HomeMy WebLinkAboutRES CC 2016 3536 2016 0720 RESOLUTION NO. 2016-3536
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF MOORPARK, CALIFORNIA, APPROVING THE
SEVEN YEAR CAPITAL IMPROVEMENT PROGRAM
FOR FISCAL YEAR 2015/2016 — FISCAL YEAR
2021/2022
WHEREAS, a.proposed Seven Year Capital Improvement Program (CIP) for
FY 2015/2016 — FY 2021/2022 has been presented to City Council; and
WHEREAS, the CIP is a planning and programming tool to identify the City's
capital projects related to Public Works and their funding sources; and
WHEREAS, pursuant to California Government Code Section 65401, on May 24,
2016, the Moorpark Planning Commission found the CIP to be in conformance with the
Moorpark General Plan, with the exception of the Moorpark Avenue Widening project
which includes a second southbound lane from Casey Road to Third Street that is not
identified in the General Plan and the Circulation Element; and
WHEREAS, pursuant to California Government Code Section 65402, on May 24,
2016, the Moorpark Planning Commission also found the planned acquisition of street
right-of-way for certain specified projects described in the CIP, to be in conformance
with the Moorpark General Plan, with the exception of the Moorpark Avenue Widening
project which includes a second southbound lane from Casey Road to Third Street that
is not identified in the General Plan and the Circulation Element.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK
DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. The May 24, 2016 finding of the Moorpark Planning Commission
that the Seven Year CIP for FY 2015/2016 — FY 2021/2022 is in conformance with the
Moorpark General Plan, with the exception of the Moorpark Avenue Widening project,
pursuant to California Government Code Section 65401, is adopted.
SECTION 2. The May 24, 2016 finding of the Moorpark Planning
Commission that the planned acquisition of street right-of-way for certain specified
projects described in the CIP, is in conformance with the Moorpark General Plan, with
the exception of the Moorpark Avenue Widening project, pursuant to California
Government Code Section 65402, is adopted.
SECTION 3. The Seven Year Capital Improvement Program for FY 2015/2016
— FY 2021/2022 is approved.
Resolution No. 2016-3536
Page 2
SECTION 4. The City Clerk shall certify to the adoption of this resolution
and shall cause a certified resolution to be filed in the book of original resolutions.
PASSED AND ADOPTED this 20th day of July, 2016.
-t-t--e-A.-)c
Ja ice S. Parvin, Mayor
ATTEST:
N4.4.4.4 /`'_ " _ ' 1>-.'-.'ice 57'
Maureen Benson, City ClerkC „- �v
\s4�c VV
Resolution No. 2016-3536
Page 3
STATE OF CALIFORNIA )
COUNTY OF VENTURA ) ss.
CITY OF MOORPARK )
I, Maureen Benson, City Clerk of the City of Moorpark, California, do hereby
certify under penalty of perjury that the foregoing Resolution No. 2016-3536 was
adopted by the City Council of the City of Moorpark at a regular meeting held on the
20th day of July, 2016, and that the same was adopted by the following vote:
AYES: Councilmembers Mikos, Millhouse, Pollock, Van Dam, and Mayor Parvin
NOES: None
ABSENT: None
ABSTAIN: None
WITNESS my hand and the official seal of said City this 13th day of September,
2016.
Maureen Benson, City Clerk
(seal)
r /
-31,:))kc
h
�rc12
QPaK C44/.c
Q. o
O A&1
Nei
• W.
411)
W
O 0
A ^
OR T 0V
Eo
CITY OF MOORPARK
DEPARTMENT OF PUBLIC WORKS
Seven Year
Capital Improvement Program
FY 2015/2016 - FY 2021/2022
JANICE PARVIN, MAYOR
ROSEANN MIKOS, COUNCILMEMBER
KEITH MILLHOUSE, COUNCILMEMBER
DAVID POLLOCK, COUNCILMEMBER
MARK VAN DAM, COUNCILMEMBER
STEVEN KUENY
-CITY MANAGER-
SEAN CORRIGAN, P.E.
-CITY ENGINEER/PUBLIC WORKS DIRECTOR-
JULY 14,2016
Approved July 20, 2016
Resolution No. 2016-3536
Table of Contents
Page
A. Introduction A-1
B. Project Descriptions B-1
100 Streets B-3
101 8002: Slurry Seal ProgramB-4
102 8076: SR-118/Collins Drive Westbound Off-Ramp Improvements and Signals
Modification . B-5
103 Walnut Canyon Road Sidewalk Improvements . B-6
104 8026: Spring Road WideningB-7
105 8012: Princeton Avenue Widening . B-8
106 8013: Los Angeles Avenue Widening: Spring Road to Moorpark Avenue B-9
107 8069: Spring Road/Charles Street Bus Turn-Out . B-10
108 8058: Los Angeles Avenue Widening at Shasta AvenueB-11
109 Underground Utility Projects . B-12
110 8051: Underground District No. 2: L. A.Avenue Transmission Lines . B-13
111 8066: Underground Utilities: L.A.Avenue at the Arroyo Simi Bridge . B-14
112 8039: Rail Crossing Improvements at Spring Road . B-15
113 8084: Arroyo Drive Overlay . B-16
114 8071: Bus Shelter Improvements and Other Bus Stop Amenities B-17
115 8061: North Hills ParkwayB-18
116 5056: High Street Streetscape/Parking ImprovementsB-19
117 8045: 23 FWY North Alignment . B-20
118 Wicks Road Sidewalk and Asphalt Overlay . B-21
119 8056: Metrolink South Parking Lot South Entry . B-22
120 Gabbert Road Rail Crossing . B-23
121 High Street[West] Reconstruction . B-24
122 8080: Railroad Crossing Improvements at Arroyo Drive . B-25
123 8040: Moorpark Avenue Widening Project . B-26
124 Lengthen Curb Radii at Designated Intersections B-27
125 Los Angeles Avenue Widening West of Tierra Rejada Road B-28
126 Casey Road Extension . . B-29
127 8087: Moorpark Avenue Left Turn Lane . B-30
128 8093: Asphalt Overlay on Spring Road,Princeton Avenue, and Poindexter Avenue B-31
129 8063: Metrolink North Parking Lot Expansion . B-32
200 Trails and Walkways B-33
201 8001: Sidewalk Reconstruction ProjectB-34
202 Pedestrian/Bicycle Projects B-35
203 8035: Arroyo Simi Trail Improvements . . B-36
204 8059: Drain No.2 TrailB-37
205 Sidewalk&Bicycle Lane at AVRC . B-38
206 Walnut Canyon Road Westside Championship Drive to Peter's Driveway B-39
207 Civic Center Pedestrian Access and Bus Stop Improvements B-40
208 8095 Arroyo Drive Bike/Ped Project . . B-41
Table of Contents (Cont.)
Page
300 Traffic Signals B-43
301 Not Assigned B-44
302 8058: Los Angeles Avenue and Shasta Avenue . B-45
303 8077: SR-118/Collins Drive Eastbound On/Off Ramps B-46
304 Not Assigned B-47
305 8013: Los Angeles Avenue and Millard Street B-48
306 8061: Los Angeles Avenue West of Butter Creek Road B-49
400 Medians and Parkways B-51
401 8047: Medians: Los Angeles Avenue . B-52
402 8026: Medians: Spring Road B-53
403 Not Assigned B-54
404 8048: Parkway: Poindexter Avenue . B-55
405 SR-23/Tierra Rejada Road Interchange Landscaping B-56
406 Not Assigned B-57
407 Not Assigned B-58
408 Peach Hill Parkways B-59
500 Storm Drains B-61
501 8088: Master Plan of Drainage B-62
502 Gabbert Canyon/Walnut Canyon System Improvements B-63
503 Shasta Drain B-64
504 8065: Millard Drain B-65
505 Villa Del Arroyo Drain B-66
506 Miscellaneous Drainage Improvements B-67
507 Arroyo Simi Channel Improvements B-68
508 GIS Storm Drain Layer B-69
C. Program Expenditure Summary c-1
• Total Program Project Costs: Spread to Funding Year C-3
• FY2015/16 Total: Spread to Funding Sources C-7
• Total Program: Spread to Funding Sources C-11
D. Projects on the Congestion Management Plan [CMP] Road Network D-1
Appendix `I': List of Completed Projects 1-1
Appendix `II': Description of Funding Sources H-1
Appendix `III': List of Potential Projects III-i
Appendix `IV': Approving Resolution No. 2016-3536 1v-i
City of Moorpark
Capital Improvement Program
A. Introduction
This is the updated Seven Year Capital Improvement Program (CIP) for the City of Moorpark,
Department of Public Works for the period covering FY 2015/16 through FY 2021/22. The primary
purpose of this CIP is to provide the City Council with a framework for identifying, planning and
prioritizing needed municipal capital improvements. The year each project is recommended to be
funded, is an indication of the priority given to each project. The figures cited in the FY 15/16 column,
should be identical to the appropriations approved in the FY 2015/16 Budget for capital improvement
projects for(8000 series).
Projects have been organized into the five (5) Sections noted below. The projects identified in this CIP
include both City funded projects as well as major projects which are likely to be constructed by land
developers. The projects listed in Section 100 include future streets which are identified in the
Circulation Element of the Moorpark General Plan. The projects listed in Section 500 include future
needed storm drains identified in the Moorpark Master Drainage Study. Also included in Section 500
are certain projects of importance to the City which are planned to be constructed by the Ventura
County Watershed Protection District.
A brief description of the contents of this CIP is as follows:
• A: this Introduction;
• B: a project description page for each project;
• C: a summary of total program expenses by fiscal year;
• D: a list of the projects on the Network Congestion Management Program (CMP);
• Appendix `I': a list of completed projects through 2015.
• Appendix `II': a description of the funding sources referenced herein.
• Appendix `III': a list of potential projects.
A summary of the total estimated program expenditures is as follows:
Section FY15/16 FY16/17 FY17/18 FY18/19
100 Streets 8,693,863 7,930,014 2,731,963 845,000
200 Trails&Walkways 693,266 455,500 115,000 40,000
300 Traffic Signals 0 175000 0 0
400 Medians/Parkways 75,914 850,000 316,000 52,000
500 Storm Drains 150,000 0 450,000 800,000
Total 9,613,043 9,410,514 3,612,963 1,737,000
Section FY 19/20 FY20/21 FY21/22 Total
100 Streets 100,000 5,150,000 5,000,000 30,450,840
200 Trails&Walkways 40,000 40,000 40,000 1,423,766
300 Traffic Signals 0 0 0 175,000
400 Medians/Parkways 0 0 0 1,293,914
500 Storm Drains 0 7,500,000 7,500,000 16,400,000
Total 140,000 12,690,000 12,540,000 49,743,520
City of Moorpark
Capital Improvement Program
B. Project Descriptions
Individual project descriptions are set forth in this section. Each project description
includes a location map, a project cost estimate, a proposed schedule, and recommended
funding sources.
It should be noted that there has been no preliminary engineering performed for most of
the projects programmed in future years. The cost estimates provided for those projects
are a rough estimate only and should not be relied upon to predict actual costs. These
estimates were included in the project descriptions in order to provide a general idea of
the total estimated program costs. Individual project cost estimates will be revised as
engineering for each project is developed.
Streets
City of Moorpark
Capital Improvement Program
Project Name: Slurry Seal Program Code No. 101 .
Account No. 8002 .
Location Map
Various Streets (to be determined)
Project Description
Bi-annual Slurry Seal/ARAM project. Resurfacing of one-third of the City's streets every other year. Past
Slurry Seal Projects are listed in Appendix `I'. The scope of work often includes the removal and
replacement of pavement in poor condition, and the application of crack sealer where needed. The next
slurry seal project is scheduled for Summer 2017. Effective FY 2016/2017, CIP 8098 will replace 8002.
Project Funding Schedule Total Cost: x+5,764,851 .
Prior Yrs FY 15/16 FY Y 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 35,525
R-O-W
Construction 4,346,432 1,185,339
Inspection 197,556
Total 4,579,513 1,185,339 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY Y 19/20 FY 20/21 FY 21/22
2002:CTM 218,236
2603:LTF 2,509,076 832,776
2605:Gas Tax 52,142 321,063
2609:Grant 99,200 31,500
2610:Grant 479,323
2611:Prop lB 1,168,332
2400:Parks 53,203
Total 4,579,512 1,185,339 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: SR-118/Collins Drive Westbound Off-Ramp Improvements and Signal Code No. 102 .
Modification. Account No. 8076 .
Location Map
sR',e •—Z--*
a„% ' :\ a
7\
.
Itt
NV . ... .......... ......
a ill . • o NVI€r- if
a
PROJECT
1
Project Description
This project involves the modification of the westbound SR-118 off-ramp and signal to provide an un-
signalized right turn lane from the westbound SR-118 off-ramp to Collins Drive. This project is partially funded
by Moorpark Community College.
Project Funding Schedule Total Cost: $550,000
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY Y 18/19 FY 19/20 FY 20/21 FY 21/22
Design 75,000
R-O-W
Construction 475,000
Inspection
Total 0 0 0 i 75,000 475,000 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2603:LTF
1000 General
Other Sources 75,000 475,000
Total 0 0 0 75,000 475,000 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Walnut Canyon Road Sidewalk Improvements . Code No. 103.
Account No. ---- .
Location Map
_ NL11 I ]L )-, I
? al
d'i ) L14
4
.....
....4ry
Iv/ T - 5130
PROJECT A' '
1107jrZey, iis/
\--vi
ar,
Case •d �� P PP 111W4111V411-1 it ,1 tt Si_
ME
M R[771 I ITBPI I II F71i
Project Description
Construction of additional pavement and a sidewalk on the west side of Walnut Canyon Road, north of
Casey Road. This project is to be constructed by the developer of Tract 5130.
Project Funding Schedule Total Cost: $500,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 500,000
Inspection
Total 0 500,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 500,000 0
Developer
Total 0 500,000 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Spring Road Widening: Los Angeles Avenue to Flinn Avenue. Code No. 104 .
Account No. 8026 .
Location Map
iEW,cil l§ti I I
11 �'" �i . •er
111011111111111111 :!
suillum.40 _ PROJECT
EROPIIIIIIPIL�i
AvP00
A
Los Angeles Ave(SR 118)
T f
N
Project Description
Construction of improvements and modifications to Spring Road, from a point south of Los Angeles
Avenue northerly to Flinn Avenue. This project requires the acquisition of additional street right-of-way,
widening, new curb, gutter and sidewalk along the east side of the street. Ultimate improvements will
include four (4) travel lanes, six foot (6') wide bike lanes, a fourteen foot (14') wide landscaped median
and double left-turn lanes southbound on Spring Road.
Project Funding Schedule Total Cost: 1,250,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 77,778 42,222
R-O-W 272,178 87,822
Construction 44,380 655,620
Inspection 70,000
Total 394,336 855,664 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2501:L A AOC 394,336 855,664
Total 394,336 855,664 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Princeton Avenue Widening Realignment and Reconstruction . Code No. 105 .
Account No. 8012 .
