
Subject: Re: K&Z Cabinets - Break room 544 cabinets Key's
Jhon. Those was part of bldg A one key for all. If you want us change it will be change order.Thank you
Sent from my Verizon Wireless B1ackBerry
From: "Squillace,John Jr" <jrsquillace @balfourbeattyus.com>
Date: Tue, 11 Sep 201219:13:28 -0500
To: Hugo Cervera<hcervera@ zcabt.com>
Cc: Hammond,Jeff<JeffHammond@balfourbegMMs.com>
Subject: K&Z Cabinets-Break room 544 cabinets Key's
Hugo,
I'm currently not onsite however was informed that the locks for the lockers break room 544 were not replaced. Each of
those were to be keyed separately.
When will K&Z Cabinets have locks for these?
Thank You,
John Squillace Jr I Project Engineer,LEED Green Assoc.,CMIT,CISEC,QSP
office:805.523.00151 mobile:805-607-3637 1 email:irsc�uillace�balfourbeattvus.com
Balfour Beatty Construction 1 612 Spring Rd.,Moorpark Ca 930211 www.balfourbeattyus.com
1
111
Request For Information
Project [10935] - Ruben Castro Human Date 1/9/2012
Services Center
GonStw-tdbn Project 10935000
Number
Balfour Beatty Construction
799 Moorpark Avenue
Moorpark, CA 93021 RFI No. 0270
Fax: 866-523-5686
Primary Responder Emily Kay Date 1/9/2012
HMC Architects Status Submitted
633 W. 5th Street
third floor Resolved Date
Los Angeles, CA 90071-2005 Reason for Request Insufficient
USA Action Requested Direction
CC Probable Cost Effect
From John Squillace, Jr. Probable Time Effect
Balfour Beatty Construction
Priority High
Response Due 1/16/2012
Subject Lockers in break room 544
Drawing No. A2.1, A8.5.1 Detail No./Paragraph
CSI Code
Information Requested
On sheet A2.1, break room 544 appears to show lockers on the north wall. On elevation sheet A8.5.1,
detail 7 does not show these on the north wall.
Per a conversation with the County of Ventura, they would like laminate lockers installed in the break
room.
Please confirm with the County of Ventura the height, length, width, and locking requirements for the
laminate lockers and provide updated plan sheets.
Recommendation
Posted to Drawings
Subcontractor Name Balfour Beatty
Subcontractor's RFI#
Response Information
Responder Date Response
JEmlly Ka
Disclaimer
112
Refer to SK-270.1 and SK-A270.2 and specification section 10 51 23 for height, length,
width and locking requirements for the plastic laminate lockers.
Gricelda Perez, HMC Architects
101/19/2011
Emily Kay (HMC Architects)
Authorized Signature Printed Name Date
Distribution
Recipient Company Method Date
Dennis Balfour Beatty Construction - Email: dkuykendall @barnhart- 1/9/2012
Kuykendall Southwest balfourbeatty.com
Emily Kay HMC Architects Email: emily.kay@hmcarchitects.com 1/9/2012
Hajnal Avery Ventura County Health Email: Hajnal.Avery@ventura.org 1/9/2012
Services
Jeff Hammond Balfour Beatty Construction - Email: jhammond @barnhart- 1/9/2012
Southwest balfourbeatty.com
John Squillace, Balfour Beatty Construction - Email: jrsquillace @balfourbeattyus.com 1/9/2012
Jr. Southwest
Michael Vachon Balfour Beatty Construction - Email: mvachon @barnhart- 1/9/2012
Southwest lbalfourbeatty.com
Zakiel Gallegos IHMC Architects Email: Zakiel.Gallegos @hmcarchitects.com 1/9/2012
113
1
24
8'-0" PL1
65
'-0"
EA.
