HomeMy WebLinkAboutAGENDA REPORT 2009 0401 CC REG ITEM 09B rFEM 9 . 8.
CITY OF MOORPARK,CALIFO-�>!A
City CitwnCII Meeting
bt,,, __... - to
AVOW_
MOORPARK CITY COUNCIL
AGENDA REPORT 9-a c�
TO: The Honorable City Council
FROM: Mary K. Lindley, Parks, Recreation, & Community Services Director
BY: Roger O. Blais, Parks and Landscape Manager
DATE: March 20, 2009 (CC Meeting of April 1, 2009)
SUBJECT: Consider Award of Contract to California Skate Parks, Inc. for the
Poindexter Park Expansion Project and Consider an Agreement with
Pacific Materials Laboratories for Soils Testing, Lab Work and
Inspections, and Authorize Loan of $1,500,000 From Special Project
Fund to Park Improvement Zone 1 Fund
DISCUSSION
On December 17, 2008, City Council approved the design and specifications for
construction of the Poindexter Park Expansion. The estimated budget presented to the
Council was $2,383,000. The bid process for construction of the project closed on
March 10, 2009, and the City Council is now being asked to approve the award of
contract to the lowest qualified responsive bidder, California Skate Parks, Inc.
The Poindexter Park Expansion project is an approximately 2 acre expansion which
includes site demolition, grading, drainage and various improvements: in-ground skate
park, full-court basketball court, new play lot designed for youth between the ages of 8
and 12, landscaping, pathways, and picnic amenities. In addition, an Add Alternate for
24,297 square feet of sod, in place of hydro seed, was included in the bidding
document.
Contractors bidding this project were required to meet specific experience qualifications
above the typical standard licensing, bonding capacity, and insurance requirements
related to the construction of the park improvements and skate parks. To ensure that the
City would receive a high-quality skate park, the contractor submitting the bid proposal (the
general or prime) also had to demonstrate that they had completed at least three similar
public park projects with an in-ground concrete skate parks and similar amenities since
January 2004, within the state of California, in which the skate park construction
constituted at least $500,000 of the total construction cost, and was deemed satisfactory to
the owner of the project. They are also required to have a class A General Engineering
License and the contractor or its subcontractor must be able to provide evidence of
experience in cast-in-place concrete and shotcrete work.
The bid results, based on the construction of the project as originally designed, and with
the above design alternative are as follows: 1100020
Honorable City Council
April 1, 2009
Page 2
Contractor Base Bid Add Alternate #1
Valley Crest Landscape Development $ 1,670,000. $ 12,900.
California Skate Parks, Inc. $ 1,745,326. $ 20,000.
The bids were reviewed for completeness and mathematical errors. Staff contacted the
references submitted and determined that the low bidder Valley Crest Landscape
Development, does not meet the required qualifications for this project. Of the ten
references submitted by Valley Crest, only one reference provided the construction
requirements necessary to meet our City qualifications as the entity submitting a
proposal for this project.
California Skate Parks, Inc. submitted four references — all were positive. A reference
check shows that California Skate Parks is highly recommended. They meet all required
qualifications of the project manual and specifications for this project, and possess the
necessary licenses to perform the work and have experience constructing similar
projects for other cities in California.
Based on the lowest qualified base bid of California Skate Parks, Inc., the construction
cost remains within the FY 2008/09 total budget allocation for this project. City Council
is now being asked to approve the award of contract to the lowest qualified responsible
bidder, California Skate Parks, Inc. In addition, staff proposes that City Council reject
the one Add Alternate for sod. Staff believes that seed germination will be established
for grass areas during optimal growth periods, and that sod will not be necessary.
Staff proposes that the City Council reject the bid of Valley Crest Landscape
Development. While this company has excellent recognition of performance in the
landscape industry, they did not meet the requirements of having completed three skate
parks since January 2004 to qualify as required in the bid document.