Location Map
3 t 23 FWY
ti
�� �o�� ����/sum .„ 0�
■age:
nimay '•• %'•1111610 . jjII %i rrrrrrrrrrrr
1111111111
PROJECT
11111111
23FWY
Il / a
Project Description
Widening, realignment and reconstruction of Princeton Avenue from a point east of Spring Road to South
Condor Drive. Additional street right-of-way is being acquired to provide an eighty-eight feet (88') wide
corridor — sufficient to allow for future widening of the road to four lanes. The current project design
provides for only one lane in each direction with a paved median and paved shoulders. The project plans
call for the realignment and reconstruction of the street pavement, the construction of storm drains and the
construction of retaining walls as required.
Project Funding Schedule Total Cost: $10,381,573 .
Prior Yrs FY 15/16 FY 16/17 FY 17/1.8 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 799,414 142,346
R-O-W 2,196,812 798
Construction 29,410 6,933,089
Inspection 250,000
Total 3,055,341 142,346 7,183,887 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2501: LAOC 3,036,584 142,346 6,096,643
2609: Grant 18,756 1,087,244
Total 3,055.340 142,346 7,183,887 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Los Angeles Avenue Widening: Spring Road to Moorpark Avenue. Code No. 106 .
Account No. 8013 .
Location Map
C .. 1 ( I L I I Esther Lyle 11 H I 1— ®®®[
i .
n _ using', -a. . (•4-2
73
0 = Iiiiiiiiiiiril aluu■•iiiiill■■u■.r.j -
o Los An t eles -
0 �,�-`� ;.
• PRO CT a
01 .J. T� . . . Ct ..
Project Description
Widening of Los Angeles Ave to provide for six (6) travel lanes of traffic, and widen Spring Rd from the
McDonald's driveway south to the gas station. At Spring Rd, Los Angeles Ave's centerline will be shifted
to the south to avoid acquiring right-of-way from the residential properties along the north side of the
street. The additional right-of-way in this area will be acquired from the south side of the street. At
Moorpark Avenue the additional street right-of-way will be acquired from the north side of the street. The
project includes westbound right-turn lanes at Spring Road and at Moorpark Avenue, and a new traffic
signal at Millard Street.
Project Funding Schedule Total Cost: $4,233,457 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 828,108 460,798
R-O-W 1,547,129 107,028
Construction 71,572 1,121,363
Inspection 4,019 93,440
Total 2,450,828 1,782,629 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2501:LA AOC 2,450,828 985,859
2604:Grant 796,770
Total i 2,450,828 1 1,782,629 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Spring Road/Charles Street: Bus Turn-Out Project. Code No. 107 .
Account No. 8069 .
Location Map
I J �, N
a $
m
a e
n
Charles St Cb
arya
Sr
j
PROJECT
Princeton Ave
High St ---
0
m
o.
a •
Project Description
The construction of a bus turn-out on the east side of Spring Road just south of Charles Street. Additional
street right-of-way will have to be acquired in order to implement this project.
Project Funding Schedule Total Cost: $164,216 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 13,968
R-O-W 248 39,000
Construction 106,000
Inspection 5,000
Total 14,216 0 0 150,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM 14,216 150,000
Total 14,216 0 0 150,000 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Los Angeles Avenue Widening at Shasta Avenue Code No. 108 .
Account No. 8058 .
Location Map
1111
� 1.71.7i ■
ic■ �-.' erest Ave
:1.61.11111
- ° ■
•fif A
PROJECT
Cil
r—r
Project Description
The construction of widening the south side of Los Angeles Avenue between Maureen Lane and Leta
Yancy Road, along the frontage of the vacant property of Tentative Tract 5882 [Pacific Communities]. A
traffic signal will be constructed at the intersection of Los Angeles Avenue and Shasta Avenue during the
development of Tract 5882 [Pacific Communities]. It is the intent of the City to seek reimbursement from
the developer of Tract 5882 for City costs incurred to implement this project.
Project Funding Schedule Total Cost: $1,637,832.
I Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 76,000 20,557
R-O-W
Construction 55,832 1,032,168
inspection 76,893 164,107
Total 208,725 1,216,832 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2501:L A AOC 208,275 1,216,832
Total 208,275 1,216,832 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Underground Utility Projects Code No. 109
Account No. ---- .
Location Map
Locations to be determined
Project Description
City costs related to the development and implementation of various underground utility projects and/or
formation of Underground Utility Districts for such purpose. Project Codes 110 and 111 describe
immediate future efforts in this regard. This project (#109) has been included in order to program future
"undergrounding" projects, the location and scope of which are to be determined. As projects are
identified, they will be added to the CIP as separate projects.
Project Funding Schedule Total Cost: 10,000,000
Prior Yrs FY Y 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 5,000,000 5,000,000
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 5,000,000 5,000,000
Total 0 0 0 0 0 0 5,000,000 5,000,000
City of Moorpark
Capital Improvement Program
Project Name: Underground Utility District No 2 . Code No. 110.
Account No. 8051 .
Location Map
I cn 1 \ II o
PkOJEC
m 9
— D erest Ave -- r
Los An•eles Ave
II
Project Description
Establishment and implementation of an underground utility district along Los Angeles Avenue between
Shasta Avenue and Millard Street to underground the high voltage transmission lines and remove all poles
and overhead wires. SCE Rule 20A monies in the approximate amount of$400,000 arc not included in the
budget figures shown below.
Project Funding Schedule Total Cost: $ 726,448 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 240 726,208
Inspection
Total 240 0 0 726,208 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2330: AD 92-1 426,447
2501: LA AOC 240 299,761
Rule 20A
Total 240 0 0 726,208 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Underground Utilities at the Los Angeles Avenue Bridge Code No. 111.
Account No. 8066
Location Map
AN®NNNNNN®N
'-®NEIN=:NN®
111117
s PlIgeles ple
PROJECT
•
Project Description
This is a project to "underground" the overhead utility wires on the north side of Los Angeles Avenue east
and west of the Arroyo Simi Bridge. Currently, project funding via the LA AOC is proposed to be
reimbursed from unexpended funds from the Community Facilities District for the Moorpark Marketplace
project.
Project Funding Schedule Total Cost: $468,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 15,078 136,922
R-O-W
Construction 305,000
Inspection 3,000
Total 15,078 0 444,922 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2501: LA AOC 13,414 444,636
2001:TSM 1,664 286
Total 15,078 0 444,922 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Rail Road Crossing Improvements at Spring Road . Code No. 112 .
Account No. 8039 .
Location Map
I I
Princeton Ave
High St
IIIIIItlllllllllllllllllllllllllllltllllllllllllllllllllllllll/1111111111111 11111111111111111111
PROJECT
I
Dorothy Ave � • �
o.
Project Description
This project provides for street widening and improvements to the rail crossing by adding a center median
and four(4) crossing gates. The project also includes acquisition of additional street right-of-way and street
widening on the east side of the street between the rail crossing and Princeton Avenue to provide an
additional right-turn lane and bike lanes on both sides of the street. SCRRA (Metrolink) is managing the
construction of the project which is estimated at a total cost of $3.3 million. Metrolink is contributing
$1.1 million towards the project which is not included in the funding schedule below since Metrolink is
paying their contractor directly and their funds will not flow through the City's budget.
Project Funding Schedule Total Cost: $2,246,524 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 153,570 46,469
R-O-W 116,848
Construction 850,681 1,038,956
Inspection 40,000
Total 1,121,099 1,125,425 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2603:LTF 290,367
2902:MRA 122,849
2501:LA AOC 707,882 1,125,425
Total 1,121,098 1,125,425 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Arroyo Drive Overlay . Code No. 113
Account No. 8084
Location Map
Park 'f Dr
'i `
III ` �
1 . "' I a• PROJECT
ammo4 anksisvaitior
141111110,140
•
Project Description
Pavement rehabilitation on Arroyo Drive from Collins Drive to entrance of Villa del Arroyo Mobile Home
Park.
Project Funding Schedule Total Cost: $537,000
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 656 9,344
R-O-W
Construction 517,000
Inspection 10,000
Total 656 0 536,344 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2611:prop 1B 656
2605:Gas Tax 536,344
Total 656 0 536,344 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Bus Shelters and Other Bus Stop Improvements Code No. 114 .
Account No. 8071 .
Location Map
Various Locations(to be determined)
Project Description
The construction of bus stop improvements at various locations. Current year costs are for the relocation of
the bus stop at the Community Center and the installation of five (5) new bus stop shelters at various
locations. Future funding is for other Bus Stop improvements which may be required in the next few years.
Project Funding Schedule Total Cost: $95,798 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 26,060 69,738
Inspection
Total 26,060 0 69,738 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
5000 Transit 26,060 69,738
Undetermined
Total 26,060 0 69,738 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: North Hills Parkway . Code No. 115 .
Account No. 8061 .
Location Map
A slp \\tt
[ ,.$
'V
Q.001 iiirii���i�iiiiiiiiiifii�liiiiiiiiiii4
iiii fries.
H�����/
... 0041
OEMI Z
r.rY liMiiif
il PROJECT r.a.. or — . .
lirlir
.f.■
/ _,..----- -_...-----.--- IX _. . . iimigtriMI
1 1 nal
1 1111111•
I
I }I = 1 i ; ._.. =- -_-
Ih-- w
• i 111 Mas ilia:, ■ ! =MO IX
(_7 _I P -
Project Description
The construction of a new east-west arterial street north of Casey Road. The westerly end of the street is
proposed to connect to Los Angeles Avenue, via a future railroad undercrossing, at a point west of Butter
Creek Road. Initially, the easterly terminus of this new street will be Spring Road with the potential to
continue east to a connection with the 23 Freeway North Alignment (Project 8045). The project includes
widening of Gabbert Road from the new street south to the railroad crossing. Segments of this project will
be constructed by developers (Tract 5147, Tract 5130, Tract 5045, TTM 5906, Hitch Ranch, Centex and
the studio project) and other segments funded by the Citywide Traffic Mitigation Fund.
Project Funding Schedule Total Cost: $3,234,812
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20-21 FY 21/22
Design 1,028,172 960,973
R-O-W 886,409
Construction 59,258 300,000
Inspection
Total 1,973,839 0 1,260,973 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY Y 18/19 FY 19/20 FY 20/21 FY 21/22
2002:Traf Mit 1,573,628 1,260,973
2610:TCF 400,211
Total 1,973,839 0 1,260,973 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: High Street Streetscape Code No. 116 .
Account No. 5056 .
Location Map
imm■immEHNEI ■INIEl MEL E ■•■■■N 1 1
Charles St Charles St
W PRO ECT E
c
a " a
g N >v
I' ! .4 0° r
HIGH ST a
I II II I I I IQI IIII IIII I III III I IIII IIII1111111IIII III III IIII1111111IIII IIIII IIII I III IIIII IIIIIIII IIII Ilil III III I I111111I Ili11111111I II I II I I III III IIIIIIII1111111I I II IIII IIII II I II II IIIII I II II I I I I I I I II I IIIIII IIII I II I I IIIIII I I III III I IIIIIIIII II I I I I I I II IIIIII III
S.P. T
Project Description
Development of a project to make possible modifications and improvements to the streetscape and parking
along High Street. When and if a project is deemed feasible, further design and construction expenditures
will be budgeted.
Project Funding Schedule Total Cost:
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: 23 FWY North Alignment . Code No. 117 .
Account No. 8045.
Location Map
--\'''' • *-—7-7- ,.:: i :::'Jig; \t;\
...,
_ ,_ _ _. ,,, ,,,,„,...,.... ,
. . ........ 0,„ . —
h �N Y,•r
� tS
PROJECT ;v,,,�• \ .0 v. =-z
.� _.a-_,,,_ r '1':/ �/Iii. �j� •�,,
Mil t �,J t11N•
ry e•.,,,i I 04yy4 i
T1 �. � `4-
`4 �* j y. 1 �����\\\\\\\\\\
jf t; • �i \\\\\\
i1` —, ��%�Ji/i. tl il,• ,
,,,,,,,,,.,„, ,, 1----'- ,V4',..,,'''.
1 1N 1..11:111.1.111 IIunf III ic�1�. , /b�'J'•� ( �``��4
Project Description
Construction of a roadway from the SR-118 Freeway to Broadway with a connection to North Hills
Parkway at Spring Road. Initial costs are for the development of design concepts.
Project Funding Schedule Total Cost: $214,489
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 192,201 22,288
R-O-W
Construction
Inspection
Total 192,201 22,288 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2002:Trf.Mit. 192,201 22,288
Undetermined
Total 192,201 22,288 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: _ Wicks Road Sidewalk and Asphalt Overlay . Code No. 118 .
Account No.
Location Map
-...-,11LI ., f L
f i
i
_i_i_n_
AO
e/ 1-- \
1! TR 51130
PROJECT r' '
VilwpAiThltripiiiit
Casey Rd ♦ �'
Mk
Sri
41
lIidi !Ltt st , x_-__ in
H I FILM IITEI ; rill
Project Description
Construction of a sidewalk on the south side of Wicks Road and asphalt overlay from Walnut Canyon
Road to the end.
Project Funding Schedule Total Cost: Developer .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Metrolink South Parking Lot South Entry . Code No. 119 .
Account No. 8056 .
Location Map
—
r 1—I
n- . _ ( I 1 t ; Ll_
)i _ , 4 High St
MetrolinkiAmtrak Station
PROJECT SITE
''..4.1%4N '
Poindexter Ave I ___
—
First St
1n
/
v
m
t---� 1 i
Project Description
Relocation of the entry to the south Metrolink parking lot to a point on First Street east of Moorpark
Avenue.
Project Funding Schedule Total Cost: $1,535,777
Prior Yrs FY 15/16 FY 16/1.7 FY 17/18 FY 18/19 ' FY 19/20 FY 20/21 FY 21/22
Design 34,943 45,107
R-O-W 587,767 510,301
Construction 27,927 314,732
Inspection 15,000
Total 650,637 885,140 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM 336,971 151,228
2603:LTF 33,983
2604:CMAQ 72,476 509,119
4004: Special 185,000
5000:TDA 22,207 224,793
Total 650,637 885,140 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Gabbert Road Rail Crossing Improvements Code No. 120 .
Account No. ---- .
Location Map
A
PROJECT
cr
Nnol
11111IIIIIIIIIIIIIIII
111111111111111111111111gill.IIIIIIIIIIIIIIIII
,,IIIIIuIuIIuIIIIIIIIIIIIIIIIIIIIIuIII ___
plllllllllllllll<ll
1
11111111
IIIIIIIIIIIIIIIIIIIIIpItIoIIIlInIIdIIIeiIX
tle`11AVI011111
a.
a
Project Description
The construction of the street widening and related improvements on Gabbert Road at the rail crossing will
be undertaken by AB Properties (Tract 5147) per the conditions of their Tract Map and Development
Agreement requirements. There will be no City funds used for the construction of these improvements. The
project is shown here in order to identify projects which are implementing components of the Circulation
Element of the General Plan.
Project Funding Schedule Total Cost: Developer .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Developer
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: High Street WestCode No. 121 .
Account No. ---- .
Location Map
1
PROJECT - o rf
O
5-
1.-
g
< A
7��������������/////////l//lf/l!� HIGH ST N
111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111111 IIIIIIIIIIIIII 1111IIIIIIIIII IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII
S.P.R.R.
Project Description
Widening, realignment, and reconstruction of High Street west of Moorpark Avenue. The scope of work
would include a study to determine the precise alignment of this roadway project, as well as the westerly
extension of the project to serve the properties in this area(Hitch Ranch).
