HomeMy WebLinkAboutAGENDA REPORT 2008 0319 CC REG ITEM 10NMOORPARK CITY COUNCIL
AGENDA REPORT
TO: Honorable City Council
FROM: Yugal K. Lail, City Engineer /Public Works Directo
DATE: March 4, 2008 (CC Meeting of 03/19/08)
M ON.
�.�
4
SUBJECT: Consider Selection of a Consultant to Prepare Construction Plans,
Specifications and Cost Estimate (PS &E) for the Princeton Avenue
Widening Project (Project 8012) and a Resolution Amending the
Fiscal Year 2007/08 Budget for Said Project
DISCUSSION
A. Background and Overview
On January 16, 2008, the City Council received and considered a report regarding
the status of design and right -of -way acquisition efforts for Project 8012: the
widening and realignment of Princeton Avenue west of Condor Drive (see map:
Attachment 1). In that report staff mentioned that work was proceeding on efforts
necessary to retain a civil engineering firm to prepare construction plans,
specifications and cost estimate (PS &E) for the project. This report recommends
selection of an engineering consultant firm to undertake that effort.
B. Current Project Status
1. Environmental Document: A Mitigated Negative Declaration /Environmental
Assessment for the subject project, was approved by the City Council in May
1999.
2. Right -of -Way Acquisition: The initial design identified 38 parcels where
additional right -of -way would be required. To date, 26 of those parcels have been
acquired. Acquisition of the remaining parcels have been put on hold pending
determination of the revised right -of -way needs to be identified by the re- design.
S: \Public Works\Everyone \Staff Reports\2008 \March \Princeton Redesign.doc
1001-45
Honorable City Council
March 19, 2008
Page 2
3. Initial Design: The initial project design is summarized as follows:
• Increase the width of the street right -of -way from 50' to 88' in order to allow
for the possible future widening of to street to 4 travel lanes, should the City
ever determine that action to be necessary. A description of the cross - section
for that possible future project is as follows:
Description Width (ft)
Four 12' wide travel lanes 48
Center median 14
Two 8' paved shoulders (Bike Lanes) 16
Two 5' sidewalks 10
E-1.1
• Widen and realign the street to provide the following improvements within that
88' right -of -way corridor:
Description Width (ft)
Two 12' wide travel lanes 24
Center median 14
Two 8' paved shoulders (Bike Lanes) 16
Two 17' wide dirt shoulders beyound the edge of pavement 34
88
C. Redesign: Revised Project Scope and Requirements
East End. The design for the north side of the street at the east end of the project
includes the construction of large and expensive retaining walls, driveways and other
improvements required to accommodate and protect certain residential properties
and structures. During the development of the initial design it was determined that
the foundations for the structures on the hillside on the north side of the road were
substandard, and that the pile driving required to construct the planned retaining
walls would likely cause severe property damage. For that reason, it was decided to
proceed with a full take of all of the properties on the north side of the street, east of
the freeway bridges. Accordingly, the design for the north -side improvements in this
area is now obsolete. It is anticipated that the need for retaining walls and related
improvement is now much less than that called for in the initial design. It is
anticipated, therefore, that a redesign for these project components will result in a
net savings in total project costs.
West End. The City was unable to reach agreement regarding property value, with
the owners of certain properties on the north side of the street at the west end of the
project. A re- evaluation of project needs and requirements showed that the project
could very likely be constructed within the current right -of -way if the City was to
delete the two 17' wide dirt shoulders within the 88' wide right -of -way corridor
required by the design concept approved by the City Council. The anticipated
redesign would move the road to the south and have an approximate two foot
unpaved shoulder for the north, and curbs, gutters, sidewalk, and a landscape
SAPublic Works \Everyone \Staff Reports\2008 \March \Princeton Redesign.doc t t,AO'146
Honorable City Council
March 19, 2008
Page 3
easement on the south. In the event the City desired to construct four travel lanes in
the future, additional right -of -way on the north would be needed.
Redesign: For the above reasons, staff is recommending that new plans and
specifications be prepared which adequately address current project restraints and
requirements.
A description of the proposed project requirements for the re- design is attached as
Attachment 2. Cross sections for the Initial design and the proposed revised project
are shown on Attachment 3.
D. Request for Proposals & Responses
A Request for Proposals (RFP) for conceptual design, and final project design and
specifications was prepared and provided to the following civil engineering design
firms:
• Tetra Tech
• Penfield & Smith; and
• Parsons Group.