As stated above, at the time of the December 17, 2008, Council meeting, the estimated
budget for the project was $2,383,000. With the bidding phase now completed, the
revised budget is as follows:
Description Completed Pending Total
Work Work
Construction $1,745,326
Construction Plans & Specifications $77,000
Conceptual Plan $26,000
Plan Check, Permits & Reproductions $ 15,000
Soils/Lab Testing $ 47,100
S:\Community Services\ADMINISTRATIVE\CC Reports\2009W1-09(Poindexter Pk Construction Contract
Award).doc
,►0021
Honorable City Council
April 1, 2009
Page 3
Construction Management $ 43,000
Contingency (15%)* $ 278,000
Preliminary Site Work** $14,000
Total $117,000 $2,128,426 $2,245,426
* Included in calculation of 15% contingency
*'Water well and tree removal
The fiscal year 2008/09 includes $2,295,369 for the project, $49,943 more that the
current cost estimate.
In the April 18, 2007, Council Agenda Report, the proposed funding source of the
project was $89,495 from the State Park Bond and the remaining from the Park
Improvement Fund (PIF). At that time, it was proposed that $700,000 (the approximate
cost of the skatepark) come from the PIF — Community Wide Zone Fund, used for
projects with community wide benefit including Arroyo Vista Community Park, and the
remaining from PIF - Zone 1 (downtown), the Zone that Poindexter Park is within. PIF
consists of fees paid by residential developers in-lieu of setting aside parkland. It was
recognized that Zone 1 does not have the necessary fund balance available; however, it
was projected that within the next 10 years, or at build out, Zone 1 will have a fund
balance of approximately $5.5 million and that the Community Wide Zone Fund would
have a fund balance of approximately $8.8 million. Additionally, prior to the recent
adoption of the State's budget, all Park Bond appropriations were placed on hold.
Therefore, there may be a delay in the receipt of the City's $89,495 bond funds beyond
the completion of the project. As a result of the short fall in Zone 1, and the potential
delay in payment of the park bond, the City Council will need to approve a loan from
either the City's Endowment Fund, Special Projects Fund, General Fund, or
Redevelopment Agency for approximately what would be necessary.
Based on our current cost estimates, funding for the project is as follows:
Funding Source Allocation
State Park Bond $ 89,495
PIF — Zone 1 (requires a temporary loan $1,455,931
of approximately $1.5 million
Community Wide Zone $ 700,000
Total Revenue $2,245,426
To proceed with construction, the City needs to secure the services of a soils testing,
inspection, and lab testing consultant. Staff proposes using Pacific Materials Laboratory
(PML) at a cost not to exceed $47,100. PML has performed work for the City on a
number of park improvement projects, most recently the Veterans Memorial Park
SACommunity Services\NDMINISTRATIVE\CC Reports\200944-1-09 (Poindexter Pk Construction Contract
Award).doc
+t004D22
Honorable City Council
April 1, 2009
Page 4
Project and Arroyo Vista Recreation Center Expansion Project. The cost of the soil
testing and inspection work was included in the project budget presented above.
FISCAL IMPACT
As discussed above, the total estimated cost of the project is $2,245,426 (includes
contingency), approximately $50,000 less than what was included in the fiscal year
2008/09 budget. However, PIF Zone 1 and the park bond funding sources require
temporary loans totaling approximately $1.5 million. The Council should note that the
interest that would be earned by the loaning funding source will be negatively impacted
in an amount of $20,000 to $50,000 per year for every $1 million loaned; although, the
interest would be repaid based on the average LAIF rate for the previous, along with the
principal. The timeline for the repayment of the loan will depend on the pace of new
development and the payment of parkland fees. Annual maintenance and operations
cost for the two acre expansion is estimated to be $18,000.
