MOORPARK CITY COUNCIL
ACTION:- 01
AGENDA REPORT o
TO: The Honorable City Council
FROM: Jeremy Laurentowski, Landscape/Parks Maintenance' .jam
Superintendent
DATE: June 8, 2010 (CC Meeting of June 16, 2010)
SUBJECT: Consider Change Order Nos. 1, 2 and 3 for the Community
Center and Arroyo Vista Recreation Center Roofing Project
and Consider Resolution Amending the Fiscal Year 2009110
Budget
BACKGROUND
The Agreement to replace the flat roof at the Community Center and Arroyo Vista
Recreation Center was approved by City Council on October 7, 2009. Commercial
Roofing Systems, Inc. was awarded the contract and construction began on March
19, 2010. To date, the project at both facilities is approximately 90% complete.
However, during the installation process several problems were discovered with the
current installation of the existing Heating, Ventilation and Air Conditioning (HVAC)
units at the Community Center and the current condition of the plywood
underlayment at the Arroyo Vista Recreation Center. Both of these issues will
require Change Orders, as the additional work exceeds the contract funding limit.
The contract amount for this project is $103,296. However, a contingency was not
included in the budget. Staff does not anticipate any further change orders for this
project.
DISCUSSION
Change Order No. 1: It was brought to staffs attention that the existing HVAC units
installed on top of the Community Center roof were not installed per the current
installation standards of the National Roofing Contractors Association (NRCA). The
HVAC units were installed directly on top of the existing insulation and roofing
material and were not secured to the actual roof surface. In addition, the roofing
material manufacturer, the Garland Company, informed the City that they would not
stand behind their 30-year warranty if the roof cracks or leaks due to the current
installation of the HVAC units. According to the Garland Company, the HVAC units
264
Honorable City Council
June 16, 2010
Page 2
will vibrate and possibly open seams over time. In order to meet current NRCA
installation standards, two 6"x12" wood sleepers for each of the three HVAC units will
need to be attached directly to the building and roof top surface.
Change Order No. 2: During the roof top installation of the HVAC sleepers, the
roofing contractor discovered that the original sleepers were installed directly over
and perpendicular to the existing engineered truss joists, not a structural beam
member. The current installation cannot be replicated in-kind, as the weight of the
existing HVAC units is distributed over the joists without structural support.
Engineered truss joists are not structural in design and are not intended to take the
weight load of the HVAC units. With concurrence from the City Engineer and
Building Official, it has been determined that the best solution to provide structural
support for the future HVAC units would be to install 6"02" beams under the existing
roof to support the units. The new beams will span 14' between the building's
existing structural beams and align with the new sleepers installed on the roof.
Change Order No. 3: During the roof top installation at the Arroyo Vista Recreation
Center, the roofing contractor discovered dry-rot and water damage to the existing
plywood underlayment. Staff anticipated that some damage to the existing roof
structure would be discovered. However, the extent of the damage could not be
assessed until the existing roof was removed. Due to the uncertainty of the repair
work, the cost to replace the plywood underlayment, or any damage to the existing
building structure, was not included in the contract.
FISCAL IMPACT
A contingency was not established in the budget for this project. However, staff has
determined that the additional funding required to complete the necessary repairs is
available in the FY 2009/2010 Facilities Division (7620) expenditure accounts.
Change Order No. 1:
Staff recommends utilizing the available funding in the FY 2009/2010 Facilities
Division (7620), Community Facilities Property Maintenance expenditure accounts
and transferring the additional required funding from the Facilities Division
expenditure accounts.
Utilize the following for CO No. 1:
1000-7620-0000-9252 — Community Facilities Property Maintenance $2,000.00
Transfer the following for CO No. 1 to the Community Facilities Property Maintenance
expenditure account:
1000-7620-7704-9252 — Active Adult Center Property Maintenance $2,300.00
1000-7620-0000-9102 — Community Facilities Contractual $1,169.47
Total $5,469.47
265
Honorable City Council
June 16, 2010
Page 3
Staff has determined that the cost to replace the HVAC sleepers will be absorbed by
the funding available from the recently obtained Energy Efficiency Grant as required
installation for the future HVAC units. The City is currently out to bid on the project to
replace the HVAC units at the Community Center as the energy savings would be
substantial and staff expects to start construction at the end of June.
