BACKGROUND
In early 2006 the City completed construction of Phase 1 of the Tierra Rejada Road
Median Landscaping Project, which extended from Spring Road easterly to a point west
of the State Route 23 freeway. Phase 2 of the project is for the installation of median
landscaping within Caltrans right-of-way under and near the freeway overpass bridges,
(Attachment 1). That work had to be deferred until after completion of the freeway
widening project by Caltrans. The freeway work is now completed and it is now
appropriate to proceed with construction of Phase 2 of the median landscaping project.
DISCUSSION
A. Project Scope
The subject project provides for the removal of the AC pavement and guardrails within
the medians under the freeway, and in Caltrans right-of-way for the construction of
irrigation, landscaping, and hardscape to match the existing improvements on Phase
1 of this project.
B. Plans and Specifications
Project plans and specification for the subject project have been placed on top of the
file cabinets in the City Council conference room.
S:\Public Works\Everyone\Staff Reports\2008\Maff R Med Ph 2 ad.doc �/ �
Honorable City Council
May 7, 2008
Page 2
C. Project Approval — Design Immunity
It is recommended below that the City Council approve the project plans and
specifications in order to document City Council approval of the scope and design of
the project. Such approval is also required for the purpose of establishing design
immunity pursuant to Section 830.6 of the Government Code of the State of
California.
D. Environmental Clearance
This project is Categorically Exempt under Class 4b of the California Environmental
Quality Act (CEQA). Subsequent to the requested City Council action to approve the
project, certification of this exemption will be prepared and filed by staff.
E. Caltrans Permit
Subsequent to City Council approval of the project, staff will prepare and submit an
encroachment permit application to Caltrans. Subsequent to award of the construction
contract, the City selected contractor will seek and obtain a duplicate permit from
Caltrans.
F. Schedule
The anticipated schedule for the project is as follows:
• May 8: submit Caltrans application
• June 10: receive Caltrans Permit
• June 15: advertise
• July 22: open bids
• August 20: award contract
• September 3: commence construction
• December 3: anticipated completion
FISCAL IMPACT
A. Proiect Cost
The current estimated project cost is summarized as follows:
Description Amount($)
Design 1,000
Construction 50,000
Inspection 2,000
Total 53,000
SAPublic Works\Everyone\Staff Reports\2008\May\T R Med Ph 2 ad.doc 10l.i 06 0
Honorable City Council
May 7, 2008
Page 2
B. Current Budget
The project is funded from the Spring Road /Tierra Rejada Road AOC Fund (Fund
2502). The current budget carryover amount from Phase 1 of the project, is
summarized as follows:
Remaining
Total Phase 1 FY 07/08
Account No. Approprioations ($) Costs ($) Budget ($)
2502.8310.8042.9601 - Design 33,624 (31,474) 2,150
2502.8310.8042.9640 - Construction 894,083 (859,445) 34,638
2502.8310.8042.9650 - Inspection 5,113 (1,080) 4,033
2502.8310.8042.9331 - Maintenance 4,376 (4,376) 0
Total 937,196 (896,375) 40,821
Staff anticipates that it will be necessary to amend the budget at the time of award of
contract, to fully fund the project.
STAFF RECOMMENDATION
Approve the plans and specifications for the subject project and authorize staff to
advertise for bids upon receipt of the required Caltrans permit.
Attachment
1. Location Map
SAPublic Works\Everyone\Staff Reports\2008\Maff R Med Ph 2 ad.doc �+
ATTACHMENT 1
o�vw ,/Z
\ \
qr
♦ .f S
♦
TIERRA REJADA ROAD MEDIAN ISLAND
LANDSCAPE AND HARDSCAPE IMPROVEMENTS
jf
0 06w