Project Funding Schedule Total Cost: $430,000
Prior Yrs FY 15/16 FY 16/17 ' FY 17/18 FY 18/19 FY 19/20 FY 20/2.1 FY 21/22
Design 30,000
R-O-W 80,000
Construction 300,000
Inspection 20,000
Total 0 0 0 110,000 320,000 0 1 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 110,000 320,000
Total 0 0 0 110,000 320,000 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Railroad Crossing Improvements at Arroyo Drive . Code No. 122 .
Account No. 8080 .
Location Map
x � wwt.a �Campus L '1 1 Park `ti`-'Ji' Dr
4'
f4( lamas 111 PROJECT
Cow
aftsisal non
1:17
SPRY i' sit •, -\ 1111111.10
11116 Ow
1.44
Project Description
The construction of street widening and other improvements on Arroyo Drive at the railroad crossing east
of Collins Drive. PUC and Caltrans have proposed funding through Section 130 for this project.
Project Funding Schedule Total Cost: 1,000,000
Prior Yrs FY 15/16 FY 16/17 I FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 1,000,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 1,000,000
Total 0 0 0 1,000,000 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Moorpark Avenue Widening Project . Code No. 123 .
Account No. 8040 .
Location Map
11R-11 111:1
PROJECT SITE most11
ps ■ U1L ' if
L En t ! j
am: =,ami
=x COM =1 1 1 �I
MK AIMa> ��I
Project Description
Widening of Moorpark Avenue to add a southbound lane along the west side from Casey Road to Third
Street. Includes street realignment at First Street and Poindexter Avenue (Prior Project 8057) and rail
crossing improvements (Prior Project 8038). Prior year appropriations for those projects have been returned
to funding sources. Prior to commencing work on this project, the General Plan and Circulation Element
must be updated to identify the second southbound lane. Therefore, funding has been moved to Future
Years beyond the FY 15/16 CIP budget.
Project Funding Schedule Total Cost: $1,745,620.
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 262,920 370,755
R-O-W 655,237 300,000
Construction 156,708
Inspection
Total 1,074,865 0 0 670,755 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2002:TM Fund 134,245 670,755
2501:LAOC 156,708
2902:MRA 783,912
Total 1,074,865 0 0 670,755 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Lengthen Curb Radii at Designated Intersections Code No. 124 .
Account No. ---- .
Location Map
Locations to be Determined
Project Description
This project constructs modifications to existing improvements on major arterials, including the State
Highways, to lengthen the curb radii at certain corners to facilitate turning movements and ease congestion.
Project Funding Schedule Total Cost: $300,000
Prior Yrs FY Y 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 50,000
R-O-W 100,000
Construction 150,000
Inspection
Total 0 0 0 0 50,000 100,000 150,000 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 50,000 100,000 150,000
Total 0 0 0 0 50,000 100,000 150,000 0
City of Moorpark
Capital Improvement Program
Project Name: Los Angeles Avenue Widening West of Tierra Rejada Road . Code No. 125
Account No. _ ---- .
Location Map
a.
Q
A
• ME Milli . ,
:
' ■II USIA
..yV�sya� 1p 0
PROJECT • UPI!• !UIW
!1=1
Project Description
The construction of street widening on Los Angeles Avenue west of Tierra Rejada Road, as a function of
the development of property in this area. This project is proposed to be funded by development. It is
shown here to reflect implementation of the Circulation Element of the Moorpark General Plan.
Project Funding Schedule Total Cost: Developer .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Casey Road Westerly Extension Code No. 126 .
Account No. ---- .
Location Map
Project Description
The Circulation Element of the Moorpark General Plan calls for the westerly extension of Casey Road to
connect to Gabbert Road. This future project is to be constructed by developers.
Project Funding Schedule Total Cost: Developer .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Developer
Funded
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name:_ Moorpark Avenue Left Turn Lane . Code No. 127 .
Account No. 8087 .
Location Map
1 _[_HARLES STREET
MOOR ARK
AVE
i
HIGH STREET
7
WiliallEr
_ _ ---
..icePROJECT
NORTH J
Project Description
This project will be incorporated into Metrolink's Sealed Corridor railroad crossing improvement project.
The improvements include revisions to the traffic signal to provide a protected left-turn phase for the
shared left and through northbound lane. Both sides of Moorpark Avenue will be widened to
accommodate a raised center median and will improve the intersection turning movements.
Project Funding Schedule Total Cost: $ 200,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 25,000
R-O-W 150,000
Construction 25,000
Inspection
Total 200,000 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2501:LA AOC 200,000
Total 200,000 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Asphalt Overlay on Spring Road, Princeton Avenue, Poindexter Avenue . Code No. 128 .
Account No. 8093
Location Map
1. - -I //// ri%Pr 0,:i
_.- 7,.c‘i--vA. ,'
r
witEner rar C r�qw _ _ i , Project i..
�tw. �- �f- _ illi Limits ---, \ Q
_i yG► _ =_- rL,7 t-j, � 1 y, —\3,\_:-A Project
1
_ J Limits
W i ;,• " '_'`'
:q_...,
Project .11111! !
Limits — �`� k'A(p!�
c
,__,,1
1 _____-- _ ---0,.
,..., . ..„-----
_____
- ..._ ,...,'- _. [ .
k ceenmerce A 1 Con•or! — _—i __--/
Project Description
Pavement rehabilitation on Spring Road (Tierra Rejada Road to Monte Vista Nature Park); Princeton
Avenue (Condor Drive to Campus Park Drive); Poindexter Avenue (N. Commerce Avenue to Gabbert
Road); and Gabbert Road (Poindexter Avenue to a point approximately 200-ft south of Poindexter
Avenue.)
Project Funding Schedule Total Cost: $ 770,0011
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 50,000
R-O-W
Construction 670,000
Inspection 50,000 _
Total 0 769,800 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2609:Grants 637,416
2603:Local 132,384
Total 0 769,800 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name:_Metrolink North Parking Lot Expansion Code No. 129 .
Account No. 8063 .
Location Map
197 313 233 1]! 273 263 297 111 349 3!5 Jm 411
L
f {I1r.l 1' 11i Vli
PROJECT
3Mur.
Project Description
Convert vacant lot (approximately 150-ft wide x 120-ft long) west of Metrolink North Parking Lot into a
formal parking lot, adding an estimated 35-40 parking stalls. The project also includes slurry sealing the
existing North Parking Lot(owned by VCTC).
Project Funding Schedule Total Cost: $ 377,037 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 65,000 26,700
R-O-W
Construction 140,000 130,337
Inspection 4,000 11,000
Total 0 209,000 168,037 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM 60,000
2611:Prop 1B 149,000 168,037
Total 0 209,000 168,037 0 0 0 0 0
Trails & Walkways
City of Moorpark
Capital Improvement Program
Project Name: Sidewalk Reconstruction Project . Code No. 201 .
Account No. 8001 .
Location Map
Various Locations (to be determined)
Project Description
Replacement of sidewalks, curbs, and gutter at various locations. Recurring project each fiscal year with an
estimated cost of$50,000/Year. Effective FY 2016/2017, CIP 8097 will replace 8001.
Project Funding Schedule Total Cost: $124,539
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 124,539
Inspection
Total 124,529 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17'18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2605:Gas Tax
2603:TDA 124,539
Art. 8
Total 124,539 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Bicycle/Pedestrian Facility Improvement Project Code No. 202 .
Account No. ----
Location Map
The Location of Future Projects
To Be Determined
Project Description
The construction of bicycle and/or pedestrian facility improvements, partially funded by a TDA Article 3
State grant [SB-821]. As projects are approved and added to the Budget, a new project will be added to the
CIA.
Project Funding Schedule Total Cost: $280,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 40,000 40,000 40,000 40,000 40,000 40,000 40,000
Inspection
Total 0 40,000 40,000 40,000 40,000 40,000 40,000 40,000
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2603: LTF 20,000 20,000 20,000 20,000 20,000 20,000 20,000
2602:TDA-3 20,000 20,000 20,000 20,000 20,000 20,000 20,000
Total 0 40,000 40,000 40,000 40,000 40,000 40,000 40,000
City of Moorpark
Capital Improvement Program
Project Name: Arroyo Simi Trail Improvements . Code No. 203
Account No. 8035
Location Map
Q r ' I �` /
MOORP•RK 1� 'tc " ., ��''�� _ __ w
.‘f %1‘ M. •) . a
.t. } `,. '` pi , !- +� MOORPA•K
ri„-ii.4
it_rair . ,
______.._______irl
OPPPIFI
i mil
Igt*
. ,, 0.--1. 7,. , litirr
�� � ter" ,
�� I17F1 `i" ••ARK " :fir" 1r — Mt(:ain.. , .. T ��, ice" 9�a rArrE"14,�. � a 9'021 �sr
,dW � 1
� �..* ,,.,,., .,- w i y-� , t X9302 _/ �: art
pmert
kr-Fi4 11r-,. , , err' ' I..;' ' ill
.i,.......ct.o. ,...4.....7.44t. . ..,, ,vg .0.1 ,,,,..,,,, ., i , „•,- } dr, .
)7,.
Project Description
Prior Year costs are for the Arroyo Simi Trail Feasibility Study. That study evaluated options for the
possible future development of a trail system, generally along the levee road of the Arroyo Simi, from the
westerly City Limit easterly to Madera Road in the City of Simi Valley. Future expenses for projects to
implement segments of the trail system are yet to be determined. Ramps from the Spring Road bridge
down to the proposed trail are included in the design for future channel improvements.
Project Funding Schedule Total Cost: $150,000
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 150,000
R-O-W
Construction
Inspection
Total 150,000 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM 0
2603:LTF 30,000
2604: CMAQ 120,000
Undetermined
Total 150,000 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Drain No. 2 Trail Code No. 204 .
Account No. 8059 .
Location Map
Campus Park Dr
t
Pad E. ME
M�INtEAI
/i/
Park
lit;
it PROJECT
FR"
118
' s
yam` �a •
t' 41 II�W Mew hik
Project Description
This project is to provide for the construction of a trail extending from the east end of Campus Park Drive,
across the watercourse referred to as Drain No. 2, then south under the freeway through an existing access
tunnel to Arroyo Drive. Prior year costs were for the development of a feasibility study to determine access
and design requirements. Review and finalization of the study has been placed on hold. Future costs are for
the acquisition of those access rights, preparation of the design and construction of the project. Cost
estimates for this project have not yet been developed and the funding for future year projects has not yet
been determined.
Project Funding Schedule Total Cost: $28,554 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 28,554
R-O-W
Construction
Inspection
Total 28,554 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001: TSM 28,554
Undetermined
Total 28,554 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Sidewalk& Bicycle Lane at AVRC Code No. 205
Account No.
Location Map
SII
dry
t15, Arroyo
Siatf
Project Site
ARROYO VISTA
c01`,iMui j TY
PARK
North
Project Description
Build a 1,200 foot sidewalk and bicycle path connecting Arroyo Vista Recreation Center's existing sidewalk
to the Pedestrian Bridge. This project is budgeted and administered by the Parks, Recreation and
Community Services Department(Project 7713).
Project Funding Schedule Total Cost: $618,766
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 43,766
R-O-W
Construction 575,000
Inspection
Total 0 618,766 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM 552,766
2602:TDA 66,000
Total 0 618,766 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Walnut Canyon Road Westside Championship Drive to Peter's Driveway. Code No. 206
Account No. ---- .
Location Map
CHAMPIONSHIP DRIB s,
+ 1 Project Site
r y fti
5� tii ytiti
1
II SPRING .
r •ROAD
•
Project Description
Construct a five (5) foot P.C.C. sidewalk from Championship Drive to Peters' driveway along the existing
multi-purpose trail.
Project Funding Schedule Total Cost: $75,000
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 75,000
Inspection
Total 0 0 0 75,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM 75,000
Total 0 0 0 75,000 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Civic Center Pedestrian Access and Bus Stop Improvement . Code No. 207 .
Account No. ----
Location Map
1111
Casey oa icks Roa.
N.
111 1111
Moorpark Ave Everett Street
Civic Center - -
QCharles Street
lainut Street
PROJECT
I t.
Project Description
Construct sidewalk, bus turn-out with shelter, and ADA ramps connecting the library to the Active Adult and
Community Center. This project is budgeted and administered by the Parks, Recreation and Community
Services Department (Project 7032).
Project Funding Schedule Total Cost: $200,000
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20 21 FY 21/22
Design 34,500
R-O-W
Construction 165,500
Inspection
Total 0 34,500 165,500 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2602: Art 3 17,250 65,500
5000: Art 8C 20,000
2001:TSM 17,250 80,000
Total 0 34,500 165,500 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Arroyo Drive Bike/Ped Project . Code No. 208
Account No. 8095
Location Map
r
Campus Park Dr
Salt 311111 I
a _
11111111111I. ♦ t�
IMP
anwwa
IMLIirainey
118
f .�►� 3�k, `-;��•� •�..� VP, • PROJECT
•
• - om, •
Project Description
Construction of a sidewalk on the south side of Arroyo Drive from the main entrance of Villa del Arroyo
Mobile Home Park to the east end of the Park.
Project Funding Schedule Total Cost: $200,000
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 15,000
R-O-W
Construction 170,000
Inspection 15,000
Total 0 0 200,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM 100,000
2602:TDA 100,000
Total 0 0 200,000 0 0 0 0 0
Traffic Signals
City of Moorpark
Capital Improvement Program
Project Name: . Code No. 301 .
Account No. _----
Location Map
Not Assigned
Project Description
Project Funding Schedule Total Cost:
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Traffic Signal: Los Angeles Avenue and Shasta Avenue . Code No. 302 .
Account No. 8058 .
Location Map
c� co
_ o _
a e,
3 •�
Everest Ave
IN.
Los Angeles Ave (SR118)
\11 r
PROJECT
a
Project Description
Developer for Pacific Communities (TR5053) to construct the traffic signal at the intersection of Los
Angeles Avenue and Shasta Avenue.
Project Funding Schedule Total Cost: Developer .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection •
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY Y 20/21 FY 21/22
Developer
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: SR-118/Collins Drive Eastbound On/Off-Ramp Signalization and Striping Code No. 303 .
Modification. Account No. 8077 .
Location Map
f
Xr `
0 ;sq,lit
6127/J
11
PROJECT ti,,
11
. \ . 'f.
40, ,
Project Description
This project involves signalizing the eastbound SR-118 on/off-ramps intersection and converting the
westbound through lane to a westbound through lane and a right turn lane, modifying the striping to provide
two left turn lanes from the off ramp to northbound Collins Drive based on Caltrans' preliminary design.
Project Funding Schedule Total Cost: 5175,000
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 175,000
Inspection
Total 0 0 175,000 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2001:TSM
2501: LA AOC
2604: CMAQ
Other Sources 175,000
Total 0 0 175,000 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: . Code No. 304 .
Account No.
Not Assigned
Project Description
Project Funding Schedule Total Cost:
Prior Yrs FY 15/16 FY 16/17 FY Y 17/18 FY Y 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY11/22
Fund 4000
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Traffic Signal: Los Angeles Avenue and Millard Street . Code No. 305 .
Account No. 8013 .