Proposals were received from Penfield & Smith and from the Parsons Group.
E. Evaluation and Recommended Selection
Staff reviewed and evaluated the two proposals received. It was the determination of
staff that the proposal submitted by Penfield & Smith best met the needs of the City.
The negotiated fee for the services to be provided is $279,148. It is recommended
below that this firm be retained to prepare the revised project design.
F. Schedule
Date
Milestone
04/15/2008
Design Kick -off
10/01/2008
Design concept completed / R -O -W needs known
04/01/2009
Design completed
06/01/2009
Right -of -Way acquisition completed
06/01/2009
Approve Design / Advertise for Bids
09/01/2009
Start construction
FISCAL IMPACT
SAPublic Works \Everyone\Staff Reports\2008 \March \Princeton Redesign.doc ; 0014
Honorable City Council
March 19, 2008
Page 4
1. Estimated Project Cost Summary: An estimate of total project costs is as
follows:
Element
Expenses ($)
Total
Design
$
500,000.00
Relocation
$
22,900.00
Right -of -Way
$
1,500,000.00
Construction
$
2,000,000.00
Inspection
$
200,000.00
Estimated Total
$
4,222,900.00
2. FY 07108 Budget A re -cap of the FY 2007/08 Budget for this project is as
follows:
Prior
Years
Description
Expenses ($)
Design
257,738
Relocation
22,900
Right -of -Way
846,611
Construction
0
Inspection
0
Total 1,127,249
Current
FY 07/08 Total
Budget ($) Appropriations ($)
136,509 394,247
0 22,900
674,389 1,521,000
0 0
0 n
810,898 1,938,147
3. Budget Amendment Attached is a Resolution (Attachment 4) amending the
FY 2007/08
Budget to fully fund projected design costs.
That Resolution is
summarized
as follows:
Current
Proposed Revised
FY 07/08
Proposed
FY 07/08
Description
Budget ($)
Change ($)
Budget ($)
Design
136,509
150,000
286,509
Relocation
0
0
Right -of -Way
674,389
0
674,389
Construction
0
0
0
Inspection
0
0
0
Total 810,898
150,000
960,898
4. Total Revised Appropriations: If the attached Resolution
is adopted, the total
appropriations to date for this project will be as follows:
Prior
Revised
Years
FY 07/08
Total
Description
Expenses ($)
Budget ($)
Appropriations ($)
Design
257,738
286,509
544,247
Relocation
22,900
0
Right -of -Way
846,611
674,389
1,521,000
Construction
0
0
0
Inspection
0
0
0
Total 1,127,249
960,898
2,065,247
SAPublic Works \Everyone \Staff Reports\2008 \March \Princeton Redesign.doc 0 10 U 1 Y v
Honorable City Council
March 19, 2008
Page 5
5. Funding Source: The funding source for this project is Fund 2501: Los
Angeles Avenue AOC Fund.
STAFF RECOMMENDATIONS (Roll Call Vote)
1. Approve selection of Penfield & Smith to prepare conceptual design, construction
plans, specifications and cost estimate for the subject project.
2. Authorize the City Manager to sign necessary contract documents.
3. Adopt Resolution No. amending the Budget for the subject project.
ATTACHMENTS:
1 Location Map
2 Project Scope and Requirements
3 Cross Sections
4 Resolution
SAPublic Works \Everyone \Staff Reports\2008Warch \Princeton Redesign.doc 1 b1 ['1
ATTACHMENT 1
PROJECT�� CONDOR DR.
LIMITS 46
0
U
a
099.
a9
NNIE VIEW N PJ� PRINCETON AVE.
u Cj F y 0 vi
ST. yo c~> UCjC�P c^`�< QRZNG — — IDAGOlON1A i
a ST. u `E CT �'� Zd _ - — — — a AvEN
= F CHARLES ST.
a HIGH ST. N —
R.R. 9RTww
w FITCH AVE.
0 -
a-
Vl
a AVE, -
FLINN N
1 =
ES P
VICINITY MAP
N.T.S.