Change Order No. 2:
Staff recommends utilizing the available funding in the FY 2009/2010 Facilities
Division (7620), Community Facilities Property Maintenance expenditure account and
transferring the additional required funding from the Community Facilities Contractual
expenditure account.
Utilize the following for CO No. 2:
1000-7620-0000-9252 — Community Facilities Property Maintenance $3,000.00
Transfer the following for CO No. 2 to the Community Facilities Property Maintenance
expenditure account:
1000-7620-0000-9102 — Community Facilities Contractual $3,577.17
Total $6,577.17
Change Order No. 3:
Staff recommends transferring the available funding in the FY 2009/2010 Facilities
Division (7620), Arroyo Vista Recreation Center Contractual and Shop and Operating
Supplies expenditure accounts to the Arroyo Vista Recreation Center Property
Maintenance expenditure account.
Transfer the following for CO No. 3 to the Arroyo Vista Recreation Center Property
Maintenance expenditure account:
1000-7620-0000-9102 — AVRC Contractual $1,000.00
1000-7620-0000-9204 — AVRC Shop and Operating Supplies $1,492.80
Total $2,492.80
STAFF RECOMMENDATION Roll Call Vote
1. Approve Change Orders No. 1, 2 and 3 as described in the Agenda Report, and
2. Adopt Resolution No. 2010 -
Attachment: Resolution 2010 -
266
RESOLUTION NO. 2010 -
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
MOORPARK, CALIFORNIA AMENDING THE FISCAL YEAR 2009/10
BUDGET TO ALLOCATE $14,541 TO THE COMMUNITY CENTER AND
AVRC ROOFING PROJECTS FROM OTHER FACILITIES
MAINTENANCE ACCOUNTS
WHEREAS, on July 1, 2009, the City Council adopted the Operating and Capital
Improvement Budget for Fiscal Year 2009/10; and
WHEREAS, on June 16, 2010 a staff report has been presented to the City
Council requesting a budget amendment in the aggregate amount of $14,541 to fund
the roofing projects at the Community Center and AVRC; and
WHEREAS, Exhibit "A" hereof describes said budget amendment and its
resultant impacts to the budget line items.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK
DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1: That a Budget Amendment in the aggregate amount of $14,541 as
more particularly described in Exhibit "A", is hereby approved.
SECTION 2: The City Clerk shall certify to the adoption of this resolution and
shall cause a certified resolution to be filed in the book of original resolutions.
PASSED AND ADOPTED this 16'h day of June, 2010.
Janice S. Parvin, Mayor
ATTEST:
Debbie S. Traffenstedt, City Clerk
267
EXHIBIT A
BUDGET AMENDMENT FOR
GENERAL FUND
COMMUNITY CENTER & AVRC ROOFING
CHANGE ORDERS #1, #2 & #3
FY 2009110
FUND BALANCE ALLOCATION:
Fund Title Fund-Account Number Amount
Total $
EXPENDITURE APPROPRIATION:
Account Number Current Budget Revision Amended Budget
1000.7620.7705.9621 $ 72,000.00 $ 12,048.00 $ 84,048.00
1000.7620.7701.9621 $ 17,000.00 $ 2,493.00 $ 19,493.00
1000.7620.0000.9252 $ 19,025.00 $ 5,000.00 $ 14,025.00
1000.7620.7704.9252 $ 3,000.00 $ 2,300.00 $ 700.00
1000.7620.0000.9102 $ 24,400.00 $ 5,748.00 $ 18,652.00
1000.7620.0000.9204 $ 10,725.00 $ (1,493.00) $ 9,232.00
Total $ 146,150.00 1 $ - $ 146,150.00
Finance Approval.
268