Location Map
— 3
yMoonson Ct Sherman iewo
l
Los Angeles Ave (SR118)
-n
PROD ECT - Millard St
#{lestcoti Ct y
I 1 I
LJ
Project Description
The Los Angeles Avenue Widening Project between Moorpark Avenue and Spring Road [Project 106]
includes the construction of a traffic signal at the intersection of Los Angeles Avenue and Millard Street.
This project will be partially funded by the developer of property south of the intersection [Shea Homes —
Tentative Tract 5133].
Project Funding Schedule Total Cost: See # 106 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY Y 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Fund 2501
Fund 2604
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Traffic Signal: Los Angeles Avenue West of Butter Creek Road . Code No. 306 .
Account No. 8061 .
Location Map
N. . iir, ot
ririrrfr��if���i/fi / iri iir7////r
i Ni�,$P/�// —a— r
r R �/ rim _
"��/ wore......., I.
• .w...w' _w bl
i/ t I�
w �! 11111WOMNINNI Wilt
w'w WIN
nor
I 1111.118
11 j
I 1111.1111
1":11871-
I ti 1 I I w sirs ""\ 11 . _w '-
7,_____
a
wwR
51�S �;
� �r �• : �. II
. —v.3 us MEMwwr. —KY'
swim ".y ..� 6..., 1
�a J ( � �eMair - • ww
PROJECT
Project Description
This project is for the construction of a traffic signal at the future intersection of Los Angeles Avenue and
the westerly terminus of the North Hills Parkway [see Project 115].
Project Funding Schedule Total Cost: See#115 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Total 0 0 0 0 0 0 i 0 0
Medians & Parkways
City of Moorpark
Capital Improvement Program
Project Name: Los Angeles Avenue Medians . Code No. 401
Account No. 8047
Location Map
F*~
.00
Y r•nw
I am 111 ii WI fil 111 14" Ill '
\1
111 ram
or ■ !. jr
um . '—'dY
■ ' 11j�: ■ II �. r� N .. �■ .. ,,•
I }I.II Li I - ` :• -- - r
11
LOS ANGELES '1■ + �! �w oft.. I/
v w
Ni, s 4 A
..,' ■ w. it
� ■ ■■ ANon...' '
_ I ! j PROJECT m-1 _ , ■ NIIIIMEIr
If
Project Description
The construction of raised landscaped medians on Los Angeles Avenue (SR-118), from the SR-23 freeway
westerly to Tierra Rejada Road. Phase 1 will include that area east of Spring Road to the SR-23. Phase 2
will be incorporated into the Los Angeles Avenue Widening project from Spring Road to Moorpark
Avenue.
Project Funding Schedule Total Cost: 351,609
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 275,695 75,914
R-O-W
Construction
Inspection
Total 275,695 75,914 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2501: L A AOC 275,695 75,914
Total 275,695 75,914 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Medians: Spring Road . Code No. 402 .
Account No. 8026 .
Location Map
iii,Lili LILIU-4-'•
will"
pc 111111
MI (
11111111 1 4'r /11-'
11111111 I%
11111111 ;%
11111111
11111111
1111/111 1
_y-
i�
Liall i%
11111111 PROJECT
11111111 i%
1i1i1111 Ifi
11111N11 .j g ..,..,,.
f 7 i
7174!II
Los Angebs Avs(SR11 )
Project Description
The Spring Road Widening Project [Project 104] includes the construction of raised, landscaped medians
between Los Angeles Avenue and Flinn Avenue.
Project Funding Schedule Total Cost: See No. 104 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Fund 2501
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Code No. 403 .
Account No.
Location Map
Not Assigned.
Project Description
Project Funding Schedule Total Cost:
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 I FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs I FY 15/16 FY 16/17 FY 17/18 FY 1.8/19 FY 19/20 FY Y 20/21 FY 21/22
2502: STR AOC
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Poindexter Avenue parkways . Code No. 404 .
Account No. 8048 .
Location Map
�a
��� PROJECT Union Pacif c SCRRA —N.f
11111111 I IIIIIIIIIIIIIIIII 1111111111111011111111111111111111111111 IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIaIIII11111I11111111�11IIIIIIIIIIIIIIIIIII IIII^Illllllr
I e
* �_ •U•MED) 111111
IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIllllvel 111111
poinde eC A --� tib■■s> N
IIIIIIIIIIIIIIIIIIIIIIIIiII
111111 1p�
/IF `— Ave PINIII�:TiYJII t
Project Description
The installation of trees and shrubs, with irrigation, along the north side of the street east of Gabbert Road,
on railroad property. This project will require the approval by the Southern California Regional Rail
Authority [SCRRA] for the easterly portion, and the Union Pacific Railroad [UP] for the westerly portion.
A funding source for future maintenance costs has not yet been determined.
Project Funding Schedule Total Cost: $115,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 10,000
R-O-W
Construction 100,000
Inspection 5,000
Total 0 0 0 115,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2150:Trees 115,000
Total 0 0 0 115,000 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Freeway Landscaping at the Tierra Rejada Road Interchange . Code No. 405
Account No. ----
Location Map
\ vi, . iiimblida
tsar
o e ,\1
.00a 1 ... PROJECT
lel
4,c - 1\1
fin; 4
T
c
b
r
r
m
0
Project Description
This project calls for the installation of irrigation and landscaping within the on/off ramp areas at the Tierra
Rejada Road / State Route 23 Freeway interchange. This project will require a Cooperative Agreement
with Caltrans related to City funding of both construction and future maintenance of this landscaping. A
project cost estimate has not yet been developed and the funding source has not yet been determined. In
2008, the City funded the planting of over 100 oak trees in the ramp areas during the SR-23 Freeway
Widening project.
Project Funding Schedule Total Cost: 5296,281
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W 50,000
Construction 46,281 200,000
Inspection
Total 46,281 0 50,000 200,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 50,000 200,000
2150 trees 46,281
Total 46,281 0 50,000 200,000 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: . Code No. 406 .
Account No. ---- .
Location Map
Not Assigned.
Project Description
Project Funding Schedule Total Cost: $
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY Y 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined.
Undetermined
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Code No. 407 .
Account No. ---- .
Location Map
Not Assigned
Project Description
Project Funding Schedule Total Cost:
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY Y 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Peach Hill Parkways . Code No. 408 .
Account No. ---- .
Location Map
0 PROJECT Ill
m s gdI_na
A�
Bodega PI < Silver Oak Ln
ran -9 Ll
o
A
c
Peach Hill Rd en
3
o
xi
- Laurelhurst Rd a
AMU 4111b, i
Project Description
Installation of Parkway Landscaping on both sides of the "east-west" segment of Peach Hill Road between
Mesa Verde Drive and Rolling Knoll Road.
Project Funding Schedule Total Cost: $53,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 1,000
R-O-W
Construction 50,000
Inspection 2,000
Total 0 0 0 1,000 52,000 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 1,000 52,000
Total 0 0 0 1,000 52,000 0 0 0
Storm Drains
City of Moorpark
Capital Improvement Program
Project Name: Master Plan of Drainage Update Code No. 501 .
Account No. 8088 .
Location Map
Entire City
Project Description
This project is to prepare an update to the 1995 Citywide Master Plan of Drainage. This project will be
undertaken upon completion of the Letter of Map Revisions to the Digital Flood Insurance Rate Maps.
Project Funding Schedule Total Cost: $150,00(1 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design 150,000
R-O-W
Construction
Inspection
Total 0 150,000 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
2800: 150,000
Endowment
Total 0 150,000 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Gabbert Canyon/Walnut Canyon Improvements . Code No. 502 .
Account No. ---- .
Location Map
Walnut�r,,,4,
Canyon ■
Drain
t. 6M • •• •�,its•••
r.
eif
_ ' l
• e •Il P L. ti I Pr -'-'-%4-i r,•.
• •', 1 --.
Gabbert t� -.1...,,, �• _� j -.
• Canyon �.. e ,�.' w "`' ...
•Drain :). -0,2'-- rw� —*". .- .• �_s
K -T
• Irma.
Project Description
The existing Ventura County Watershed Protection District [VCWPD] facilities within the Gabbert Canyon
and Walnut Creek watersheds are inadequate. This project calls for the construction of new detention,
diversion and capacity enhancement improvements to those existing facilities. The 2006 cost estimate for
those improvements was estimated to be $12,000,000 plus financing costs. No implementation or
financing plan has yet been developed. Some of the required improvements have been, or are planned to
be, constructed by land development projects within this watershed.
Project Funding Schedule Total Cost: $15,000,000_.
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 7,500,000 7,500,000
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 7,500,000 7,500,000
Total 0 0 0 0 0 0 7,500,000 7,500,000
City of Moorpark
Capital Improvement Program
Project Name: Shasta Drain Code No. 503
Account No. ---- .
Location Map
l l If I l .. I
•■
INN
..� � t
NE
mi .▪En -NM
■�� IIIU
•
-N--
: l l l l
—e Existing rain • • • •
■
• Proect: • • • •
Everest
_! Ave
••
• Los Angeles Ave(SR118)
• 1 I \
Project Description
Construction of a storm drain to serve the residential area north of the intersection of Los Angeles Avenue
and Shasta Avenue, as identified in the City's Master Plan of Drainage. No funding source has been
identified for this project. The 1995 cost estimate for this project was $188,000. However, the full scope
and cost of this project has never been determined.
Project Funding Schedule Total Cost: $800,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction 800,000
Inspection
Total 0 0 0 0 800,000 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 800,000
Total 0 0 0 0 800,000 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Millard Drain Code No. 504 .
Account No. 8065 .
Location Map
1
•
•
•
aExisting Drain: • • • • »� Esther Ave
Project: . . . •
LL
•
•
Moonsong Ct • • • Sherman Ave
AJ _ _ _ Lr
J11 • •
• 1 ••.
•■ ■ ■•
Los Angeles Ave(SR118) •
• •
—
Project Description
Construction of a storm drain similar in function to that identified in the City's Master Plan of Drainage as
the "Freemont Drain", located north of the intersection of Los Angeles Avenue and Millard Street. The
current design concept for this project anticipates a storm drain running easterly along the north side of Los
Angeles Avenue from the existing Los Angeles Avenue culvert to Millard Street, and then northerly along
the east side of Millard Street for a short distance.
Project Funding Schedule Total Cost: $250,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/1.9 FY 19/20 FY 20/21 FY 21/22
Design 25,000
R-O-W
Construction 200,000
Inspection 25,000
Total 0 0 0 250,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY Y 21/22
Undetermined 250,000
Total 0 0 0 250,000 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Villa Del Arroyo Drain Code No. 505 .
Account No. ---- .
Location Map
tad a!y.
lir It lit on i
=WU: [_4/
4"-0.1. 110-1"
Iwo ono
Existing.42".Drain '
(Scope of.project yeti CMP
To be determined) ' `.
04.18.
Yo Slav .
Project Description
There is a culvert under Arroyo Drive at the entrance to the Villa Del Arroyo Mobile Home Park, which
connects to a storm drain pipe owned by the Mobile Home Park. This "private" drain line extends southerly
to the arroyo. It has been determined that the function of that storm drain is impaired and that remedial
action must be taken in order to provide adequate drainage for both the City street and the Mobile Home
Park. Consistent with the provisions of a Settlement Agreement between the City and the Mobile Home
Park, the property owner is required to take corrective action to remedy this problem.
Project Funding Schedule Total Cost: By Property Owner .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Miscellaneous Drainage Improvements Code No. 506 .
Account No. ---- .
Location Map
Location of Improvements To Be Determined
Project Description
This project is for the construction of miscellaneous drainage improvements, throughout the City, as
required.
Project Funding Schedule Total Cost: 5200,000 .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 15/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 200,000 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Undetermined 200,000
Total 0 0 0 200,000 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: Arroyo Simi Channel Improvements . Code No. 507 .
Account No. ----
location Map
PfdariAl Iff=_-
II.,-__----Apj .---2.-- --.. — .tw--- • .......-.. - - ---_--._
/ ----'----1"1110M./11110*, 444\whin.--
I.I I I I 0 1!El 1 1741-.0 pi/ AtirrtM-'- \ k, I* 1-11111
R�
jjaillkil-71,,m4Arilifk,i.7,,-14,Atr ilk --
/ i.„.__. fir7....,, ,, 6. 0, 2..L.::.: 1-.161._'.41 400.1:41111.1117 . _._ .Airiffia
11111
ifoo iiN .11P i:':':.'
t:if ,.ffl.n= = `Iii'Tali' AJ..,„.*
=� ii; jriJ .Oa Arro, o Simi Pro'ect
,7
•
:_init--."\ \
� ) _� dm __
: , .iz 416:111,11..,;‘.. • . ,. _ � N
::)-et iii
All P-
ltii I
, t.,,. ,... ..,,,,..
.,., ,,,, . ,,..,,,,,,,,,.., .. ,.: :,,,„„„:„....,...4,,k „:,%,,;„,,,. ,
in
;:r-2.,...--- • • _ t,^„mai_,LL —l�-\ A,,,,., � ' all
Project Description
A number of projects, to be undertaken by the Ventura County Watershed Protection Agency, to construct
improvements to the Arroyo Simi to render it capable of containing flows from a 100 year storm event, in a
manner satisfactory to the Federal Emergency Management Agency [FEMA]. When those projects are
completed, revisions to the FEMA flood zone maps will be processed to remove as many areas as possible
from flood zones.
Project Funding Schedule Total Cost: by VCVVPD .
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
Project Name: GIS Storm Drain Layer . Code No. 508
Account No. ---- .
Location Map
Entire City
Project Description
This project is to create a storm drain layer in the City's GIS. The storm drain layer will include a map of
the City's storm drain pipes, channels, catch basins, inlets, and outlets as well as data for each element.
This project is funded by the Countywide Stormwater Management Project to consolidate all storm drain
systems within Ventura County in GIS.
Project Funding Schedule Total Cost:
Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Design
R-O-W
Construction
Inspection
Total 0 0 0 0 0 0 0 0
Funding Sources
Source Prior Yrs FY 15/16 FY 16/17 FY 17/18 FY 18/19 FY 19/20 FY 20/21 FY 21/22
Total 0 0 0 0 0 0 0 0
City of Moorpark
Capital Improvement Program
C. Program Expenditure Summaries
• Total Program Project Costs: Listed By Fiscal Year C-3
• FY 2015/16 Total: Spread to Funding Source C-7
• Total Program {All Seven Years}: Spread to Funding Sources C-11
Total Program Project Costs
Listed by Fiscal Year
^• � N oo M co O O O O O r
N I--' ylbo
O .. b+ cose)O .6 8 .. ^ 40 b pL 8 O ,=,
• O p�O�j' O O2f v.f O 8 O 8 O O
N 0. VS r- N C [^ v1 f Oo O �O M N N N
N O'
O I.
VD M
O O O O O O O O Q O O O O O O O O O O O O co O o 0 0 o O C o O h6 O O O O O C O
_ O o
N O O O O
} C "r ...r
O
V.
aO O O O O O O O O O O O O O O O O O O O O O O O O O O OC O Q O O O O O O O pO
N O �{
Vi
ON O O O O O O O O O O O O O O O O O O O O O O O O O O O O 0 o O O O O O O O O O O
,-.5,.„
O O
O o
_j OC7.