0
iU')
DA SIGMGE
A. NORTH
BREAK ROOM #544 7
1/4" = 1'-0"
.G/�Ni��c INTERIOR ELEVATION ASANOTED
bQy � CITY OF MOORPARK Project No
C3
HMC RUBEN CASTRO HUMAN 2307002
NO. C-28828 * k I re interiors wennin SERVICE CENTER Date
Arch tectu n 9
HMC ARCHITECTS 01/19/2012
612 SPRING ROAD
833 W.5TH STREET,THIRD FLOOR Drawing No
LOS
OF C A4 ip o LES,CA1ON �0 MOORPARK, CA 93021 T 25428300
Fax: 213.542.8301 SK—A270.1
14
STT
n
FINISH WALL
0
1'-6"
•b_
ADA SIGNAGE
�.
Z
D
N
PLASTIC LAMINATE
..
LOCKERS TO MATCH
PLASTIC LAMINATE
0 rn
n ; $
O N C
"o 0 �z n
CASEWORK COLOR
4" TOE KICK
FINISH FLOOR
5
�j
m� 3 c
x
ACCESIBLE LOCKERS(SEE FLOOR PLAN FOR LOCATION)
�
�i1
'PROVIDE LATCH AND LOCKING HARDWARE THAT DOES NOT
REQUIRE TWISTING,PINCHING OR GRASPING TO OPERATE.
D O ;o mp u
W g -i_
'1%OF TOTAL LOCKERS PER FLOOR PER CBC 111 6B.6.4
PLASTIC LAMINATE LOCKERS
1
Apyg�yg
0
SECTION
111.21
n
0
�.
Z
D
N
..
•
vq ����
'Y
0 rn
n ; $
O N C
"o 0 �z n
~
9Dro
5
�j
m� 3 c
x
K
�
�i1
°y
D O ;o mp u
W g -i_
Apyg�yg
0
HMCArchhects
SECTION 10 5123
PLASTIC LAMINATE LOCKERS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Plastic laminate locker units with hinged doors.
B. Base,top and filler panels.
C. Hooks, locks and hardware.
1.02 REFERENCES
A. NEMA LD-1 and LD-3- High Pressure Decorative Laminates.
B. PS 1 - Construction and Industrial Plywood.
C. PS 20-American Softwood Lumber Standard.
D. PS 51 - Hardwood and Decorative Plywood,
E. ADA—Americans with Disabilities Act of 1990
1. ADA Standards —ADA Title 11 [III] Regulations and the 2010 ADA Standards for
Accessible Design.
F. CACRM - California Access Compliance Reference Manual, updated July 1, 2008,
based on the 2010 California Building Code.
1.03 SUBMITTALS
A. Shop drawings showing locker types, sizes, configurations, layout of groups of lockers,
accessories and numbering plan.
B. Manufacturer's installation instructions.
1.04 MOCKUP
A. Provide one full size locker for Owner review in size, type and color as specified.
B. Accepted unit may be incorporated into final Work.
1.05 PROTECTION
A. Protect locker finishes and adjacent surfaces from damage during installation.
2307002 Revised 1/19/12 PLASTIC LAMINATE LOCKERS
HMC city of moorpark 10 51 23 - 1
116
i7,[V CAnch&-cts
PART 2- PRODUCTS
2.01 MANUFACTURERS
A. Products of following manufacturers form basis for design and quality intended.
1. Ideal Products Inc., Brea, CA.
2. Treeforms Lockers, Greensboro, N.C.
3. Fiberesin Industries, Inc., Oconomowoc,WI.
4. Classic Woodworking, Inc., Tualatin, OR.
5. Hollman, Inc., Edmond, OK.
B. Or equal as approved in accordance with Division 01 General Requirements for
substitutions.
2.02 LAMINATE MANUFACTURERS
A. Products of following manufacturers form basis for design and quality intended.
1. Formica Corporation, Cincinnati, OH.
2. Ralph Wilson Plastics Co., Temple, TX.
3. Nevamar Corporation, Odenton, MD.
4. Pionite Decorative Laminates, Maumee, IL.
5. Laminart, Elk Grove Village, IL.
B. Or equal as approved in accordance with Division 01 General Requirements for
substitutions.
2.03 LAMINATE MATERIALS
A. Plastic Laminate Locker Surfaces: NEMA LD-1, decorative high pressure laminate,
general purpose type, .028 inch thick at door surfaces, color as selected in wood grains
or solid.
B. Laminate Backing Sheet: NEMA LD-3 BKS/-91 Backing grade, undercoated plastic
laminate, with face material of.028 inches or general purpose type.