STAFF RECOMMENDATION Roll Call Vote
1) Approve the project's scope of work to exclude the one Add Alternate;
2) Reject bid proposal of Valley Crest Landscape Development and award the
construction agreement to California Skate Parks, Inc. at a cost not to exceed
$1,745,326;
3) Authorize the City Manager to execute the agreement on behalf of the City and to
amend the construction contract for project contingencies in an amount not to exceed
$261,798;
4) Approve a contract with Pacific Materials Laboratory (PML) for soils testing, lab work,
and inspections at a cost not to exceed $47,100, and authorize the City Manager to
execute the agreement on behalf of the City and to amend the contract for project
contingencies in the amount not to exceed $10,000; and
5) Approve a loan of up to $1.5 million from the Special Projects Fund to be repaid with
interest based on the average LAIF rate for the previous year.
Attachment: Budget Amendment Resolution
SACommunity Services\HDMINISTRATIVE\CC Reports\2009\4-1-09(Poindexter Pk Construction Contract
Award).doc 1 UU 023
RESOLUTION NO. 2009 -
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF MOORPARK, CALIFORNIA AUTHORIZING
A LOAN OF UP TO $1,500,000 FROM THE SPECIAL
PROJECTS FUND (4004) TO THE PARK
IMPROVEMENT ZONE 1 FUND (2111) FOR THE
POINDEXTER PARK EXPANSION
WHEREAS, on July 2, 2008, the City Council adopted the Operating and Capital
Improvement Budget for Fiscal Year 2008/09; and
WHEREAS, the adopted budget included an aggregate appropriation in the Park
Improvement Zone 1 Fund (2111) of $2,295,369 for Capital Improvement Project No.
7801 - Design and Construction of Poindexter Park Expansion; and
WHEREAS, the same budget provided that the Park Improvement Community
Wide Fund (2100) would transfer $700,000 to Park Improvement Zone 1 Fund (2111) to
partially finance the Poindexter Park Expansion Project; and
WHEREAS, a staff report has been presented to the City Council requesting a
loan of up to $1,500,000 from the Special Projects Fund (4004) to the Park
Improvement Zone 1 Fund (2111) for the Poindexter Park Expansion Project, with
variable interest based on the average interest rate earned by LAIF from the previous
year; and
WHEREAS, said staff report directs the loan funds to be transferred from Special
Projects Fund (4004) to the Park Improvement Zone 1 Fund (2111) when needed and
the principal and interest to be repaid as new development and parkland fees are
collected; and
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK
DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1: The loan of up to $1,500,000 from the Special Projects Fund
(4004) to the Park Improvement Zone 1 Fund (2111), with variable interest based on the
average interest rate earned by LAIF from the previous year, is hereby approved.
SECTION 2: That a fund transfer of up to $1,500,000, as particularly described
in Exhibit "A", is hereby approved.
)00024
Resolution No. 2009 -
Page 2
SECTION 3: At fiscal year end, Finance department shall transfer out any
surplus fund balance in the Park Improvement Zone 1 Fund (2111) to the Special
Projects Fund (4004) to repay the principal and interest accrued for the period until the
loan is fully satisfied.
SECTION 4: The City Clerk shall certify to the adoption of this resolution and
shall cause a certified resolution to be filed in the book of original resolutions.
PASSED AND ADOPTED this 15t day of April, 2009.
Janice S. Parvin, Mayor
ATTEST:
Maureen Benson, Assistant City Clerk
Attachment: Exhibit 'A': Budget Appropriation and Fund Transfer Detail
'►00025
Resolution No. 2009 -
Page 3
Exhibit A
Budget Amendment for
Special Projects and Park Improvement Zone 1 Funds
for Transfer $1,500,000 Loan Required for Poindexter
Park Expansion Project
FY 2008/09
A. Fund Allocation
Fund Description Account Amount
Special Projects Fund 4004-5500 1,500,000
Total 1,500,000
B. Appropriation Allocation
Adopted Budget
Budget Number Budget Change Revised Budget
FROM:
4004-7800-7803-9820 $0 1,500,000 $1,500,000
TO:
2111-3720 $0 1 1,500,000 1 $1,500,000
Finance Approval:
00002b