O
- O § O O O O O O c O 0 0 0 0 0 0 0 0 0 0 § 0 0 § 0 0 0 0 0 o O § O O O O co O O C
i' - '�,,.� 'tel n -r
°.o O § 0 0 0 0 § O O A 0 0 0 0 O O O O O O § § O O O O O O 'C O § O O O § O O O pO
" —
enN
f•-•
0 0 0 0 § 0 0 0 0 0 ry o 3 o en 0 0 o O o 0 0 o O o 0 o 0 o O o § c o 0 o Q Q Q e
v i eg g g .°^g ^TS 25 vii
c„ o;, -I-
I--
so
r
h eOMn 0 0 O� o O o 0 0 0 0 0 0 00 o O o 0 0 0 0 0 0 o Q Q o § o o s o Q o o so
} Z85 vni c to00 .d fPe l p00 Lhoa ppb 000 xr� epi
ttoo
Vl 00 4--.
',74.
00 [� N T �D T
VD CO
00
N O O eV -4 0 O .. g § Q O O r O O O O O §
O C .0 O $ a O O O O O r,f
v. 00 n b �
r M � Fi N � b N O C 8 8 ry
se-t. M O N C
M N
0: M
It'
u
' F R , .
V
N Ts e
.a. _ • _ �Lp 6 O C) O
O y •7 1:4 ' 4 3
T p
con 3 .S o = as `t� = " .5 O -.' 0 bA > a Sc) =
� vz co a `4 •Q tR > ,� �� a esu °° yaJ p° va 3 = .M 0 ..� t = u
a C 3 0 . y � • � � b E ,g g c � 2° 5 3 � •5 '� N a �' - D > Q iu-
> _ 0 v 6 00 " z •2 ' ? c a X' DO a� g v v 0o X �° >yy rn c
>• > c. v 00 '0 = R a1 A.C. in 'w > :Q > O F m 3 °'
Q �_R 3 Q con ?? E to P.
c q�q v' TCJ �y >t ¢ Co ' G Q Q z pS�y+ .. E^ a °' as >
7 Z `-� "' G ' c0 y > �050 y _ im C ,��' •K u•� ON a=i y C A T ,�y "3 V c" N 'J _ Y
`� c � c 0n c1i Q d ari d Q.° X a,c=n .= `n .= 4 8 °' c" a Q >+ @' - E ; >0 3
2• 15' oC S' •Q�c ¢ a¢ a < a a g o neo o a� cen o y o °, as "Q ", 0 A R ami E S2
�° a ,� v, F1 ' cn 2 ..1 tv�Dopa p� -1 3 4 a 4 Z Z 3 2 CpC. rc`.�11 M2 .vv.1 C`� 210 � oV con o.. pd ce-1 app. C.0 Cd cCpn.
C) O Vi O u O a O O O O O O .-. N M a• h 0 F 07 Q N F.I. N N N N N N e°S fV F I N N N N N N
N 0 0 0 0 0 0 0 ? 0 0 O O 8p "r O O O p O p8 O O O C O
(�J p O O O O 6 -- O O O O O O eq
F O O Cr. O O O Cr O O O G C ° 01,
N vi h ul 4n O M O O O O O 'g �".
N .N. ONO _ N un N - O 0000 N N u b oho r
rCLVD
c __ -5.
a _
N O U. C C O C C O O O O O O O = 0 0 O O O O O O pCD coQ
Q O ^OJ' O
O ._
O G o -r
U. N n �'
v
O O O O O O O O O O O O O O O O 00 O O O O O O _
O -
O CD g
O O _
5.
u" r' r Hr` ri
O O O O O O O O O O O O O O O O O O O O O O O O O _
N
LL
Oh O O O .: c _ 0 0 0 0 0 0 0 0 O 0 0 0 0 0 0 0 0 O
O
00 O O
h N C O rl
›.r Yl op V)
W. 00 00 r rn
00 O O O O = _ 0 0 0 0 00 0 0 00 O d O O O O 00 O O 8
_ p O rr,
n` O CD
O O C O pO - a
.N• `a 55; O C 5,5
Li.. -. N 'eV N ?
M,
r- O O 00 O O O O OC C O O CO O O O O O O O O O O O O C .,r
0siDCD 0 O In
>.. - Ct
I.-
_ '
� , h r i
U. 00 - "l
T
VO O O O O O C V O O O O O O O R O O O O O O G =
•-- O - R
WI' ON v, en
N N 7.
U.
P
i O O O O un
00
eO 0 0 0 0 0 b O O O O O O O O C �n
} N r- Cr
0. h vD N Cr. T
ry N r C
M M s°
O
-5. A
O z1 1 °° ', r- -
sr,
' OO ' O O
00 00 00 00 N I I I I
pCD
I I I
00 00 00
1=J
CC
6°- 9 . o
F
o a z a
!n N U = V1
175.p�
N �..I CO
t0 = N
. C
00
c. � � - 3. Y p c T ° ,�
N $c �, Vim' ` g $ a � $ $ o�. ° 3 .9 t ° C
po-- ° pn_ �x .fib $S �n.fib y D d ��° inc.
o c Q odd ¢ a o 'o Q o o 00 I A° H
00', a � Z .] cnZ -1 -A d � rnZ0. (4 ZZa = 20cn2 > 2 0 D. ;,7
Al° QJ o Q E
a' ,, CSC N M !r V1 CD X 2 4 2 R 2 47 �l' ..cl) un N un h V1 V1 CD V'1
cd O F M M M M rn O O +� 0 0 0 0 0 0 0 0
FY 2015/16 Total Project Costs
Spread to Funding Sources
2015/16 to 2021/22 Capital Improvement Program
FY2015/16 Funding Sources
Account 1000 2000 2001 2002 2150 2501 2502 2602
Code Project Name Number General Fund Traf Safety TSM Traf M tigiation Trees L A AOC STR AOC TDA Art 3
Streets&Trails
101 Slurry Seal 8002
102 SR118/Collins Dr Rarrp/Sg Mod 8076
103 Walnut Canyon Rd S/W Imp
104 Spring Rd Widening 8026 949,442
105 Princeton Ave.Widening 8012 142,346
106 L A Ave: Spg to Mpk 8013 985,859
107 Spring/Charles Bus Turn-Out 8069
108 L A Ave:Shasta 8058 1,506,000
109 Underground Utility Projects
110 L A Ave Undergrounding 8051
111 Undrgrnd:New L A Ave 8066
112 Rail Xing:Spring Rd 8039 43,669
113 Arroyo Drive Overlay 8084
114 Bus Shelter Improvements 8071
115 North Hills Parkway 8061
116 high St.Streetscape/Parking 5056
117 North Extension of SR 23 8045 7%288
118 Wicks Road Sidewalk and Asphalt Overlay
119 Metrolink South Parking Lot Entry 8056 151,228
120 Gabbert Rd Rail Xing
121 high Street West
122 Arroyo Drive
123 Moorpark Ave Widening Proj 8040
124 Lengthen Curb Radii
125 L.A.Ave West ofT.RRd.
126 Casey Rd Ext.
127 Moorpark Ave Left Turn Lane 8087
128 OwlaySpang,Prtrceton pulrawte',Gabbet 8093
129 Metrolink North Parking Lot 8063 60,000
Sub-Total 0 0 211,228 22288 0 3,627,316 0 0
Trails&Walkways
201 Sidewalks 8001
202 Ped 1 Bicycle Project ---- 20,000
203 Arroyo Sim Trail Improvements 8035
204 Drain#2 Trail 8059
205 Sidew alk&Bicycle Lane at AV RC ---- 552,766 66,000
206 Peter's Driveway
207 Civic Center Fad&Bus Stop Imp ---- 17,250 17,250
208 Arroyo Drive Sidew alk
209 Sidewalks 8097
Sub-Total 0 0 570,016 0 0 0 0 103,250
Traffic Signals
301 Not Assigned
302 L A Ave/Shasta 8058 see 108
303 SR118/Collins Dr EJB Ramps 8077
304 Not Assigned
305 L A/Mllard 8013 see 106
306 L A/Near ButterCreek 8061 see 115
Sub-Total 0 0 0 0 0 0 0 0
Medians and Parkways
401 L A Ave Medain 8047 75,914
402 Spring Median 8026 see 104
403 Not Assigned
404 Poindexter Pkwy 8048
405 T R at Freeway
406 Not Assigned
407 City Entry Signs
408 Peach Fill Pkwy
Sub-Total C 0 0 0 0 75,914 0 0
Storm Drains
501 Master Drainage Study 8088
502 Gabert/Walnut
503 Shasta Drain
504 Mllard Drain 8065
505 Villa Del Arroyo Drain
506 Mac.lrrprovements
507 Arroyo Sim Channel trrpr.
508 GIS Storm Drain Layer
Sub-Total 0 0 0 0 0 0 0 0
Total 0 0 781,244 22,288 0 3,703,230 0 103,250
2015/16 to 2021/22 Capital Improvement Program
FY2015/16 Funding Sources
Account 2603 2604 2605 2609/2610
Code Project Name Number LTF Fed Grant Gas Tax State Grants Other Undetermined Total
Streets&Trails
101 Slurry Seal 8002 832,776 321,063 31,500 1,185,339
102 SR118/Collins Dr Ramp/Sig Mod 8076 0
103 Walnut Canyon Rd S/W imp ---- 500,000 500,000
104 Spring Rd Widening 8026 855,664
105 Princeton Ave.Widening 8012 142,346
106 L A Ave: Spg to Mpk 8013 796.770 1,782,629
107 Spring/Charles Bus Turn-Out 8069 0
108 L A Ave:Shasta 8058 1,216,032
109 Underground Utility Projects ---- 0
110 L A Ave Undergrounding 8051 0
111 Undrgrnd:New L A Ave 8066 0
112 Rail Xing:Spring Rd 8039 1,125,425
113 Arroyo Drive Overlay 8084 0
114 Bus Shelter Improvements 8071 0
115 North Hills Parkw ay 8061 0
116 High St.Streetscape/Parking 5056 0
117 North Extension of SR23 8045 22,288
118 Wicks load Sidew alk and Asphalt Overlay 0
119 Metrolink South Parking Lot Entry 8056 509,119 224,793 885,140
120 Gabbert Rd Rail Xing ---- 0
121 High Street West ---- 0
122 Railroad Grossing at Arroyo Drive ---- 0
123 Moorpark Ave Widening Roj 8040 0
124 Lengthen Curb Radii ---- 0
125 L.A.Ave West of T.R Rd. ---- 0
126 Casey Rd Westerly Ext. ---- 0
127 Moorpark Ave Left Turn Lane 8087 0
128 Overlay Spring,Princeton,Poindex 8093 132,584 637,416 770,000
129 Metrolink North Parking Lot 8063 149,000 209,000
Sub-Total 965,360 1,305,889 321,063 668,916 373,793 500,000 8,693,863
Trails&Walkways
201 Sidew alks 8001 0
202 Pad/Bicycle Project ---- 20,000 40,000
203 Arroyo Sim Trail Improvements 8035 0
204 Drain#2 Trail 8059 0
205 Sidew alk&Bicycle Lane at AVRC ---- 618,766
206 Peter's Driveway ---- 0
207 Civic Center Fad&Bus Stop Imp ---- 34,500
208 Arroyo Drive Sidew alk ---- 0
209 Sidew alks 8093 0
Sub-Total 20,000 0 0 0 0 0 693,266
Traffic Signals
301 Not Assigned ---- 0
302 L A Ave/Shasta 8058 0
303 SR118/Collins Dr EJB Ramps 8077 0
304 Not Assigned ---- 0
305 L A/!Allard 8013 0
306 L A/Near ButterCreek 8061 0
Sub-Total 0 0 0 0 0 0 0
Medians and Parkways
401 L A Ave Medain 8047 75,914
402 Spring Median 8026 0
403 Not Assigned ---- 0
404 Fbindexter Fkw y 8048 0
405 T Rat Freeway ---- 0
406 Not Assigned ---- 0
407 City Entry Signs ---- 0
408 Peach Hill Pkwy ---- 0
Sub-Total 0 0 0 0 0 0 75,914
Storm Drains
501 Master Drainage Study 8088 150,000 150,000
502 Gabert/Walnut ---- 0
503 Shasta Drain ---- 0
504 Millard Drain 8065 0
505 Villa Del Arroyo Drain ---- 0
506 Misc.Improvements ---- 0
507 Arroyo Sim Channel krpr. ---- 0
508 GIS Storm Drain Layer ---- 0
Sub-Total 0 0 0 0 150,000 0 150,000
Total 985,360 1,305,889 321,063 668,916 523,793 500,000 9,613,043
Total Program
FY 2015/16 through FY 2021/22
Spread to Funding Sources
2015/16 to 2021/22 Capital Improvement Program
Funding Sources Totals:FY 2015/16 thru FY 2021/22
Account 1000 2000 2001 2002 2150 2501 2502 2602
Code Project Name Number General Fund Traf Safety TSM Traf Mlti at1Qn Trees L A AOC STR AOC TDA Art 3
Streets&Trails
101 Slurry Seal 8002
102 SR118/Collins Dr Ramp/Sig Mod 8076
103 Walnut Canyon Rd S/W Imp —
104 Spring Rd Widening 8026 949.442
105 Princeton Ave.Widening 8012 4.955,102
106 L A Ave: Spg to Mpk 8013 985.859
107 Spring/Charles Bus Turn-Out 8069 150,000
108 L A Ave: Shasta 8058 1.506.000
109 Underground Utility Projects —
110 L A Ave Undergrounding 8051 299,761
111 Undrgmd: New L A Ave 8066 286 444,636
112 Rail)Ong:Spring Rd 8039 43,669
113 Arroyo Drive Overlay 8084
114 Bus Shelter Improvements 8071
115 North Hills Parkway 8061 1,260,973
116 High St. Streetscape/Parking 5056
117 North Extension of SR 23 8045 22,288
118 Wicks Road Sidewalk and Asphalt Overlay
119 Metrolink South Parking Lot Entry 8056 151,228
120 Gabbert Rd Rail)Ong
121 High Street West ---
122 Arroyo Drive ---
123 Moorpark Ave Widening Proj 8040 670,755
124 Lengthen Curb Radii
125 L.A.Ave West of T. R. Rd. —
126 Casey Rd Ext. —
127 Moorpark Ave Left Turn Lane 8087
128 Overlay Swim.Prirreron Pdrveaer.aC cabOerr 8092
129 Metrolink North Parking Lot 8063 60.000
Sub-Total 0 0 361,514 1,954,016 0 9,184,469 0 0
Trails&Walkways
201 Sidewalks 8001
202 Ped/Bicycle Project — 140.000
203 Arroyo Simi Trail Improvements 8035
204 Drain#2 Trail 8059
205 Sidewalk&Bicycle Lane at AVRC — 552.766 66,000
206 Peters Driveway — 75.000
207 Civic Center Ped&Bus Stop Imp — 97.250 82,750
208 Arroyo Drive Sidewalk — 100,000 100,000
209 Sidewalks 8093
Sub-Total 0 0 825,016 0 0 0 0 388,750
Traffic Signals
•
301 Not Assigned --
302 L A Ave/Shasta 8058 see 108
303 SR118/Collins Dr E/B Ramps 8077
304 Not Assigned
305 L A/Millard 8013 see 106
306 L A/Near ButterCreek 8061 see 115
Sub-Total 0 0 0 0 0 0 0 0
Medians and Parkways
401 L A Ave Medain 8047 875.914
402 Spring Median 8026 see 104
403 Not Assigned
404 Poindexter Pkwy 8048 115.000
405 T R at Freeway —
406 Not Assigned —
407 City Entry Signs —
408 Peach Hill Pkwy
Sub-Total 0 0 0 0 115,000 875.914 0 0
Storm Drains
501 Master Drainage Study 8088
502 Gabert/Walnut —
503 Shasta Drain --
504 Millard Drain 8065
505 Villa Del Arroyo Drain —
506 Misc. Improvements —
507 Arroyo Sim Channel Impr. —
508 GIS Storm Drain Layer
Sub-Total 0 0 0 0 0 0 0 0
Total 0 0 1,186,530 1,954,016 115,000 10,060,383 0 388,750
2015/16 to 2021/22 Capital Improvement Program
Funding Sources Totals:FY 2015/16 thru FY 2021/22
Account 2603 2604 2605 2609/2610
Code Project Name Number LTF Fed Grant Gas Tax State Grants Other Undetermined Total
Streets&Trails
101 Slurry Seal 8002 832,776 32.1.063 31,500 1,185,339
102 SR118/Collins Dr Ramp/Sig Mod 8076 550,000 550,000
103 Walnut Canyon Rd S/W Imp --- 500,000 500.000
104 Spring Rd Widening 8026 855.664
105 Princeton Ave.Widening 8012 1,087,244 5,592,346
106 L A Ave: Spg to Mpk 8013 796.770 1.782,629
107 Spring/Charles Bus Turn-Out 8069 150.000
108 L A Ave: Shasta 8058 1,216,032
109 Underground Utility Projects - 10.000.000 10,000,000
110 L A Ave Undergrounding 8051 426,447 726,208
111 Undrgmd: New L A Ave 8066 444,922