C. Sides, top, bottom and shelves: Low pressure decorative melamine overlay.
2.04 WOOD MATERIALS
A. Softwood Lumber: PS 20; Graded in accordance with WI Custom Grade, Douglas
Firm hemlock, Ponderosa Pine or Sugar Pine.
2.05 SHEET MATERIALS
A. Core, one of following:
1. Wood Particleboard: ANSI A208.1, Table I, Grade 1-M-3, composed of wood
chips, medium density made with water-resistant binder.
2. Plywood PS 51; rotary cut Philippine Mahogany, or other close-grain hardwood
plywood with SOUND Grade face veneer and crossband layer of Grade C or
better. 45 pound. per cubic foot industrial grade particleboard.
2307002 Revised 1/19/12 PLASTIC LAMINATE LOCKERS
HMC city of moorpark 10 51 23 -2
117
H Vr...Ar h&-cts
2.06 ACCESSORIES
A. Adhesives: Phenol resin with catalytic agent set under a pressure of not less than 30
pounds per square inch or any contact adhesive that has been approved by Southern
California Air Quality Management District.
B. Bolts, Nuts, Washers, Lags, Pins and Screws: Manufacturer's size and type to suit
application.
C. Hooks: Power epoxy coated steel, 2 single and 1 double, each compartment.
2.07 FABRICATION
A. Shop assemble lockers for delivery to site in units easily handled and to permit
passage through building openings.
B. When necessary to cut and fit on site, provide materials with ample allowance for
cutting.
C. Apply plastic laminate finish in full uninterrupted sheets consistent with manufactured
sizes. Make corners and joints hairline.
2.08 LOCKER UNITS
A. Locker Units: 12 inches wide by 18 inches deep by 60 inches high overall size; five
tier.
B. Bodies: Frameless construction, flush doors, 3/4 inch thick components with 3/8 inch
thick back, self edge banded.
C. Hinges: Heavy duty type, concealed three for doors 42 inches and higher, two for
doors under 42 inches high. Attach with particleboard screws in pre-drilled holes.
p. Locking:
1. Provide one key-controlled combination cam lock for each locker. Master key all
key locks. Provide six(6) master keys.
E. Provide head and jamb trim, end panels, filler panels and metal tops to close off all
openings.
F. Provide ventilation openings at top and bottom of each locker.
G. Finish edges smooth without chips or dents.
H. Provide polished aluminum number plates with black numerals not,less than 1/2 inch
high. Attach plates with silicone adhesive.
2.09 FINISHES
A. Color of Exterior Surfaces: Selected from manufacturer's standard color chart. Interior
Surfaces: Manufacturer's standard Beige or Neutral.
2307002 Revised 1/19/12 PLASTIC LAMINATE LOCKERS
HMC city of moorpark 10 51 23 -3
118
1 41V1CAmh&ec
2.010 ACCESSIBLE COMPLIANT LOCKERS
A. Comply with the Americans with Disabilities Act Accessibility Guidelines (ADAAG).
B. Handle: install mechanism, maximum 48"AFF.
1. Latching and locking shall not require twisting, pinching or grasping to operate.
C. Assigned Lockers: Minimum one, or 5 percent of total lockers; with appropriate symbol
sign per ADAAG 4.1.3(12)(c).
1. Provide 6 by 6 inches International Symbol of Accessibility sign, aluminum
metal, riveted in place, color: Blue No. 15090 Federal Standard 595B.
PART 3- EXECUTION
3.01 PREPARATION
A. Verify bases and recesses are properly sized and located.
3.02 INSTALLATION
A. Install lockers secure, plumb, square and in line. Set on manufacturer's standard wood
base. Verify location of backing.
B. Anchor lockers with appropriate anchor devices to suit materials encountered. Install
minimum one fastener at bottom and at top in each unit module.
C. Fasten adjoining locker units together to provide rigid installation.
D. Install head and jamb trim, end panels, filler panels to completely close off openings.
END OF SECTION
2307002 Revised 1/19/12 PLASTIC LAMINATE LOCKERS
HMC city of moorpark 10 51 23 -4
119