�ii150
Attachment 2
Re- Design: Project Scope and Requirements
West of Nogales Avenue: For the roadway segment between the westerly limits of the project
and Nogales Avenue, the roadway shall be "shifted" to the south (into the 17' wide dirt shoulder
provided for in the Prior Design). The revised roadway cross section and design elements for this
segment shall include the following:
• New design for an eight feet (8') wide sidewalk on the south side of the street (back of walk to
be at the R -O -W line);
• Provisions for street lights and utility pole relocations into the new south side sidewalk, in a
manner which fully addresses ADA requirements;
• Provisions for a five feet (5) wide landscape easement south of the south R -O -W line, for
certain given segments as described in Attachment 2;
• Redesign of the south side retaining walls required to relocated same to the south line of the
landscape easements, for those segments to have landscape easements (Note: South face
of the retaining walls shall be at the south line of the landscape easement);
• New design for a six feet (6') high block wall to be constructed on top of the retaining wall;
• New design for parkway landscaping and irrigation in the parkway landscape easements;
• New design for curb and gutter on the south side [curb face to be eight feet (8') north of the
south street R -O -W line] with proper gutter flow line elevations;
• Redesign of the storm drains and addition of south side catch basins, as required;
• Relocation of the roadway centerline nine feet (9') to the south (see Attachment 3);
• Redesign of roadway pavement elevations required to accommodate centerline shift to the
south and gutter flow line elevations;
• Revised roadway cross - section:
➢ 8' sidewalk (south side)
➢ 8' paved shoulder
➢ 12' EB lane
➢ 14', paved median
➢ 12' WB lane
➢ 8' paved shoulder
➢ No sidewalk on north side; and
➢ North side edge of pavement shall be 62' north of the south R -O -W line;
• The paved median shall be stripped to accommodate left -turn ingress and egress from /to
properties on both sides of the street;
• Elimination of soil - nailed walls on the north side of the street, to the fullest extent possible;
Note: The north side edge of pavement will be twenty -six feet (26') south of the north side
R -O -W line. [Again, in that said rights may not be needed, the City may not acquire
certain rights -of -way from north side properties at the west end of the project.]
• Redesign of the north side dirt drainage swales, as necessary;
• Redesign of any north side culvert inlets, as necessary;
• Redesign of north side driveway approaches, as required;
Note: In that the Revised Project may not impact the existing toe of slope on the north side
of the street, little or no driveway improvements or modification may be necessary.
SAPublic Works \Everyone\Staff Reports\2008Warch\Princeton Redesign.doc ' 00151
Attachment 2 (page 2)
2. East of Nogales Avenue: For the roadway segment between Nogales Avenue and the easterly
limits of the project, the roadway shall be "shifted" to the south (into the 17' wide dirt shoulder
provided for in the Prior Design). The revised roadway cross section and design elements for this
segment shall include the following:
• New design for an eight feet (8') wide sidewalk on the south side of the street (back of walk to
be at the R -O -W line);
• Provisions for street lights and utility pole relocations into the new south side sidewalk, in a
manner which fully addresses ADA requirements;
• New design for driveway aprons where required (ADA compatible);
• New design for curb and gutter on the south side [curb face to be eight feet (8') north of the
south street R -O -W line] with proper gutter flow line elevations;
• Redesign of the storm drains and addition of south side catch basins, as required;
• Relocation of the roadway centerline nine feet (9') to the south (see Attachment 3);
• Redesign of roadway pavement elevations required to accommodate centerline shift to the
south and gutter flow line elevations;
• Roadway design shall be mindful for the City's intent to require the construction (by a land
developer) of a new traffic signal at the Nogales Avenue intersection;
• Revised roadway cross - section:
➢ 8' sidewalk (south side);
➢ 8' paved shoulder;
➢ 12' EB lane
➢ 14' to 13' wide, paved median, striped to allow left -turn ingress and egress into driveways
(13' wide median is required at the east end where existing curb, gutter and sidewalk is to
remain);
➢ 12' WB lane #1;
➢ 12' WB lane #2
Notes: 1. The #2 WB lane shall extend to a point approximately 200' west of Nogales to
provide for an acceleration lane from the future signalized intersection.
2. The design element amends the design parameters set forth in Section B.
➢ 5' north side sidewalk (west of existing sidewalk); and
➢ 10' at back of sidewalk
Notes: 1. The existing north side sidewalk, curb and gutter shall remain.
2. The existing curb face is 15' south of the north R -O -W line.
3. The sidewalk in this area is wider than 5' feet (i.e. the R -O -W north of the
back of the sidewalk in this area is less than 10' wide.