112 Rail Xing: Spring Rd 8039 1.125.425
113 Arroyo Drive Overlay 8084 536,344 536,344
114 Bus Shelter Improvements 8071 69,738 69,738
115 North Hills Parkway 8061 1,260,973
116 High St.Streetscape/Parking 5056 0
117 North Extension of SR 23 8045 22,288
118 Wicks Road Sidewalk and Asphalt Overlay 0
119 Metrolink South Parking Lot Entry 8056 509.119 224,793 885,140
120 Gabbert Rd Rail)Gng - 0
121 High Street West - 430,000 430,000
122 Railroad Crossing at Arroyo Drive - 1,000,000 1,000.000
123 Moorpark Ave Widening Proj 8040 670,755
124 Lengthen Curb Radii -- 300.000 300,000
125 L.A. Ave West of T. R. Rd. - 0
126 Casey Rd Westerly Ext. - 0
127 Moorpark Ave Left Turn Lane 8087 0
128 Overlay Spring, Princeton, Poindex - 132,584 637,416 770,000
129 Metrolink North Parking Lot 8093 317,037 377,037
Sub-Total 965,360 1,943,305 857.407 1,118,744 1.270.978 12,230,000 30,450,840
Trails&Walkways
201 Sidewalks 8001 0
202 Ped/Bicycle Project -- 140,000 280,000
203 Arroyo Simi Trail Improvements 8035 0
204 Drain#2 Trail 8059 0
205 Sidewalk&Bicycle Lane at AVRC - 618,766
206 Walnut Canyon Rd Peter's Drwy - 75,000
207 Civic Center Ped&Bus Stop Imp - 20.000 200.000
208 Arroyo Drive Sidewalk - 200,000
209 Sidewalk 8097 50,000 50,000
Sub-Total 140,000 0 0 0 20,000 0 1,423,766
Traffic Signals
301 Not Assigned -- 0
302 L A Ave/Shasta 8058 0
303 SR118/Collins Dr E/B Ramps 8077 175.000 175.000
304 Not Assigned - 0
305 L A/Millard 8013 0
306 L A/Near ButterCreek 8061 0
Sub-Total 0 0 0 0 110,000 0 175,000
Medians and Parkways
401 L A Ave Medain 8047 875,914
402 Spring Median 8026 0
403 Not Assigned - 0
404 Poindexter Pkwy 8048 115.000
405 T Rat Freeway - 250,000 250,000
406 Not Assigned - 0
407 City Entry Signs -- 0
408 Peach Hill Pkwy - 53,000 53,000
Sub-Total 0 0 0 0 0 303,000 1.293.914
Storm Drains
501 Master Drainage Study 8088 150,000 150,000
502 Gabert/Walnut - 15,000,000 15,000,000
503 Shasta Drain -- 800,000 800,000
504 Millard Drain 8065 250.000 250,000
505 Villa Del Arroyo Drain - 0
506 Misc. Improvements - 200.000 200,000
507 Arroyo Sim Channel Impr. - 0
508 GIS Storm Drain Layer - 0
Sub-Total 0 0 0 0 150.000 16,250,000 16,400,000
Total 1,105,360 1,943,305 857,407 1,118.744 1,615,978 28,783,000 49,743,520
City of Moorpark
Capital Improvement Program
D. Congestion Management Program
The purpose of the Ventura County Transportation Commission's (VCTC) Congestion
Management Program (CMP) is to monitor certain street segments and/or intersections
on the CMP Road Network (see Map), to confirm that the Level of Service (LOS) [a
measurement of the level of congestion] on those segments, or at those intersections,
does not deteriorate below certain stipulated levels. Increased traffic generated by
development is one of the major causes of increased traffic congestion and, therefore,
the deterioration of the LOS. The CMP requires each Agency to identify projects
designed to increase capacity and/or otherwise improve the efficient and effective
movement of traffic. The projects set forth in this seven year program, which are on the
CMP Road Network and which could reduce congestion, are listed on the following
page.
I
O
Jj o ,1 �%I
, ,,, .
, i14, ,
�� o
to
Z
z
o
44EUP111. 1 NM IP L11
I ) WI z
� O
II' 11U
IS
II,: fr.
A AA1 I Ibk ,
,,w, •
,,,,,T, Ar , - If ,,
vzi. \ \ Li, ,,r- „ owe"
m171 4 ,,,..,.1....- i i _ . t 4
O ..,...0„....=
0,1 ,,Aji \ ,, EA , 44-0
r1 nayK... ii4t
,,„,,,04
AINIIIINIptat „.....,„. .,...,,
! \ .,, ., ' it Faill it Afflii 1 ri. __
14
k -
Tit
. ..,,,,a.
4 .400 I
ILL I
I Y Pilioll 2
, , i 410. ../ -
111174. prip 41 , ,
iti 4 -. -----**
, , 4
1 IIII E_Q
.. • - 41:13Fv ,
--41
fik .00 i
..
L.
i
N
N
Os pO00 v, 0 N O O O O N
O O ClY V
u.. N N O
Oro O N N 00 aac
an rn
iii
0 0 0 0 0 0 0 0 0 0 O
N
W
_1
ry 0 0 0 0 0 0 O O O O =
O
N
}'
LL
•
NC O 0:O O G 0 0 0 0 0
O. 1
}
C4
P O O O O O 0 O O O 0 0
00
}
LL
000 .n0 If) 0 0 0 O ii)
N N r
r r N
0 0" o
_., so
r 0 0 0 -0 = = 0 0 0 O
'o
}
Lti
sO p 00 h
C+ .D O _ O O O O N
n �� O N P
Y L} Oro O N
C M
V
a
,p ; !!!!T1 cc
I
7k ik r-;
83 83
N N
d Iq 00 00 $ .O0
z
E
m -. x o
m Q . E F
en 0 0 a
C N 5 V' V'
0/ 0b a '15
c g o F • `S
dy E . 0 0< O8 ¢ L0 < S
0. E - ..JZ ..) 7, aa .a
L.oI -yy 4, u
Q 0 0 - N N 0 0 0
City of Moorpark
Capital Improvement Program
Appendix `I'
Completed Projects
The following is a list of known Streets and Roads Projects constructed subsequent to the incorporation
of the City in 1983.
Project Name Description
1985
Streets&Trails
Sidewalk Construction East Side of Moorpark Avenue,Third Street to Los Angeles Avenue
Sidewalk Construction West side of Moorpark Avenue from Community Center to High Street
Sidewalk Construction West side of Moorpark Avenue from North of Poindexter Avenue to Third Street
Asphalt Overlay Various Streets including High Street,Gabbert Road,Third Street, Bard Street,
Sherman Avenue, Second Street and Sarah Avenue
1987
Streets&Trails
Asphalt Overlay Spring Road South of Williams Ranch Road (by Developer)
Sidewalk Construction South side of Williams Ranch Road(by Developer)
Slurry Seal Project Various Streets throughout the City
Railroad Crossing Construction of rubberized railroad crossing on Old Los Angeles Avenue(east of
College View Avenue)
Traffic Signals
Los Angeles Avenue& Construction of a traffic signal at Los Angeles Avenue& Tierra Rejada Road/
Tierra Rejada Road Gabbert Road
Los Angeles Avenue& Construction of a traffic signal at this intersection
Condor Drive
Parkways and Medians
Campus Park Drive Construction of landscape improvements to medians on Campus Park Drive(two
Developers)
Tree Replacement Removal and replacement of parkway trees on a number of streets in the
downtown area
Spring Road&Peach Construction of landscape improvements at the southwest corner
Hill Road
Spring Road Drainage Construction of a box culvert on the west side of Spring Road south of Los
Improvement Angeles Avenue
1988
Streets&Trails
Tierra Rejada Bridge Construction of a four lane(with median)bridge across the Arroyo Simi
Traffic Signals
Traffic Signal: Los Construction of a traffic signal at this intersection
Angeles Avenue&
Princeton Avenue
1989
Streets&Trails
Spring Road Railroad Construction of rubberized railroad crossing on Spring Road
Crossing
Moorpark Avenue Construction of rubberized railroad crossing on Moorpark Avenue
Railroad Crossing
Curb/Gutter/Sidewalk North side of High Street,east of Magnolia Street
Construction
Asphalt Reconstruction Various streets including Millard Street,Harry Street,Dorothy, Esther,Roberts
&Overlay Avenues, Laurelhurst Road,Campus Park Drive&Maureen Lane
Traffic Signals
Los Angeles Avenue& Construction of a traffic signal at this intersection
Science Drive
Tierra Rejada Road& Construction of a traffic signal at this intersection(Developer)
Peach Hill Road
Tierra Rejada Road& Construction of a traffic signal at this intersection(Developer)
Walnut Creek Road
Tierra Rejada Road& Construction of a traffic signal at this intersection(Developer)
Mt.Meadows Drive
Storm Drains
Moorpark Avenue Construction of storm drain improvements north of High Street(by Caltrans)
1990
Streets&Trails
Slurry Seal Project Various streets throughout the City
Sidewalk Construction East side of Spring Road, Los Angeles Avenue to Roberts Avenue(by Developer)
Sidewalk Reconstruction Replacement of damaged sidewalks(including tree limb and root pruning)
throughout the City.
Traffic Signals
Los Angeles Avenue& Major reconstruction of the traffic signal at this intersection(by Developer)
Spring Road
Traffic Signal: Campus Construction of a traffic signal at this intersection
Park Drive&Delfen
Street
Parkways and Medians
Tierra Rejada Road Construction of landscape improvements to Tierra Rejada Road medians from the
Median Edison Easement easterly to a point east of Southhampton Road
Tierra Rejada Road Construction of landscape improvements to the parkway on the north side of
Parkway Tierra Rejada Road east of Peach Hill Road(Developer)
1991
Streets&Trails
High Street& Spring Reconstruction of curb, gutter& sidewalk at southeast corner(by Caltrans)
Road
Avenida Colonia& Reconstruction of these two streets including the construction of new curbs,
Nogales Street gutters and sidewalks and the construction of a portion of the Happy Camp
Canyon covered box culvert to allow for the connection of these two streets
Los Angeles Avenue North side street improvements from Liberty Bell Road to Maureen Lane,
Widening including an additional westbound travel lane,curb,gutter and sidewalk
Sidewalk Construction West side of Spring Road,Los Angeles Avenue to Roberts Avenue
Sidewalk Construction North side of Los Angeles Avenue between Spring Road and Millard Street
Sidewalk Construction West side of Spring Road between Roberts Avenue and the railroad tracks
Handicap Access Ramps Construction of handicap access ramps at various locations throughout the City
Traffic Signals
First St./Poindexter Construction of a traffic signal at this intersection to fulfill the City's portion of a
Avenue @ Moorpark City/State Agreement to signalize both this intersection and Moorpark Avenue/
Avenue High Street
Storm Drains
Happy Camp Box Construction of a covered box culvert for the Happy Camp drain at Los Angeles
Culvert Avenue crossing(Unit III)and at the intersection of Nogales Street and Avenida
Colonia
1992
Streets&Trails
Sidewalk Reconstruction The reconstruction of the sidewalk on the east side of Tierra Rejada Road south of
Los Angeles Avenue,including the replacement of street trees
High Street Storm Drain Construction of a storm drain from Walnut Street to Magnolia Street and a
and Sidewalks sidewalk on the north side of the street between Bard Street and Magnolia Street
Charles Street Reconstruction of the street from Moorpark Avenue to Bard Street,including the
Reconstruction(Ph. I) construction of a storm drain and new curbs,gutters and sidewalks
Traffic Signals
Spring Road&Peach Construction of a traffic signal at this intersection
Hill Road
Collins Dr.&Campus Construction of a traffic signal at this intersection by Caltrans as a part of the
Park Dr. freeway construction project
High St.&Moorpark Construction of a traffic signal at this intersection by Caltrans to fulfill Caltrans'
Avenue portion of a City/State Agreement to signalize this intersection and Poindexter
Avenue/First Street/Moorpark Avenue
Peach Hill Rd& Spring Construction of a traffic signal at this intersection
Rd
Parkways and Medians
Williams Ranch Road Construction of a landscaped barrier across Williams Ranch Road near the Edison
Landscape Barrier Easement
East side Tierra Rejada Replacement of the street trees on the east side of the street south of Los Angeles
Road @ Los Angeles Avenue in conjunction with the reconstruction of sidewalks in that area
Avenue
1993
Streets&Trails
Asphalt Overlay Project Construction of an asphalt overlay on the following streets: 1)Tierra Rejada Road
at the Route 23 Freeway; 2)Peach Hill Road; &3)Campus Park Drive
Slurry Seal Project Construction of Slurry Seal on various streets throughout the City
Los Angeles Avenue @ Construction of street improvements, storm drains,traffic signals, landscaping and
Park Lane,etc. related improvements on Los Angeles Avenue,Park Lane, Lassen Avenue and
Liberty Bell Road required for the construction of the Mission Bell Plaza, funded
by Assessment District 92-1 [**CMP].
Peach Hill Road East of Extension of Peach Hill Road east of Spring Road to the future Science Drive
Spring Road (constructed by the developer of the Carlsberg Specific Plan to serve the Mesa
Verde Middle School)
Traffic Signals
Tierra Rejada Rd& Street widening project included the construction of a"permanent"traffic signal to
Spring Rd replace the temporary traffic signal at this location [**CMP]
Los Angeles Ave&Park Construction of a traffic signal at this intersection as a part of the street and storm
Lane drain improvements funded by Assessment District 92-1 [**CMP]
Los Angeles Avenue& Construction of a traffic signal at this intersection as a part of the off-site and
Liberty Bell Road storm drain improvements funded by Assessment District 92-1 [**CMP]
Parkways&Medians
Sherman Avenue Replacement of the rear property walls for the properties on the south side of
Property Wall Sherman Avenue(north side of Los Angeles Avenue between Spring Road and
Millard Street)
Los Angeles Avenue: Construction of parkway landscaping on the north side of Los Angeles Avenue
Spring Road to Millard between Spring Road and Millard Street
Street
Tierra Rejada Road/ Repair of a slope failure on the south side of Tierra Rejada Road east of Peach Hill
Peach Hill Road Slope Road
Repair
Storm Drains
Sunnyslope Place Debris Construction of an access road to facilitate the maintenance of a storm water
Basin Access Road debris basin north of Sunnyslope Place
1994
Streets&Trails
Lassen Alley Construction of pavement improvements to complete the drainage improvements
Improvements at the south end of McFadden Avenue and Cornett Avenue
Charles Street Reconstruction of the street from Bard Street to Spring Road, including the
Reconstruction(Ph. II) construction of a storm drain and new curbs,gutters and sidewalks
Spring Road Berm Construction of an asphalt berm on the east side of the street north of Peach Hill
Road in order to prevent erosion of the slope supporting the street
Flory Area Sidewalks Construction of sidewalks on certain streets in the vicinity of Flory Elementary
School,partially funded by an SB-821 pedestrian facility grant, including Second
Street,Bard Street,Third Street,Flory Avenue, Millard Street,Roberts Avenue,
and Harry Street
Tierra Rejada Road Realignment and reconstruction of Tierra Rejada Road east of Spring Road,
Realignment and increasing the roadway to four lanes and adding a center raised median [**CMP]
Reconstruction
Grimes Canyon Road Street improvements(including widening)near the entrance(Turfway Road)to
Tract 4081 (constructed by the developer)
Park Lane and Lassen Improvements to Park Lane north of Los Angeles Avenue and Lassen Avenue,to
Avenue serve the Mission Bell Plaza Shopping Center(AD 92-1)
Traffic Signals
Tierra Rejada Road& Construction of a traffic signal at this intersection(Developer) [**CMP]
Mountain Trail Street
Tierra Rejada Rd& Construction of a traffic signal at this intersection(Developer) [**CMP]
Arroyo Vista Access Rd
/Countrywood Drive
Tierra Rejada Road @ Construction of a traffic signal at this intersection(Developer) [**CMP]
Shopping Center Entry
Parkways&Medians
Installation of landscaping in the extension of the center median in Tierra Rejada
Tierra Rejada Rd Road just west of Spring Road
Median at Spring Rd
Construction of a block wall and landscaping at the northeast corner of Los
Shasta Avenue/Los Angeles Avenue and Shasta Avenue to meet right-of-way acquisition requirements
Angeles Avenue Wall
[NE Corner]
East Side Spring Road
South of Peach Hill Road Construction of parkway landscaping on the east side of Spring Road south of
Peach Hill Road
Los Angeles Avenue @ Construction of parkway landscaping on the north side of Los Angeles Avenue at
Shasta Avenue Shasta Avenue
Storm Drains
AD 92-1 Construction of storm drains along the north side of Los Angeles Avenue,Park
Lane,and within easements on the Mission Bell Plaza property
1995
Streets & Trails
High Street Decorative Installation of underground conduits for electrical,telephone,cable television,
Street Lights street lights and a decorative lighting system,plus the installation of nostalgic
decorative street lights on High Street
Freeway Connector Construction of bridges and related improvements required to connect the Route
Project 23 Freeway to the Route 118 Freeway(Caltrans) [**CMP]
City Maintenance Yard Conversion of property at 675 Moorpark Avenue to a City Maintenance facility
Metro Link Parking Lot/ Construction of the south Metro Link parking lot and access driveway(SCRRA)
Driveway [**CMP]
Lassen Avenue @ Modifications to Lassen Avenue to provide entrances to the north end of the
Mission Bell Plaza Mission Bell Plaza Shopping Center parking lot from Sierra Avenue and from
Park Lane
Slurry Seal Project Application of slurry seal and related work to approximately one-third of the
residential streets in the City
Tecolote, Canario, Etc. Construction of an asphalt overlay on Tecolote Court, Canario Court, and a
portion of North Granadilla Drive
Walnut Canyon Road @ Widening of Route 23 by Caltrans to provide a center turning lane at Wicks Road
Casey Road and Casey Road
First Street/Bard Street Reconstruction of First Street and Bard Street including reconstruction of
pavement,curb,gutter and sidewalks
Parkways&Medians
Moorpark Estates Entry Installation of entry signs at Shasta Avenue and Los Angeles Avenue and at
Poindexter Avenue and Sierra Avenue
Shasta Avenue/Los Construction of a block wall and landscaping at the northwest corner of Los
Angeles Avenue Wall Angeles Avenue and Shasta Avenue to meet right-of-way acquisition requirements
[NW Corner]
Poindexter Avenue @ Construction of parkway landscaping on the south side of Poindexter Avenue at
Sierra Avenue Sierra Avenue
Princeton Avenue Construction of parkway and median landscaping on Princeton Avenue
Campus Park Drive Construction of parkway landscaping on the south side of Campus Park Drive east
and west of Princeton Avenue
Tierra Rejada Road Restoration of slope slippage on the south side of Tierra Rejada Road near Peach
Slope Restoration Hill Road
Bard Wall Construction of a wall at the north end of Bard Street,just north of First Street
Virginia Colony Planter Construction of a landscaped planter at the corner of Virginia Colony Place and
Los Angeles Avenue
Irrigation Crossover Construction of conduits for future irrigation water lines and valve control wires at
Conduits a number of locations including: Tierra Rejada Road at Courtney Lane; Courtney
Lane on the west side of Tierra Rejada Road and Southhampton Road at Tierra
Rejada Road
Spring Road Parkway Removal and replacement of damaged sidewalks and the installation of tree well
Trees grates along the west side of Spring Road south of Peach Hill Road,to preserve
existing parkway trees.
1996
Streets& Trails
Millard Street Area Construction of sidewalks on Sherman Avenue, Esther Avenue,Roberts Avenue
Sidewalks and other streets
Poindexter Avenue Complete reconstruction of this street west of Chaparral Middle School
Everett Street Complete reconstruction of this street,including curb,gutter and sidewalk
Walnut Street Complete reconstruction of this street,including curb,gutter and sidewalk
Bard Street Complete reconstruction of this street between Charles Street and High Street
Magnolia Street Complete reconstruction of this street north of Charles Street
Tierra Rejada Road Construction of an asphalt overlay on this street east of Spring Road
Spring Road Construction of an asphalt overlay on this street south of Peach Hill Road
Old Los Angeles Avenue Construction of an asphalt overlay on this street east of the rail crossing located
east of Collins Drive
Flory Avenue Construction of an asphalt overlay on this street
Magnolia Street Construction of an asphalt overlay on this street south of Charles Street
Goldman Avenue Construction of an asphalt overlay on this street
Spring Road Median/ Construction of modifications to the south leg of the intersection of Spring Road
Double Left Turn Lane and Los Angeles Avenue to provide for a double left turn lane and a raised center
median
Painted Sky Street Repair of street improvements damaged by a street subsidence
Subsidence Repair
Public Works Yard Construction of additional improvements to expand the City Maintenance Yard at
Expansion 675 Moorpark Avenue
Traffic Signals
Collins Drive&Campus Construction of a traffic signal at this intersection by Caltrans,as a apart of the
Park Drive Freeway Connector construction project
Moorpark Road&Tierra Construction of a traffic signal at this intersection by the City, with partial funding
Rejada Road from the County of Ventura
Parkways& Medians
Home Acres Buffer Area Construction of a landscaped buffer area,including an emergency access road and
a flood control maintenance road,at the west end of Shadyridge Drive in Tract
4021 (funded by Zone 8 of AD 84-2)
Storm Drains
Tierra Rejada Road Sub- Construction of a sub-drain system along Tierra Rejada Road between Walnut
Drain System Canyon Road and Mountain Trail Street to convey subsurface water to storm drain
inlets
Tierra Rejada Road Inlet Installation of a catch basin on the north side of the center median on Tierra
East of Spring Road Rejada Road east of Spring Road
1997
Streets&Trails
Flinn Avenue Reconstruction of Flinn Avenue east of Spring Road,constructed in conjunction
Reconstruction with the Spring Road storm drain project
Moorpark Avenue Construction of an asphalt overlay on this street,constructed in conjunction with
[South] A/C Overlay the construction of the Moorpark Avenue storm drain project
AVCP Access Bridge Construction of a pedestrian,equestrian,emergency access bridge across the
Arroyo Simi,to connect Arroyo Vista Community Park to Liberty Bell Road
Arroyo Vista Construction of a paved surface between the end of the park access road and the
Community Park Bike Arroyo Vista Park Access Bridge,partially funded by an SB-821 bicycle facilities
Path grant
Storm Drains
Moorpark Avenue Storm Construction of a storm drain system extending from the south side of Los
Drain System Angeles Avenue northerly to a point north of First Street, with storm drain laterals
serving Flory Avenue and the Metro Link parking lot
Spring Road Storm Drain Construction of a storm drain system extending from the south side of Los
System Angeles Avenue northerly to Flinn Avenue,and then extending easterly on Flinn
Avenue
1998
Streets&Trails
Downtown Alley Reconstruction of the alleys south of First Street
Reconstruction
Valley Road Reconstruction of the street
Construction of retaining walls and related improvements required to provide
Wicks Road Slope slope stabilization to support Wicks Road
Stabilization
Wicks Road A/C Construction of an asphalt overlay on the westerly portion of this street
Overlay
Bonnie View Street A/C Construction of an asphalt overlay on this street
Overlay
Maureen Lane Reconstruction of Maureen Lane south of Los Angeles Avenue
Reconstruction
Storm Drains
Science Drive Storm Construction of two storm drain systems serving the Carlsberg Specific Plan(by
Drain System Developer),one serving the streets and a separate system conveying run-off from
common areas to vernal ponds
1999
Streets&Trails
Peach Hill Road Widening to the south side of the street east of Spring Road,in order to provide a
westbound left-turn lane.
Poindexter Avenue Widening to the north side of the street east of Gabbert Road, including new curb,
gutter and sidewalk, and the re-striping of the street to provide a painted median
and Bike Lanes.
New Los Angeles Avenue Widening to the south side of the street to provide six(6)lanes of traffic (by
Widening Developer). [**CMP]
Spring Road Widening Construction of widening to the east side of Spring Road from Tierra Rejada Road
northerly to the Arroyo Simi Bridge(by developer).
Casey Road Widening Widening to the south side of the street west of Walnut Canyon Road.
Old L.A.Avenue Surface crossing improvements to the rail crossing(by SCRRA).
Rail Crossing
Gabbert Road Surface crossing improvements to the rail crossing(by Union Pacific)
Miller Parkway Construction of a new collector street between Tierra Rejada Road and New Los.
Angeles Avenue(by developer).
Tierra Rejada Road Improvements to the north side of the street,just west of the freeway(by
developer).
Traffic Signals
Casey Road/Walnut Construction of a traffic signal,funded by the City,Caltrans and the Moorpark
Canyon Road Unified School District. [**CMP]
Peach Hill Road and Installation of a new traffic signal at this new intersection(by developer).
Miller Parkway
Tierra Rejada Road and Installation of a new traffic signal at this new intersection(by developer).
Miller Parkway [**CMP]
Commercial Entry and Installation of new traffic signal at this new intersection(by developer). This
Miller Parkway signal is to be made operational when the center is opened.
New Los Angeles Modifications to the traffic signal at the intersection of New Los Angeles Avenue
Avenue&Miller and Science Drive,to accommodate the addition of Miller Parkway as the south
Parkway leg of the intersection.(by developer) [**CMP].
New Los Angeles Installation of traffic signals at the on and off-ramps to the freeway, in order to
Avenue at the Route 23 allow ingress and egress traffic to and from White Sage Road(private) [by
Freeway Caltrans and the developer].
Parkways&Medians
Spring Road Medians Construction of new landscaped medians and parkways (east side)from Tierra
and Parkways Rejada Road northerly to the Arroyo Simi Bridge(by developer).
2000
Streets&Trails
Spring Road Bridge Reconstruction of the Spring Road Bridge at the Arroyo Simi,to provide
sidewalks,bike lanes and a raised median.
Asphalt Overlay The construction of an asphalt overlay and related improvements to the following
streets: Talmadge Rd.; Marquette St.;Gabbert Rd. (north of Poindexter Ave.);
Spring Road(north of High St.); Fitch Ave.;Minor St.; Robert St.; Harry St.;Ruth
Ave.;Dorothy Ave.; Mt.Trail(east of Walnut Creek Rd.); Collins Dr.; Campus
Park Dr.; Princeton Ave.;High Street; Spring Road(New L.A Ave. to Bridge);
and Christian Barrett Drive.
Spring Road Rehabilitation of Spring Road between New Los Angeles Avenue and High Street.
Rehabilitation The cost of this project was reimbursed by Caltrans as required by a Highway
Relinquishment Agreement.
Los Angeles Avenue Rehabilitation of Los Angeles Avenue between High Street and Princeton Avenue.
Rehabilitation The cost of this project was reimbursed by Caltrans as required by a Highway
Relinquishment Agreement. Upgrades to the middle portion of this street segment
are being deferred until the Los Angeles Avenue East project is constructed.
Parkways&Medians
Freeway Landscaping Installation of freeway landscaping from Collins Drive to a point west of
Princeton Avenue(by Caltrans).
Storm Drains
Tierra Rejada Road Construction of additional storm drain inlets to better handle peak storm flows.
Inlets
L. A. Ave.Drain Installation of new inlets east of Spring Road to eliminate flooding.
2001
Streets& Trails
New Los Angeles Widening to the south side of the New Los Angeles Avenue[SR-118] bridge over
Avenue Bridge Widening the Arroyo Simi to provide six(6)lanes of traffic. [**CMP]
Los Angeles Avenue: Widening to the south side of the street to provide three(3)eastbound lanes(by
Moorpark Avenue to Developer). [**CMP]
Park Lane
Los Angeles Avenue: Construction of street widening to the south side of the street at the old Caltrans
East of Leta Yancy Rd Maintenance Yard,in order to provide three(3)eastbound lanes,curb,gutter and
sidewalk. [**CMP]
Traffic Signals
Los Angeles Avenue& Modifications to the striping to provide a double left-tum lane at the east leg of the
Tierra Rejada Road intersection. [**CMP]
Parkways&Medians
Los Angeles Avenue Installation of median landscaping and irrigation in the new raised median on Los
Angeles Avenue south of the Princeton Avenue freeway ramps.
Tierra Rejada Road Installation of parkway landscaping on the north side of Tierra Rejada Road east
and west of Southhampton Road, funded by the Zone 2 improvement assessment
[AD84-2].