• The paved median shall be stripped to accommodate left -turn ingress and egress from /to
properties on the south sides of the street;
• A left -turn pocket shall be provided for left -turn staging for westbound traffic approaching
Nogales Avenue;
• Deletion of all driveways, and related improvements, on the north side of the street, in that
area between the east limits and the freeway bridges (Note: all existing structures on the
north side in this area are to be removed);
• Redesign of soil - nailed walls (and /or retaining walls) on the north side of the street, between
the east limit and the freeway bridges, as required;
• Redesign of any north side culvert inlets, as necessary, including the addition of curbface
inlets, if any;
S:\PubIicWorks\Everyone\Staff Reports\2008 \March\Princeton Redesign.doc A00152
Attachment 3
Prior Design Cross - Section
(looking east)
17" 8' 12' 14' 12' 8' 17'
1 1 1 1 1 1 1 1
D C B A B C D
<----------------------- - - - - -- 88' ------------------------ - - - - >1
R -O -W
K— 9' ->I
Center line shift
Revised Project
West of Nogales
Cross - Section
(looking east)
26" 8' 12' 14' 12' 8' 8' 5'
1 1 1 1 1 1 1--------- I- - - - - -I
D C B A B C E F
I<----------------------- - - - - -- 88' ------------------------ - - - - >1
R -O -W
Revised Project
East of Nogales
Cross - Section
(looking east)
10" 5' 8' 12' 12' 13' 12' 8' 8'
I------------ I- - - - - -I I I I I I I---- - - - - -I
G E C B B A B C E
<----------------------- - - - - -- 88' --------------------- - - - - -- >1
R -O -W
A Paved Median E Sidewalk
B Travel Lane F Landscape Easement
C Paved Shoulder G Back of Walk
D Dirt Shoulder Scale" 1" = 15
SAPublic Works \Everyone \Staff Reports\2008\March \Princeton Redesign.doc ;00153
Attachment 4
RESOLUTION NO. 2008-
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
MOORPARK, CALIFORNIA, AMENDING THE FISCAL YEAR
2007/08 BUDGET TO APPROPRIATE ADDITIONAL FUNDS
FOR PROJECT 8012: PRINCETON AVENUE WIDENING
PROJECT [L. A. AVE. AOC FUND (FUND 2501)]
WHEREAS, on June 20, 2007, the City Council adopted the Budget for Fiscal Year
2007/08; and
WHEREAS, a staff report has been presented to the City Council requesting
budget adjustments in the aggregate amount of $150,000; and
WHEREAS, Exhibit "A ", attached hereto and made a part hereof, describes said
budget amendments and their resultant impacts to the budget line item(s).
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF MOORPARK DOES
HEREBY RESOLVE AS FOLLOWS:
SECTION 1. That a Budget amendment in the aggregate increase of $150,000,
as more particularly described in Exhibit "A ", is hereby approved.
SECTION 2. The City Clerk shall certify to the adoption of this resolution and shall
cause a certified resolution to be filed in the book of original resolutions.
PASSED AND ADOPTED this 19th day of March 2008.
Patrick Hunter, Mayor
ATTEST:
Deborah S. Traffenstedt, City Clerk
Attachment: Exhibit "A" — Budget Amendment Detail
SAPublic Works\Everyone \Staff Reports\2008Warch \Princeton Redesign.doc 00154
Resolution No. 2008-
EXHIBIT "A"
BUDGET AMENDMENT FOR
Project 8012: Princeton Avenue Widening Project
FY 2007 -2008
FUND ALLOCATION FROM:
Fund
Los Angeles Ave. AOC
Account Number
2501 -5500
Amount
150,000
I Total $ 150,000
DISTRIBUTION OF APPROPRIATION TO EXPENSE ACCOUNTS:
Account Number Current Budget ReW
2501 - 8310- 8012 -9601: Design $ 136,509 $
2501 - 8310 - 8012 -9609: Relocation $ _ $
2501 - 8310 - 8012 -9610: Ri ht -of -Wa $ 674,389 $
T
Approved as to Form:
• : E�
on Amended Budge
10,000 $ 286,509
-1$ 67
1
SAPublic Works \Everyone \Staff Reports\2008 \March \Princeton Widen Budget_Mar2008 Exhibit A i 0 015 S