2002
Streets&Trails
Underground Utility The undergrounding of all overheard utilities,other than high voltage electrical
District No. 2000-1 lines, on Los Angeles Avenue between Gabbert Road and Millard Street. Project
was constructed by SCE and funded by SCE pole replacement monies and Rule
20A undergrounding accruals.
Miller Parkway/Peach Construction of widening at the northeast corner to allow south-to-north U-Turn
Hill Road U-Turn movements.
2003
Streets&Trails
Arroyo Trail Study Feasibility Study and Implementation Plan for an arroyo levee trail from the
westerly City limit to Madera Road in the City of Simi Valley.
Moorpark Road City costs related to a County of Ventura Road Department Project to construct a
Realignment new,realigned Moorpark Road intersecting Tierra Rejada Road at Miller
Parkway.
Curb Ramp Project Construction of curb ramps at a number of locations(mainly"T-intersections")
throughout the City.
2003 Slurry Seal Project Application of Slurry Seal to approximately one-third of the streets in the City.
2003 AC Overlay Construction of an asphalt overlay on a number of streets throughout the City.
Project
GASB-34 Infrastructure Preparation of a study to inventory,quantify, categorize and determine the value
Inventory Report of the City's infrastructure improvements. Depreciation rates and replacement cost
estimates were also derived from that effort.
Curb/Gutter Repair Replacement of damaged curb and gutter at numerous locations throughout the
Project City.
Parkways&Medians
Peach Hill Road Construction of parkway landscaping on Peach Hill Road between Mesa Verde
Parkway Drive and Peach Hill Park.This project was constructed by the Peach Hill HOA.
Traffic Signals
L. A.Avenue at the Installation of a new traffic signal by the developer of the shopping center.
Marketplace Shopping
Center
Miller Parkway& Installation of a new traffic signal by the developer of the shopping center.
Patriot Drive
2004
Streets&Trails
Flinn Avenue The realignment of Flinn Avenue to align with Second Street.The project
Realignment included the widening of Spring Road north of Flinn Avenue,the construction of a
raised median on Spring north of Flinn Avenue and the construction of a traffic
signal at the intersection of Spring Road and Second Street.
Civic Center Driveway The widening of the driveway into City Hall.
Modification
Street Light A CDBG funded project to relocate and add street lights in the neighborhood
Modification—Millard southeast of Moorpark Avenue and First Street.
Tract
Traffic Signals
Double Left-Turn Lane Construction of improvements to provide a double left-turn lane for southbound
on Spring Road at Tierra traffic.
Rejada Road
Spring Rd and Second Construction of a traffic signal at the intersection of Spring Road and Second
Street Street/Flinn Avenue.
Parkways&Medians
Spring Road Parkway Removal of existing eucalyptus trees and the construction of new tree wells,with
West side deep root irrigation,between Peach Hill Rd. and Christian Barrett Drive.
Tierra Rejada Rd Removal of existing trees and installation of new tree wells,with deep root
Parkway,East side irrigation,between Harvester and Courtney.
Spring Road Median Installation of median landscaping north of Second Street.
Storm Drains
Loraine Drain Construction of storm drainage facilities northwest of the Spring Road Bridge(by
a developer)to meet needs identified in the Master Drainage Study as the"Loraine
Drain"or the"No Name Drain".
2005
Streets&Trails
Grimes Canyon Road at Construction of roadway improvements by a Developer.City costs related to the
Championship Drive acquisition of needed rights-of-way were reimbursed by the Developer.
Traffic Signals
Casey Signal The modification of the traffic signal at Casey Road and Walnut Canyon Road
Modification [State Route 23] to provide a left-turn arrow for northbound traffic [funded by
developer(Pardee Homes)].
Storm Drains
Little Hollow Sub Drain Construction of a sub-drain to intercept subsurface water and convey same to a
storm drain in an effort to prevent future damage to the asphalt pavement.
2006
Streets&Trails
Los Angeles Avenue Construction of roadway widening to the south side of the street, including
Widening at Maureen addition pavement,curb,gutter, sidewalk and property walls,and the construction
Lane of a traffic signal at the intersection of Los Angeles Avenue and Maureen Lane.
[**CMP]
Traffic Signals
Los Angeles Avenue at Construction of a traffic signal at this intersection. [**CMP]
Maureen Lane
Parkways&Medians
Tierra Rejada Road Construction of median landscaping on Tierra Rejada Road between Spring Road
Medians and the Route 23 freeway.
2007
Streets& Trails
Freeway Sign Replacement of freeway off-ramp signs required by street name changes for New
Replacement Los Angeles Avenue and Princeton Avenue.
Downtown Trail Study The Downtown Trail Study was completed. Future implementation will be
considered when and if funding sources are identified.
Spring Road Extension Construction of the extension of Spring Road northerly from Charles Street to
connect to Walnut Canyon Road.
'C' Street(Ridgecrest Construction of the east-west local collector street(Ridgecrest Drive)along the
Drive) northerly boundary of the City(Pardee Homes), from Spring Road easterly to the
proposed realigned Route 23.
Spring Road Wall Construction of a block wall and landscaping on the west side of Spring Road
from Los Angeles Avenue to the railroad crossing.
Traffic Signals
Campus Park Drive and Signal and striping changes were funded and constructed by the developer of the
Collins Drive property at the southwest corner.
Spring Road and Charles New traffic signal installed by developer.
Street
Spring Road and Elk New traffic signal installed by developer.
Run Drive
Spring Road and New traffic signal installed by developer.
Ridgecrest Drive
Spring Road and Walnut New traffic signal installed by developer.
Canyon Road(SR-23)
Traffic Controller and Construction of controller and other hardware,improvements,and/or for the
Operations upgrading of traffic signal operations through improved software, at designated
Improvements intersections.
Parkways&Medians
Los Angeles Avenue Construction of parkway landscaping on the south side of Los Angeles Avenue
and Tierra Rejada Rd from Butter Creek Road to Maureen Lane,and the construction of parkway and
Parkways median landscaping on Tierra Rejada Road south of Los Angeles Avenue.
Princeton Avenue Modification of the median and median landscaping on Princeton Avenue at
Median Modification Campus Park Drive.
2008
Streets&Trails
Lighted Crosswalk on Replacement of freeway off-ramp signs required by street name changes for New
Moorpark Avenue at Los Angeles Avenue and Princeton Avenue.
Second Street
Asphalt Overlay Construction of an asphalt overlay,and related work,along the entire length of
Projects Tierra Rejada Road and on Second Street.
Slurry/ARAM Project Pavement rehabilitation of various City streets completed in FY 08/09.
Traffic Signals
Traffic Signal Construction of a hardwire traffic signal interconnect system to allow for the
Interconnect: Los coordination of all of the traffic signals along the Los Angeles Avenue corridor
Angeles Avenue (SR-118).
Traffic Signal Construction of a hardwire traffic signal interconnect system to allow for the
Interconnect:Tierra coordination of all of the traffic signals along Tierra Rejada Road between
Rejada Road Countrywood Drive and the Route 23 freeway.
2009
Streets& Trails
Moorpark Road Dual Perform intersection modifications to provide dual left turn lanes on Moorpark
Left Turn Lanes Road to Tierra Rejada Road.
Lassen Avenue Construction of a Bikeway/Walkway path extending westerly from Moorpark
Bikeway/Walkway Avenue near Third Street,within the Lassen Avenue street right-of-way.
High Street Widening and extension of High Street west of Moorpark Avenue and
Rehabilitation construction of Post Office parking lot.
Parkways&Medians
Tierra Rejada Road Construction of median landscaping on Tierra Rejada Road between Brennan
Medians Road and the Route 23 freeway.
Storm Drains
Walnut Canyon Drain Replacement of open channel drain with covered reinforced concrete pipe from
Improvement the west end of the High Street extension to approximately 350 feet north of High
Street
2010
Streets& Trails
Mountain Trail Street/ Pavement rehabilitation and construction of a landscaped median in Mountain
Spring Road Pavement Trail Street from Tierra Rejada Road to Country Hill Road,and pavement
Rehabilitation rehabilitation on Spring Road from Peach Hill Road to a point approximately 2000
feet to the south.
Julliard Avenue and Asphalt overlay of Julliard Avenue from Campus Park Drive to Loyola Street and
Reedley Street Overlay Reedley Street from Julliard Avenue west to the end due to damage caused by a
ruptured waterline.
Parkways& Medians
City Entry Signs Installation of City Entry Signs on Princeton Avenue on each side of the 118
Freeway; and on Tierra Rejada west of the 23 Freeway.
Mountain Trail Street/ Construction of a landscaped median in Mountain Trail Street from Tierra Rejada
Spring Road Pavement Road to Country Hill Road.
Rehabilitation
2011
Streets&Trails
Metrolink Security Wall Extension of the security wall along the Metrolink south parking lot property line.
& Camera System Metrolink security camera system completed in FY 07/08.
Traffic Signal
Collins Drive and Construction of a traffic signal at the intersection of Collins Drive and University
University Drive Drive.
Los Angeles Avenue Modification of the traffic signal to provide protected phases(Left Green Arrows)
and Tierra Rejada Drive for the north and south legs of the intersection,as well as a right green arrow for
northbound Tierra Rejada Road [**CMP]
2012
Streets&Trails
Alderbrook Street Asphalt overlay on Alderbrook Street from Honeybrook Court to River grove
Asphalt Overlay Court and on Walnut Creek Road from Tierra Rejada to Misty Grove Street.
2012 Pavement ARAM and slurry seal of various City Streets.
Rehabilitation
2012 Sidewalk Replacement of sidewalks,curbs,and gutter at various locations.
Reconstruction
Spring Road Overlay Asphalt overlay on northbound Spring Road from Flinn Avenue to the railroad
crossing.
Storm Drains
Spring Road Storm Installation of a catch basin on northbound Spring Road at the Police Services
Drain Center driveway with a connection to the existing storm drain on the west side of
Spring Road. The project included a storm drain connection to the Ruben Castro
Human Services Center site.
2013
Streets&Trails
SR-23 FWY Sound Construction of freeway sound walls adjacent to the homes on Crab Apple Court at
wall the eastern boundary of Tract 4975 (Toscana at Serenata)within the Carlsberg
At Tierra Rejada Specific Plan area,bordering the west side of the SR-23 Freeway
2013 Pavement Replacement of faded pavement striping,arrows and legend at various locations.
Markings
2014
Streets&Trails
Railroad crossing at Street widening and at-grade rail crossing improvements including a center median,
Spring Road four vehicle crossing gates,pedestrian crossing gates,concrete sidewalk,dedicated
northbound right turn lane and bike lanes in both directions.
Carnpus Canyon Drive Relocation of the crosswalk on Campus Canyon Drive at Monroe Avenue and
Crosswalk Construction of new curb ramps.
2015
Streets& Trails
2015 Pavement ARAM, slurry seal, and crack-fill of various City Streets.
Rehabilitation
**Note: CMP denotes that the project was on the Congestion Management Program roadway network and
was related to congestion management.
City of Moorpark
Capital Improvement Program
APPENDIX II: Description of Funds
Fund Remarks
1000 — General Fund: Revenues derived It should be noted that State law requires the City to
from property tax, sales tax, motor vehicle in maintain an established level of effort of General Fund
lieu fees and other non-restricted sources. expenditures for streets [called a Maintenance of Effort
(MOE)], in order to continue to receive certain State
grant funds.The current MOE amount is$342.
2000...........— Traffic ....Safety Fund: Revenues Revenue to this Fund is only about $125,000 per year. In
derived from vehicle code fines, which are recent years this fund has been used primarily to fund the
restricted to construction / maintenance of Crossing Guard program.
traffic control devices, streets, equipment, and
supplies for traffic enforcement, accident
prevention and crossing guards.
2001 — Traffic Systems Management: The purpose of this Fund is fmance system
Revenues derived from fees based on the air improvements that improve circulation and reduce
quality impacts of land development projects. emissions.
Said funds are to be used on projects or
programs designed to mitigate those air
quality impacts.
2002 — Citywide Traffic Mitigation: The purpose of this fund is to improve circulation by
Revenues derived from development fees to constructing major capacity enhancement projects.
fund mitigation measures to better
accommodate the increased traffic flow
generated by those development projects.
.....2150 — Trees and Landsc............................._...._._._._......................................,.......,............,..,..,................................-..........____ ___.........._....................................................-._......._.........._._._._._._._................_..._._......_._.__._......
aping: Revenues
derived from development fees to fund
various landscape improvements.
23xx — Assessment Districts: Revenues Project 111, the Los Angeles Avenue Undergrounding
derived from maintenance & improvement Project, is partially funded by Fund 2330 [AD92-1:
district assessments, which have been Mission Bell Plaza].
earmarked for improvement projects. A
separate Fund has been established for each
District and/or Zone within a District.
Also included in this category are Community
Facility District Funds.
Fund Remarks
2501 —Los Angeles Avenue AOC: Revenues Various projects to be financed by this Fund include: 1)a
derived from fees paid by land development number of projects required in order to provide six (6)
projects located within a designated area, for lanes of traffic along the New Los Angeles Avenue /Los
the purpose of constructing roadway Angeles Avenue corridor, and 2) the reconstruction and
improvements within that area. The properties realignment of Princeton Avenue east of High Street.
subject to this fee consist of all of the areas of
the City located north of the Arroyo Simi,
plus the property south of the Arroyo and east
of the freeway[S.D.I. Property].
2502 — Spring Road / Tierra Reiada Road Projects funded or partially funded by this source include
AOC: Revenues derived from fees paid by the Tierra Rejada Traffic Signal Interconnect System and
land development projects located within a the Tierra Rejada Road median landscaping project.
designated area, for the purpose of
constructing roadway improvements within
that area. The properties subject to this fee
consist of all of the area of the City located
south of the Arroyo Simi.
2503 — Casey Rd / Gabbert Rd AOC: No appropriations have yet been made to projects from
Revenues derived from fees paid by land this Fund.
development projects located in that area
generally located northwest of Walnut
Canyon Road(Moorpark Avenue) and the rail
corridor, for the purpose of constructing
roadway improvements within that area.
2602 — TDA Article 3: A portion of State These funds are allocated to the cities in the County by
sales tax revenues which is restricted to the the Ventura County Transportation Commission (VCTC)
construction or improvement of pedestrian via a competitive grant process.
and/or bicycle facilities.
2603 — TDA Article 8A: TDA Article 8 Historically, these monies have been used to fund major
monies are derived from a portion of State street improvement and maintenance projects, such as
sales tax revenue, which is apportioned to slurry seal application and asphalt overlay projects.
each city based on population. The City
allocates these monies between TDA Article
8C funds, which become revenues to the
City's Transit Fund (Fund 5000), and TDA
Article 8A funds, which become revenues to
the Local Transportation Fund [LTF] (Fund
2603) to fund street improvement and
maintenance.
2604 — Federal Grants: Revenues received
via various federal grant programs, including:
the Surface Transportation Program (STP)
and Congestion Mitigation Air Quality
(CMAQ).
2605 — Gas Tax: Revenues derived from a
tax on motor vehicle fuel sales,apportioned to
local agencies based on a formula using
population, road miles and other factors.
These revenues are restricted to expenditures
for street maintenance and related costs.
2609 / 2610 — Other State Grants:
Revenues derived from various State grant
programs.